Table 11.6 Implementation Schedule for Cultural
Heritage
EIA Ref # |
Environmental Protection Measures / Mitigation Measures |
Location
/ Timing |
Implementation
Agent |
Implementation
Stages* |
Relevant
Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S8.6.1- S8.6.3 |
Archaeology Further archaeological
investigation is recommended for the two areas within the Chung Hau
Archaeological Sites, including Area E and the site of the abandoned factory,
as well as the works area not covered by the previous survey. The construction of the proposed
U-channel at Ling Tsui Tau Village should minimise any excavation works
within the boundary of the Chung Hau Archaeological Site. Subject to the
findings of the further investigation, a watching brief is recommended for
any excavation works undertaken by a qualified archaeologist approved by AMO
in order to record and collect any artefacts and/or archaeological data
during excavation. If significant archaeological deposits are found, a rescue
excavation may need to be undertaken. Built Heritage Specific construction
method should be selected to avoid vibration impact on the retaining wall and
buildings of the Yuen Compound during construction of the proposed retaining
wall and rubble seawall. Monitoring of vibration impacts should be conducted during
the construction works to ensure no damage to the existing structures of the
Compound. |
Work
site/During construction phase |
Contractor |
|
Ö |
|
|
- |
# All recommendations and requirements resulted
during the course of EIA/EA Process, including ACE and / or accepted public
comment to the proposed project.
* Des - Design, C - Construction, O –
Operation, and Dec - Decommissioning