7                        CULTURAL HERITAGE

7.1                  Introduction

7.1.1            The proposed U-channel at Butterfly Hill near Ling Tsui Tau Village within the boundary of the Chung Hau Archaeological Site and the Yuen Compound located at Luk Tei Tong River has been identified as an area of cultural heritage with archaeological significance located within the proposed works area.

 

7.2                  Cultural Heritage Mitigation Measures

7.2.1            Further archaeological investigation was recommended for the affected two areas within the Chung Hau Archaeological Site (AS), including the works area within Area E and the site of the abandoned factory as well as works area not covered by the previous archaeological survey.  Figure 7.1 shows the locations of the two areas within the AS.  The construction of the proposed U-channel at Ling Tsui Tau Village should minimise any excavation works within the boundary of the Chung Hau Archaeological Site.

7.2.2            Specific construction method should be selected to avoid vibration impact on the retaining wall and buildings of the Yuen Compound (Figure 7.2) during construction of the proposed retaining wall and rubble seawall. The implementation schedule of the recommended mitigation measures is presented in Appendix A.

 

7.3                  Baseline Monitoring

7.3.1            Baseline monitoring should be carried out to establish the existing condition of the cultural heritage resources.

 

7.4                  Construction Phase Monitoring and Audit

7.4.1            Subject to the findings of the further investigation, for any excavation works within the AS, a watching brief was recommended in order to record and collect any artefacts and/or archaeological data during excavation. If significant archaeological deposits are found, a rescue excavation may need to be undertaken before the construction work takes place. 

7.4.2            Monitoring of vibration impacts should be conducted during the construction works to ensure no damage to the existing structures of the Compound.

7.4.3            All measures undertaken by the Contractor during the construction phase in the vicinity of the AS and Yuen Compound should be audited by the ET, on a regular basis to ensure the compliance with the intended aims of the recommended mitigation measures.  Site inspections should be conducted at least once per month during the construction period, to avoid any possible damage through on-site liaison with the Contractor and ER before and during the works, covering:

 

·        Check and ensure no exceedence of approved works area; and

·        Inspection of the surrounding area and ground, particularly the Yuen Compound, to ensure that the existing features are not impacted.