Appendix 2.2 Preliminary Construction Programme
Location 2006 2007 2008 2009
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Site Clearance                                                                          
Outlets to Silver River                                                                          
  Pak Ngan Heung Outlet (CH350 -250)                                                                          
    Excavation                                                                          
    Retaining Wall                                                                          
    Backfilling                                                                          
  Luk Tei Tong Outlet (CH225 - CH175)                                                                          
    Excavation                                                                          
    Retaining Wall                                                                          
    Backfilling                                                                           
  Tai Tei Tong Outlet                                                                          
    Excavation                                                                          
    Retaining Wall                                                                          
    Backfilling                                                                          
Pak Ngan Heung – Box (CH250 -CH75)                                                                          
Pak Ngan Heung River                                                                          
  Excavation (CH75 - CH0)                                                                          
  Low Flow Diversion Pipes and bund                                                                          
  Retaining Wall/Wing Walls                                                                          
  Backfilling/Channel Lining                                                                          
Luk Tei Tong River (CHB175 - CHB0)                                                                          
  Excavation (CHB175 - CHB0)                                                                          
  Retaining Wall                                                                          
  Backfilling/Channel Lining                                                                          
Luk Tei Tong By-pass Channel                                                                          
  Construction of gabion channel (d/s to u/s)                                                                          
  Box Culvert LTT2                                                                          
  Box Culvert LTT1                                                                          
Tai Tei Tong River                                                                          
  Widening of Bottleneck - U/S                                                                          
  Widening of Bottleneck - Mid Section                                                                          
Ling Tsui Tau U-channel                                                                          
  U-channel                                                                          
  Retaining Wall