Table 2.4 Considerations of Various Drainage Options
Drainage Options |
Environmental Benefit |
Environmental Dis-benefit |
Recommendation |
Reason & Considerations |
Maintenance of existing
river |
(a) The area to be affected by
the proposed drainage improvement works will be the least. (b) The existing condition of
rivers will be improved. For example, the contaminated soil and waste settled
in the river bed will be removed. (c) The disturbance to the
ecological system and water quality in existing rivers will be of small
scale. |
No major environmental
dis-benefits are anticipated. |
Not recommended. |
(a) This option can only marginally improve the capacity of the existing rivers. (b) The flood protection level provided is still very low due to the small size of existing rivers. Severe flooding in the areas will continue. |
By-pass channel or box
culvert |
(a) Existing rivers will not
be disturbed and there is no disturbance to the ecological system and water
quality in existing rivers. |
Extensive land resumption
is required for the construction of by-pass channel or box culvert. The
public will be seriously disturbed. |
By-pass box culvert Pak Ngan Heung River. By-pass channel Luk Tei Tong (2) River |
(a)
The construction of by-pass channel or box culvert will require
extensive land resumption and will impose adverse impact to other areas
further away from the flooding spots. (b)
Along Luk Tei Tong (2) River and Pak Ngan Heung River, most of the
areas are abandoned agricultural lands and marsh. There are sufficient
available space for the construction of the by-pass box culvert and channel.
The diversion scheme is considered feasible and acceptable. Locals and green
groups also accepted the proposal. (c)
The impact to existing marsh at Luk Tei Tong would be minimum by
adopted ecological friendly design details. The existing river will be
untouched. |
Interception and Flood Storage |
(a) Existing rivers will not
be disturbed and there is no disturbance to the ecological system and water
quality in existing rivers. |
(a) Extensive land resumption
is required for construction of storage pond or interception channel. (b)
Environmental
impacts to other areas will result.
The upstream area, which is mainly composed of dense vegetation area,
agricultural land, residential area and nurseries, will be seriously
affected. |
Not recommended |
(a) This option is also not a
cost-effective solution given the large volume of runoff needed to be stored
which results in resumption of large piece of land for the construction of a
large stormwater storage pond. The plan area of the pond can be reduced by
half if the depth of the pond is increased to 6m. However, a pumping station is then required for pumping the
water away after the storms. The
required land resumption is still very substantial and the objection from
public cannot still be avoided. (b) This option is therefore
considered not acceptable. |
Floodwall and Pumping Station |
(a) Existing rivers will not
be disturbed and there is no disturbance to the ecological system and water
quality in existing rivers. |
(a) Floodwall has limited
scope for improving the aesthetic. The visual impact is of concerns, in
particular, if the floodwall is high. |
Not recommended |
(a)
Floodwall can be constructed along the rivers to contain the
floodwater during extreme rainstorm events.
However, the capacities of the concerned rivers are very low and a
high floodwall of minimum 2m is needed. (b)
The floodwall protection does not provide a long-term solution
because it contains floodwater at a higher water level and causes flooding of
the local drainage systems behind the floodwalls. Flooding in adjacent areas still persists. (c) To eliminate the severe
flooding outside the floodwalls, the floodwalls are required to be
constructed further away from the existing rivers such that an additional
flood plain flow area is allowed for conveyance of flow during extreme
rainstorms. The formation of flood plain flow area requires substantial land
resumption. (d) Consideration has been
given to pumping the surface runoff in the rivers to the downstream in order
to reduce the water level and hence height of the floodwalls. However, the
peak discharges are very substantial and temporal. It is technically
impracticable to pump the peak surface runoff away without the use of
detention pond. (e) Therefore, this option is
not further considered. |
Deepening and Widening of
Existing Rivers |
(a) The existing condition of
the rivers will be improved by the proposed engineering works by applying
appropriate ecological friendly design. For example, Gabion lining with
planting pits can enhance the ecological condition and provide shelter for
the river habitats; the contaminated soil and waste settled in the riverbed
will be removed, eroded river bank will be re-constructed. (b)
As the improvement works will be carried out along the existing
rivers, it can avoid major resumption of land and environmental impacts in
other areas. |
The existing rivers and
ecological system will be disturbed. |
River widening ü
Luk Tei Tong River Improve bottlenecks ü
Tai Tei Tong River |
(a)
The prime reason for flooding is that the existing rivers do not have
adequate drainage capacity. The most effective solution is to widen and
deepen the existing rivers. (b)
As the river widening works will be carried out mainly along the
existing rivers, there will be significant reduction of land resumption as
compared to other options. (c)
River widening is more reliable and low cost option to improve the
drainage of rivers compared to the other options. (d)
The channel design should provide an ecological and aesthetical
acceptable solution, taking into account hydraulic performance and operation
requirements of the channel. (e)
Appropriate mitigation measures are required to be implemented such
that the environmental impact is kept to acceptable limit. (f)
This option is recommended and the proposed channels are lined with
gabion block, and natural bed to retain the river ecology, and to improve the
aesthetic, visual and environmental aspect of the river widening works. (g)
For the Pak Ngan Heung River, river widening would affect the
existing shrine and Fung Shui Tree. This area is culturally sensitive and any
change to the shrine and Fung Shui tree at the existing bridge will be
objected by the villager. Besides, one of the reasons for flooding is the
sharp bend of the river near the existing bridge. Widening and deepening
cannot remove the sharp bend and the problem. Therefore, this option is not
recommended to Pak Ngan Heung River. |
Construction of Earth
Bunds at both sides of Luk Tei Tong (2) River |
(a) No excavation was required for the affected area except the area covered by the foundation of the earth bunds. (b) The existing river would be untouched. |
(a) Permanent loss of marsh area. (b) Visual impact due to the proposed earth bunds would be substantiated. |
Not recommended |
(a) The earth bunds would occupy substantial area of the marsh area and cause permanent loss of marsh area and associated ecology. (b) The earth bunds would obstruct surface runoff flowing into the existing river and aggravate the flooding situation. (c) Visual impact is of concern. |