Table 10.1 Summary
of Key Environmental Outcomes/ Benefits
Issue |
Environmental
Outcomes/Benefits |
The
Project |
After completion: · relieve the
risk of flooding · minimise
economic loss · minimise
disruption to everyday life especially during the wet season in Mui Wo. · sustain the
residential developments Benefited
areas: · Tai Tei Tong,
Luk Tei Tong, Mui Wo Town, Chung Hau, Ling Tsui Tau, Pak Ngan Heung. Potential
consequences without the Project:
· Persistent flooding along the Pak Ngan Heung River, Luk Tei Tong
River, Luk Tei Tong (2) River, Ling Tsui Tau and Mui Wo Town; · Hinder future development in Mui Wo, Southern Lantau. · Damage to property and nuisance to the public. |
Drainage
Options, Alignment and Construction Methods |
The
factors such as social, ecological and other environmental aspects have been
considered in light of different drainage options, alignment and construction
method. The following outcomes are found:
(a) The
proposed alignments of the river channels follow the existing ones as far as
possible. The affected area and hence land resumption and house clearance are
minimum.
(b) Diversion
box culvert and channel are recommended in Pak Ngan Heung and Luk Tei Tong
(2) River respectively to avoid affecting the existing rivers.
(c) The
proposed works provide a direct and effective way to discharge stormwater and
prevent flooding.
(d) The
potential environmental impacts would be local and limited to the
construction stage. The impacts could be mitigated by appropriate measures
and choice of suitable construction methods.
(e) The
proposed drainage improvement works provide a longer-term solution for
flooding.
The following
ecological-friendly design would be incorporated into the channel designs in
order to mitigate the environmental impact. For Pak Ngan Heung, Tai
Tei Tong and Luk Tei Tong Rivers: · The existing
river will not be deepened and the existing riverbed will be untouched as far
as practicable. · Channel beds
would be constructed using natural materials such as small cobbles and
boulders. Where possible, construction would utilise suitably sized
cobbles/boulders found in the existing rivers. This recreated habitat would
provide a suitable environment for many organisms dependent on the existing
watercourses. · Channel banks
would be largely trapezoidal, and lined with gabion blocks. · The depth of
the channels would be varied to re-create the pool-riffle sequence found in
natural streams. · Larger pools in
the stream and river currently maintained for crop irrigation would be
re-instated. For Luk Tei Tong (2)
River: · A bypass
drainage is proposed to convey floodwater to Luk Tei Tong River during heavy
rainstorm. · The Luk Tei
Tong By-pass Channel bed would be reinforced with geo-textile matting. The
matting would be overlain with turf taken from adjacent areas of Luk Tei Tong
Marsh that would be directly affected by the proposed works. This area would
be maintained as compensatory marshland habitat. · The banks of
the whole proposed Channel would be lined with rock-filled gabion. |
Construction
Programme |
The preliminary construction programme was designed
to minimize the potential environmental impact by taking account of the
following factors:
(a) High
flooding risk for the outlets - the improvement works for the outlets
should be carried out in the dry season only.
(b) Impact to the existing marsh at Luk Tei
Tong - as agreed with the green group, the construction works for the
proposed Luk Tei Tong By-pass Channel should be carried out in the dry season
in order to minimize the potential impact on the existing marsh area at Luk
Tei Tong. (c) Cumulative impacts – in order to
minimize the potential impacts to the existing sensitive receivers and
public, the cumulative impacts for the concurrent projects, as well as those
proposed works under this project have been duly considered. The Contractor
should be encouraged to programme the construction activities under the project
in such a manner that ongoing activities would be separated physically as far
as possible from one another and other construction sites. |
Construction
Air Quality Impact |
·
Potential air
quality impacts: dust nuisance and gaseous emissions from the construction
plant and vehicles ·
Mitigation
measures: implement the Air Pollution Control (Construction Dust)
Regulation and good site practices. ·
No adverse air
quality impact would be anticipated. |
Construction
Noise Impact |
·
Unmitigated cumulative construction noise levels: 62 dB(A) to 100
dB(A). ·
Recommended mitigation measures: adopting quiet construction plant;
using movable/temporary noise barriers; and implementing good site practices.
·
Under mitigated scenario, all the NSRs would be protected to comply with
the daytime construction noise standard as set out in the EIAO-TM, except the
NSR in close proximity to the works sites of retaining wall at Pak Ngau Heung
River outlet. However, it is expected
that the residual impacts would be short-term and localized. ·
An EM&A programme would be implemented to monitor construction
noise impact. |
Water
Quality Impact |
· Key potential
source of water quality impact: excavation works during construction phase. · Minimisation of potential impacts: working method controls
recommended e.g. excavation works carried out in dry condition and
containment measures used within the channel. · Other potential
sources of impacts: construction site runoff and drainage; debris, refuse and
liquid spillages from general construction activities; and sewage effluents
from the construction workforce. · Minimisation of water quality deterioration: implementation of
adequate mitigation measures, proper site management and good housekeeping
practices; and appropriate treatment of sewage effluents. · Site
inspections would be conducted during the construction phase. · No unacceptable
impacts on water quality would be anticipated. |
Waste Management Implications |
· Main waste:
excavated materials from the three rivers (approx. 45,200 m3). · Excavated
material with suitable characteristics should be reused on-site as far as
practicable (approx. 6,400 m3). Surplus material would require
disposal to a public filling area. ·
Other
wastes generated by construction activities: general refuse from the workforce,
chemical wastes from plant and vehicle maintenance, and C&D material from
the demolition of existing structures and site clearance. · With implementation of the
recommended mitigation measures for the handling, transportation and disposal
of the identified waste, no residual waste management impacts would be
expected. |
Ecology |
· River channels designed to provide suitable habitats for existing
aquatic communities, and to largely compensate for impacts to marsh habitats.
A specific EM&A programme would be implemented to monitor the relative
effectiveness of river and marsh habitat recreation. · Potential impacts to a breeding colony of the locally rare
White-shouldered Starling would be largely avoided through scheduling of
works close to the colony outside of the breeding season. A specific EM&A
programme would be implemented to ensure impacts to the colony are avoided
and minimised. · Impacts to woodland habitats and trees compensated through landscaping
measures. · Fish and amphibian species of conservation interest potentially
occurring within works areas would be temporarily translocated from works
areas to suitable nearby habitats or holding aquariums to minimise impacts. · A fish ladder constructed in Pak Ngan Heung River would allow
migration of fish species in this river, thus improving the value of the
river to fish communities. |
Impact
of Cultural Heritage |
· Further investigation and a
watching brief are recommended for the excavation works associated with the
proposed U-channel at Ling Tsui Tau Tsuen within the Chung Hau Archaeological
Site. ·
Careful construction and vibration monitoring are recommended to
minimize the potential vibration impact to the existing retaining wall and
associated structures of the Yuen Compound during the construction of rubble
seawall and retaining wall at the Luk Tei Tong River. |