Table 11.1       Implementation Schedule for Construction Dust Control

EIA Ref #

Environmental Protection Measures / Mitigation Measures

Location / Timing

Implementation Agent

Implementation Stages*

Relevant Legislation and Guidelines

Des

C

O

Dec

 

S3.7.1

Implementation of the Air Pollution Control (Construction Dust) Regulation and good site practices:

·        Use of regular watering to reduce dust emissions from exposed site surfaces and unpaved road, with complete coverage, particularly during dry weather;

·        Use of frequent watering for particularly dusty static construction areas and areas close to ASRs;

·        Tarpaulin covering of all dusty vehicle loads transported to, from and between site location;

·        Establishment and use of vehicle wheel and body washing facilities at the exit points of the site;

·        Routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs;

·          Stockpiled excavated materials should be covered with tarpaulin, and should be removed off-site within 24 hours to avoid any odour nuisance arising.

Work site / During the construction period

Contractor

 

Ö

 

 

Air Pollution Control (Construction Dust) Regulation

# All recommendations and requirements resulted during the course of EIA/EA Process, including ACE and / or accepted public comment to the proposed project.

* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning