Table 11.1 Implementation Schedule for Construction Dust Control
EIA Ref # |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant
Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S3.7.1 |
Implementation of the Air Pollution Control (Construction Dust)
Regulation and good site practices: ·
Use of regular watering to reduce dust emissions from exposed site
surfaces and unpaved road, with complete coverage, particularly during dry
weather; ·
Use of frequent watering for particularly dusty static construction
areas and areas close to ASRs; ·
Tarpaulin covering of all dusty vehicle loads transported to, from
and between site location; ·
Establishment and use of vehicle wheel and body washing facilities at
the exit points of the site; ·
Routing of vehicles and positioning of construction plant should be
at the maximum possible distance from ASRs; ·
Stockpiled excavated materials should be covered with tarpaulin, and
should be removed off-site within 24 hours to avoid any odour nuisance
arising. |
Work site / During the
construction period |
Contractor |
|
Ö |
|
|
Air Pollution
Control (Construction Dust) Regulation |
# All recommendations and requirements resulted during
the course of EIA/EA Process, including ACE and / or accepted public comment to
the proposed project.
* Des - Design, C - Construction, O – Operation, and
Dec - Decommissioning
Table 11.2 Implementation Schedule for Construction Noise Control
EIA Ref # |
Environmental
Protection Measures / Mitigation Measures |
Location /
Timing |
Implementation
Agent |
Implementation
Stages* |
Relevant
Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S4.8.1 |
Good Site
Practice ·
Only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction program; ·
Silencers
or mufflers on construction equipment should be utilized and should be
properly maintained during the construction program; ·
Mobile
plant, if any, should be sited as far from NSRs as possible; ·
Machines
and plant (such as trucks) that may be in intermittent use should be shut
down between work periods or should be throttled down to a minimum; ·
Plant known
to emit noise strongly in one direction should, wherever possible, be orientated
so that the noise is directed away from the nearby NSRs; and ·
Material
stockpiles and other structures should be effectively utilized, wherever
practicable, in screening noise from on-site construction activities. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN2/93
and Noise Control Ordinance |
S4.8.2- S4.8.4 |
Use of quiet PME |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN2/93
and Noise Control Ordinance |
S4.8.5- S4.8.6 |
Use of movable noise barriers and temporary
noise barrier |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN2/93
and Noise Control Ordinance |
S4. |
Environmental
Monitoring and Audit (EM&A) programme is recommended to be implemented
during the construction stage. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
- |
# All recommendations and requirements resulted during
the course of EIA/EA Process, including ACE and / or accepted public comment to
the proposed project.
* Des - Design, C - Construction, O – Operation, and
Dec - Decommissioning
Table 11.3 Implementation Schedule for Water Quality Control
Environmental
Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
||||
Des |
C |
O |
Dec |
|||||
S5. |
Construction Site
Runoff and Drainage ·
Before
commencing any site formation work, all sewer and drainage connections shall
be sealed to prevent debris, soil, sand etc. from entering public
sewers/drains. ·
Temporary
ditches shall be provided to facilitate run-off discharge into appropriate
watercourses, via a silt retention pond.
No site run-off shall enter the freshwater marshes at Luk Tei Tong. ·
Sand/silt
removal facilities such as sand traps, silt traps and sediment basins shall
be provided to remove sand/silt particles from runoff to meet the
requirements of the Technical Memorandum standard under the Water Pollution
Control Ordinance. The design of silt
removal facilities shall be based on the guidelines provided in ProPECC PN
1/94. All drainage facilities and
erosion and sediment control structures shall be inspected monthly and
maintained to ensure proper and efficient operation at all times and
particularly during rainstorms. ·
Water
pumped out from foundation excavations shall be discharged into silt removal
facilities. ·
During
rainstorms, exposed slope surfaces shall be covered by a tarpaulin or other
means. Other measures that need to be implemented before, during, and after
rainstorms are summarized in ProPECC PN 1/94. ·
Exposed
soil areas shall be minimized to reduce potential for increased siltation and
contamination of runoff. ·
Exposed
soil surfaces shall be protected by paving or fill material as soon as
possible to reduce the potential of soil erosion. ·
Open
stockpiles of construction materials or construction wastes on-site of more
than 50 m3 shall be covered with tarpaulin or similar fabric
during rainstorms. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO |
S5. |
General
Construction Activities ·
Debris and
refuse generated on-site shall be collected, handled and disposed of properly
to avoid entering the river channels, the Luk Tei Tong freshwater marshes and
local storm water drains. Stockpiles
of cement and other construction materials shall be kept covered when not
being used. ·
Oils and
fuels shall only be used and stored in designated areas which have pollution
prevention facilities. All fuel tanks
and storage areas shall be provided with locks and be sited on sealed areas,
within bunds of a capacity equal to 110% of the storage capacity of the
largest tank. The bund shall be
drained of rainwater after a rain event. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO |
S5.7.5 |
Sewage
from Construction Workforce Temporary sanitary facilities, such as
portable chemical toilets, shall be employed on-site. A licensed contractor shall be responsible
for appropriate disposal and maintenance of these facilities. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
WPCO |
S5.7.6 |
River
Channel Excavation Works Excavation and widening works for the
drainage improvements to the Pak Ngan Heung River, Tai Tei Tong River and Luk
Ti Tong River shall be carried out in sections (approximately 300 – 400 m in
length) and in dry condition.
Containment measures such as bunds and barriers shall be used within
the river channel and the excavation works restricted to within an enclosed
dry section of the channel. The
excavation and widening works shall be carried out in the dry season as far
as practicable. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
|
S5.7.7 |
Maintenance Desilting of River Channels For maintenance desilting of
the re-profiled river channels of Pak Ngan Heung River, Tai Tei Tong River
and Luk Ti Tong River, temporary barrier walls shall be used to provide a dry
work zone for desilting work.
Maintenance desilting shall be carried out during periods of low flow
in the dry season. |
Work site / During the
operation period |
Contractor |
|
|
Ö |
|
|
S.5.9.1 |
During construction
phases, monitoring
of downstream water quality within the rivers should be undertaken,
together with regular site audits. |
With the
rivers / During the construction
period |
Contractor |
|
Ö |
|
|
|
# All
recommendations and requirements resulted during the course of EIA/EA Process,
including ACE and / or accepted public comment to the proposed project.
* Des - Design, C -
Construction, O – Operation, and Dec - Decommissioning
Table 11.4 Implementation Schedule for Waste Management Implications
# All
recommendations and requirements resulted during the course of EIA Process,
including ACE and / or accepted public comment to the proposed project.
·
Des - Design,
C - Construction, O - Operation and Dec – Decommissioning
Table 11.5 Implementation Schedule for Ecological Requirements
EIA Ref # |
Environmental Protection
Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and
Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S7.7.1- S7.7.
S7.8.2, S7.8.4 S7.8.1 S7.8.18 |
Design of River
Channels The scale of impacts to river habitats would be
determined largely by the design of drainage channels built to replace
existing rivers. Ecological requirements have been considered during the
design of drainage improvement works, and are described as follows. Pak Ngan Heung River
Drainage improvements would be implemented by
constructing an underground channel that would bypass a sharp bend in the
river close to Butterfly Hill. Under normal conditions, flow would be
maintained within the existing river channel. During high flow events, excess
floodwaters would be conveyed through the by-pass channel
|
River
channels during design/construction phase. |
Project Proponent/ Contractor. |
Ö |
Ö |
|
|
- |
S7.8. |
Avoidance of
Disturbance to The works programme has been considered to avoid
impacts to breeding wildlife where possible. Works within Luk Tei Tong Marsh
and the confluence of the three rivers would be restricted to the dry season,
thereby avoiding impacts to White-shouldered Starlings (Sternus sinensis)
that have been recorded breeding in the Disused Watchtowers close to the
river confluence, and also to other avifauna and herpetofauna species that
may breed within Luk Tei Tong Marsh. |
River
outlets during construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.5 |
Minimise Sedimentation
All excavation works carried out within or close
to water bodies should be carried out in the dry season where possible, with
construction carried out by land-based plant. Excavation works within
river/stream channels should be restricted to an enclosed dry section of the
river, with containment measures such as bunds and barriers used within the
river to minimize the impacts upon the downstream water body. Site runoff
should be directed towards regularly cleaned and maintained silt traps and
oil/grease separators to minimise the risk of sedimentation and pollution of
river water. The silt and oil/grease separators should be appropriately
designed for the local drainage and ground conditions. To minimize leakage
and loss of sediments during excavation in narrow channels, tightly sealed
closed grab excavators should be deployed where material to be handled is wet. |
Works areas during
construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.6 |
Minimise Noise Impacts Noise mitigation measures including the use of
quiet construction plant and temporary noise barriers should be implemented
to minimise disturbance to habitats adjacent to the works areas. |
Works areas during
construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.7 |
General Site Practice Standard good site practice measures should be
implemented throughout the construction phase. The measures should include: ·
Placement of equipment or
stockpile in designated works areas and access routes selected on existing
disturbed land to minimise disturbance to natural habitats and vegetation,
particularly mature trees. ·
Construction activities
should be restricted to work areas that should be clearly demarcated. The
work areas should be reinstated after completion of the works. ·
Waste skips should be
provided to collect general refuse and construction wastes. The wastes should
be disposed of timely and properly off-site. ·
General drainage arrangements
should include sediment and oil traps to collect and control construction
site run-off. ·
Open burning on works
sites is illegal, and should be strictly prohibited. |
Works areas during
construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.8 |
Minimise Operation Phase
Disturbance Impacts The following measures are recommended to
minimise potential impacts resulting from operational phase activities: ·
To minimise sedimentation,
de-silting should be limited to the dry season (November-March). ·
For maintenance desilting
of the re-profiled river channels, temporary barrier walls shall be used to
provide a dry zone for desilting work. ·
The implementation of
de-silting and other activities that could disturb aquatic fauna should be
phased to ensure some areas of relatively undisturbed habitat remain
available for resident aquatic fauna at all times. ·
Waste material produced
during de-silting should be disposed of in a timely and appropriate manner. |
River Channels during
operation phase. |
Maintenance Agent. |
|
|
Ö |
|
- |
S7.8.9- S7.8.11 S7.8.1 S7.8. |
Luk Tei Tong To minimise impacts to Luk Tei Tong Marsh, No
footpath would be constructed along the bypass channel. Construction of the Bypass Channel would be
limited to one dry season only, thereby minimising disturbance impacts to
wetland fauna potentially breeding in the Marsh Area. Operation phase impacts resulting from desilting
works within the LTT The following key features
would be included in the Channel design:
·
The Bypass Channel bed
would be approximately 800mm below the existing ground level, and would be
lined with turf taken from areas of Luk Tei Tong Marsh that fall within the
footprint of the proposed Channel. This area would be maintained as
compensatory marshland habitat. So as to maintain the flood protection
function of the channel, vegetation within the Channel would be maintained at
a height of about 300mm. ·
A low weir would be
constructed at the downstream end of the Bypass Channel, serving to retain
rainwater and some diverted floodwaters in the Channel. As the channel would
be slightly lower than the existing ground level, and water within the
channel would be retained, it is anticipated that habitats within the channel
provide a more valuable wetland habitat than adjacent areas of Luk Tei Tong
Marsh, where wetland vegetation is not particularly well established. ·
The banks of the proposed
Channel would be lined with rock-filled gabion, and topped with small (200mm
high) earth bund. The gabion lining is required to stabilize the banks of the
Channel, and the earth-bund would prevent surface water from surrounding
areas of the marsh from draining into the Channel. The intention of re-using
turf from the channel alignment is to provide suitable soil conditions for
wetland habitats within the Bypass Channel. Additionally, roots and seeds of
some plant species within the turf would speed up the establishment of
wetland vegetation within the Channel. It should be noted though that parts
of the Channel alignment are currently dominated by the weed Mikania
micrantha, which would require removal prior to the construction phase. Reference should be made
to Nature Conservation Practice Note No. 01/2003.
The construction of the
LTT
|
LTT |
Project Proponent, Contractor, Maintenance Agent |
Ö |
Ö |
Ö |
|
- |
S7.8. |
Minimise Impacts
to Trees by Ling Tsui
Tau U-Channel To minimise impacts to woodland habitats,
the alignment of the proposed U-Channel should avoid nearby mature trees as
far as practicable. |
Ling Tsui Tau U-Channel during
design/construction phase. |
Project Proponent/ Contractor. |
Ö |
Ö |
|
|
- |
S7.8. S7.8.14 |
Capture-Surveys
of Fish and Amphibian
Species of Conservation Interest Proposed works at the
rivers have the potential to impact fish species of conservation interest. To
minimize these potential impacts, it is recommended that capture-surveys of
the proposed works areas are conducted prior to the commencement of
construction works in the channel. These surveys should include fish species
of conservation interest recorded during the surveys (Flagtail, Kuhlia
marginata & Predaceous Chub, Parazacco spilurus), with
particular attention paid to the Flagtail. Either of these species caught
during the surveys should be re-located to areas of the watercourse upstream
of the proposed works areas, or to aquaria set up close to the works areas.
Maintenance of the fish prior to translocation would be undertaken by an
ecologist appointed by the Project Proponent. The capture surveys should be
conducted in the dry season by a suitably qualified ecologist(s) appointed by
the Project Proponent. For the Flagtail (which will probably occur in low
densities at PNH River), further surveys should be conducted to confirm the
presence and numbers of fish in the streams closer to the time of
construction. A detailed methodology for fish translocation (based in part
upon the Flagtail survey results) should be formulated during the detailed
design stage of the Project.
In addition to fish
species of conservation interest, the proposed drainage improvement works
could also result in direct impacts to two amphibian species of conservation
interest, RTF and Chinese Bullfrog. It is therefore recommended that
additional capture surveys are conducted prior to the commencement of works
to locate any individuals of these two species within the works areas. The
surveys should be conducted in the wet season (March/April-October), when
these species are calling and are generally more conspicuous. Any individuals
captured during the survey should be relocated to similar nearby habitats
outside of the works areas. The capture surveys should be conducted by a
suitably qualified ecologist(s) appointed by the Project Proponent. A
detailed methodology for faunal translocation should be formulated during the
detailed design stage of the Project.
|
|
Ecologist.
|
Ö |
Ö |
Ö |
|
- |
|
|
|
|
|
|
|
|
|
S7.8. |
Compensatory Tree
and Shrub Planting Planting of trees and other vegetation along the
banks of the newly created channels would provide compensation for
unavoidable tree-felling and loss of small areas of open and secondary
woodland habitat resulting from the proposed TTT and PNH River Channel and
Ling Tsui Tau U-Channel works. Compensatory planting would make use of native
plant species with flowers/fruits attractive to wildlife. Compensation in
terms of woodland area and trees planted would be on at least a 1:1 ratio,
covering an area of at least 0.13ha. |
Detailed
landscape design during design phase, planting during construction phase. |
Designer/Contractor. |
Ö |
Ö |
|
|
- |
S7.10.1- S7.10.7 |
Environmental
Monitoring & Audit The proper implementation of recommended ecological
mitigation measures should be audited. A specific monitoring
programme of improved sections of PNH and LTT Rivers is recommended. The
programme should provide data on the re-establishment of aquatic/riparian
communities in the channels, and allow an assessment of the relative success
of mitigation measures to be made. Baseline data should be collected several
months before the commencement of the construction phase, with monitoring
conducted on a monthly basis during the construction phase, and every two
months a year for 4 years after the completion of works. Data collected
should include the following parameters:
|
Prior
to and during Construction Phase. Operation Phase. |
EM Team and Ecologist(s) |
Ö |
Ö |
Ö |
|
- |
# All recommendations and requirements resulted
during the course of EIA/EA Process, including ACE and / or accepted public
comment to the proposed project.
* Des - Design, C - Construction, O – Operation, and Dec -
Decommissioning
Table 11.6 Implementation Schedule for Cultural
Heritage
EIA Ref # |
Environmental Protection
Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and
Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S8 |
Archaeology Further archaeological investigation is recommended
for the two areas within the Chung Hau Archaeological Sites, including Area E
and the site of the abandoned factory, as well as the works area not covered by the
previous survey. The construction of the proposed U-channel at Ling
Tsui Tau Village should minimise any excavation works within the boundary of
the Chung Hau Archaeological Site. Subject to the findings of the further
investigation, a watching brief is recommended for any excavation works
undertaken by a qualified archaeologist approved by AMO in order to record
and collect any artefacts and/or archaeological data during excavation. If
significant archaeological deposits are found, a rescue excavation may need
to be undertaken. Built Heritage Specific construction method should be
selected to avoid vibration impact on the retaining wall and buildings of the
Yuen Compound during construction of the proposed retaining wall and rubble
seawall. Monitoring of vibration impacts should be conducted during the
construction works to ensure no damage to the existing structures of the
Compound. |
Work
site/During construction phase |
Contractor |
|
Ö |
|
|
- |
# All recommendations and requirements resulted
during the course of EIA/EA Process, including ACE and / or accepted public
comment to the proposed project.
* Des - Design, C - Construction, O – Operation, and Dec -
Decommissioning