6.1.1
This section identifies the types of
wastes that are likely to be generated during the construction of the drainage
improvement works for the Pak Ngan Heung River, Tai Tei Tong River, Luk Tei Tong
River and Luk Tei Tong By-pass
Channel (2) River and evaluates the potential
environmental impacts that may result from the handling and disposal of these
waste arisings. The main solid waste management implications are related to
excavated material from earthworks for the river improvement works. Mitigation measures and good site practices,
including waste handling, storage and disposal have been recommended with
reference to the applicable waste legislation and guidelines.
6.2.1
The following legislation relates to
the handling, treatment and disposal of wastes in the Hong Kong SAR and was
used in assessing potential impacts:
· Waste Disposal Ordinance (Cap. 354);
· Waste Disposal (Chemical Waste)
(General) Regulation (Cap. 354);
· Land (Miscellaneous Provisions)
Ordinance (Cap. 28);
·
Public Health and Municipal Services
Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation;
and
· Dumping At Sea Ordinance (Cap. 466).
Waste Management
6.2.2
The Waste Disposal Ordinance
(WDO) prohibits the unauthorised disposal of wastes. Construction waste is not directly defined in the WDO but is
considered to fall within the category of “trade waste”. Trade waste is defined as waste from any
trade, manufacturer or business, or any waste building, or civil engineering
materials, but does not include animal waste.
Under the WDO, wastes can be disposed of at sites licensed by the
Environmental Protection Department (EPD).
6.2.3
Under the regulation of WDO, the Chemical
Waste (General) Regulation 1992 provides regulations for chemical waste
control, and administers the possession, storage, collection, transport and
disposal of chemical wastes. The EPD has
also issued a ‘guideline’ document, the Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes (1992), which details how the
Contractor should comply with the regulations on chemical wastes.
6.2.4
The Public Cleansing and Prevention of
Nuisances Regulation provides control on illegal tipping of wastes on
unauthorised (unlicensed) sites.
Construction and
Demolition (C&D) Materials
6.2.5
The current policy related to the
dumping of C&D material([1])
is documented in the Works Branch Technical Circular No. 2/93, ‘Public Dump’. Construction and demolition materials that
are wholly inert, namely public fill, should not be disposed of to landfill,
but taken to public filling areas which usually form part of reclamation schemes. The Land (Miscellaneous Provisions)
Ordinance requires that dumping licences are obtained by individual or
companies who deliver public fill to public filling areas. The licences are issued by the Civil
Engineering and Development Department
(CEDD) under
delegated powers from the Director of Lands.
6.2.6
In addition
to the Works Branch Technical Circular (WBTC), EPD and CEDD have produced a leaflet titled ‘New Disposal Arrangements for
Construction Waste’ (1992) which states that C&D material with less than
30% by weight of inert material (that is, public fill) will be accepted at
landfill. If the material contains more
than 30% inert material, the waste must be sorted with suitable material and
sent to public filling area and the non-inert material (that is, C&D waste)
sent to landfill for final disposal.
6.2.7
Measures have been introduced under Environment,
Transport and Works Bureau (ETWB) TCW No. 33/2002 to enhance the management
of C&D material including rock, and to minimize its generation at
source. The enhancement measures
include: (i) drawing up a Construction and Demolition Material Management Plan
(C&DMMP) at an early design stage to minimize C&D material generation;
(ii) vetting of the C&DMMP prior to upgrading of the project to Category A
in the Public Works Programme; and (iii) providing the contractor with
information from the C&DMMP in order to facilitate him in the preparation
of the Waste Management Plan (WMP) and to minimize C&D material generation
during construction. Projects
generating less than 50,000m3 C&D material or importing less
than 50,000m3 fill material are exempt from the
C&DMMP. A new technical circular
ETWB TCW 15/2003 was recently issued to introduce additional measures to
enhance waste management on construction sites. The circular sets out the policy and procedures requiring
contractors to prepare and implement an enhanced WMP to encourage on-site
sorting of C&D material and to minimize their generation during the course
of construction.
6.2.8
The ETWB TCW No. 34/2002 sets out the
management framework for dredged/excavated sediment. This Technical Circular outlines the procedures to be followed in
assessing and classifying sediment and explains the marine disposal arrangement
for the classified material. The
sediment quality criteria for the classification of sediment are presented in Table
6.1. Dumping permits from EPD are required for marine disposal of
dredged/excavated materials.
General
6.3.1
The methodology for assessing potential
waste management impacts during the construction phase of the Project included
the following tasks:
·
estimation
of the types and quantities of wastes to be generated as a result of
construction activities;
·
assessment
of potential impacts from the management of solid wastes with respect to
potential hazards, air and odour emissions, noise and wastewater discharges;
·
evaluation
of the opportunities for reducing waste generation;
·
identification
of disposal options for each type of waste; and
·
assessment
of impacts on the capacity of waste collection, transfer and disposal
facilities.
Excavated Riverbed
Material
6.3.2
A sediment quality characterization
survey was carried out in December 2003 to characterize the level of
contamination in the riverbed material of Pak Ngan Heung River, Tai Tei Tong
River, Luk Tei Tong River and Luk Tei Tong (2) River for the purpose of this
EIA. The works comprised collecting
samples at a total of seven locations within the three river channels for
chemical testing (Figure 6.1).
The methodology for the sampling and laboratory testing of the riverbed
samples was agreed with EPD prior to the commencement of the survey.
6.3.3
The riverbed samples were tested in
the laboratory for the following parameters:
(i)
Metals concentrations including chromium (Cr), copper (Cu),
mercury (Hg), lead (Pb), cadmium (Cd), nickel (Ni), zinc (Zn), silver (Ag) and
arsenic (As).
(ii)
Concentrations
of organic compounds: total polychlorinated biphenyls (PCBs) and polyaromatic
hydrocarbons (PAHs).
6.3.4
The chemical contaminant criteria
under the management and classification system for excavated material destined
for marine disposal are listed in Table 6.1 below.
Table 6.1 Sediment Quality Classification Criteria
Contaminants
|
LCEL
|
UCEL
|
Heavy
Metal (mg/kg dry weight)
|
Cadmium
(Cd)
|
1.5
|
4
|
Chromium
(Cr)
|
80
|
160
|
Copper
(Cu)
|
65
|
110
|
Mercury
(Hg)
|
0.5
|
1
|
Nickel
(Ni)
|
40
|
40
|
Lead
(Pb)
|
75
|
110
|
Silver
(Ag)
|
1
|
2
|
Zinc
(Zn)
|
200
|
270
|
Metalloid
(mg/kg dry weight)
|
Arsenic
|
12
|
42
|
Organic-PAHs
(µg/kg dry weight)
|
PAHs
(Low Molecular Weight)
|
550
|
3160
|
PAHs
(High Molecular Weight)
|
1700
|
9600
|
Organic-non-PAHs
(µg/kg dry weight)
|
Total
PCBs
|
23
|
180
|
Source: Appendix A of ETWB TCW No. 34/2002
Management of Dredged / Excavated Sediment
Note: LCEL
– Lower Chemical Exceedance Level
UCEL
– Upper Chemical Exceedance Level
6.3.5
Sediments are categorised with
reference to the LCEL and UCEL, as follows:
Category L Sediment with
all contaminant levels not exceeding the LCEL.
The material must be dredged, transported and disposed of in a manner
that minimises the loss of contaminants either into solution or by suspension.
Category M Sediment with any one or more contaminant levels exceeding
the LCEL and none exceeding the UCEL.
The material must be dredged and transported with care, and must be
effectively isolated from the environment upon final disposal unless appropriate
biological tests demonstrate that the material will not adversely affect the
marine environment.
Category H Sediment with any one or more
contaminant levels exceeding the UCEL.
The material must be dredged and transported with great care, and must
be effectively isolated from the environment upon final disposal.
6.3.6
For projects with disposal
requirements of less than 50,000 m3 Category L sediment, the
allocation of sediment disposal space had been delegated to Director of
Environmental Protection (DEP) in accordance with ETWB TCW No. 34/2002.
6.3.7
The chemical testing results of the
riverbed samples as compared with the classification criteria are presented in Table
6.2. The chemical testing results
indicate that Category L material was found at all sampling locations.
Table
6.2 Contaminant Levels of Riverbed
Soil Samples and Their Categories
Sampling Station No.
|
LMW
|
HMW
|
Total
PCBs
|
Metals
|
Overall Category
|
PAHs
|
PAHs
|
mg/kg
|
ug/kg
|
ug/kg
|
Ug/kg
|
Ag
|
As
|
Cd
|
Cr
|
Cu
|
Ni
|
Pb
|
Zn
|
Hg
|
S1
|
<550
|
<1700
|
<23
|
<0.1
|
1.1
|
0.1
|
<1
|
1.8
|
<1
|
22
|
37
|
0.09
|
L
|
S2
|
<550
|
<1700
|
<23
|
0.4
|
1.8
|
<0.1
|
2.1
|
4.0
|
1.2
|
23
|
47
|
0.2
|
L
|
S3
|
<550
|
<1700
|
<23
|
0.2
|
11
|
0.1
|
2.7
|
2.3
|
<1
|
10
|
55
|
0.1
|
L
|
S4
|
<550
|
<1700
|
<23
|
<0.1
|
6.5
|
<0.1
|
2.2
|
4.5
|
1.2
|
18
|
42
|
0.09
|
L
|
S5
|
<550
|
<1700
|
<23
|
0.4
|
<1
|
<0.1
|
2.2
|
2.0
|
1.1
|
22
|
44
|
0.2
|
L
|
S6
|
<550
|
<1700
|
<23
|
0.3
|
1.7
|
0.1
|
3.9
|
2.7
|
1.2
|
34
|
31
|
0.1
|
L
|
S7
|
<550
|
<1700
|
<23
|
0.5
|
2.4
|
<0.1
|
1.5
|
1.7
|
<1
|
7.6
|
22
|
0.3
|
L
|
Notes:
1. LMW = Low molecular
weight PAHs, that is, acenaphthene, acenaphthylene, anthracene, fluorene,
naphthalene and phenanthrene.
2. HMW = High
molecular weight PAHs, that is, benzo[a]anthracene, benzo[a]pyrene, chrysene,
dibenzo[a,h]anthracene, fluoranthene, pyrene, benzo[b]fluoranthene,
benzo[k]fluoranthene, indeno[1,2,3-c,d]pyrene and benzo[g,h,i]perylene.
6.4.1
The construction activities to be carried
out for the proposed Project would generate a variety of wastes that can be
divided into distinct categories based on their composition and ultimate method
of disposal. The identified waste types
include:
·
construction
and demolition (C&D) materials;
·
chemical
waste; and
·
general
refuse.
6.4.2
The nature of each type of waste
arising is described in the following section, together with an evaluation of
the potential environmental impacts associated with these waste arisings.
6.4.3
During the
operation phase, maintenance
desilting would be required for the river channels.
Desilting will be carried out by excavators or
labourers as described in Section 2.7. The removed silt and
debris will then be loaded into covered lorries and transported to the
designated landfill site for disposal.
Construction and Demolition
(C&D) Materials
6.4.4
Construction of the drainage
improvement works for Pak Ngan Heung River, Tai Tei Tong River, Luk Tei Tong
River and Luk Tei Tong By-pass
Channel (2) River would involve earthworks for
the new river channels to the required profile and formation levels, and for
the outlets to the Silver River.
The excavated materials would comprise mostly soil, gravel and boulders from
the fields and river/stream channels. Based
on the preliminary design, the total volume of excavated material from the construction of the river channels was estimated
by the Project Engineer to be approximately 82,24845,20045 m3.
6.4.5
The results
of the sampling and laboratory testing provide information on the
characteristics of the excavated material from the riverbed. The samples collected at all 7 sampling
locations were described as coarse gravel.
Excavated material from the river improvement works would be suitable
for disposal to a public filling area.
6.4.6
It was
estimated by the Project Engineer that approximately 96,400,000 m3 of the excavated
material from the construction of the river channels could be reused on-site as
fill material for backfilling of the box culverts and drainage pipes. Temporary stockpiles of excavated materials
would be required on-site before disposal.
Considering the unpolluted nature of the excavated material, reuse
on-site would not result in any unacceptable environmental impact. It is proposed that small cobbles and rocks
from the existing rivers be re-used in the recreated channel beds as far as
possible, subject to suitable size requirements. Surplus excavated material (approx. 38,8004573,248
m3) would be transported by trucks to the designated barging point
for disposal at the designated public filling area, or transported directly to
the public filling area.
6.4.7
C&D material would also be
generated from the demolition of existing crossings over the river channels and
structures. The total volume of C&D
material was estimated by the Project Engineer to be approximately 2,4363,462
m3 and would comprise
mostly concrete, brick, metal and cement plaster/mortar. C&D waste would be generated during site clearance and the estimated volume of C&D waste for
a contract of this size was approximately 12,47218,180 m3. These C&D wastes would comprise
vegetation and top soil and would be delivered to a designated landfill site
for disposal. A summary of the
estimated volumes of surplus excavated material generated from earthworks for
the new river channels, as well as C&D material generated from the
demolition of existing crossings and structures and from site clearance is
presented in Table 6.3 below.
Table 6.3 Summary of C&D Material
Volumes
Location
|
Surplus Excavated Material
(m3)
|
C&D Waste (m3)
|
C&D Material
(m3)
|
River Channel
|
Structures
|
Site
Clearance
|
Structures
|
|
Pak
Ngan Heung River
Apr ‘08 – Jun ‘09
|
12,480
|
381
|
4,500
|
95
|
17,457
|
Luk
Tei Tong (2) RiverBy-pass Channel
Nov ’08 – Mar ‘09
|
10,17216,668
|
213126
|
4,3005,560
|
5331
|
14,73922,385
|
Luk Tei Tong River
Apr ’07
– Jul ‘08
|
12,300
|
853
|
3,520
|
213
|
16,887
|
Tai Tei Tong River
Apr ’07
– Oct ‘07
Nov ’08 –
Jan ‘09
|
31,80093
|
5881,323
|
4,600152
|
147331
|
37,135,699
|
Total
|
73,24838,845
|
2,7701,949
|
18,18012,472
|
487692
|
93,86454,782
|
Say
|
75,20041,700
|
13,20018,700
|
93,90054,800
|
Note:
1.
All volumes are bulk volumes, assuming bulk volume : in-situ volume = 1
: 0.75
2.
Surplus excavated material to be disposed to public filling area
3.
C&D waste to be disposed to landfill
Chemical Waste
6.4.8
The maintenance and servicing of construction
plant and equipment may possibly generate some chemical wastes, for instance,
cleaning fluids, solvents, lubrication oil and fuel. Maintenance of vehicles
may also involve the use of a variety of chemicals, oil and lubricants.
6.4.9
Since a large number of the
construction activities will be carried out in close proximity to river and
stream channels and residential dwellings, chemical wastes arising during the
construction phase may pose environmental, health and safety hazards if not
stored and disposed of in an appropriate manner as stipulated in the Waste
Disposal (Chemical Waste) (General) Regulations. The potential hazards include:
· toxic effects
to workers;
· adverse impacts
on water quality from spills and associated adverse impacts on fresh water
biota; and
· fire hazards.
6.4.10
Materials classified as chemical
wastes will require special handling and storage arrangements before removal
for appropriate treatment at the Chemical Waste Treatment Facility at Tsing
Yi. Wherever possible opportunities
should be taken to reuse and recycle materials. Mitigation and control requirements for chemical wastes are
detailed in Section 6.5.10. Provided
that the handling, storage and disposal of chemical wastes are in accordance
with these requirements, adverse environmental impacts are not expected to
result.
General Refuse
6.4.11
Throughout the construction stage, the
workforce would generate general refuse comprising food scraps, waste paper,
empty containers, etc. Release of
general refuse into the river and stream channels should not be permitted as
introduction of these wastes is likely to have detrimental effects on water
quality in the area. Effective
collection of site wastes would be required to prevent waste materials being
blown around by wind, flushed or leached into the aquatic environment, and
odour nuisance. The work sites may also
attract pests and vermin if the waste storage area is not well maintained and
cleaned regularly. Disposal of refuse
at sites other than approved waste transfer or disposal facilities can also
result in similar impacts.
6.4.12
With the implementation of the
recommended waste management practices at the site, adverse environmental
impacts would not arise from the storage, handling and transportation of
refuse.
Good Site Practices
6.5.1
Appropriate waste handling,
transportation and disposal methods for all waste arisings generated during the
construction works should be implemented to ensure that construction wastes do
not enter the river and stream channels.
6.5.2
It is expected that adverse impacts
from waste management would not arise, provided that good site practices are
strictly followed. Recommendations for
good site practices during construction include:
·
nomination
of approved personnel, such as a site manager, to be responsible for good site
practices, and making arrangements for collection of all wastes generated at
the site and effective disposal to an appropriate facility;
·
training
of site personnel in proper waste management and chemical waste handling
procedures;
·
provision
of sufficient waste disposal points and regular collection for disposal;
·
appropriate
measures to minimise windblown litter and dust during transportation of waste
by either covering trucks or by transporting wastes in enclosed containers;
·
regular
cleaning and maintenance programme for drainage systems, sumps and oil
interceptors;
·
a recording system for the amount of wastes generated,
recycled and disposed (including the disposal sites) should be proposed; and
·
a
Waste Management Plan should be prepared and submitted to the Engineer
for approval. One may make reference to
ETWB TCW No. 15/2003 for details.
6.5.3
In order to monitor the disposal of
C&D material at landfills and public filling areas, as appropriate, and to
control fly tipping, a trip-ticket system should be included as one of the
contractual requirements to be implemented by an Environmental Team undertaking
the Environmental Monitoring and Audit work.
One may make reference to WBTC No. 21/2002 for details.
Waste Reduction Measures
6.5.4
Good management and control can
prevent the generation of significant amounts of waste. Waste reduction is best achieved at the
planning and design stage, as well as by ensuring the implementation of good
site practices. Recommendations to
achieve waste reduction include:
·
segregation
and storage of different types of waste in different containers, skips or
stockpiles to enhance reuse or recycling of materials and their proper
disposal;
·
separate
labelled bins should be provided to segregate aluminium cans from other general
refuse generated by the workforce, and to encourage collection of by individual
collectors;
·
any
unused chemicals or those with remaining functional capacity should be
recycled;
·
maximising
the use of reusable steel formwork to reduce the amount of C&D material;
·
prior
to disposal of C&D waste, it is recommended that wood, steel and other
metals should be separated for re-use and / or recycling to minimise the
quantity of waste to be disposed of to landfill;
·
proper
storage and site practices to minimise the potential for damage or
contamination of construction materials;
·
plan
and stock construction materials carefully to minimise amount of waste
generated and avoid unnecessary generation of waste; and
·
minimize
over ordering of concrete, mortars and cement grout by doing careful check
before ordering.
6.5.5
In addition to the above good site
practices and waste reduction measures, specific mitigation measures are
recommended below for the identified waste arisings to minimise environmental
impacts during handling, transportation
and disposal of these wastes.
Construction and
Demolition Material
6.5.7
When disposing C&D material at a
public filling area, it should be noted that the material shall only consist of
soil, rock, concrete, brick, cement plaster/mortar, inert building debris,
aggregates and asphalt. The material shall
be free from marine mud, household refuse, plastic, metals, industrial and
chemical waste, animal and vegetable matter, and other material considered to
be unsuitable by the Filling Supervisor.
6.5.8
The C&D material generated from
demolition of existing structures and river crossings should be sorted on-site
into inert C&D material (that is, public fill) and C&D waste. Suitable areas should be designated within
the works site boundaries for temporary stockpiling of C&D material. Within stockpile areas, the following
measures should be taken to control potential environmental impacts or
nuisance:
·
covering
material during heavy rainfall;
·
locating
stockpiles to minimize potential visual impacts; and
·
minimizing
land intake of stockpile areas as far as possible.
Excavated Riverbed
Material
6.5.9
It is anticipated that the excavated
riverbed material may need to be temporarily stockpiled on-site prior to
disposal off-site. Details of
environmental control measures to be taken at the stockpiling area to prevent
water pollution are discussed in Section 5. Use of water-tight trucks would be required
for the transportation of excavated riverbed material to the designated barging
point for disposal at the designated public filling area, or transported
directly to the public filling area.
Chemical Wastes
6.5.10
If chemical wastes are produced at the
construction site, the Contractor would be required to register with the EPD as
a Chemical Waste Producer and to follow the guidelines stated in the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes. Good
quality containers compatible with the chemical wastes should be used, and
incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical
waste container indicating the corresponding chemical characteristics of the
chemical waste, such as explosives, flammable, oxidizing, irritant, toxic,
harmful, corrosive, etc. The Contractor
should use a licensed collector to transport and dispose of the chemical wastes
generated at the Chemical Waste Treatment Centre at Tsing Yi, or other licenced
facility, in accordance with the Waste Disposal (Chemical Waste) (General)
Regulation.
General Refuse
6.5.11
General refuse should be stored in
enclosed bins or compaction units separate from C&D material. A reputable
waste collector should be employed by the contractor to remove general refuse
from the site, separately from C&D material. An enclosed and covered area
is preferred to reduce the occurrence of 'wind blown' light material.
6.6.1
With the implementation of the
recommended mitigation measures for the handling, transportation and disposal of
the identified waste arisings, residual impacts would not be expected during
the construction of the proposed drainage improvement works.
6.7.1
Waste management would be the contractor’s
responsibility to ensure that all wastes produced during the construction of
the Project are handled, stored and disposed of in accordance with good waste
management practices and EPD’s regulations and requirements. The recommended
mitigation measures should form the basis of the site Waste Management Plan to
be developed by the Contractor at the construction stage.
.