Table 2.2 Summary of Key Continuous Public Involvement
Date |
Subject |
21 May 04 |
Public Consultation with
Village Representatives in Mui Wo |
21 May 04 |
Public Consultation with
Green Lantau Association |
4 June 04 |
Follow up discussions with
DSD to review the proposed works at Tai Tei Tong |
29 June 04 |
Follow up discussions with
DSD to review the proposed works at Tai Tei Tong |
15 July 04 |
Public Consultation with
Village Representatives in Mui Wo |
15 July 04 |
Public Consultation with
Green Lantau Association |
29 July 04 |
Joint site inspection with
green groups including Green Power and World Wild Fund to Mui Wo |
3 Aug 04 |
Presentation of the
proposed works to green groups |
25 Aug 04 |
Joint site visit with Green Lantau Association –
Proposed Luk Tei Tong (2) River |
25 Aug 04 |
Mui Wo Rural Committee
Meeting – Proposed Works in Mui Wo |
18 Oct 04 |
Consultation with Islands
District Council |
26 Nov 04 |
Consultation with Village
Representatives and Mui Wo Rural Committee |