Table 11.2 Implementation Schedule for Construction Noise Control
EIA Ref # |
Environmental Protection Measures / Mitigation Measures |
Location
/ Timing |
Implementation
Agent |
Implementation
Stages* |
Relevant
Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S4.8.1 |
Good Site Practice ·
Only well-maintained plant should be operated on-site and plant
should be serviced regularly during the construction program; ·
Silencers or mufflers on construction equipment should be utilized and
should be properly maintained during the construction program; ·
Mobile plant, if any, should be sited as far from NSRs as possible; ·
Machines and plant (such as trucks) that may be in intermittent use
should be shut down between work periods or should be throttled down to a
minimum; ·
Plant known to emit noise strongly in one direction should, wherever
possible, be orientated so that the noise is directed away from the nearby
NSRs; and ·
Material stockpiles and other structures should be effectively
utilized, wherever practicable, in screening noise from on-site construction
activities. |
Work
site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN2/93 and Noise Control Ordinance |
S4.8.2- S4.8.4 |
Use of quiet PME |
Work
site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN2/93 and Noise Control Ordinance |
S4.8.5- S4.8.6 |
Use of movable noise
barriers and temporary noise barrier |
Work
site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN2/93 and Noise Control Ordinance |
S4.11.1 |
Environmental
Monitoring and Audit (EM&A) programme is recommended to be implemented
during the construction stage. |
Work
site / During the construction period |
Contractor |
|
Ö |
|
|
- |
# All recommendations and requirements resulted
during the course of EIA/EA Process, including ACE and / or accepted public
comment to the proposed project.
* Des - Design, C - Construction, O –
Operation, and Dec - Decommissioning