Table 11.5 Implementation Schedule for Ecological Requirements
EIA Ref # |
Environmental Protection Measures / Mitigation Measures |
Location
/ Timing |
Implementation
Agent |
Implementation
Stages* |
Relevant
Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S7.7.1- S7.7.7. S7.8.2, S7.8.4 S7.8.15- S7.8.18 |
Design of River Channels The scale of impacts to river habitats would be determined largely by
the design of drainage channels built to replace existing rivers. Ecological
requirements have been considered during the design of drainage improvement
works, and are described as follows. Pak Ngan Heung River
Drainage improvements
would be implemented by constructing an underground channel that would bypass
a sharp bend in the river close to Butterfly Hill. Under normal conditions, flow
would be maintained within the existing river channel. During high flow
events, excess floodwaters would be conveyed through the by-pass channel,
Under this design,
modification to the existing PNH River would be limited to two short sections
upstream and downstream of the proposed Bypass Channel. At the downstream
section, the river channel would be slightly widened, with new vertical
concrete retaining walls constructed along the banks of the channel. The
channel widening would result in some new sections of riverbed being created,
which would be lined with natural materials such as small cobbles and
boulders. The existing riverbed and substrates would be retained.
The upstream section of
PNH River would be widened and slightly re-aligned. The new channel banks
would be trapezoidal in cross-section, and lined with rock-filled gabion.
Pits would be provided in the gabion bank to allow for planting and
establishment of riparian vegetation. The depth of the new channel bed would
be varied to re-create the pool-riffle sequence found in the existing River,
and a small weir at the upstream end of the existing river currently
maintained for crop irrigation would be re-instated. Similar to the
downstream section, the newly constructed riverbed would be lined with
natural materials such as cobbles and boulders.
Tai Tei Tong River
Proposed drainage
improvements at TTT River would be limited to the widening of three small
bottlenecks along the existing river. The bottleneck at the downstream end of
TTT River (close to the confluence of the three rivers) would be widened
along one bank only, with a new concrete retaining wall constructed along
this bank. At the two upstream bottlenecks, the newly widened banks would be
stabilised with rock-filled gabion.
Luk Tei Tong
River
Lower section of the LTT
River would be slightly widened and deepened (total length 225m). Ecological
enhancement features to be included along the improved river section would
include:
·
The channel bed would be constructed using natural materials such as
small cobbles and boulders. ·
The depth of the channel would be varied to re-create the pool-riffle
sequence found in the existing river. ·
The new channel banks would be trapezoidal in cross-section, and
lined with rock-filled gabion. Pits would be provided in the gabion bank to
allow for planting and establishment of riparian vegetation. Luk Tei Tong (2)
River
The proposed works would
largely avoid direct impacts to the river by creating a flood Bypass Channel,
with just small sections of the existing river connecting to the upstream and
downstream ends of the Bypass Channel affected. Similar to the PNH River,
existing flow within the flow LTT (2) River would be maintained under normal
conditions, with excess flow diverted to the Bypass Channel during high flow
events. Unlike the PNH River Bypass Channel, the LTT Bypass Channel would be
open, not routed underground.
General As the new drainage
channels would be approximately the same width as the existing watercourses,
it is anticipate that most of the substrates used to line the new channel
beds can be taken from the existing rivers. Rocks unearthed during excavation
works for this Project or material purchased from local quarries would be
used as material to fill gabion bank linings and as additional substrate to
line the riverbeds if required.
In time, it is expected
that vegetation will naturally re-colonise newly constructed channel
sections. To expedite this process, planting of suitable aquatic, emergent
and riparian plant species within the beds and gabion-lined sections of
channels will be undertaken following the completion of works (Table 2.7
lists some suggested species for use in this planting). Additionally, the
gabion lining will be hydroseeded. Planting design will be finalised in the
detailed design stage.
The newly created PNH
River drainage channel is expected to provide a suitable habitat for the fish
species of conservation interest (Flagtail, Kuhlia marginata)
previously recorded from the river. To further increase the value of the PNH
River for this and other fish species, it is recommended that a small fish
ladder is constructed at the upstream end of the new channel. The existing
agricultural weir at this location currently impedes the movement of fish
between upstream and downstream sections of the river. The fish ladder would
facilitate movement past this obstacle, extending the range of fish
communities in both upstream and downstream areas. A conceptual layout of the
proposed fish ladder is given in Figure 7.3, showing a basic design of
rock-ramp fishway commonly adopted in Australia and other countries to
facilitate the passage of various fish species over low obstructions. The detailed
design of the ladder would be finalised at a later stage of this Project.
|
River
channels during design/construction phase. |
Project Proponent/ Contractor. |
Ö |
Ö |
|
|
- |
S7.8.3. |
Avoidance of Disturbance to Breeding Fauna The works programme has
been considered to avoid impacts to breeding wildlife where possible. Works
within Luk Tei Tong Marsh and the confluence of the three rivers would be
restricted to the dry season, thereby avoiding impacts to White-shouldered
Starlings (Sternus sinensis) that have been recorded breeding in the
Disused Watchtowers close to the river confluence, and also to other avifauna
and herpetofauna species that may breed within Luk Tei Tong Marsh. |
River
outlets during construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.5 |
Minimise Sedimentation All excavation works
carried out within or close to water bodies should be carried out in the dry
season where possible, with construction carried out by land-based plant. Excavation
works within river/stream channels should be restricted to an enclosed dry
section of the river, with containment measures such as bunds and barriers
used within the river to minimize the impacts upon the downstream water body.
Site runoff should be directed towards regularly cleaned and maintained silt
traps and oil/grease separators to minimise the risk of sedimentation and
pollution of river water. The silt and oil/grease separators should be
appropriately designed for the local drainage and ground conditions. To
minimize leakage and loss of sediments during excavation in narrow channels,
tightly sealed closed grab excavators should be deployed where material to be
handled is wet. |
Works areas during construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.6 |
Minimise Noise Impacts Noise mitigation measures
including the use of quiet construction plant and temporary noise barriers
should be implemented to minimise disturbance to habitats adjacent to the
works areas. |
Works areas during construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.7 |
General Site Practice Standard good site practice measures should be implemented throughout
the construction phase. The measures should include: ·
Placement of equipment
or stockpile in designated works areas and access routes selected on existing
disturbed land to minimise disturbance to natural habitats and vegetation,
particularly mature trees. ·
Construction activities
should be restricted to work areas that should be clearly demarcated. The
work areas should be reinstated after completion of the works. ·
Waste skips should be
provided to collect general refuse and construction wastes. The wastes should
be disposed of timely and properly off-site. ·
General drainage
arrangements should include sediment and oil traps to collect and control
construction site run-off. ·
Open burning on works
sites is illegal, and should be strictly prohibited. |
Works areas during construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.8 |
Minimise Operation Phase Disturbance Impacts The following measures are recommended to minimise potential impacts
resulting from operational phase activities: ·
To minimise sedimentation,
de-silting should be limited to the dry season (November-March). ·
For maintenance
desilting of the re-profiled river channels, temporary barrier walls shall be
used to provide a dry zone for desilting work. ·
The implementation of de-silting
and other activities that could disturb aquatic fauna should be phased to
ensure some areas of relatively undisturbed habitat remain available for
resident aquatic fauna at all times. ·
Waste material
produced during de-silting should be disposed of in a timely and appropriate
manner. |
River Channels during operation phase. |
Maintenance Agent. |
|
|
Ö |
|
- |
S7.8.9- S7.8.11 S7.8.19- S7.8.23 |
Luk Tei Tong Bypass
Channel To minimise impacts to Luk
Tei Tong Marsh, No footpath would be constructed along the bypass channel. Construction of the Bypass
Channel would be limited to one dry season only, thereby minimising
disturbance impacts to wetland fauna potentially breeding in the Marsh Area. Operation phase impacts
resulting from desilting works within the LTT Bypass Channel are expected to
be very minor in scale, given that water flow (and therefore sediment
deposition) within the channel would be minimal for much of the year, except
during spate events. Vegetation control would be required 1-2 times per year
at most to prevent the excessive growth of (especially woody) vegetation that
would impede the drainage capacity of the channel. These measures do not
necessarily conflict with the maintenance of the channel as marshland, as the
removal and control of vegetation would be required anyway to maintain the
sub-climatic vegetation community found in marsh habitats. It is recognised,
however, that regular cutting of vegetation could prevent the re-establishment
of wetland communities, with potential disturbance to breeding fauna of
particular concern. It is therefore recommended that vegetation control is
undertaken outside of the main breeding season for wildlife (April-August) to
avoid potential impacts. The following key
features would be included in the Channel design:
·
The Bypass Channel bed would be approximately 800mm below the
existing ground level, and would be lined with turf taken from areas of Luk
Tei Tong Marsh that fall within the footprint of the proposed Channel. This
area would be maintained as compensatory marshland habitat. So as to maintain
the flood protection function of the channel, vegetation within the Channel
would be maintained at a height of about 300mm. ·
A low weir would be constructed at the downstream end of the Bypass
Channel, serving to retain rainwater and some diverted floodwaters in the
Channel. As the channel would be slightly lower than the existing ground
level, and water within the channel would be retained, it is anticipated that
habitats within the channel provide a more valuable wetland habitat than
adjacent areas of Luk Tei Tong Marsh, where wetland vegetation is not
particularly well established. ·
The banks of the proposed Channel would be lined with rock-filled
gabion, and topped with small (200mm high) earth bund. The gabion lining is
required to stabilize the banks of the Channel, and the earth-bund would
prevent surface water from surrounding areas of the marsh from draining into
the Channel. The intention of
re-using turf from the channel alignment is to provide suitable soil
conditions for wetland habitats within the Bypass Channel. Additionally,
roots and seeds of some plant species within the turf would speed up the
establishment of wetland vegetation within the Channel. It should be noted
though that parts of the Channel alignment are currently dominated by the
weed Mikania micrantha, which would require removal prior to the
construction phase. Reference should be made to Nature Conservation Practice
Note No. 01/2003.
The construction of the
LTT By-pass Channel is expected to take approximately 5 months. There is some
concern that during this period, vegetation in sods of turf removed from the
channel alignment would suffer some die-back before being replaced within the
channel. To minimize potential die-back, it is recommended that turf removal
(and channel construction) is limited to sections no more than 100m in
length. The construction sequence would involve excavating the first 100m of
the channel (at the downstream end of the alignment). Turf from this section
would be moved to a temporary storage area. To minimize potential damage to
this vegetation, the turf would not be stacked in layers during storage, and
would be adequately watered for the duration of the storage period (i.e., 1-2
times daily). Following removal of the first 100m of turf, the second 100m of
the channel would be excavated, and turf from this section immediately installed
in the first excavated section of the channel. This process would be repeated
until the last section of the channel is excavated. Turf removed from the
first 100m section and stored during the construction would be used to
re-vegetate this area. Even if some die-back occurs, it is expected that the
roots and seed-bank within the turf will provide adequate material for the
re-generation of vegetation following re-introduction into the LTT Bypass
Channel. Furthermore, vegetation from adjacent areas of the marsh would also
be expected to re-colonise substrates within the Channel, which would provide
a suitable growing medium for vegetation recorded from the marsh area. A
programme would be established to monitor the ecology (including vegetation
communities) of the LTT By-pass Channel during the operation phase. If there
appears to be any problem with vegetative re-establishment, remedial measures
(including the planting of riparian/emergent /aquatic vegetation) would be
implemented.
The new wetland area within
the Bypass Channel would cover an area of approximately 0.6ha. Although this
would be slightly smaller than the 0.8ha of existing habitat affected by the
improvement works, wetlands provided within the channel alignment would be of
higher ecological value than the habitats they would replace, providing
adequate compensation for habitat loss.
Temporary works areas
adjacent to the Bypass Channel alignment would be re-instated with the planting
of appropriate wetland plant species following the completion of construction
works. No long-term impact to these areas are expected. |
LTT Bypass Channel |
Project Proponent, Contractor,
Maintenance Agent |
Ö |
Ö |
Ö |
|
- |
S7.8.12 |
Minimise Impacts to Trees by Ling Tsui Tau U-Channel To minimise impacts to
woodland habitats, the alignment of the proposed U-Channel should avoid
nearby mature trees as far as practicable. |
Ling Tsui Tau U-Channel during design/construction
phase. |
Project Proponent/ Contractor. |
Ö |
Ö |
|
|
- |
S7.8.13- S7.8.14 |
Capture-Surveys of Fish and Amphibian Species of Conservation Interest Proposed works at the
rivers have the potential to impact fish species of conservation interest. To
minimize these potential impacts, it is recommended that capture-surveys of
the proposed works areas are conducted prior to the commencement of
construction works in the channel. These surveys should include fish species
of conservation interest recorded during the surveys (Flagtail, Kuhlia
marginata & Predaceous Chub, Parazacco spilurus), with
particular attention paid to the Flagtail. Either of these species caught
during the surveys should be re-located to areas of the watercourse upstream
of the proposed works areas, or to aquaria set up close to the works areas.
Maintenance of the fish prior to translocation would be undertaken by an
ecologist appointed by the Project Proponent. The capture surveys should be
conducted in the dry season by a suitably qualified ecologist(s) appointed by
the Project Proponent. For the Flagtail (which will probably occur in low
densities at PNH River), further surveys should be conducted to confirm the
presence and numbers of fish in the streams closer to the time of construction.
A detailed methodology for fish translocation (based in part upon the
Flagtail survey results) should be formulated during the detailed design
stage of the Project.
In addition to fish
species of conservation interest, the proposed drainage improvement works
could also result in direct impacts to two amphibian species of conservation
interest, RTF and Chinese Bullfrog. It is therefore recommended that
additional capture surveys are conducted prior to the commencement of works
to locate any individuals of these two species within the works areas. The
surveys should be conducted in the wet season (March/April-October), when
these species are calling and are generally more conspicuous. Any individuals
captured during the survey should be relocated to similar nearby habitats
outside of the works areas. The capture surveys should be conducted by a
suitably qualified ecologist(s) appointed by the Project Proponent. A
detailed methodology for faunal translocation should be formulated during the
detailed design stage of the Project. |
Works
areas prior to construction
activities. Maintenance throughout construction phase. |
Ecologist. |
Ö |
Ö |
Ö |
|
- |
|
|
|
|
|
|
|
|
|
S7.8.24 |
Compensatory Tree and Shrub Planting Planting of trees and other
vegetation along the banks of the newly created channels would provide
compensation for unavoidable tree-felling and loss of small areas of open and
secondary woodland habitat resulting from the proposed TTT and PNH River
Channel and Ling Tsui Tau U-Channel works. Compensatory planting would make
use of native plant species with flowers/fruits attractive to wildlife.
Compensation in terms of woodland area and trees planted would be on at least
a 1:1 ratio, covering an area of at least 0.13ha. |
Detailed
landscape design during design phase, planting during construction phase. |
Designer/Contractor. |
Ö |
Ö |
|
|
- |
S7.10.1- S7.10.7 |
Environmental Monitoring & Audit The proper implementation of recommended ecological mitigation measures
should be audited. A specific monitoring
programme of improved sections of PNH and LTT Rivers is recommended. The
programme should provide data on the re-establishment of aquatic/riparian communities
in the channels, and allow an assessment of the relative success of
mitigation measures to be made. Baseline data should be collected several
months before the commencement of the construction phase, with monitoring
conducted on a monthly basis during the construction phase, and every two
months a year for 4 years after the completion of works. Data collected
should include the following parameters:
§
Water
quality (e.g., dissolved oxygen, pH, conductivity, salinity, BOD, nutrient
concentrations);
§
Sediment
characteristics;
§
Water
flow;
§
Avifauna
species and densities;
§
Aquatic
macroinvertebrate community species composition and abundance;
§
Fish
community species composition and abundance;
§
Adult
odonate community species composition and abundance;
§
Aquatic,
emergent and riparian vegetation community species composition and abundance.
Reports on the findings
of each monitoring trip should be submitted to Agriculture, Fisheries and
Conservation Department (AFCD) for review. A final report summarising the monitoring
results over the entire monitoring period should be prepared to serve as a
reference for future projects of this kind. Monitoring should be conducted by
a qualified ecologist(s) with over 6 years relevant experience.
Monitoring of the LTT
Bypass Channel would be required to confirm that the proposed Channel design
has provided suitable compensation for impacts to Luk Tei Tong Marsh. It is
suggested that ecological monitoring of habitats within the Channel should be
undertaken for a period of at least 4 years. Data collected should include
the following key parameters:
§
Water
quality (e.g., dissolved oxygen, pH, conductivity, salinity, BOD, nutrient
concentrations);
§
Sediment
characteristics;
§
Water
depth and flow;
§
Avifauna
species and densities;
§
Aquatic
macroinvertebrate community species composition and abundance;
§
Fish
community species composition and abundance;
§
Herpetofauna
community species composition and abundance;
§
Adult
odonate community species composition and abundance;
§
Aquatic,
emergent and riparian vegetation community species composition and abundance.
To provide baseline
data, it is suggested that the same parameters are measured along a strip of
existing marsh habitat adjacent to the Channel alignment. A comparison of
species diversity and densities along the Bypass Channel alignment and at the
reference site would allow the effectiveness of habitat creation to be
assessed. Monitoring of both the Channel and Reference Site should be
conducted 6 times a year for 4 years after the completion of works. Reports
on the findings of each monitoring trip should be submitted to AFCD for
review. A final report summarising the results of monitoring over 4 years
should be prepared to serve as a reference for future projects of this kind. Monitoring
should be conducted by a qualified ecologist(s) with over 6 years relevant
experience.
The newly constructed
PNH and LTT River Channels, and LTT Bypass Channel are expected to provide a
similar habitat to the habitats they would replace. It is therefore
anticipated that wildlife found in the existing rivers and marsh would
successfully re-colonise the new channels. However, if the post-construction
phase monitoring demonstrates that re-colonisation is unsuccessful the
following contingency plan should be implemented:
·
Baseline/reference data should be compared with post-construction
phase data. Any substantial differences in habitat characteristics (e.g.,
water quality, aquatic/emergent vegetation) should be noted. ·
The potential cause of differences between baseline/reference and
post-construction phase habitat characteristics (e.g., changes in water
depth, sediment characteristics) should be identified. ·
Measures to further rehabilitate the habitat characteristics of the
channels should be implemented. Such measures could include: -
Minor re-profiling of the channel bed(s) could be implemented to
increase micro-habitat diversity within the channels. By excavating small
areas of the bed, areas of slow flowing water would be created within river
habitats, and small pools of very slow-flowing or standing water would be
created within the marsh. -
Increasing heterogeneity of substratum would again increase
micro-habitat diversity: providing substrates of different sizes would
provide niches for organisms preferring small sediments (e.g., burrowing
dragonfly larvae) and larger cobbles/boulders (e.g., Heptageniid mayfly
nymphs). -
Planting of suitable aquatic, emergent and riparian vegetation could
serve to increase vegetative cover. -
Management of water levels within the LTT Bypass Channel could be
implemented by modifying the height of the weirs at either end of the
Channel; thus optimizing conditions for wetland habitat establishment within
the Channel. ·
Further monitoring of abiotic and biotic parameters should be
conducted to determine the relative success of the contingency habitat
rehabilitation measures. A specific monitoring programme for the White-shouldered Starlings is
recommended. A qualified ecologist with over 6 years relevant experience
should conduct the monitoring. Monthly baseline surveys of the Disused
Watchtowers should be undertaken in the wet season prior to the commencement
of construction phase activities. The aim of baseline surveys should be to
establish whether or not any breeding Starlings are still present. If
breeding activities are identified, the number of breeding pairs, the success
of breeding and responses to any disturbance should be recorded. During the
construction phase, monthly surveys of the Watchtowers are recommended. Information
should be collected on behaviour, breeding activity, and any response to
disturbance. The source of any disturbance impacts should be identified. |
Prior
to and during Construction Phase. Operation Phase. |
EM Team and Ecologist(s). |
Ö |
Ö |
Ö |
|
- |
# All recommendations and requirements resulted
during the course of EIA/EA Process, including ACE and / or accepted public
comment to the proposed project.
* Des - Design, C - Construction, O –
Operation, and Dec - Decommissioning