1                        INTRODUCTION

1.1                  Background to the Study

1.1.1           The Drainage Services Department substantially completed the “Stormwater Drainage Master Plan Study in Sai Kung, East Kowloon and Southern Lantau” (DMP Study) in September 2000.  The DMP Study identified deficiencies and flooding problems in the existing drainage systems in Sai Kung, East Kowloon and Southern Lantau.  The Preliminary Project Feasibility Study (PPFS) Report for the drainage improvements in Southern Lantau was subsequently completed in March 2002.

1.1.2           The PPFS identified constraints, proposed a preliminary development option and recommended further investigations and studies for the drainage improvement works in Southern Lantau.

1.1.3            Metcalf & Eddy Limited (M&EL) have been commissioned by the Drainage Services Department (DSD) of the Hong Kong SAR Government in May 2003 to undertake the “Drainage Improvement in Southern Lantau – Investigation” (hereinafter referred to as “the Assignment”), with environmental support from Maunsell Environmental Management Consultants Limited.

1.1.4           A Preliminary Environmental Review (PER), undertaken in the PPFS stage, identified part of the drainage improvement works in Southern Lantau as a Designated Project under Schedule 2 Part I of the Environmental Impact Assessment Ordinance (EIAO) that requires an environmental permit under the EIAO for its construction and operation.  The Designated Project includes the drainage improvement works in Pak Ngan Heung River, Tai Tei Tong River, Luk Tei Tong River and Luk Tei Tong (2) River in the Mui Wo area (hereafter referred to as “the Project”). 

1.1.5           Figure 1.1 shows the location plan of the proposed works.  An application for an Environmental Impact Assessment (EIA) Study Brief was obtained from the Environmental Protection Department (EPD), registered under the EIAO as EIA Study Brief No. ESS-101/2002.  An EIA Study for the Project has been undertaken as part of the Assignment, in accordance with the EIA Study Brief and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

1.2                   

1.2                 Purpose and Scope of the EIA Study

1.2.1           In accordance with the EIA Study Brief, the main objective of the EIA study is to provide information on the nature and extent of potential environmental impacts arising from the construction and operation of the Project and related activities taking place concurrently, and to contribute to decisions on the overall environmental acceptability of the Project, after the implementation of environmental mitigation measures. 

1.2.2           The scope of this EIA study covers the proposed drainage improvement works in Mui Wo for Pak Ngau Heung River, Tai Tei Tong River, Luk Tei Tong River and Luk Tei Tong (2) River.  The EIA Report has also reported on the need of the Project and addressed alternative drainage options in Section 2.

 


1.3                  EIA Study Area

1.3.1           The assessment area for the purpose of this EIA study, as specified in the EIA Study Brief, is presented below:

 

·              Air quality impact assessment – area within 500m from the Project boundary.

·              Noise impact assessment – areas within 300 m from the Project boundary.  If the first layer of noise sensitive receivers provides acoustic shielding to those receivers further from the site, the assessment area could be reduced accordingly.

·              Water quality impact assessment –areas within 500m from the Project boundary, covering the Luk Tei Tong freshwater marsh. 

·              Ecological impact assessment – the assessment area for terrestrial ecological assessment includes areas within 500 m distance from the site boundary of the works areas, or the area likely to be impacted by the Project.  For aquatic ecology, the assessment area is the same as for water quality assessment.

·              Cultural heritage impact study - sites of cultural heritage that may be adversely affected by the Project.

 

1.4                  Structure of the Report

1.4.1           The background of the Project and the objectives of this Report are introduced in Section 1.  A description of the Project is provided in Section 2.  Sections 3 to 8 detail the results of the environmental impact assessment of each key subject area, covering relevant legislation, environmental conditions, assessment criteria and methods, and assessment findings:

 

·        Section 3:  Air quality

·        Section 4:  Noise

·        Section 5:  Water Quality

·        Section 6:  Waste Management Implications

·        Section 7:  Ecology

·        Section 8:  Cultural heritage

1.4.2           An outline of the requirements for the environmental monitoring and audit (EM&A) programme is presented in Section 9.  The EM&A programme is presented in detail in a separate EM&A Manual.  An overall conclusion of the EIA Study is given in Section 10.  A detailed implementation schedule of the recommended mitigation measures is provided in Section 11.