Table 3.3 Event / Action Plan for Construction Noise
EVENT |
ACTION |
|||
|
ET |
IC(E) |
ER |
CONTRACTOR |
Action Level |
1.
Notify
IC(E) and Contractor; 2.
Carry
out investigation; 3.
Report
the results of investigation to the IC(E), ER and Contractor; 4.
Discuss
with the Contractor and formulate remedial measures; 5.
Increase
monitoring frequency to check mitigation effectiveness. |
1. Review
the analysed results submitted by the ET; 2.
Review
the proposed remedial measures by the Contractor and advise the ER
accordingly; 3.
Supervise
the implementation of remedial measures. |
1.
Confirm receipt
of notification of failure in writing; 2.
Notify
Contractor; 3.
Require
Contractor to propose remedial measures for the analysed noise problem; 4.
Ensure remedial
measures are properly implemented. |
1. Submit
noise mitigation proposals to IC(E); 2. Implement
noise mitigation proposals. |
Limit Level |
1.
Identify
source; 2.
Inform
IC(E), ER, EPD and Contractor; 3.
Repeat
measurements to confirm findings; 4.
Increase
monitoring frequency; 5.
Carry
out analysis of Contractor’s working procedures to determine possible
mitigation to be implemented; 6.
Inform
IC(E), ER and EPD the causes and actions taken for the exceedances; 7.
Assess
effectiveness of Contractor’s remedial actions and keep IC(E), EPD and ER
informed of the results; 8.
If
exceedance stops, cease additional monitoring. |
1.
Discuss
amongst ER, ET, and Contractor on the potential remedial actions; 2.
Review
Contractors remedial actions whenever necessary to assure their effectiveness
and advise the ER accordingly; 3.
Supervise
the implementation of remedial measures. |
1.
Confirm receipt
of notification of failure in writing; 2.
Notify
Contractor; 3.
Require
Contractor to propose remedial measures for the analysed noise problem; 4.
Ensure remedial
measures properly implemented; 5.
If exceedance
continues, consider what portion of the work is responsible and instruct the
Contractor to stop that portion of work until the exceedance is abated. |
1.
Take
immediate action to avoid further exceedance; 2.
Submit
proposals for remedial actions to IC(E)
within 3 working days of notification; 3.
Implement
the agreed proposals; 4.
Resubmit
proposals if problem still not under control; 5.
Stop
the relevant portion of works as determined by the ER until the exceedance is
abated. |