Table 6.3 Summary of C&D Material
Volumes
Location |
Surplus Excavated Material (m3) |
C&D Waste (m3) |
C&D Material (m3) |
||
River Channel |
Structures |
Site Clearance |
Structures |
|
|
Pak Ngan Heung River Apr ‘08 – Jun ‘09 |
12,480 |
381 |
4,500 |
95 |
17,457 |
Luk Tei Tong By-pass Channel Nov ’08 – Mar ‘09 |
10,172 |
213 |
4,300 |
53 |
14,739 |
Luk Tei Tong River Apr ’07 – Jul ‘08 |
12,300 |
853 |
3,520 |
213 |
16,887 |
Tai Tei Tong River Apr ’07 – Oct ‘07 Nov ’08 – Jan ‘09 |
3,893 |
1,323 |
152 |
331 |
5,699 |
Total |
38,845 |
2,770 |
12,472 |
692 |
54,782 |
Say |
41,700 |
13,200 |
54,800 |
Note:
1.
All volumes are bulk volumes, assuming bulk
volume : in-situ volume = 1 : 0.75
2.
Surplus excavated material to be disposed to
public filling area
3.
C&D waste to be disposed to landfill