APPENDIX
5.1 – Event / Action Plan for Construction Noise
Event |
ACTION |
|||
|
ET Leader |
IC (E) |
ER |
Contractor |
Action Level |
1.
Notify IC(E) and Contractor 2.
Carry out investigation 3.
Report the results of investigation to the IC(E)
and Contractor 4.
Discuss with the Contractor and formulate
remedial measures 5. Increase monitoring frequency to check
mitigation effectiveness |
1.
Review the analysed results submitted by the ET 2.
Review the proposed remedial measures by the
Contractor and advise the ER accordingly 3.
Supervise the implementation of remedial measures |
1.
Confirm receipt of notification of failure in
writing 2.
Notify Contractor 3.
Require Contractor to propose remedial measures
for the analysed noise problem 4.
Ensure remedial measures are properly implemented |
1.
Submit noise mitigation proposal to IC(E) 2.
Implement noise mitigation proposals |
Limit Level |
1.
Notify IC(E), ER, EPD and Contractor 2.
Identify source 3.
Repeat measurement to confirm findings 4.
Increase monitoring frequency 5.
Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented 6.
Inform IE(E), ER and EPD the causes & actions
taken for the exceedances 7.
Assess effectiveness of Contractor’s remedial
actions and keep IC(E), EPD and ER informed of the results 8. If exceedance stops, cease additional
monitoring |
1.
Discuss
amongst ER, ET, and Contractor on the potential remedial actions 2.
Review
Contractor’s remedial actions whenever necessary to assure their the ER
accordingly 3.
Supervise
the implementation of remedial measures |
1. Confirm receipt of notification of failure in writing 2. Notify
Contractor 3. Require
Contractor to propose remedial measures for the analysed noise problem 4. Ensure
remedial measures are properly implemented 5. If
exceedance continues, consider what portion of the work is responsible and instruct
the Contractor to stop that portion of work until the exceedance is abated |
1. Take
immediate action to avoid further exceedance 2. Submit
proposal for remedial actions to IC(E) within 3 working days of notification 3. Implement
the agreed proposals 4. Resubmit
proposals if problem still not under control 5. Stop
the relevant portion of works as determined by the ER until the exceedance is
abated |