Table 2.1 Summary of Existing Drainage Conditions in Mui Wo
Locations |
Drainage Conditions |
Pak Ngan Heung River |
(a) In some parts of the river, the flood protection level is less than 1-in-2 years and the river will not be able to contain flood flow within its banks during heavy rainstorms. (b) The previous flood records have revealed that floodwater overtopped an existing bridge near Mui Wo Rural Committee Road and flooded houses immediately downstream of the river. (c) For the upstream area of Pak Ngan Heung River, the flooding problems are caused by very fast super-critical flow around bends. The super-critical flow has a great inertia and prefers to flow straight ahead rather than around bends and hence causing overtopping. In addition, cross-waves and bow-waves are created. A box culvert has been proposed to convey the flow directly to downstream without passing through sharp bend during heavy rainstorm. (d)
Around the main confluence at downstream of Pak Ngan
Heung River, the problem is mainly due to low bank levels. The area is at
risk of flooding caused by both high sea water level and extreme rainfall. |
Ling Tsui Tau |
(a)
Ling
Tsui Tau is a flooding black spot. (b)
Due
to the inadequate drainage system, surface runoff from Butterfly Hill cannot
be effectively discharge to Pak Ngan Heung River during heavy rainstorm. |
Luk Tei Tong (2) River |
(a)
The Luk Tei Tong (2) River is a tributary of Luk Tei
Tong River. It flows through an existing floodplain in the north of Luk Tei
Tong Village. (b)
Most parts of the Luk Tei Tong (2) River has a flood
protection level of less than 1-in-2 years and it is far too small (1m – 1.5m
wide) for conveying flow during extreme storm events. This is the main cause
of widespread flooding in northern edge of Luk Tei Tong Village which cuts
off the footpaths and isolates houses in floodplain. |
Luk Tei Tong River |
(a)
Luk Tei Tong River is the continuation of a newly
engineered channel that crosses the Mui Wo Marsh. The upstream section of the
river was constructed by the Home Affairs Department under the Rural Planning
and Improvement Strategy (RPIS) Project from in 1998. (b)
The Luk Tei Tong River stretches from the confluence
with the Luk Tei Tong (2) River to the confluence with the Silver River. (c)
Most parts of downstream of Luk Tei Tong River remain
natural and have flood protection of less than 2 years. |
Tai Tei Tong River |
(a)
The downstream of Tai Tei Tong River has a flood
protection level of less than 1-in-10 year. (b)
During heavy rainstorm, floodwater will overflow from
existing rivers and inundate adjacent houses. |
Table 2.2 Summary of Key Continuous Public Involvement
Date |
Subject |
21 May 04 |
Public Consultation with Village Representatives in Mui Wo |
21 May 04 |
Public Consultation with Green Lantau Association |
4 June 04 |
Follow up discussions with DSD to review the proposed works at Tai
Tei Tong |
29 June 04 |
Follow up discussions with DSD to review the proposed works at Tai
Tei Tong |
15 July 04 |
Public Consultation with Village Representatives in Mui Wo |
15 July 04 |
Public Consultation with Green Lantau Association |
29 July 04 |
Joint site inspection with green groups including Green Power and
World Wild Fund to Mui Wo |
3 Aug 04 |
Presentation of the proposed works to green groups |
25 Aug 04 |
Joint site
visit with Green Lantau Association – Proposed Luk Tei Tong (2) River |
25 Aug 04 |
Mui Wo Rural Committee Meeting – Proposed Works in Mui Wo |
18 Oct 04 |
Consultation with Islands District Council |
26 Nov 04 |
Consultation with Village Representatives and Mui Wo Rural Committee |
Table 2.3 Summary of Key Comments/Recommendations from the Public
Concerned Parties |
Key Comments/ Recommendations |
Responses |
Villagers, Village
Representatives and Rural Committee |
(a) The project was supported. (b) To revise the alignment of the proposed river in order to avoid
resuming building lots and houses. (c) The flooding situation at Tai Tei Tong was not severe and agreed to
reduce the scope of works at Tai Tei Tong. |
(a) The alignment of Luk Tei Tong River was revised to avoid resuming
existing building lots and houses. (b) The scope of works at Tai Tei Tong River was reduced from full-scale
training to only improvement of 3 bottlenecks. |
Green groups |
(a) Existing riverbed should be untouched as far as possible. (b) More ecological friendly design should be included. (c) To avoid drawing down the water table at Luk Tei Tong Marsh |
(a) The masonry and grasscrete lining was revised to gabion lining with
planting pits. (b) Natural substrates, pools and riffles will be provided at the
riverbed. (c) The existing river will be untouched and will not be deepened as far
as possible. (d) Shallow but wide section is proposed for the Luk Tei Tong (2) River.
The proposed river channel is only 0.8m deep to avoid drawing down the ground
water table of Luk Tei Tong Marsh. In addition, 200mm high embankment will be
constructed at both sides of the river banks to avoid surface runoff flowing
to the proposed river. (e) Gabion blocks will be provided at the outlets to enhance the
ecological environmental wherever the space is adequate. |
Option E River Training of
Existing Drainage System – To widen and/or
deepen the existing rivers in order to increase the drainage capacity of the
drainage system.
Option F Construction of
Earth Bunds at both sides of Luk Tei Tong (2) River – For the drainage improvement works for Luk Tei Tong (2) River, EPD and
AFCD had advised to consider constructing earth bunds at both sides of the Luk
Tei Tong (2) River in order to contain the floodwater from overflowing to
adjacent area.
Table 2.4 Considerations of Various Drainage Options
Drainage Options |
Environmental Benefit |
Environmental Dis-benefit |
Recommendation |
Reason & Considerations |
Maintenance of existing river |
(a)
The area to be affected by the proposed drainage improvement works
will be the least. (b)
The existing condition of rivers will be improved. For example, the
contaminated soil and waste settled in the river bed will be removed. (c)
The disturbance to the ecological system and water quality in
existing rivers will be of small scale. |
No major environmental dis-benefits are anticipated. |
Not recommended. |
(a) This option can only marginally improve the capacity of the existing rivers. (b) The flood protection level provided is still very low due to the small size of existing rivers. Severe flooding in the areas will continue. |
By-pass channel or box culvert |
(a)
Existing rivers will not be disturbed and there is no disturbance to
the ecological system and water quality in existing rivers. |
Extensive land resumption is required for the construction of by-pass
channel or box culvert. The public will be seriously disturbed. |
By-pass box culvert Pak Ngan Heung River. By-pass channel Luk Tei Tong (2) River |
(a)
The construction of by-pass channel or box culvert will require
extensive land resumption and will impose adverse impact to other areas
further away from the flooding spots. (b)
Along Luk Tei Tong (2) River and Pak Ngan Heung River, most of the
areas are abandoned agricultural lands and marsh. There are sufficient
available space for the construction of the by-pass box culvert and channel.
The diversion scheme is considered feasible and acceptable. Locals and green
groups also accepted the proposal. (c)
The impact to existing marsh at Luk Tei Tong would be minimum by
adopted ecological friendly design details. The existing river will be
untouched. |
Interception and Flood
Storage |
(a)
Existing rivers will not be disturbed and there is no disturbance to
the ecological system and water quality in existing rivers. |
(a)
Extensive land resumption is required for construction of storage
pond or interception channel. (b) Environmental impacts to other areas will
result. The upstream area, which is
mainly composed of dense vegetation area, agricultural land, residential area
and nurseries, will be seriously affected. |
Not recommended |
(a)
This option is also not a cost-effective solution given the large
volume of runoff needed to be stored which results in resumption of large
piece of land for the construction of a large stormwater storage pond. The
plan area of the pond can be reduced by half if the depth of the pond is
increased to 6m. However, a pumping
station is then required for pumping the water away after the storms. The required land resumption is still very
substantial and the objection from public cannot still be avoided. (b)
This option is therefore considered not acceptable. |
Floodwall and Pumping
Station |
(a)
Existing rivers will not be disturbed and there is no disturbance to
the ecological system and water quality in existing rivers. |
(a)
Floodwall has limited scope for improving the aesthetic. The visual
impact is of concerns, in particular, if the floodwall is high. |
Not recommended |
(a)
Floodwall can be constructed along the rivers to contain the floodwater
during extreme rainstorm events.
However, the capacities of the concerned rivers are very low and a
high floodwall of minimum 2m is needed. (b)
The floodwall protection does not provide a long-term solution because
it contains floodwater at a higher water level and causes flooding of the
local drainage systems behind the floodwalls. Flooding in adjacent areas still persists. (c)
To eliminate the severe flooding outside the floodwalls, the
floodwalls are required to be constructed further away from the existing
rivers such that an additional flood plain flow area is allowed for
conveyance of flow during extreme rainstorms. The formation of flood plain
flow area requires substantial land resumption. (d)
Consideration has been given to pumping the surface runoff in the
rivers to the downstream in order to reduce the water level and hence height
of the floodwalls. However, the peak discharges are very substantial and
temporal. It is technically impracticable to pump the peak surface runoff
away without the use of detention pond. (e)
Therefore, this option is not further considered. |
Deepening and Widening of Existing Rivers |
(a)
The existing condition of the rivers will be improved by the proposed
engineering works by applying appropriate ecological friendly design. For
example, Gabion lining with planting pits can enhance the ecological
condition and provide shelter for the river habitats; the contaminated soil
and waste settled in the riverbed will be removed, eroded river bank will be
re-constructed. (b) As the improvement works will be carried out along the existing rivers, it can avoid major resumption of land and environmental impacts in other areas. |
The existing rivers and ecological system will be disturbed. |
River widening ü
Luk Tei Tong River Improve bottlenecks ü
Tai Tei Tong River |
(a)
The prime reason for flooding is that the existing rivers do not have
adequate drainage capacity. The most effective solution is to widen and
deepen the existing rivers. (b)
As the river widening works will be carried out mainly along the
existing rivers, there will be significant reduction of land resumption as
compared to other options. (c)
River widening is more reliable and low cost option to improve the
drainage of rivers compared to the other options. (d)
The channel design should provide an ecological and aesthetical
acceptable solution, taking into account hydraulic performance and operation
requirements of the channel. (e)
Appropriate mitigation measures are required to be implemented such
that the environmental impact is kept to acceptable limit. (f)
This option is recommended and the proposed channels are lined with
gabion block, and natural bed to retain the river ecology, and to improve the
aesthetic, visual and environmental aspect of the river widening works. (g)
For the Pak Ngan Heung River, river widening would affect the
existing shrine and Fung Shui Tree. This area is culturally sensitive and any
change to the shrine and Fung Shui tree at the existing bridge will be
objected by the villager. Besides, one of the reasons for flooding is the
sharp bend of the river near the existing bridge. Widening and deepening
cannot remove the sharp bend and the problem. Therefore, this option is not
recommended to Pak Ngan Heung River. |
Construction of Earth Bunds at both sides of Luk Tei Tong (2) River |
(a) No excavation was required for the affected area except the area covered by the foundation of the earth bunds. (b) The existing river would be untouched. |
(a) Permanent loss of marsh area. (b) Visual impact due to the proposed earth bunds would be substantiated. |
Not recommended |
(a) The earth bunds would occupy substantial area of the marsh area and cause permanent loss of marsh area and associated ecology. (b) The earth bunds would obstruct surface runoff flowing into the existing river and aggravate the flooding situation. (c) Visual impact is of concern. |
Pak Ngan Heung River
Ling Tsui Tau U-Channel
Tai Tei Tong River
Luk Tei Tong (2) River and Luk Tei
Tong River
(a)
Open
Concrete channel
(b)
Trapezoidal
channel with natural bed and grass concrete/masonry side slopes
(c)
Rectangular
drainage channel
(d)
Box
Culvert
(e)
Gabion
Channel with natural substrates
Table 2.5 Summary of Project Elements
Works Programme |
Mid 2006 to Mid
2009 |
||||
Major
Elements in Pak Ngan Heung River and Ling Tsui Tau U-Channel |
|||||
(a) Open
Trapezoidal Channel |
Length = 80m |
Depth = 2.5m – 3.5m
|
Bed width = 8m |
||
|
Gabion walls with rip-rap
bases and natural substrates. |
||||
(b) Rectangular
Channel |
Length = 100m |
Depth = 3m – 3.5m |
|||
|
Rip-rap bedding and
concrete vertical walls of rip-rap bedding |
||||
(c) Diversion Box
Culvert |
Length = 180m |
3 cells 3m(W) x
2m(H) |
|||
(d) U-Channel (Ling
Tsui Tau) |
Length = 200m |
750mm U-channel |
|||
|
|
|
|||
Major
Elements in Luk Tei Tong By-pass Channel |
|||||
(a) Rectangular
Shape |
Length = 350m |
Depth = 0.8m |
Bed width = 14m –
18m |
||
|
A minimum of 200mm high embankment will
be constructed at most of the section of the channel to avoid surface runoff
from existing marsh flowing to the proposed by-pass channel. In order to
match with the downstream Luk Tei Tong river, the height of the embankment
would be gradually
increased to about 1500mm at only the non-sensitive areas. |
||||
(b) Reprovision of
crossings |
2 numbers (1 vehicular
crossing and 1 pedestrian crossing) |
||||
|
|
|
|||
Major
Elements in Luk Tei Tong River |
|||||
(a) Open
Trapezoidal Channel |
Length = 240 |
Depth = 3m |
Bed Width = 3m |
||
|
Gabion walls with
rip-rap bases and natural substrates. |
||||
Major
Elements in Tai Tei Tong |
|||||
(a) River Widening |
3 bottlenecks only |
|
|
||
|
Existing river bed
will be untouched and the bank will be reinstated by gabion blocks. |
||||
(i)
Use natural
bed along the watercourses.
(a)
Riverbeds
should not be lined with concrete. The natural stream bed and substrate should
be retained or recreated.
(b)
Riverbanks
should not be lined with concrete. Soft engineering materials such as
rock-filled gabion should be utilised as far as possible.
(ii)
Retain
and/or recreate natural river channels and water levels.
(a)
Existing
river should be untouched as far as possible and no deepening works is
proposed.
(b)
Consideration
is given to the preservation of meanders and water level management to preserve
river habitats. For example, diversion channels are proposed in the Pak Ngan
Heung River and Luk Tei Tong (2) River. Only during peak flow events would
over-flow from the river be conveyed to the downstream section by passing through
the proposed channel/box culvert. Flow conditions would be maintained in the
meander to preserve existing ecological condition.
(c)
Natural
features of the rivers (such as pool/riffle sequences and meanders) should be
retained or recreated wherever possible.
(iii)
Maintain
water table to minimize the impact to existing riparian life.
(a)
Consideration
is given to maintain water table in the rivers. Minimizing the excavation to
the bottom level of the rivers can maintain water tables. For example, shallow
and wide section of Luk Tei Tong By-pass Channel River is proposed instead of deepening of the river to increase
its hydraulic capacity.
(iv)
Provide
planting of native species along channels
(a)
Tree
preservation and planting near open channel should be considered on a
case-by-case basis.
(b)
Compensatory
planting should be provided to mitigate for the loss of riparian vegetation.
a) Loss of vegetation due to channel re-alignment and excavation works of box culvert
b) Exposed channel bank and bed after channel re-alignment
c) Exposed wall surfaces created by construction of retaining walls and wing walls
d) Creation of flat areas due to backfill of existing channel
a)
Reinstatement
planting by hydroseeding grass seed mix should be provided for the peripheral
disturbed areas during construction. Transplantation of existing trees should
be located in this area. Compensatory planting, using the existing species as
far as possible, should also be provided for any loss of vegetation.
b)
Amenity
planting that generally includes trees, shrubs and ground cover for roadside
planting and woodland planting should be provided along re-provisioned
footpaths and slopes. The proposed species are generally wet-soil tolerated or
adaptable to the site situation, and compatible with the existing vegetation.
Backfilled areas should be planted to enhance the landscape value. For area
above covered box culvert where soil depth is 500 mm, groundcover and
low-growing herbaceous planting is proposed.
c)
Natural
Colonisation for Gabion will take place for the trapezoidal channel banks to minimize the
visual impact, except the channel sections where tidal influence happens at
most of the time that masonry lining would be proposed.
d)
Grasscrete
linings with hydroseeding for low flow diversion dam and ramp.
Hydroseeding mix shall include herbaceous or graminaceous species that are
adaptable to normal or wet soil condition when it is not flooded, or flood tolerant
and suitable for margin of water bodies, or even able to submerge into water.
e)
Channel
bed planting at particular location is proposed so as to mimic the existing
site-specific natural setting. Details are provided under Chapter 7 (Ecological Impact)
of the EIA report.
f)
Exposed
wall surfaces should be finished with masonry to match with existing wall surfaces in
adjacent areas
Table 2.6 Proposed Planting Species
Grasscrete |
Amenity Planting (Roadside & Woodland) |
Bacopa monnieri Centella asiatica Colocasia esculenta Cyperus malaccensis Eleocharis dulcis Eleocharis equisetina Eleocharis spiralis Equisetum debile Eragrastis atrovirens Fimbristylis acuminata Fimbristylis camplanata Hydrocotyle sibthoripioides Juncus effuses Leersia hexandra Lepironia articulata Ludwigia ascendens Phragmites australis Polygonum hydropiper Sagittaria guayanensis |
Acacia confusa (Tree) Acacia mangium (Tree) Albizia lebbek (Tree) Bischofia trifoliate (Tree) Casuarina equisetifolia (Tree) Celtis sinensis (Tree) Cinnamomum camphora (Tree) Eriobotrya japonica (Tree) Ficus hispida (Tree) Ficus microcarpa (Tree) Ficus superba (Tree) Glyptostrobus pensilis (Tree) Litsea glutinosa (Tree) Macaranga tanarius (Tree) Melaleuca leucadendron (Tree) Sapium sebiferum (Tree) Sterculia lanceolata (Tree) Syzygium jambos (Tree) Terminalia catappa (Tree) Thespesia populnea (Tree) Tristania conferta (Tree) Caesalpinia crista (Salt-tolerant Vine) Clerodendrum inerme (Salt-tolerant Shrub) Crinum asiaticum (Salt-tolerant Herb) Vitex rotundifolia (Salt-tolerant Shrub) |
|
Alocasia odorata (Shrub) Calliandra haematocephala (Shrub) Cestrum noctumum (Shrub) Ficus microcarpa ‘Golden leaf’ (Shrub) Gordonia axillaries (Shrub) Lantana spp. (Shrub) Philodendron spp. (Shrub) Rhaphiolepis indica (Shrub) Syngonium spp. (Shrub) Scindapsus aureus (Climber) Wikstroemia indica (Shrub) Centella asiatica
(Herbaceous) Chrysopogon aciculatis
(Herbaceous) Lepironia articulata (Ground cover) Iris tectorum (Herbaceous) Miscanthus floridulus (Herbaceous) Nephrolepis exaltata (Ground cover) Rhapis excelsa (Herbaceous) |
Special
Considerations
(i)
executing
the works in the dry behind temporary bunds, thus minimising the rivers from
potential impact by high levels of suspended solid generated from the disturbed
soil surface; and
(ii)
following
site practice outlined in ProPECC PN 1/94 Construction Site Drainage.
(i)
where
possible, excavation work should be scheduled for the dry season to minimise
the silty water running downstream; and
(ii)
earthworks
should be surrounded by temporary flood protection bunds.
Table 2.7 Summary of Construction Methods and Alternative Consideration
Major Works |
Locations |
Major Activities |
Reasons &
Consideration of alternative method |
River Training |
River widening and
deepening ü
Luk Tei Tong River River widening ü
Luk Tei Tong By-pass Channel ü
Sections of Pak Ngan Heung River |
Earthworks include excavation by mechanical plant;
disposal of excavated soil by dump trucks; and compacting by mechanical
plant. |
It is a common construction method. The impact to
the environment is local and temporary. It can be mitigated by appropriate
measures. It is recommended to
maintain the existing river on one side and to carry out the widening works
on the other side. This can ensure
the river is maintained at any time to minimise the impact. The construction works will be carried out
at dry condition to minimize the adverse effect on the rivers. Working in wet condition inside the rivers
or temporary culverting the rivers are not recommended. |
Retaining Walls, Box
Culvert and Floodwall |
Retaining walls Bottlenecks, inlet, outlet
of rivers, as well as back side of gabion channel Box Culverts ü
Pak Ngan Heung Diversion Box Culvert ü
Crossings at Luk Tei Tong By-pass Channel |
Earthworks include excavation by mechanical plant;
disposal of excavated soil by dump trucks; and compaction by mechanical
plant. |
It is a common construction method. The impact to
the environment can be mitigated by appropriate measures. |
|
Concreting works include formwork erection, reinforcement fixing and
in-situ concreting. Piling works include installation of steel
casings, reinforcement fixing and concreting. |
The walls will be cast in-situ and it is a common
construction technique. Precast unit for the retaining walls and box
culvert is not preferable. As the
size of retaining wall and box culvert is large, it requires a large plant to
handle and install the precast units.
Due to limited space, it is not feasible to transport the precast
units to site for installation. Bored piles are used for the construction of retaining
wall where space is limited.
Percussion and driven piles are not recommended due to noise
generation during construction. |
(b) Impact
to the existing marcsh
at Luk Tei Tong - as agreed with the green group, the construction works
for the proposed Luk Tei Tong By-pass Channel should be carried out in the dry
season. As such, the potential
impact to the existing marsh area at Luk Tei Tong could be minimized.
(c) Cumulative
impacts – in order to minimize the potential impacts to
the existing sensitive receivers and public, the cumulative impacts for the concurrent
projects, as well as those the proposed works under this project have been duly
considered. The Contractor
should be encouraged to programme the construction activities under the
project in such a manner that ongoing activities would should be separated physically as far as
possible from one
another and other
construction sites.
Concurrently
Projects in the Vicinity |
Programme |
Outlying Sewerage Stage 2 – Mui Wo Village
Sewerage (Package 1A) |
Late 05
to Mid 07 |
Construction
of Emergency Vehicular Access and Sewerage Works at Luk Tei Tong, Mui Wo |
Late 04
to Late 06 |