Table 11A.1 Implementation Schedule for Construction
Dust Control
EIA Ref
# |
Environmental Protection Measures / Mitigation
Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant
Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S3.7.1 |
Implementation of the Air Pollution Control (Construction Dust)
Regulation and good site practices: ·
Use
of regular watering to reduce dust emissions from exposed site surfaces and
unpaved road, with complete coverage, particularly during dry weather; · Use of frequent watering
for particularly dusty static construction areas and areas close to ASRs; · Tarpaulin covering of all
dusty vehicle loads transported to, from and between site location; · Establishment and use of
vehicle wheel and body washing facilities at the exit points of the site; · Routing of vehicles and
positioning of construction plant should be at the maximum possible distance
from ASRs; ·
Stockpiled
excavated materials should be covered with tarpaulin, and should be removed
off-site within 24 hours to avoid any odour nuisance arising. |
Work site / During the
construction period |
Contractor |
|
Ö |
|
|
Air
Pollution Control (Construction Dust) Regulation |
# All recommendations and requirements
resulted during the course of EIA/EA Process, including ACE and / or accepted
public comment to the proposed project.
* Des - Design, C - Construction, O –
Operation, and Dec - Decommissioning
Table 11A.2 Implementation Schedule for Construction
Noise Control
EIA Ref # |
Environmental
Protection Measures / Mitigation Measures |
Location
/ Timing |
Implementation
Agent |
Implementation
Stages* |
Relevant
Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S4.8.1 |
Good Site
Practice ·
Only well-maintained
plant should be operated on-site and plant should be serviced regularly
during the construction program; ·
Silencers or mufflers
on construction equipment should be utilized and should be properly
maintained during the construction program; ·
Mobile plant, if any,
should be sited as far from NSRs as possible; ·
Machines and plant
(such as trucks) that may be in intermittent use should be shut down between
work periods or should be throttled down to a minimum; ·
Plant known to emit
noise strongly in one direction should, wherever possible, be orientated so
that the noise is directed away from the nearby NSRs; and ·
Material stockpiles
and other structures should be effectively utilized, wherever practicable, in
screening noise from on-site construction activities. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC
PN2/93 and Noise Control Ordinance |
S4.8.2-
S4.8.4 |
Use of quiet PME |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC
PN2/93 and Noise Control Ordinance |
S4.8.5-
S4.8.6 |
Use of movable noise barriers and temporary noise
barrier |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC
PN2/93 and Noise Control Ordinance |
S4. |
Environmental
Monitoring and Audit (EM&A) programme is recommended to be implemented
during the construction stage. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
- |
# All recommendations and requirements
resulted during the course of EIA/EA Process, including ACE and / or accepted
public comment to the proposed project.
* Des - Design, C - Construction, O –
Operation, and Dec - Decommissioning
Table 11A.3 Implementation Schedule for Water
Quality Control
Environmental
Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
||||
Des |
C |
O |
Dec |
|||||
S5. |
Construction Site
Runoff and Drainage ·
Before commencing any
site formation work, all sewer and drainage connections shall be sealed to
prevent debris, soil, sand etc. from entering public sewers/drains. ·
Temporary ditches
shall be provided to facilitate run-off discharge into appropriate
watercourses, via a silt retention pond.
No site run-off shall enter the freshwater marshes at Luk Tei Tong. ·
Sand/silt removal
facilities such as sand traps, silt traps and sediment basins shall be
provided to remove sand/silt particles from runoff to meet the requirements
of the Technical Memorandum standard under the Water Pollution Control
Ordinance. The design of silt removal
facilities shall be based on the guidelines provided in ProPECC PN 1/94. All drainage facilities and erosion and
sediment control structures shall be inspected monthly and maintained to
ensure proper and efficient operation at all times and particularly during
rainstorms. ·
Water pumped out from
foundation excavations shall be discharged into silt removal facilities. ·
During rainstorms,
exposed slope surfaces shall be covered by a tarpaulin or other means. Other
measures that need to be implemented before, during, and after rainstorms are
summarized in ProPECC PN 1/94. ·
Exposed soil areas
shall be minimized to reduce potential for increased siltation and
contamination of runoff. ·
Exposed soil surfaces
shall be protected by paving or fill material as soon as possible to reduce
the potential of soil erosion. ·
Open stockpiles of
construction materials or construction wastes on-site of more than 50 m3
shall be covered with tarpaulin or similar fabric during rainstorms. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO |
S5. |
General
Construction Activities ·
Debris and refuse
generated on-site shall be collected, handled and disposed of properly to
avoid entering the river channels, the Luk Tei Tong freshwater marshes and
local storm water drains. Stockpiles
of cement and other construction materials shall be kept covered when not
being used. ·
Oils and fuels shall
only be used and stored in designated areas which have pollution prevention
facilities. All fuel tanks and
storage areas shall be provided with locks and be sited on sealed areas,
within bunds of a capacity equal to 110% of the storage capacity of the
largest tank. The bund shall be
drained of rainwater after a rain event. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
ProPECC PN 1/94; WPCO |
S5.7.5 |
Sewage from
Construction Workforce Temporary sanitary facilities, such as portable
chemical toilets, shall be employed on-site.
A licensed contractor shall be responsible for appropriate disposal
and maintenance of these facilities. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
WPCO |
S5.7.6 |
River
Channel Excavation Works Excavation and widening works for the drainage
improvements to the Pak Ngan Heung River, Tai Tei Tong River and Luk Ti Tong
River shall be carried out in sections (approximately 300 – 400 m in length)
and in dry condition. Containment
measures such as bunds and barriers shall be used within the river channel
and the excavation works restricted to within an enclosed dry section of the
channel. The
excavation and widening works shall be carried out in the dry season as far
as practicable. |
Work site / During the construction period |
Contractor |
|
Ö |
|
|
|
S5.7.7 |
Maintenance Desilting of River Channels For maintenance desilting
of the re-profiled river channels of Pak Ngan Heung River, Tai Tei Tong River
and Luk Ti Tong River, temporary barrier walls shall be used to provide a dry
work zone for desilting work.
Maintenance desilting shall be carried out during periods of low flow
in the dry season. |
Work site / During the operation period |
Contractor |
|
|
Ö |
|
|
S.5.9.1 |
During construction
phases, monitoring
of downstream water quality within the rivers should be undertaken,
together with regular site audits. |
With the rivers / During the construction period |
Contractor |
|
Ö |
|
|
|
# All
recommendations and requirements resulted during the course of EIA/EA Process,
including ACE and / or accepted public comment to the proposed project.
* Des -
Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 11A.4 Implementation Schedule for Waste
Management Implications
# All
recommendations and requirements resulted during the course of EIA Process,
including ACE and / or accepted public comment to the proposed project.
·
Des - Design, C -
Construction, O - Operation and Dec – Decommissioning
Table 11A.5 Implementation Schedule
for Ecological
Requirements
EIA Ref # |
Environmental
Protection Measures / Mitigation Measures |
Location /
Timing |
Implementation
Agent |
Implementation
Stages* |
Relevant
Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S7.7.1- S7.7.
S7.8.2, S7.8.4 S7.8.1 S7.8.18 |
Design
of River Channels The scale of
impacts to river habitats would be determined largely by the design of
drainage channels built to replace existing rivers. Ecological requirements
have been considered during the design of drainage improvement works, and are
described as follows. Pak Ngan Heung River Drainage improvements would be implemented by
constructing an underground channel that would bypass a sharp bend in the
river close to Butterfly Hill. Under normal conditions, flow would be
maintained within the existing river channel. During high flow events, excess
floodwaters would be conveyed through the by-pass channel
|
River
channels during design/construction phase. |
Project Proponent/ Contractor. |
Ö |
Ö |
|
|
- |
S7.8. |
Avoidance
of Disturbance to The works programme has been considered to avoid
impacts to breeding wildlife where possible. Works within Luk Tei Tong Marsh
and the confluence of the three rivers would be restricted to the dry season,
thereby avoiding impacts to White-shouldered Starlings (Sternus sinensis)
that have been recorded breeding in the Disused Watchtowers close to the
river confluence, and also to other avifauna and herpetofauna species that
may breed within Luk Tei Tong Marsh. |
River
outlets during construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.5 |
Minimise Sedimentation
All excavation works carried out within or close
to water bodies should be carried out in the dry season where possible, with
construction carried out by land-based plant. Excavation works within
river/stream channels should be restricted to an enclosed dry section of the
river, with containment measures such as bunds and barriers used within the
river to minimize the impacts upon the downstream water body. Site runoff
should be directed towards regularly cleaned and maintained silt traps and
oil/grease separators to minimise the risk of sedimentation and pollution of
river water. The silt and oil/grease separators should be appropriately
designed for the local drainage and ground conditions. To minimize leakage
and loss of sediments during excavation in narrow channels, tightly sealed
closed grab excavators should be deployed where material to be handled is
wet. |
Works areas during
construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.6 |
Minimise Noise Impacts Noise mitigation measures including the use of
quiet construction plant and temporary noise barriers should be implemented
to minimise disturbance to habitats adjacent to the works areas. |
Works areas during
construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.7 |
General Site Practice Standard good site practice measures should be
implemented throughout the construction phase. The measures should include: ·
Placement of equipment or
stockpile in designated works areas and access routes selected on existing
disturbed land to minimise disturbance to natural habitats and vegetation,
particularly mature trees. ·
Construction activities
should be restricted to work areas that should be clearly demarcated. The
work areas should be reinstated after completion of the works. ·
Waste skips should be
provided to collect general refuse and construction wastes. The wastes should
be disposed of timely and properly off-site. ·
General drainage
arrangements should include sediment and oil traps to collect and control
construction site run-off. ·
Open burning on works
sites is illegal, and should be strictly prohibited. |
Works areas during
construction phase. |
Contractor. |
|
Ö |
|
|
- |
S7.8.8 |
Minimise Operation Phase
Disturbance Impacts The following measures are recommended to
minimise potential impacts resulting from operational phase activities: ·
To minimise sedimentation,
de-silting should be limited to the dry season (November-March). ·
For maintenance desilting
of the re-profiled river channels, temporary barrier walls shall be used to
provide a dry zone for desilting work. ·
The implementation of
de-silting and other activities that could disturb aquatic fauna should be
phased to ensure some areas of relatively undisturbed habitat remain
available for resident aquatic fauna at all times. ·
Waste material produced
during de-silting should be disposed of in a timely and appropriate manner. |
River Channels during
operation phase. |
Maintenance Agent. |
|
|
Ö |
|
- |
S7.8.9- S7.8.11 S7.8.1 S7.8. |
Luk Tei Tong To minimise impacts to Luk Tei Tong Marsh, No
footpath would be constructed along the bypass channel. Construction of the Bypass Channel would be
limited to one dry season only, thereby minimising disturbance impacts to
wetland fauna potentially breeding in the Marsh Area. Operation phase impacts resulting from desilting
works within the LTT The following key features would be included in
the Channel design:
·
The Bypass Channel bed
would be approximately 800mm below the existing ground level, and would be
lined with turf taken from areas of Luk Tei Tong Marsh that fall within the
footprint of the proposed Channel. This area would be maintained as
compensatory marshland habitat. So as to maintain the flood protection
function of the channel, vegetation within the Channel would be maintained at
a height of about 300mm. ·
A low weir would be
constructed at the downstream end of the Bypass Channel, serving to retain
rainwater and some diverted floodwaters in the Channel. As the channel would
be slightly lower than the existing ground level, and water within the
channel would be retained, it is anticipated that habitats within the channel
provide a more valuable wetland habitat than adjacent areas of Luk Tei Tong
Marsh, where wetland vegetation is not particularly well established. ·
The banks of the proposed
Channel would be lined with rock-filled gabion, and topped with small (200mm
high) earth bund. The gabion lining is required to stabilize the banks of the
Channel, and the earth-bund would prevent surface water from surrounding
areas of the marsh from draining into the Channel. The intention of re-using turf from the channel
alignment is to provide suitable soil conditions for wetland habitats within
the Bypass Channel. Additionally, roots and seeds of some plant species
within the turf would speed up the establishment of wetland vegetation within
the Channel. It should be noted though that parts of the Channel alignment
are currently dominated by the weed Mikania micrantha, which would
require removal prior to the construction phase. Reference should be made
to Nature Conservation Practice Note No. 01/2003.
The construction of the LTT
|
LTT |
Project Proponent, Contractor, Maintenance Agent |
Ö |
Ö |
Ö |
|
- |
S7.8. |
Minimise
Impacts to Trees by Ling Tsui
Tau U-Channel To minimise impacts to woodland habitats, the
alignment of the proposed U-Channel should avoid nearby mature trees as far
as practicable. |
Ling Tsui Tau U-Channel during design/construction
phase. |
Project Proponent/ Contractor. |
Ö |
Ö |
|
|
- |
S7.8. S7.8.14 |
Capture-Surveys
of Fish and Amphibian
Species of Conservation Interest Proposed works at the rivers have the potential
to impact fish species of conservation interest. To minimize these potential
impacts, it is recommended that capture-surveys of the proposed works areas
are conducted prior to the commencement of construction works in the channel.
These surveys should include fish species of conservation interest recorded
during the surveys (Flagtail, Kuhlia marginata & Predaceous Chub, Parazacco
spilurus), with particular attention paid to the Flagtail. Either of
these species caught during the surveys should be re-located to areas of the
watercourse upstream of the proposed works areas, or to aquaria set up close
to the works areas. Maintenance of the fish prior to translocation would be
undertaken by an ecologist appointed by the Project Proponent. The capture
surveys should be conducted in the dry season by a suitably qualified
ecologist(s) appointed by the Project Proponent. For the Flagtail (which will
probably occur in low densities at PNH River), further surveys should be
conducted to confirm the presence and numbers of fish in the streams closer
to the time of construction. A detailed methodology for fish translocation
(based in part upon the Flagtail survey results) should be formulated during
the detailed design stage of the Project.
In addition to fish species of conservation
interest, the proposed drainage improvement works could also result in direct
impacts to two amphibian species of conservation interest, RTF and Chinese
Bullfrog. It is therefore recommended that additional capture surveys are
conducted prior to the commencement of works to locate any individuals of
these two species within the works areas. The surveys should be conducted in
the wet season (March/April-October), when these species are calling and are
generally more conspicuous. Any individuals captured during the survey should
be relocated to similar nearby habitats outside of the works areas. The
capture surveys should be conducted by a suitably qualified ecologist(s)
appointed by the Project Proponent. A detailed methodology for faunal
translocation should be formulated during the detailed design stage of the
Project.
|
|
Ecologist
|
Ö |
Ö |
Ö |
|
- |
S7.8. |
Compensatory
Tree and Shrub Planting Planting of trees and other vegetation along the
banks of the newly created channels would provide compensation for unavoidable
tree-felling and loss of small areas of open and secondary woodland habitat
resulting from the proposed TTT and PNH River Channel and Ling Tsui Tau
U-Channel works. Compensatory planting would make use of native plant species
with flowers/fruits attractive to wildlife. Compensation in terms of woodland
area and trees planted would be on at least a 1:1 ratio, covering an area of
at least 0.13ha. |
Detailed
landscape design during design phase, planting during construction phase. |
Designer/Contractor. |
Ö |
Ö |
|
|
- |
S7.10.1- S7.10.7 |
Environmental
Monitoring & Audit The proper implementation of recommended ecological mitigation
measures should be audited. A specific monitoring programme of improved
sections of PNH and LTT Rivers is recommended. The programme should provide data
on the re-establishment of aquatic/riparian communities in the channels, and
allow an assessment of the relative success of mitigation measures to be
made. Baseline data should be collected several months before the
commencement of the construction phase, with monitoring conducted on a
monthly basis during the construction phase, and every two months a year for
4 years after the completion of works. Data collected should include the
following parameters:
|
Prior
to and during Construction Phase. Operation Phase. |
EM Team and Ecologist(s) appointed by the Project
Proponent/ Contractor. |
Ö |
Ö |
Ö |
|
- |
# All recommendations and
requirements resulted during the course of EIA/EA Process, including ACE and /
or accepted public comment to the proposed project.
* Des - Design, C - Construction, O – Operation, and
Dec - Decommissioning
Table 11A.6 Implementation Schedule for Cultural
Heritage
EIA Ref # |
Environmental
Protection Measures / Mitigation Measures |
Location /
Timing |
Implementation
Agent |
Implementation
Stages* |
Relevant Legislation
and Guidelines |
|||
Des |
C |
O |
Dec |
|
||||
S8 |
Archaeology Further archaeological investigation is recommended
for the two areas within the Chung Hau Archaeological Sites, including Area E
and the site of the abandoned factory, as well as the works area not covered by the
previous survey. The construction of the proposed U-channel at Ling
Tsui Tau Village should minimise any excavation works within the boundary of
the Chung Hau Archaeological Site. Subject to the findings of the further investigation,
a watching brief is recommended for any excavation works undertaken by a
qualified archaeologist approved by AMO in order to record and collect any
artefacts and/or archaeological data during excavation. If significant
archaeological deposits are found, a rescue excavation may need to be
undertaken. Built Heritage Specific construction method should be selected to
avoid vibration impact on the retaining wall and buildings of the Yuen Compound
during construction of the proposed retaining wall and rubble seawall.
Monitoring of vibration impacts should be conducted during the construction
works to ensure no damage to the existing structures of the Compound. |
Work
site/During construction phase |
Contractor |
|
Ö |
|
|
- |
# All recommendations and
requirements resulted during the course of EIA/EA Process, including ACE and /
or accepted public comment to the proposed project.
* Des - Design, C - Construction, O – Operation, and
Dec - Decommissioning