Table 4.2 Event and Action Plan for Water Quality
Event |
ET Leader |
IC(E) |
ER |
Contractor |
Action level being exceeded by one sampling day |
Repeat in situ measurement to confirm
findings; Identify reasons for non-compliance and source(s) of impact; Inform IC(E) and
Contractor; Check monitoring
data, all plant, equipment and Contractor's working methods; Discuss mitigation
measures with IC(E) and Contractor; Repeat measurement
on next day of exceedance. |
Discuss with ET and
Contractor on the mitigation measures; Review proposals on
mitigation measures submitted by Contractor and advise the ER accordingly; Assess the
effectiveness of the implemented mitigation measures. |
Discuss with IC(E)
on the proposed mitigation measures; Make agreement on
the mitigation measures to be implemented. Assess the
effectiveness of the implemented mitigation measures. |
Inform the ER and
confirm notification of the non-compliance in writing; Rectify unacceptable practice; Check all plant and equipment; Consider changes of
working methods; Discuss with ET and
IC(E) and propose mitigation measures to IC(E) and ER; Implement the
agreed mitigation measures. |
Action level being
exceeded by more than two consecutive sampling days |
Repeat in situ measurement to confirm
findings; Identify reasons for non-compliance and source(s) of impact; Inform IC(E) and
Contractor; Check monitoring
data, all plant, equipment and Contractor's working methods; Discuss mitigation
measures with IC(E) and Contractor; Ensure mitigation
measures are implemented; Prepare to increase
the monitoring frequency to daily; Repeat measurement
on next day of exceedance. |
Discuss with ET and
Contractor on the mitigation measures; Review proposals on
mitigation measures submitted by Contractor and advise the ER accordingly; Assess the
effectiveness of the implemented mitigation measures. |
Discuss with IC(E)
on the proposed mitigation measures; Make agreement on
the mitigation measures to be implemented; Assess the
effectiveness of the implemented mitigation measures. |
Inform the ER and
confirm notification of the non-compliance in writing; Rectify
unacceptable practice; Check all plant and
equipment; Consider changes of working methods; Discuss with ET and
IC(E) and propose mitigation measures to IC(E) and ER within three working
days; Implement the
agreed mitigation measures. |
Limit level being
exceeded by one sampling day |
Repeat in situ measurement to confirm
findings; Identify reasons for non-compliance and source(s) of impact; Inform IC(E)
Contractor and EPD; Check monitoring
data, all plant, equipment and Contractor's working methods; Discuss mitigation
measures with IC(E), ER and Contractor; Ensure mitigation
measures are implemented; Increase the
monitoring frequency to daily until no exceedance of Limit level. |
Discuss with ET and
Contractor on the mitigation measures; Review proposals on
mitigation measures submitted by Contractor and advise the ER accordingly; Assess the
effectiveness of the implemented mitigation measures. |
Discuss with IC(E),
ET and Contractor on the proposed mitigation measures; Request Contractor
to critically review the working methods; Make agreement on
the mitigation measures to be implemented; Assess the
effectiveness of the implemented mitigation measures. |
Inform the ER and
confirm notification of the non-compliance in writing; Rectify
unacceptable practice; Check all plant and
equipment; Consider changes of
working methods; Discuss with ET,
IC(E) and ER and propose mitigation measures to IC(E) and ER within three
working days; Implement the
agreed mitigation measures. |