Table 7.6c Overall Impact Evaluation to Luk Tei Tong River.
Evaluation Criteria |
Luk Tei Tong River |
Habitat quality |
Moderate |
Species |
Potential disturbance and
temporary habitat loss for avifauna species of conservation interest, (Great
Egret, Casmerodius alba; Little Egret, Egretta garzetta; Striated Heron,
Butorides striatus;
Black-crowned Night Heron, Nycticorax
nycticorax; White-throated Kingfisher,
Halcyon
smyrnensis;
and Common
Teal, Anas crecca). |
Size/Abundance |
225m of river channel
directly affected |
Duration |
Direct impacts would last
for the duration of the construction phase, and a period of re-colonisation
during the operation phase. Periodic minor
disturbance throughout the operation phase due to routine maintenance (e.g.,
de-silting works). |
Reversibility |
Direct impacts
to stream/river habitats would be reversible; the newly constructed drainage
channels are expected to provide suitable habitats for aquatic communities
previously recorded from the stream/river. Periodic minor increase
in disturbance during operational phase would be temporary and reversible. |
Magnitude |
The scale of the impacts is
considered minor-moderate. |
Overall impact conclusion |
Construction Phase: Moderate. Operation Phase: Minor. |