4.1.1
This section
presents an assessment of potential noise impact associated with the
construction of the proposed drainage improvement works at Pak Ngan Heung River,
Tai Tei Tong River, Luk Tei Tong River and Luk Tei Tong By-pass Channel. The key noise issue during the construction
phase would be the use of powered mechanical equipment for various construction
activities of the Project. Appropriate
mitigation measures have been recommended, where necessary, to minimize the
potential noise impacts.
4.2.1
Noise impacts
were assessed in accordance with the criteria and methodology given in the Technical
Memoranda (TM) under the Noise Control Ordinance (NCO) and the Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM) under the Environmental
Impact Assessment Ordinance (EIAO).
4.2.2
The NCO
provides the statutory framework for noise control. This defines statutory limits
applicable to equipment used during the construction phase of the proposed
works in the study area. The NCO invokes four Technical Memoranda, which
defines the technical means for noise assessment:
·
Technical Memorandum on Noise from Places other than
Domestic Premises, Public Places or Construction Sites (IND-TM);
·
Technical Memorandum on Noise from Construction Work in
Designated Areas (DA-TM);
·
Technical Memorandum on Noise from Construction Work
other than Percussive Piling (GW-TM); and
·
Technical Memorandum on Noise from Percussive Piling
(PP-TM).
4.2.3
Under the
GW-TM, noise from construction activity is not restricted during the period
0700 - 1900 hours on weekdays, except Public Holidays. However, the EIAO-TM identifies a daytime
general construction noise limit of 75 dB(A) Leq (30 minutes) for
domestic premises and Leq(30min) 70dB(A) for schools during normal hours
(65dB(A) during examination) and all other sensitive areas where unaided voice
communication is required. This
standard was used as assessment criteria in the construction noise assessment
during daytime.
4.2.4
Between 1900
and 0700 hours and all day on Sundays and public holidays, activities involving
the use of powered mechanical equipment (PME) for the purpose of carrying out
construction work are prohibited unless a Construction Noise Permit (CNP) has
been obtained. A CNP may be granted provided that the Acceptable Noise Level
(ANL) for the noise sensitive receivers (NSRs) can be complied with. ANLs are
assigned depending upon the Area Sensitive Rating (ASRs). The corresponding
basic noise levels (BNLs) for evening and night-time periods are given in Table 4.1.
Table 4.1 Construction
Noise Criteria for Activity other than Percussive Piling
Time
Period
|
Basic
Noise Level (BNLs) (dB(A))
|
ASR A
|
ASR B
|
ASR C
|
Evening
(1900 to 2300 hours) (1)
|
60
|
65
|
70
|
Night (2300 to 0700 hours)
|
45
|
50
|
55
|
Note: (1)
includes Sundays and Public Holidays during daytime and evening
4.2.5
According to the
preliminary construction programme, all the proposed construction works would
be carried out during non-restricted hours. In case of any construction
activities during restricted hours, it would be the Contractor’s responsibility
to ensure compliance with the NCO and the relevant TM. The Contractor will be
required to submit CNP application to the Noise Control Authority and abide by
any conditions stated in the CNP, should one be issued.
4.2.6
Based on the
preliminary design information, percussive piling would not be adopted for the
proposed Project. Therefore, noise criteria as stipulated in the PP-TM would
not be applicable to this Project.
4.2.7
In this
regard, noise impacts associated with the construction of the proposed Project
would primarily be assessed against the noise criteria set out in Table 1B of
Annex 5 of the EIAO-TM.
4.3.1
The sites for
the proposed drainage improvement works at Pak Ngau Heung River, Tai Tei Tong
River, Luk Tei Tong River and Luk Tei Tong By-pass
Channel are located in Mui Wo,
South Lantau. The sites are generally
rural in nature, and mainly comprises village houses and agricultural land.
Village establishments including Tai Tei Tong, Ma Po Tsuen, Ling Tsui Tau Tsuen,
Luk Tei Tong and Ha Tsuen Long Luk Tei Tong were identified in the vicinity of
the work areas.
4.3.2
Based on the
survey maps and site visits conducted in December 2003, there was no major
noise source found within or in the vicinity of the sites. The dominant noise
sources arise from human activities and road traffic along some local access
roads.
4.4.1
In accordance with the Mui Wo Fringe Outline Zoning Plan (OZP) No. S/I-MWF/3, the land uses to the surrounding areas of the Project were zoned as Residential
Group D (“R(D)”), Open Space(“O”), Village (“V”), Government/ Institution
/Community (“G/IC”), Recreation (“REC”) and Agriculture (“AGR”). At the time of this EIA study, no
information about the development schedule and details of the areas zoned as
“R(D)” and “V” was available. Hence, no futher/planned NSR within these areas
was identified for the construction noise assessment.
4.4.2
To represent
the worst-case scenario, a number of existing NSRs in the vicinity of the
proposed drainage works, have been designated for the assessment. Table
4.2 summarizes the representative NSRs for the noise impact
assessment. Locations of the
representative NSRs are shown in Figure
4.1.
Table 4.2 Summary
of Representative Noise Sensitive Receivers
NSR
|
Location
|
Use
|
No of
Storeys
|
Distance
(m)*
|
Pak Ngau Heung River
|
PNH1
|
No. 22 Village House, Tai Tei Tong
|
Residential
|
3
|
4
|
PNH2
|
No. 1 Village House adjacent to Pak
Ngau Heung River
|
Residential
|
2
|
5
|
PNH3
|
No. 10 Village House adjacent to
Pak Ngau Heung River
|
Residential
|
2
|
4
|
PNH4
|
Village House, Ling Tsui Tau Tsuen
|
Residential
|
1
|
4
|
PNH5
|
No. 6 Village House adjacent to Pak
Ngau Heung Outlet
|
Residential
|
3
|
6
|
PNH6
|
Village House, Ling Tsui Tau Tsuen
|
Residential
|
2
|
2
|
LT1
|
Village House, Ling Tsui Tau Tsuen
|
Residential
|
2
|
17
|
LT2
|
No. 75 Village House, Ling Tsui Tau
Tsuen
|
Residential
|
1
|
1
|
Tai Tei Tong River
|
TTT1
|
No. 25 Village House, Ma Po Tsuen
|
Residential
|
2
|
27
|
TTT2
|
No. 27 Village House, Ma Po Tsuen
|
Residential
|
2
|
45
|
TTT3
|
No. 23 Village House adjacent to
Tai Tei Tong River
|
Residential
|
3
|
4
|
TTT4
|
No. 10 Village House adjacent to
Tai Tei Tong River Outlet
|
Residential
|
2
|
5
|
SCH
|
Mui Wo Shcool
|
Education
|
1
|
17
|
Luk Tei Tong River and Luk
Tei Tong By-pass Channel
|
LTT1
|
No. 135 Village House, Luk Tei Tong
|
Residential
|
3
|
1
|
LTT2
|
No. 19 Village House, Luk Tei Tong
|
Residential
|
2
|
15
|
LTT3
|
No. 36 Village House, Luk Tei Tong
|
Residential
|
3
|
32
|
LTT4
|
No. 4 Village House adjacent to Luk
Tei Tong River Outlet
|
Residential
|
3
|
1
|
Note: * Horizontal
Separation from nearest site boundary (m)
4.5.1
Noise impact
associated with the construction activities of the Project was assessed using
the standard acoustic principles and the methodology outlined in the GW-TM
issued under the NCO as well as the guideline given in Annex 13 of the EIAO-TM.
4.5.2
Prior to the
appointment of the Contractor, exact number and type of construction plant to
be adopted for the construction activities are not available. For the purpose of the assessment, a
preliminary equipment inventory (Appendix 4.1) has been assumed based on
typical construction activities of similar projects.
4.5.3
Sound power
levels (SWLs) of the PME in Appendix 4.1 were taken from Table 3 of the GW-TM. Where no sound
power level (SWL) was given in the GW-TM, reference was made to BS 5228: Part 1:1997 Noise and Vibration
Control on Construction and Open Sites.
4.5.4
In order to
provide more realistic calculations of the construction noise levels,
reasonable on-time percentage of each PME (the time when the PME is in
operation within a 30 minutes time slot) was made. Table 4.3 summarizes the on-time percentage of the PME.
Table 4.3 On-time
Percentage Assumptions of PME
PME
|
Assumed on–time %
|
Assumed
On-time Percentage for All Construction Tasks Except Construction of
Retaining Wall at Pak Ngan Heung Outlet (CH250-300) and Luk Tei Tong River
Outlet (CH195-225)
|
Generator, Drainage Pump and Mini-Excavator
|
100%
|
Systemised Piling Machinery
|
80%
|
Excavator/Loader, Roller, Concrete Lorry Mixer, Vibratory
Poker, Bar and Bender/Cutter, Crane, Osciallator, Power Rammer, Compactor
Rammer, Grout Mixer and Grout Pump
|
70%
|
Dump truck, Hydraulic Breaker
|
50%
|
Assumed On-time Percentage for Construction of Retaining
Wall at Pak
Ngan Heung Outlet (CH250-300) and Luk Tei Tong River Outlet (CH195-225)
|
Generator and Drainage Pump
|
100%
|
Concrete Lorry Mixer, Vibratory Poker, Bar and
Bender/Cutter, Crane,
|
70%
|
Power Rammer
|
50%
|
4.5.5
The assumed construction
plant inventory for unmitigated and mitigated scenarios of various construction
activities and the percentage on-time were confirmed by the project proponent
as practicable and reasonable for completing the project within the scheduled
construction programme based on the information available at this stage.
4.5.6
All items of
PME were assumed to be located at a notional or probable source position of the
segment where each activity would be undertaken. Notional noise sources for different construction areas were
assumed in accordance with the GW-TM.
According to Section 2.11 of the GW-TM,
a positive correction of 3 dB(A) for acoustic reflection has been applied to
the predicted noise levels in order to account for the façade effect at each
representative NSR.
4.5.7
The
assessment was based on the cumulative SWL of PME likely to be used for each
location, taking into account the construction period in the vicinity of the
receiver location. To predict the noise
level, PME was divided into groups required for each discrete construction
activity. The objective was to identify
the worst-case scenario representing those items of PME that would be in use
concurrently at any given time. The sound pressure level (SPL) of each
construction task at NSRs was calculated, depending on the number of plants,
their frequency of operation, and their distance from receivers. The noise levels at NSRs were then predicted
by adding up the sound pressure level of all concurrent construction tasks.
4.5.8
Construction
activities, within 300m of a given NSR at the same period, were considered to
contribute to the cumulative impact at that NSR. Noise sources from the areas greater than this distance were
excluded from the assessment.
4.6.1
The potential
source of noise impact during the construction phase of the Project would be
the use of PME for various construction activities. As indicated in the
preliminary construction programme (Appendix
2.2 refers), the construction of the proposed Project would last from June
2006 to June 2009. The major construction activities for the proposed drainage
works include:
·
Site
clearance
·
Excavation
·
Retaining
wall
·
Backfilling/Channel
lining
·
Box
culvert
·
Low
flow diversion pipes and bund
·
U-channel
construction
4.6.2
The proposed
drainage works would mostly be carried out within a linear construction site.
Construction equipment and activities would be moving along the channel
sections as the construction proceeds. Since some of the identified sensitive
receivers are in close proximity to the proposed work sites, adverse
construction noise impacts would be expected at these receivers if no noise
control measures are implemented.
4.6.3
As indicated
in Section 2.10, construction of the Project would likely interface with the
following projects:
Projects
in the Vicinity
|
Anticipated
Construction Programme
|
Outlying Sewerage Stage 2 – Mui Wo Village
Sewerage (Package 1A)
|
Late 05
to Mid 07
|
Construction
of Emergency Vehicular Access (EVA) and Sewerage Works at Luk Tei Tong, Mui
Wo
|
Late 04
to Late 06
|
4.6.4
As indicated
above, the construction of EVA and sewerage works at Luk Tei Tong would likely coincide
with this Project during the period of mid to late 2006. However, it is expected that, the major
construction works of the EVA and sewerage works at Luk Tei Tong would have
been finished substantially prior to the start of the proposed drainage improvement
works under the Project and only minor construction works would remain during
the coincidence period. As such, adverse cumulative noise impact from the
construction works of this concurrent project would not be anticipated.
4.6.5
The proposed
sewerage works under the Mui Wo Village Sewerage would take place in the
vicinity of the Pak Ngan Heung River and would likely coincide with the
proposed drainage improvement works under the Project from mid 2006 to mid
2007. In order to investigate the
potential cumulative noise impact associated with the construction activities
of this concurrent project, a cumulative noise assessment was carried out based
on the latest available information (Section 4.9).
4.7.1
As
illustrated in the preliminary construction programme, various construction
activities of the Project would be carried out concurrently during a particular
period.
4.7.2
Based
on the preliminary construction programme and the plant inventory (Appendix 4.1), unmitigated cumulative
noise impact arising from different construction activities of the Project on
the representative NSRs have been predicted.
4.7.3
The
predicted construction noise levels for the unmitigated scenario at the
representative NSRs are given in Appendix 4.2 A and Table 4.4 below. A sample calculation of construction noise level
for the unmitigated scenario is provided in Appendix 4.2.
Table 4.4 Summary
of Unmitigated Construction Noise Levels During Normal Daytime Working Hours
|
Predicted
Noise Levels, dB(A)
|
EIAO-TM
Normal Daytime Construction Noise Criteria, dB(A)
|
Pak Ngau Heung River
|
PNH1
|
69
|
-
|
92
|
75
|
PNH2
|
74
|
-
|
93
|
75
|
PNH3
|
71
|
-
|
93
|
75
|
PNH4
|
71
|
-
|
100
|
75
|
PNH5
|
69
|
-
|
97
|
75
|
PNH6
|
68
|
-
|
90
|
75
|
LT1
|
71
|
-
|
88
|
75
|
LT2
|
68
|
-
|
100
|
75
|
Tai Tei Tong River
|
TTT1
|
62
|
-
|
79
|
75
|
TTT2
|
62
|
-
|
77
|
75
|
TTT3
|
62
|
-
|
88
|
75
|
TTT4
|
67
|
-
|
85
|
75
|
SCH
|
66
|
-
|
79
|
70 (School
during normal hours)
65 (School
during examination hours)
|
Luk Tei Tong River and Luk
Tei Tong By-pass Channel
|
LTT1
|
62
|
-
|
90
|
75
|
LTT2
|
62
|
-
|
86
|
75
|
LTT3
|
63
|
-
|
83
|
75
|
LTT4
|
65
|
-
|
96
|
75
|
4.7.4
The
assessment results showed that the predicted cumulative noise levels at the
representative NSRs would range from 62 to 100 dB(A), exceeding the noise
criteria by 1 - 25 dB(A) without mitigation measures. Mitigation measures would therefore be required to abate the
construction noise impacts.
Good
Site Practices
4.8.1
Although the
noise mitigation effects are not quantifiable and the benefits may vary with
site conditions and operation conditions, good site practices and noise
management measures are easy to implement and do not impact upon the work
schedule. The following site practices should be followed during the
construction phase:
·
Only well-maintained plant should be operated on-site
and plant should be serviced regularly during the construction programme;
·
Silencers or mufflers on construction equipment should
be utilized and should be properly maintained during the construction
programme;
·
Mobile plant, if any, should be sited as far from NSRs
as possible;
·
Machines and plant (such as trucks) that may be in
intermittent use should be shut down between work periods or should be
throttled down to a minimum;
·
Plant known to emit noise strongly in one direction
should, wherever possible, be orientated so that the noise is directed away
from the nearby NSRs; and
·
Material stockpiles and other structures should be
effectively utilised, wherever practicable, in screening noise from on-site
construction activities.
Adoption
of Quiet Plant
4.8.2
The
use of quiet PME was considered to be a practicable means to abate the
potential construction noise impact. The Contractor would be able to obtain
particular models of plant that are quieter than the PME given in GW-TM. The
noise reduction achieved in this way will depend on the Contractor’s chosen
construction methods and it is considered that specifying particular plant
models would be too restrictive to Contractor’s preferred construction methods.
Hence, it is preferable and practical to specify the overall noise performance
specification of all plant on site in terms of the total SWL so that the
Contractor is allowed some flexibility to select plant to suit his needs.
4.8.3
In
this assessment, the recommended silenced PME are taken from the BS5228: Part
1:1997, which are known to be used in Hong Kong. It should be noted that
various types of quiet PME are commercially available in Hong Kong and have
been used in other designated projects. The SWL for the quiet PME adopted are
summarized in Table 4.5 below.
Table 4.5 Sound
Power Levels for Quiet PME
Quiet PME adopted
|
SWL, dB(A)
|
Reference
|
Excavator/Loader
|
105
|
BS 5228 Table C3,
item 97
|
Dump truck
|
103
|
BS 5228 Table C9,
item 39
|
Vibratory roller
|
96
|
BS 5228 Table C8,
item 25
|
Concrete lorry
mixer
|
100
|
BS 5228 Table C6,
item 23
|
Vibratory poker
|
98
|
BS 5228 Table C6,
item 40
|
Crane
|
101
|
BS 5228 Table C7,
item 114
|
Hydraulic Breaker
|
110 /106
|
BS 5228 Table C8,
item 13 and item 12
|
Generator
|
95
|
CNP103
|
4.8.4
Noise
reduction is anticipated with the use of the quiet PME (Appendix 4.3).
However, the predicted construction noise levels at some NSRs during certain
construction stages would not comply with the EIAO-TM noise criteria. Therefore,
further noise mitigation measures would be required for those affected NSRs.
Use
of Movable Noise Barrier and Temporary Noise Barrier
4.8.5
The use of
noise barriers would be an effective means to alleviate the noise impact
arising from the construction works, particularly for low-rise NSRs. Based on the site survey, all the NSRs
within the Assessment Area are low-rise in nature with 1-3 storeys. In addition, the majority of the channel
construction works would be undertaken below the ground levels of the
NSRs. As such, a 2.4m high
purpose-built site hoarding (with a superficial density of at least 7kg/m2,
and free from gaps/openings) could screen their sensitive façade from viewing
the ground-level construction equipment within the site. However, it should be noted that the
practicality of using temporary noise barriers would depend on whether there
would be sufficient space available.
Owing to site constraints, the use of temporary noise barrier would not be
practicable for all areas. In view of
the site conditions, only the works areas near NSRs PNH 4, PNH5 and LTT4 are
considered feasible to erect temporary noise barriers (Figure 4.2). Based on the assessment result, the noise
exceedances are attributable to the construction of retaining wall located less
than 15m from these NSRs. The proposed
temporary noise barriers as shown in Figure 4.2 would be designed to
have sufficient length to shield the line of site of the NSRs PNH 4, PNH5 and
LTT4 from the construction of retaining wall within 15m. With the implementation of the temporary
noise barrier, a 10 dB(A) noise reduction was assumed.
4.8.6
For the works
areas where it would not be feasible to erect temporary noise barriers, movable
noise barriers are recommended.
According to the GW-TM, a movable noise barrier with a cantilevered
upper portion located above the noise generating part of the PME could reduce
noise by 5 dB(A) or up to 10 dB(A), depending on the line of sight that could
be blocked by the barriers when viewed from the NSR. Depending on the size of
the PME, the dimension of the movable noise barrier will be designed by the
Contractor with a view to blocking the line of sight. Barrier material of
surface mass in excess of 7 kg/m2 is recommended to achieve the
maximum screening effect. The design of the movable barriers should be
certified by the Environmental Team (ET) Leader and verified by the Independent
Environmental Checker (IEC) to ensure the intended noise reduction
effectiveness can be achieved. Table
4.6 summarises the use of movable noise barrier and noise reduction for
certain items of PME. Appendix 4.4
provides the total SWL for various construction noise activities with the
adoption of quiet PME and movable noise barriers.
Table
4.6 Movable Noise Barrier
for Certain Items of PME
Construction Task
|
PME for which Movable
Barrier is Adopted
|
Barrier Correction, dB(A)
|
Site
Clearance
|
|
Excavator
|
5
|
Excavation
|
|
|
5
|
|
|
Backfilling/Channel lining
|
|
Excavator
and Concrete Lorry Mixer
|
5
|
|
|
Vibratory
Poker
|
10
|
Box Culvert
|
Piling
|
Oscillator
|
10
|
|
Earthworks
|
|
5
|
|
|
|
10
|
|
Reinforcement Fixing /
Concrete operations
|
Crane
and Concrete Lorry Mixer
|
5
|
|
|
Vibratory
Poker and Bar Bender/Cutter
|
10
|
|
Backfilling
|
|
5
|
Low Flow Diversion Pipes
and bund
|
|
Crane
and Concrete Lorry Mixer
|
5
|
|
|
Vibratory
Poker and Bar Bender/Cutter
|
10
|
U-Channel Construction
|
|
|
5
|
|
|
|
10
|
Gabion Channel
|
|
Excavator
|
5
|
|
|
Vibratory
Roller, Generator and Drainage Pump
|
10
|
Widening of Bottleneck
|
|
Excavator
|
5
|
|
|
Generator
and Drainage Pump
|
10
|
Retaining Wall-L/T Shape
|
|
Crane
and Concrete Lorry Mixer
|
5
|
|
|
Power Rammer, Vibratory
Poker, Bar Bender/Cutter, Generator and Drainage Pump
|
10
|
Retaining Wall-Mini Bored
Pile Wall
|
Installation of Temporary
Works
|
Crane
|
5
|
|
|
Systemised Pilling
Machinery, Generator, Drainage Pump, Grout Mixer, Grout Pump and Vibratory
Poker,
|
10
|
|
Earth Wall
|
|
5
|
|
|
|
10
|
|
Reinforcement
Fixing/Concrete Operations
|
Concrete
Lorry Mixer
|
5
|
|
|
Generator, Drainage Pump
Vibratory Poker and Bar Bender/Cutter
|
10
|
4.8.7
With the adoption
of the quiet PME and temporary/movable noise barriers, the mitigated noise
levels have been predicted and are summarised in Appendix 4.5 A and Table
4.7. A sample calculation of
construction noise levels for mitigated scenario is presented in Appendix 4.5.
Table 4.7 Summary
of Mitigated Construction Noise Levels During Normal Daytime Working Hours (Use
of Quiet PME and Temporary/Movable Noise Barriers)
NSR
|
Predicted
Noise Levels, dB(A)
|
EIAO-TM
Normal Daytime Construction Noise Criteria, dB(A)
|
Mitigation
Measures Proposed
|
Pak Ngau Heung River
|
|
|
PNH1
|
52
|
-
|
75
|
75
|
Use of Quiet PME and Movable Barrier
|
PNH2
|
57
|
-
|
75
|
75
|
Use of Quiet PME and Movable Barrier
|
PNH3
|
55
|
-
|
75
|
75
|
Use of Quiet PME and Movable Barrier
|
PNH4
|
49
|
-
|
78
|
75
|
Use of Quiet PME and Temporary Noise Barrier
|
PNH5
|
48
|
-
|
75
|
75
|
Use of Quiet PME and Temporary Noise Barrier
|
PNH6
|
50
|
-
|
74
|
75
|
Use of Quiet PME and Movable Barrier
|
LT1
|
54
|
-
|
71
|
75
|
Use of Quiet PME and Movable Barrier
|
LT2
|
51
|
-
|
74
|
75
|
Use of Quiet PME and Movable Barrier
|
Tai Tei Tong River
|
|
|
TTT1
|
46
|
-
|
65
|
75
|
Use of Quiet PME and Movable Barrier
|
TTT2
|
49
|
-
|
63
|
75
|
Use of Quiet PME and Movable Barrier
|
TTT3
|
47
|
-
|
74
|
75
|
Use of Quiet PME and Movable Barrier
|
TTT4
|
50
|
-
|
72
|
75
|
Use of Quiet PME and Movable Barrier
|
SCH
|
52
|
-
|
65
|
70 (during
normal hours)
65 (during examination)
|
Use of Quiet PME and Movable Barrier
|
Luk Tei Tong River and Luk
Tei Tong By-pass Channel
|
|
LTT1
|
49
|
-
|
75
|
75
|
Use of Quiet PME and Movable Barrier
|
LTT2
|
46
|
-
|
72
|
75
|
Use of Quiet PME and Movable Barrier
|
LTT3
|
47
|
-
|
68
|
75
|
Use of Quiet PME and Movable Barrier
|
LTT4
|
47
|
-
|
75
|
75
|
Use of Quiet PME and Temporary Noise Barrier
|
4.8.8
The results
indicate that due to the very close proximity to the work sites, NSR PNH4 would
be exposed to noise levels in exceedance of the noise criterion even with the
implementation of all the recommended mitigation measures.
4.8.9
Based on the
results, the exceedance is due to the close proximity of NSR PNH4 (around 5 m)
to the worksite of the retaining wall located at the Pak Ngau Heung River
outlet. In order to further alleviate
the noise impacts from the proposed drainage improvement works, the use of
other possible mitigation measures have been considered and are discussed in
the following sections.
Other
Possible Mitigation Measures
4.8.10 The possible mitigation measures to further
reduce the noise impacts may include:
Use of Acoustic Enclosure
4.8.11 In accordance with the EPD’s “A Practical Guide
for the Reduction of Noise from Construction Works”, an acoustic enclosure with
the inside lined with sound absorbing material can achieve a noise reduction of
up to 20 dB(A). Nevertheless, it should
be noted that the viability of using acoustic enclosure would largely depends
on whether there would be sufficient space available and size of the PME. Since
the work area of construction of retaining wall at the Pak Ngau Heung River
outlet would be very close (about 5m) to NSR PHN4 and the use of large PME such
as hydraulic breaker, erection of acoustic enclosure/shed was considered not
feasible. Instead, a temporary noise
barrier has been proposed to be erected in front of NSR PHN4 (Section 4.5.8
refers).
Manual Working
4.8.12 For areas where noise exceedances were
predicted, the use of manual working (i.e. use of hand tools) has been
considered. Adoption of manual working could eliminate noise impact arising
from the use of PME. However, this method would be slow and require more
manpower in comparison with the method using PME and its practicability would
depend on the nature of the works. In view of the work nature, manual working
was considered not feasible for the construction of retaining wall, which would
inevitably require the use of PME such as hydraulic breaker, pilling machine
and excavator.
Re-scheduling of Works
4.8.13 Re-scheduling of works has been considered
to ameliorate the residual impact.
However, based on the results, the noise exceedance is only due to
construction of retaining wall at Pak Ngau Heung River outlet. Therefore,
rescheduling of work was considered not applicable.
4.8.14 It is considered that all practicable
mitigation measures have been exhausted and this unavoidable noise impact would
be short-term (around four weeks) and localized.
4.9.1
As mentioned
in Section 4.6.5, the
construction of the proposed sewerage work under the Mui Wo Village Sewerage
would be between late 2005 and mid 2007.
Cumulative noise impacts from the construction works of this concurrent
project and this project is therefore expected between mid 2006 to mid
2007. Worst affected NSRs located in
the vicinity of the work sites of the Mui Wo Village Sewerage, i.e. PNH4, PNH5,
PNH6 and LTT4 were selected to check the cumulative construction noise
impacts.
4.9.2
It should be
noted that the implementation of this concurrent project would be subject to
the on-going review by relevant project proponent and details of construction
programme and plant inventory were not available at this stage. The cumulative noise assessment was
therefore conducted based on the following assumptions:
·
The sewerage works of the concurrent
project would be divided into three areas (Areas A, B and C) as shown in Drawing No. Appendix 4.6.
·
Sewerage works in Areas A, B and C
would be constructed from October 2005 to May 2006, June 2006 to December 2006
and January 2007 to July 2007, respectively.
Hence, only the works in Areas B and C would overlap with the Project.
·
Maximum SWL for the concurrent project
was estimated by the assumption that the nearest residential NSRs to the
worksites of the sewerage works would comply with the noise criterion of 75
dB(A).
4.9.3
Based on the
above assumptions, the cumulative construction noise levels from this Project
and the Mui Wo Village Sewerage were calculated and are presented in Appendix 4.6.
4.9.4
The results
indicate that the cumulative construction noise levels from the Mui Wo Village
Sewerage and the Project at all NSRs would comply with the noise criteria of 75
dB(A) throughout the overlapping period, except NSR PNH4. The exceedances at NSR PNH4 are attributable
to the construction of the retaining wall at Pak Ngau Heung River outlet under
the Project. Based on the calculation,
no adverse cumulative construction noise impact from the Mui Wo Village
Sewerage would be anticipated.
4.10.1
No residual
noise impacts would be expected, except the short-term residual impacts at NSR
PNH4 during the construction of the retaining wall at Pak Ngau Heung River
outlet. Residual impacts of about
3dB(A) were predicted at NSR PNH4 even with the implementation of all
practicable noise mitigation measures. It should be noted that the construction
noise assessment results presented in Appendix 4.5A were based on the worst
case scenario where the notional noise sources were assumed. It is therefore
envisaged that the actual exceedances would be limited only to time period when
the construction work is being carried out adjacent to the NSR PNH4 (within a radius
of about 15m). As estimated by the Engineer, the residual impact would last for
around four weeks. In sum, the residual noise impacts are short-term and
localised, and are considered minimised compared with the overall benefits of
the drainage improvements to the area.
4.11.1
An
Environmental Monitoring and Audit (EM&A) programme is recommended to be
established according to the predicted occurrence of noisy activities. All the recommended
mitigation measures should be incorporated into the EM&A programme for
implementation during the construction phase.
Details of the EM&A programme are provided in a stand-alone EM&A
Manual.