5.1
Introduction
5.1.1
The terrestrial ecological impact
assessment conducted for this Study concluded that impacts resulting from the
proposed development would be relatively minor, being on the whole restricted
to existing disturbed or low ecological value habitats and common and
widespread species. Nevertheless, impacts to some species of conservation
interest were identified that would require mitigation and monitoring.
Additionally, general measures to minimise identified terrestrial ecological
impacts were recommended. Terrestrial ecological mitigation measures and
monitoring requirements are described in the following sections.
Vegetation
5.2.1
Developments
proposed under this Project would have the potential to directly impact two
plant species of conservation interest; Small Persimmon (Diospyros vaccinioides) and Bamboo Orchid (Arundina chinensis). Affected individuals of these species
should be transplanted to suitable nearby habitats prior to the construction
phase. Transplantation should be conducted by a suitably qualified
botanist/horticulturalist. A detailed transplantation methodology should be
formulated during the detailed design stage for this Project.
5.2.2
Following transplantation, the health
and condition of individuals of the two plant species of conservation interest
affected by the proposed works should be monitored. Monitoring should cover the
12-month period following transplantation, and be conducted at least twice a
month for the first four months after transplantation, and once a month for the
remaining eight months. Monitoring should be conducted by a suitably qualified
botanist/horticulturalist appointed by the Project Proponent.
5.2.3
A
tree survey should be conducted to identify any mature trees potentially
affected by the proposed works. Felling of mature trees should be compensated
by planting of standard or heavy standard trees.
5.2.4
Landscaping
works on reclaimed land, newly created slopes and roadsides should incorporate
native plant species that are attractive to wildlife (e.g., trees producing
flowers/fruits that attract avifauna and insects).
Philippine Neon Goby
5.2.5
One
fish species of conservation interest (Philippine Neon Goby, Stiphodon artopurpureus) was recorded from a small stream
(E-WCR stream) adjacent to the proposed Western Coast Road (WCR) reclamation
alignment. To mitigate potential impacts to this species, the following
measures should be implemented.
5.2.6
Adequate
fencing/hoarding should be erected around works areas close to the E-WCR stream
during the construction phase. The hoarding/fencing would prevent and minimise
disturbance from site workers, the dumping/storage of materials close to the
stream and potential accidental spillage of pollutants into the stream.
5.2.7
Adult
Philippine Neon Gobies should be captured from the E-WCR stream and transferred
to fish tanks prior to the start of the construction phase. In this way, the
habitat conditions of the fishes can be closely monitored and controlled,
thereby maximising the probability of their survival. Following the completion of Phase I Reclamation Works (which is
expected to last for about 1 year only), the fish would be re-introduced into
the preserved E-WCR stream.
5.2.8
Detailed
methodologies for the capture and maintenance of adult fish from the E-WCR
stream should be drafted during the detailed design stage of the Project.
5.2.9
Following
completion of the Phase I Reclamation, Philippine Neon Gobies would be released
back into the preserved E-WCR stream. To maximise the breeding success of the
population, the design of reclamation works for the WCR have been considered to
maintain the connection between the E-WCR stream and marine habitats. The
alignment of the reclamation would avoid an area of marine habitat at the base
of the E-WCR stream. This area would in turn be connected to Junk Bay via a
large pipe (min 2.5m in diameter) running underneath the proposed reclamation
for the remainder of the construction phase. A permanent culvert of similar or
larger size would be constructed to replace the pipe during the operation
phase. This design would allow relatively free passage of larvae from the
stream to marine habitats, and also the migration of juvenile fish from Junk
Bay back to the stream.
5.2.10
With
regard to mitigation measures recommended for the Philippine Neon Goby, it
should be noted that the proposed reclamation works in the E-WCR Assessment
Area are not scheduled to commence until 2010. The present Goby population in
the E-WCR stream is small, relatively isolated, and therefore potentially at
risk, regardless of the potential impacts that could result from this Project
or other construction works in Junk Bay. In a ‘worst-case’ scenario, a single
severe pollution incident in the E-WCR stream or local marine habitats could
result in the local extinction of the species. Further surveys of the stream
should therefore be conducted 1-2 years before construction works commence, and
the requirement for construction phase mitigation reviewed based on the
findings of these surveys.
5.2.11
Monitoring
and audit of the mitigation measures recommended for the Philippine Neon Goby
would be required. Detailed monitoring requirements should be formulated as
part of the methodology to be drafted in the detailed design stage of the
Project, and should include:
·
To determine the extent of
construction phase mitigation measures required, surveys of the E-WCR stream
should be conducted 1-2 years before construction works commence. The surveys
should record the number of Philippine Neon Gobies present in the stream. At
least four surveys should be conducted, covering both the wet and dry seasons.
·
During the construction phase, regular
monitoring of the condition of captive fish and water quality in the fish tanks
(e.g., pH, DO, nutrient levels) would be required. Monitoring should be
conducted at least twice a month, and remedial measures (e.g., increased water
filtration/water changes to reduce nutrient levels, increasing/decreasing
aeration to maintain DO) implemented as and when required.
·
Following
the re-introduction of Philippine Neon Gobies into the E-WCR Stream, fish
populations should be regularly monitored for a period of at least 3 years. Monitoring should be conducted on
a bi-weekly basis in the first 2 months, monthly for the rest of the first year
and quarterly for the second and third year. The number and sex of fishes in the Stream should
be recorded, along with any evidence of breeding activity (e.g., presence of
juvenile fish). Care should be taken during the monitoring to avoid undue
disturbance to the stream habitat in general and Goby populations in
particular.
Good Site Practice
5.2.12
Standard
good site practice measures should be implemented throughout the construction
phase. The measures should include:
·
Placement of equipment or stockpile in
designated works areas and access routes selected on existing disturbed land to
minimise disturbance to natural habitats.
·
Construction activities should be
restricted to works areas that should be clearly demarcated. The works areas
should be reinstated after completion of the works.
·
Waste skips should be provided to
collect general refuse and construction wastes. The wastes should be properly
disposed off-site in a timely manner.
·
General drainage arrangements should
include sediment and oil traps to collect and control construction site
run-off.
·
Open burning on works sites is
illegal, and should be strictly prohibited.
Disturbance Impacts
5.2.13
Measures
should be implemented to minimise potential disturbance to habitats adjacent to
works areas where possible, particularly during the construction phase. The
following measures are recommended:
·
Use of quiet mechanical plant during
the construction phase should be adopted wherever possible.
·
General measures to reduce noise
generated during the construction phase should be effectively implemented.
·
Hoarding or fencing should be erected
around the works area boundaries during the construction phase. The hoarding
would screen adjacent habitats from construction phase activities, reduce noise
disturbance to these habitats and also to restrict access to habitats adjacent
to works areas by site workers.
Dumping/Dust Deposition
5.2.14
The
implementation of mitigation measures detailed in Section 9 of this EM&A Manual would minimise impacts to habitats adjacent to
works areas resulting from improper storage of materials or dumping of
waste.
5.2.15
Measures
to control dust emissions during the construction phase such as regular
spraying of haul roads should be implemented to minimise impacts to adjacent
vegetation and habitats. Further details of measures to minimise dust and air
quality impacts resulting from the proposed development are presented in
Section 2 of this Report.
Sedimentation/Water Quality Impacts
5.2.16
Measures
to control potential sedimentation/water quality impacts during the construction
phase should be implemented. Such measures are detailed in Section 4 of this EM&A Manual, and should include:
·
To minimize sedimentation and soil
erosion, soil excavation should be scheduled for the dry season where
practicable. Exposed areas of soil should be covered with tarpaulin or other
material to minimize potential sedimentation.
·
Interceptor channels should be
constructed around the boundaries of works areas to collect site run-off.
Run-off should be routed through silt traps/oil interceptors before being
discharged.
·
Adequate toilet facilities should be
provided for site workers.
5.2.17 During
the operation phase, it is recommended that all stormwater drainage from
Development Area 78 be routed through silt traps and oil interceptors prior to
discharge.
Auditing Requirements
5.2.18
The implementation of all mitigation
measures described in the previous sections should be subject to regular audit.