A15 implementation
schedule of the proposed mitigation measures
Table 15.1
Implementation Schedule of Air Quality Measures
EIA Ref |
EM&A Ref |
Environmental Protection
Measures* |
Location / Timing |
Implementation Agent |
Implementation Stages** |
Relevant Legislation &
Guidelines |
||
D |
C |
O |
||||||
Air
Quality - Construction Phase |
||||||||
|
|
In
order that nuisance to air sensitive receivers is minimized, it is important
to minimize dust emissions from construction activities including cut and
fill operations and trucks movements on haul road. Dust
control techniques should be considered to control dust to a level not
exceeding the AQOs as well as the 1-hour · Adoption of good site practices; · Avoid practices likely to raise dust
level; · Frequent cleaning and damping down of
stockpiles, dusty areas of the Site and the haul roads; · Reduce the speed of the vehicles (say 10 kph) on the haul road; · Reducing drop height during material
handling; · Provision of wheel-washing facilities for
Site vehicles leaving the Site; · Regular plant maintenance to minimize
exhaust emission; · Sweep up dust and debris at the end of
each shift; and · If concrete batching plant or rock
crushing plant is planned to used, a license from |
Work site / during
construction |
All contractors |
|
Ö |
|
EIAO-TM, APCO, Air Pollution Control
(Construction Dust) Regulation |
|
|
Providing
watering four times a day for dust suppression. |
Work site / during construction |
All contractors |
|
Ö |
|
EIAO-TM, APCO, Air Pollution Control
(Construction Dust) Regulation |
Air Quality - Operational
Phase |
||||||||
|
|
N/A |
|
|
|
|
|
|
*
All recommendations and requirements resulted during the course of EIA Process,
including ACE and/or accepted public comment to the proposed project.
**
D=Design, C=Construction, O=Operation
Table 15.2
Implementation Schedule of Water Quality Control Measures
EIA Ref |
EM&A Ref |
Environmental Protection
Measures* |
Location
(duration/completion of measures) |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and
Guidelines |
||
D |
C |
O |
||||||
Water Quality
- Construction Phase |
||||||||
|
|
Proposed 18
holes Golf Course Layout Design For the
construction activity which is unavoidable near natural streams (within the
buffer zone), mainly the construction of crossings, preventative mitigation
measures during the construction stage should be follow by the Contractor,
they are shown as follows: l The proposed works site inside or in the
proximity of natural streams should be temporarily isolated, through by
placement of sandbags or silt curtains and properly supported by props, to
prevent adverse impacts on the stream water qualities; l The natural bottom and existing flow in
the stream should be preserved to avoid disturbance to the stream habitats; l No direct and indirect discharge into the
natural stream is allowed from any construction work activities; l Stockpiling of construction material, if
any, should be properly covered and located away from any natural stream; l Monitor rain forecast closely and cover
any exposed spoil when rainstorms are forecated. Debris should be properly disposed of
before rainstorm to avoid any inadvertent wash away into the stream; and l Removal of existing vegetation alongside
the stream should be avoided.
When disturbance to vegetation is unavoidable, all disturbed areas
should be hydroseeded or planted with suitable
vegetation to blend in with the natural environmental upon completion of
works. |
Work site / During the
construction period |
All contractors |
|
Ö |
|
ProPECC PN 1/94; WPCO; TM-Effluent
Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland
and Coastal Water |
|
|
Runoff and Drainage
Management u Diversion
of upstream flows around the works areas for stream crossings and underground
pipes: To minimize the
impact of upstream runoff on the Works area by preventing storm flows
reaching the work areas. This will be done through provision of upstream
cut-off drains to intercept the flows and divert them around the Works
area. It would convey flows to
downstream stream courses, or other elements of temporary drainage systems
(such as storage facilities). u Temporary
covering the works areas during severe storm events: Significant rainstorm events can be
reasonably well forecast and when heavy rain is predicted, mitigation
measures should be provided for the vulnerable areas by using tarpaulins,
plastic sheets or other temporary covering to protect works area and minimize
damage and erosion. It is
recommended not to cover the newly establishment grass areas, and if
unavoidable, this should only to be done on a short term basis (less than 24
hours). u Silt
traps and sedimentation tanks for main discharge routes form works area: Sufficient and suitably sized silt traps
and/or sedimentation tanks should be provided at the downstream ends of the
systems to remove suspended solids prior to discharge. The discharge water quality shall be
compliant with the TM on Standards for
Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal
Waters under the WPCO. The
required volume of the sedimentation tanks will depend on the catchment area served. Multiple tanks in series may also be
required where runoff might be expected to be silty. u The design details of the temporary drainage system
at turf establishment area follow the same principles of the permanent
drainage system. However the
component pipes, tanks, lakes and/or pumps may differ in size, shape,
location, etc. from that of the permanent system, dependent upon the
temporary runoff areas as compared with those of the permanent system. Additionally or alternatively, the
temporary drainage system may consist of other methods to control soil
erosion and/or to facilitate the collection of surface water runoff. The temporary
drainage system will function during the period of time in which the
permanent system is not yet completed.
This circumstance will arise from the fact that the golf holes,
inclusive of the permanent drainage system, will be constructed individually. As a result, the permanent drainage
system may not be completed in its entirety until connection is made from
each respective golf hole area to the
lake/reservoir. As the permanent
drainage system is completed for each hole, the corresponding temporary
system will be decommissioned and reused elsewhere. The temporary drainage
system will be in use until the permanent system is functional in a given
area. Once the permanent system
is functional in a given area, the temporary system will be decommissioned
and, wherever possible, the components re-used in another temporary drainage
system installed elsewhere. It is
anticipated that the maximum duration of use for the temporary drainage
system in any given area will be one-year. The storage tanks
and/or lakes will be designed to segregate suspended solids (or pollutants as
may be the case in plant/equipment storage and refueling areas) as may be
necessary by contract requirements and reuse. u No irrigation, fertilizer and pesticide
applications to the turf would be permitted during rainstorm events or when
heavy rainstorm is predicted 24 hours before the application. u Runoff from materials storage areas,
particularly fuel and chemicals storage area should be separated from the
main drainage systems (bunded, if necessary) and
provided with dedicated facilities throughout the construction period, such
as petrol interceptors. The Contractor
shall follow good site practices and be responsible for the design,
construction, operation, and maintenance of all the mitigation measures as
specified in ProPECC PN1/94 on construction site drainage
through the construction period.
These practices include: l
Temporary
ditches should be provided to facilitate run-off discharge into appropriate
watercourses, via a silt retention pond. l
All
drainage facilities and erosion and sediment control structures should be
inspected monthly and maintained to ensure proper and efficient operation at
all times. l
Excavation
of soil that cannot be avoided during the wet season, and exposed surface or
open stockpiles should be covered with tarpaulin or other means. Other measures that need to be
implemented before, during and after rainstorms are summarized in ProPECC PN1/94. l
Exposed
soil areas should be minimized to reduce potential for increase siltation and contamination of runoff. l
Earthwork
final surfaces should be well compacted and subsequent permanent work (turf
establishment) should be immediately performed. l
The
Contractor shall contain within the site all surface runoff generated from
the construction works, concreting works, dust control and vehicle washing,
etc. l
The
Contractor shall arrange other measures, such as provision of sand bags or
temporary diversion systems to prevent washing away of soil, silt or debris
into any nearby natural streams.
Any runoff shall be diverted into appropriate sediment traps before
discharging to the nearby drainage system. The discharge water quality shall be
compliant with the TM on Standards for
Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal
Waters under the WPCO. l
The
Contractor shall observe and comply with the Water Pollution Control
Ordinance (WPCO) and its subsidiary regulations by implementing environmental
protection measures (such as the use of silt traps) and preventing any point
or non-point source of pollution. |
Work site / During the
construction period |
All contractors |
|
Ö |
|
ProPECC PN 1/94; WPCO; TM-Effluent
Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland
and Coastal Water |
|
|
Concrete
bridge construction No work is
allowed to come into contact with the underlying stream bed during the
concrete bridge construction.
During the construction of precast concrete
bridge, if necessary, precaution measures should be taken to ensure no
potentially polluting liquid or solid wastes fall into the stream. This is essential to avoid water
quality impacts within ecologically sensitive streams. The Contractor
shall good site follow practices, including, but no limited to:: l
Construction
work area for the precast concrete should be
outside the designated stream buffer zone area; l
The
designated work area for precast concrete work
should be covered to minimize the potential water runoff during rain from the
construction area; l
All
water used within the concrete work area should be collected, stored and
recycled to reduce resource consumption.
Stormwater runoff from the works areas fro precast concreting works should drain under gravity
towards a sedimentation basin.
The overlying water from the sedimentation basin should be recycled
for reuse within the plant. The
deposited sediment should be dewatered and the dry matter should require
disposal off-site. No water
should be discharged outside the boundary of the precast
concrete works area; l
The
use of tarpaulin sheet or other means (water impermeable texture) should be
placed beneath precast concrete beam level (must be
above the stream bed level) to capture any falling object during installation
of precast concrete bridge on the footings or
abutments; l
Prohibition
of any direct and indirect discharge into the streams; l
The
concrete bridge and footings of abutments must be completely above the high
water mark; l
All
equipment and machinery must be free of leaks or excess oil and grease; l
Equipment
refueling or servicing or storage of fuel must be undertaken at a minimum of
30 meters from the stream; l
Prevent
soil and trash from getting into stream during construction by use of silt
fence, fiber rolls, gravel bags and other effective means; l
All
bare soil (abutment slope or temporary stockpile) must be covered with
tarpaulin or other means before forecast rain; and l
|
Work site / During the
construction period |
All contractors |
|
Ö |
|
ProPECC PN 1/94; WPCO; TM-Effluent
Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland
and Coastal Water |
|
|
Dredging
during Construction of Desalination Plant’s intake and outfall The intake and
outfall pipelines will be constructed by dredging the seabed to form a trench
and backfilled with a layer of bedding material (quarry run stone) before
putting the pipelines in place.
Once in place, the pipelines are covered with layers of rock armour on top of the pipelines to protect the pipelines
against damage by wave action.
The alternative backfilling material is from rock excavated during
site formation if suitable. The materials used
for the backfilling at the intake and outfall pipelines are stone and rock armour only. Transfer of
backfilling materials onto the seabed from barge should be conducted by
careful grabbing and unloading to seabed (to minimize sediment migration),
thereby minimize impacts on water quality to nearby water sensitive
receivers. As a preventative measures, silt curtain
will also be required during the backfilling activities. The expected backfilling duration is
approximate 2 months. The Contractor
shall use backhoe for dredging works at a water depth of less than In order to avoid
pollution during dredging, transporting and dumping of marine mud. Pollution avoidance measures shall
include but not be limited to the following: · The maximum daily dredging rate for closed
grab dredger should be · The maximum daily dredging rate for
backhoe should be · Silt curtain should be installed for any
dredging methods to protect the WSRs; · Closed grabs or sealed grabs should only
be used for locations with water depths > · Backhoe should only be used for locations
with water depths < · All equipment should be designed and
maintained to minimise the risk of silt and other
contaminants being released into the water column or deposited in locations
other than designated location; · Mechanical grabs should be designed and maintained
to avoid spillage and should seal tightly while being lifted; · No trailing suction hopper dredgers would
be deployed for the dredging of marine mud; · All vessels should be sized such that
adequate clearance is maintained between vessels and the sea bed at all
states of the tide to ensure that undue turbidity is not generated by
turbulence from vessel movement or propeller wash; · All pipe leakages should be repaired
promptly and plant shall not be operated with leaking pipes; · Before moving the vessels which are used
for transporting dredged materials excess material should be cleaned from the
decks and exposed fittings of vessels and the excess materials should never
be dumped into the sea except at the approved locations; · Adequate freeboard should be maintained on
barges to ensure that decks are not washed by wave action; · The Contractor should monitor all vessels
transporting material to ensure that no dumping outside the approved location
takes place. The contractor should keep and produce logs and other records to
demonstrate compliance and that journey times are consistent with designated
locations and copies of such records should be submitted to the engineer; · All bottom dumping vessels should be
fitted with tight fitting seals to their bottom openings to prevent leakage
of material; · Loading of barges and hoppers should be
controlled to prevent splashing of dredged material to the surrounding water,
and vessels should not be filled to a level which will cause overflowing of
material or polluted water during loading or transportation; and · The engineer may monitor any or all
vessels transporting material to check that no dumping outside the approved
location nor loss of material during transportation
takes place. The contractor should provide all reasonable assistance to the
engineer for this purpose. In addition,
baseline water quality monitoring before commencement of the marine works
shall be carried out in the nearby waters to obtain baseline information for
subsequence monitoring. Regular
and frequent water quality monitoring shall be carried out throughout the
whole construction period to ensure the water quality during construction is
well within the established environmental guidelines and standards. Silt Curtain In order to minimize impacts during the
whole construction period of desalination plant’s intake and discharge
outfall, silt curtains should be utilized to minimize sediment
migration. The Contractor shall
be responsible for the design, installation and maintenance of the silt
curtains to minimize the impacts on the water quality and the protection of
water sensitive receivers. The
design and specification of the silt curtains shall be submitted by the
Contractor to the Engineer for approval.
Area of the silt curtain to enclose the works area should be minimized
in order to reduce the disturbance of ecological sensitive areas nearby. A typical suspended solids reduction of 75% can be achieved with the
incorporation of silt curtain. Two-layer silt curtains have generally been
used for dredging projects of larger scale to further ensure this reduction.
However, as the scale of proposed project is considered small, it is
recommended to use single layer silt curtain which can achieve a minimum 75%
suspended solids reduction. Silt curtains
shall be formed from tough, abrasion resistant, permeable membranes, suitable
for the purpose, supported on floating booms in such a way as to ensure that
the sediment plume shall be restricted to within the limit of the works area. The silt curtain
shall be formed and installed in such a way that tidal rise and fall are
accommodated, with the silt curtains always extending from the surface to the
bottom of the water column. The removal and reinstallation of such curtains
during typhoon conditions shall be as agreed with the Director of Marine
Department. The Contractor shall regularly inspect the
silt curtains and check that they are moored and marked to avoid danger to
marine traffic. Any damage to the silt curtain shall be repaired by the
Contractor promptly and the works shall be stopped until the repair is effected to the satisfaction of the Engineer. |
Work site / During the
construction period |
All contractors |
|
Ö |
|
ProPECC PN 1/94; WPCO; TM-Effluent
Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland
and Coastal Water |
|
|
General
Construction Activities Debris and
refuse generated on-site should be collected, handled and disposed of
properly to avoid entering adjacent watercourse. Stockpiles of construction materials
should be kept covered when not being used. Oils and fuels
should only be stored/handled in designated areas
with pollution prevention facilities.
Oil interceptors need to be regularly inspected and cleaned to avoid
wash-out of oil during storm conditions. Contractor
should provide a safe storage area for chemicals on site. The Contractor is required to register
as a chemical waster producer if chemical wastes would be produced from the
construction activities. All fuel tanks
should be provided with locks and be sited on sealed areas within bunds of
capacity equal to 110% of the storage capacity of the largest tank. Good
housekeeping practices and staff training are required to minimize careless
spillage and keep the work space in a tidy and clean
conditions at all times.
Accidental spillage of chemicals in the works area would directly
affect the aquatic environment.
It is recommended that the Contractor should develop management procedures
for chemical and implement an emergency plan to deal with chemical spillage
in case of an accident. Disposal of chemical wastes should be
carried out in compliance with the Waste Disposal Ordinance. The chemical waste should be
transported to a facility licensed to receive chemical waste, such as the
Chemical Waste Treatment Facility at Tsing Yi. The Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes details
the requirements to deal with chemical wastes. |
Work site / During the
construction period |
All contractors |
|
Ö |
|
ProPECC PN 1/94; WPCO; TM-Effluent
Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland
and Coastal Water |
|
|
On-Site Sewage
Effluents In order to
prevent sewage effluents affecting water courses, the following mitigation
measures should be provided by the Contractor:- ·
Temporary
sanitary facilities, such as portable chemical toilets, should be employed
on-site to handle sewage from the workforce; ·
The toilet facilities should be more than ·
Temporary
storage tank should be provided to collect wastewater from kitchens or
canteen, if any; ·
A licensed waste collector should be deployed to
clean the chemical toilets on a regular basis which will be and disposed of at government sewage
treatment facilities; ·
Regular
environmental audit on the construction site can provide an effective control
of any malpractices and can achieve continual improvement of environmental
performance on site. It is
anticipated that sewage generation during the construction phase of the
project would not cause water pollution problem after undertaking all
required measures; and ·
Notices
should be posted at conspicuous locations to remind the workers not to
discharge any sewage or wastewater into the nearby environment during the
construction phase of the project. |
Work site / During the construction period |
All contractors |
|
Ö |
|
ProPECC PN 1/94; WPCO; TM-Effluent
Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland
and Coastal Water |
|
|
Concrete batching plant All water used
within the concrete batching plant will be collected, stored and recycled to
reduce resource consumption. This
includes water used in the concrete batching process, truck cleaning, yard
washing and dust suppression spraying.
All spent dust suppression effluent will be collected and
recycled. To minimize the
potential water quality impacts that may generate from the concrete batching
plant, a drainage system should be provided in this
site. The batching plant area should be channelled
to collect concrete washings for further treatment before reuse on-site and
prevent concrete washings from directly entering the any stream or seawater. Site runoff should also be collected
through the drainage system. To minimize the generation of contaminated site
runoff from concrete production area, the concrete batching plant should be
sheltered. Concrete
washings and site runoff should be pumped to a wastewater treatment system
with a sedimentation unit for removal of suspended solids such as waste
concrete particles, silt and grit in order to achieve the discharge
standards. pH
adjustment should also be applied if the pH value of the collected concrete
washings and site runoff is higher than the pH range specified in the
discharge licence. This can be achieved by adding
neutralizing regents, i.e. acidic additive. A discharge licence
should be applied from The drainage
system should be maintained on a regular basis to remove the deposits on the
channels. The sedimentation and pH adjustment systems should also be checked
and maintained by competent persons to ensure that the systems are
functioning properly at all times. The deposited
sediment will be dewatered and the dry matter will require disposal
off-site. The estimated maximum
concentrate batching operation period during construction is 20 months. Sand, gravel
and other bulk materials will be delivered from the production area by
conveyor boats or derrick barges to the temporary barging point, and the
material will then be loaded onto dump trucks by loaders and delivered to the
on-site storage areas. Regular
environmental inspections should be conducted to check the environmental
performance of daily operation.
These inspections will ensure proper installation and maintenance of
pollution control measures, such as checking of sedimentation basin,
wastewater recycling facility and enclosure of stockpiles, and the
implementation of other mitigation measures. |
Work site / During
the construction period |
All
contractors |
|
Ö |
|
ProPECC PN 1/94; WPCO;
TM-Effluent Standards for Effluents Discharged into Drainage and Sewerage
Systems, Inland and Coastal Water |
Water
Quality - Operation Phase |
||||||||
|
|
Provide runoff filter system and biopesticides application at Hole 5 and Hole 6. Routine water quality monitoring of
the filter system effluent water quality on nutrient and pesticides removal
performance during the operation of the filter system will be required by the
golf course operator to ensure the filter systems function properly. |
Golf
course/During the operation phase |
Golf course operator |
|
|
Ö |
|
*
All recommendations and requirements resulted during the course of EIA/EA
Process, including ACE and/or accepted public comment to the proposed project.
**
Des - Design, C = Construction, O = Operation
N/A
Not applicable
Table 15.3 Implementation
Schedule of Waste Management Measures
EIA Ref |
EM&A Ref |
Environmental Protection
Measures* |
Location / Timing |
Implementation Agent |
Implementation Stages ** |
Relevant Legislation &
Guidelines |
||
D |
C |
O |
||||||
Waste Management - Construction Phase |
||||||||
|
|
Good site
practice to minimize solid waste generation, including: u
nomination of approved personnel, such as a site manager, to be
responsible for good site practices, and making arrangements for collection
of all wastes generated at the site and effective disposal to an appropriate
facility; u
training of site personnel in proper waste management and chemical
waste handling procedures; u
provision of sufficient waste disposal points and regular collection
for disposal; u
appropriate measures to minimise windblown litter and dust during
transportation of waste by either covering trucks or by transporting wastes
in enclosed containers; u
regular cleaning and maintenance programme for drainage systems, sumps
and oil interceptors; u
a Waste Management Plan should be prepared and should be submitted to the Engineer for approval. One may
make reference to ETWB TCW No. 15/2003 for details; and u
a recording system for the amount of wastes generated, recycled and
disposed (including the disposal sites) should be proposed. |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
WDO; Public Health and Municipal Services Ordinance; The
Land (Miscellaneous Provisions) Ordinance; ETWB TCW NO. 15/2003. |
|
|
Good
management and control can prevent the generation of significant amounts of
waste. Waste reduction is best achieved at the planning and design
stage, as well as by ensuring the implementation of good site
practices. Recommendations to achieve waste reduction include: u segregation and storage of different
types of waste in different containers, skips or stockpiles to enhance reuse
or recycling of materials and their proper disposal; u separate labelled bins shall be
provided to segregate aluminium cans from other general refuse generated by
the work force, and to encourage collection of by individual collectors; u any unused chemicals or those with
remaining functional capacity shall be recycled; u maximising the use of reusable
steel formwork to reduce the amount of C&D material; u prior to disposal of C&D waste,
it is recommended that wood, steel and other metals shall be separated for
re-use and / or recycling to minimise the quantity of waste to be disposed of
to landfill; u proper storage and site practices
to minimise the potential for damage or contamination of construction
materials; u
plan and stock construction materials carefully to minimise amount of
waste generated and avoid unnecessary generation of waste; u minimize over ordering of concrete,
mortars and cement grout by doing careful check before ordering. |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
WDO; Public Health and Municipal Services Ordinance;
The Land (Miscellaneous Provisions) Ordinance; ETWB TCW NO. 15/2003. |
|
|
Site Clearance Waste Scrub
and other vegetation will be stripped for the tees, fairways, greens and
access roads. The normal route for disposal for such material is landfill but
in this case it is proposed that vegetation is passed through a
"chipper" to break down the material into a medium that can be used
as mulch / compost and provide a seed-bank for natural hydroseeding
of exposed areas. Non-inert materials should be kept
separate and reused on-site as fill in preference to disposal at public
filling areas which are operated by CEDD or disposal at landfill. |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
WDO; Public Health and Municipal Services Ordinance ; The Land (Miscellaneous Provisions) Ordinance;
ETWB TCW NO. 15/2003. |
|
|
Excavated Materials Material generated during open cut
works, and access route formation will comprise rock and soil and all this
material will be reused in the site shaping process. It is anticipated that
there will be no material requiring disposal off-site in public filling
areas. |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
WDO; Public Health and Municipal Services Ordinance;
The Land (Miscellaneous Provisions) Ordinance; ETWB TCW NO. 15/2003. |
|
|
Construction and Demolition (C&D) Material The C&D material generated from
the site formation and demolition works should be sorted on-site into inert
C&D material and C&D waste. In order to minimise
the impact resulting from collection and transportation of C&D material
for off-site disposal, the excavated material comprising fill material should
be reused on-site as backfilling material. C&D waste, such as wood,
plastic, steel and other metals should be reused or recycled and, as a last
resort, disposed of to landfill. A suitable area(s) should be designated
within the site for temporary stockpiling of C&D material and to
facilitate the sorting process. The stockpiling/sorting area should be
located far away from the identified sensitive receivers. |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
WDO; Public Health and Municipal Services Ordinance;
The Land (Miscellaneous Provisions) Ordinance; ETWB TCW NO. 15/2003. |
|
|
Site fencing Some site fencing may be
required. Attention should be
paid to WBTC No. 19/2001 which introduce a new policy requiring the use of
metallic site hoardings and signboards in order to reduce the amount of
timber used on construction sites. |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
WBTC No. 19/2001 |
|
|
Chemical
Waste Where
the construction processes produce chemical waste, the Contractor must
register with Hard
standing surfaces draining via oil interceptors shall be provided in works
area compounds. Interceptors will be regularly emptied to prevent release of
oils and grease into the surface water drainage system after accidental
spillages. The interceptor should have a bypass to prevent flushing during
periods of heavy rain. Oil and fuel bunkers should be bunded
to prevent discharge due to accidental spillages or breaches of tanks. Waste
collected from any grease traps should be collected and disposed of by a
licensed contractor. Any
construction plant which is likely to leak oil,
should have absorbent inert material e.g. sand, placed beneath it. This
material should be replaced on a regular basis and the contaminated material
should be stored in a designated, secure place. Any sand used for soaking oil
waste is classified as chemical waste and should be disposed of in accordance
with the Waste Disposal (Chemical
Waste) (General) Regulations. Lubricants
and waste oils are likely to be generated during the maintenance of vehicles
and mechanical equipment. Used lubricants will be collected and stored in
individual containers which are fully labelled. The
containers should be stored in a designated secure place. If possible such
waste should be sent to oil recycling companies; there are also companies
which collect empty oil drums for reuse or refill. Oil
and lubricant wastes are classified as chemical wastes, and if not recycled,
should be collected by licensed collector and should be treated at the
Chemical Waste Treatment Centre, Tsing Yi, or other
sites licensed for disposal of waste oil. A trip ticket system operates to
control the movement of such chemical waste and tickets have to be produced
upon the request of Some
paints and solvents are classified as chemical waste and, if used on site,
will be subject to the stringent requirements of the Waste Disposal (Chemical Waste) (General) Regulation. Empty paint
cans should be recycled or collected as waste. Any dry paint waste should be
swept up and collected in containers for disposal. No lubricants, oils, solvents or
paint products should be allowed to discharge into water courses, either by
direct discharge, or as contaminants carried in surface water runoff from the
construction site. |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
Waste Disposal (Chemical Waste) (General) Regulation |
|
|
Sewage An adequate
number of portable toilets should be provided for the on-site construction
workforce. The portable toilets
shall be maintained in a state that will not deter the workers from using
them. |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
WDO; Public Health and Municipal Services Ordinance;
The Land (Miscellaneous Provisions) Ordinance; ETWB TCW NO. 15/2003. |
|
|
General Refuse General
refuse should be stored in enclosed bins or compaction units separate from
C&D material. A reputable waste collector should be employed by the
contractor to remove general refuse from the site, separately from C&D
material. An enclosed and covered area is preferred to reduce the
occurrence of 'wind blown' light material. Solid and liquid wastes will be
generated by the construction workers during the clearance/construction
period. The refuse (mainly non-recyclable materials) will be collected
regularly in black refuse bags and delivered to the existing solid waste
disposal system and transferred to landfill for disposal. |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
WDO; Public Health and Municipal Services Ordinance;
The Land (Miscellaneous Provisions) Ordinance; ETWB TCW NO. 15/2003. |
|
|
Marine Sediments The basic
requirements and procedures for dredged mud disposal are specified under the
ETWB TCW No. 34/2002. The
management of the dredging, use and disposal of marine mud is monitored by
the Marine Fill Committee ( During
transportation and disposal of the dredged marine sediments, the following
measures should be taken to minimise potential
impacts on water quality: u
Bottom opening of barges shall be fitted with tight
fitting seals to prevent leakage of material. Excess material shall be cleaned from
the decks and exposed fittings of barges and hopper dredgers before the
vessel is moved. u
Monitoring of the barge loading shall be conducted
to ensure that loss of material does not take place during transportation. Transport barges or vessels shall be
equipped with automatic self-monitoring devices as specified by the DEP. |
Marine Dredging area / During
the construction period |
All Contractors |
|
Ö |
|
ETWB TCW NO. 34/2002. |
Waste Management - Operation Phase |
||||||||
|
|
N/A |
|
|
|
|
|
|
*
All recommendations and requirements resulted during the course of EIA Process,
including ACE and/or accepted public comment to the proposed project.
**
D=Design, C=Construction, O=Operation
Table 15.4
Implementation Schedule of Ecological Impact Measures
EIA Ref |
EM&A Ref |
Environmental
Protection Measures* |
Location / Timing |
Implementation Agent |
Implementation Stages |
Relevant Legislation &
Guidelines |
||
D |
C |
O |
||||||
Design
Phase |
||||||||
|
|
Terrestrial Ecology |
|
|
|
|
|
|
|
|
The temporary drainage system,
which would receive flows from all areas subject to earth works, would
collect all site runoff. The
collected runoff would be retained for turf grass irrigation. |
Work site / During the construction period |
All Contractor |
Ö |
Ö |
|
|
|
|
Impacts
to streams have been avoided during the design stage by designating buffer
zones. Except tributary A2 and the
old tributary B3 where short sections would be culverted,
other streams and tributaries will remain intact. Except at crossings, there will be no
direct disturbance to the stream bed.
To accommodate the construction and golf hole
design, the buffer zone of tributary B2 will be reduced from |
Work site / During the construction period |
All Contractor |
Ö |
Ö |
|
|
|
|
A
closed low flow drainage system is proposed to capture runoff by collecting
surface water from the majority of the proposed third golf course and pump it
back to the existing reservoir for reuse in irrigation. The drainage system design and concept
approach for the proposed third golf course is similar to the existing golf
course, which has been seen as successful, to minimize the impacts to nearby
sensitive receivers. |
Work site / During the construction period |
All Contractor |
Ö |
|
Ö |
|
|
|
Marine Ecology |
|
|
|
|
|
|
|
|
Five
potentials sites were surveyed for the desalination plant and the temporary
barging point. Two locations were chosen as recommended
sites. |
Temporary barging point & Dredging area/Design phase |
All Contractor |
Ö |
|
|
|
|
|
To
avoid impacts on hard coral colonies, a floating barging point (Figure 9.8)
is proposed to replace the original design (baring point supported by
piles) (Figure 9.7).
This could avoid any construction or damage on the shallow waters
where the corals are located.
Impacts on corals would thus be avoided. |
Temporary barging point/ During construction phase |
All Contractor |
Ö |
Ö |
|
|
|
|
Two
plans of pipeline alignments were considered. The site selection survey
results showed that coral colonies and some sparsely
distributed seagrass individuals were found about |
Dredging area/ During construction phase |
All Contractor |
Ö |
Ö |
|
|
|
|
A
filter system is proposed to further improve the quality of the runoff from
Hole 5 and part of the Hole 6.
Nutrients and pesticides would be absorbed by the filter system with
the effectiveness ranging from 67-96%. |
Marsh/ During the construction phase |
Golf course operator |
Ö |
|
Ö |
|
Construction
Phase |
||||||||
|
|
Terrestrial Ecology |
|
|
|
|
|
|
|
|
Haul roads would be located on future
fairway and cart paths alignments to minimise
temporary disturbance of habitats. |
Work site / During the construction period |
All Contractor |
|
Ö |
|
|
|
|
To compensate loss of trees, a total of 42
trees will be transplanted and 967 trees (more than 3:1 ratio) will be
planted on the new golf course (see tree survey reports). 90% of these trees are native, while
76% of these will be light to heavy standard trees, which will provide
instant breeding and foraging habitats for birds and butterflies. The use of light to heavy standard
trees is more preferable to seedlings as bigger trees provide habitats of
higher structural complexity. |
Work site / During the construction period |
All Contractor |
|
Ö |
|
|
|
|
Impacts
to streams have been avoided during the design stage by designating buffer
zones. Except tributary A2 and the
old tributary B3 where short sections would be culverted,
other streams and tributaries will remain intact. Except at crossings at the two small
pipe culverts at the upstream part of tributary B2 and the culvert bridge at
the upstream part of tributary B1, there will be no direct disturbance to the
stream bed. To accommodate the
construction and golf hole design, the buffer zone
of tributary B2 will be reduced from |
Work site / During the construction period |
All Contractor |
|
Ö |
|
|
|
|
Potential impacts due to site runoff would be reduced by scheduling
most of the bulk site formation works during the dry season of 2005 |
Work site / During the construction period |
All Contractor |
|
Ö |
|
|
|
|
At locations of existing
stream courses where construction works would be conducted, including the
underground pipe culvert at tributary A2 and the old tributary B3, the two
small pipe culverts at the upstream part of B2 and the culvert bridge at the
upstream part of B1, bypass flow channel or pipes would be provided before
the commencement of construction and maintain the stream flow until the crossings
and the underground pipe culvert are finished. |
Stream crossing/ During the construction period |
All Contractor |
|
Ö |
|
|
|
|
Avoid disturbance of stream
bed during the construction of the permanent bridges by using precast unit of the bridge segments transported from
other locations and installed to the proposed locations. |
Stream crossing/ During the construction period |
All Contractor |
|
Ö |
|
|
|
|
Good site practice.
Construction materials must be stored at locations away the stream courses. Site runoff would be desilted in settling ponds to reduce the potential for
suspended sediments, organics and other contaminants to enter stream and
marine environment. |
Work site / During the construction period |
All Contractor |
|
Ö |
|
|
8.9 |
Table 4.1 |
Streams
B, C, and D will be monitored monthly during the construction phase to
determine the status of Caridina trifasciata (shrimp) and Nanhaipotamon hongkongensis (freshwater crab). Stream condition will be recorded with
reference to the protective buffer zone.
Encroachment onto the buffer zone will be reported to the ER/ET. Sheet piling will be installed at the
buffer zone perimeter as needed to prevent further encroachment. Stream sedimentation will be reported
to the ER/ET, the agent causing sedimentation will be discovered, and
sedimentation will be stopped. |
Stream B, C & D/ During the construction phase |
All Contractor |
|
Ö |
|
|
|
|
Marine Ecology |
|
|
|
|
|
|
|
|
The temporary drainage system, which would
receive flows from all areas subject to earth works, would collect all site
runoff. The collected runoff
would be retained for turf grass irrigation. |
Work site / During the construction period |
All Contractor |
|
Ö |
|
|
|
|
Dredging for the two pipelines for the
desalination plant would be require 50 days and would be scheduled to the
extent possible from January to April 2006. This would avoid the flowering season
for the seagrass Halophila
ovalis, i.e. November and December (Fong et al.
2005) and the spawning season for corals, i.e. July to October (Lam 2000; Storlazzi, C. D. 2004). |
Dredging area/ during dredging period |
All Contractor |
|
Ö |
|
|
|
|
Coral colonies within the silt curtain, in
particular the 79 colonies identified during the coral mapping survey, (see
Appendix A9.2) would be transplanted.
Prior to commencement of any marine construction works for the
proposed project, the affected coral colonies would be tagged using plastic
labels and a number would be assigned to each. The tagged corals in the dredging area
at D2 site will be transplanted to the bedrock area about |
Dredging area/Prior to dredging |
All Contractor |
|
Ö |
|
|
|
|
Silt curtains will be deployed during
dredging for the desalination plant.
With the deployment of silt curtains around the dredging area for the
desalination plant, adverse water quality impacts associated with the
dredging and backfilling would be controlled to acceptable levels. |
Dredging area/Prior to dredging |
All Contractor |
|
Ö |
|
|
|
Table 4.1 |
Monitoring for transplanted corals: The
transplanted coral colonies will be regularly checked by qualified marine
ecologist quarterly for 1 year after transplantation. The presence, survival,
and health conditions of the coral colonies will be recorded. The ecological conditions of the
transplantation sites will also be reported. No action and limit level for
transplanted corals would be required. |
Coral transplantation site/ during the construction phase |
All Contractor |
|
Ö |
|
|
|
|
All anchoring points/structures of the
floating pier would be located on the shore and/or at least |
Temporary barging point/ during construction of the barging point |
All Contractor |
|
Ö |
|
|
|
|
The location of the floating pier would
also be shifted from the original location for barging point at Zone 2 and
Zone 3 of the mapping area in Site B2 (see Figure |
Temporary barging point/ during the entire construction phase |
All Contractor |
|
Ö |
|
|
|
Table 4.1 |
Natural corals
would be monitored as a precautionary measure. Prior to the commencement of all
construction works, a baseline monitoring on natural corals would be
conducted. At each of the Site C, B2, Site D2 (on the bedrock Impact monitoring
frequencies would be changed at different stages. For the natural colonies at Site D2 (on
the bedrock) and the Control Site, monitoring will be conducted weekly at the
first two weeks of dredging works for the desalination plant pipelines. If no exceedance
was recorded, the monitoring schedule would be changed to biweekly till the
pipeline construction works are finished. The presence, survival, and health
conditions of the coral colonies will be recorded. For the natural colonies at Site C, B2
and the Control Site, monitoring will be conducted monthly for the first
three months of the construction phase. If no exceedance
was recorded, the monitoring schedule would be changed to quarterly during
the rest of the construction phase.
For each monitored coral colony, the percent of sediment coverage, the
colour and the thickness of the sediment, the bleaching effect and live/dead
ratio (the health status of coral colony) shall be recorded. |
Site C, B2, the bedrock at Site D2 and the Control Site/ prior to
construction and during the construction phase |
All Contractor |
|
Ö |
|
|
|
Table 4.1 |
Seagrasses at Site D3, and
at Site D2 (if seagrasses are found at Site D2
during the baseline survey), would be monitored in conjunction with the coral
monitoring at Site D2 (natural corals on bedrock). The construction phase monitoring
schedule would be the same as for coral monitoring at Site D2, weekly during
the first two weeks of dredging works. After that, the monitoring
schedule would be changed to biweekly till the pipeline construction works are
finished. The extent of the seagrass beds, the coverage percentage and health conditions
of seagrasses will be recorded. |
Site D3 and D2/during construction |
All Contractor |
|
Ö |
|
|
Operational
Phase |
||||||||
8. |
|
Terrestrial Ecology |
|
|
|
|
|
|
|
|
Terrestrial Ecology
monitoring is not required. |
N/A |
|
|
|
|
|
|
|
The
environmentally-friendly turfgrass management
practices and the comprehensive monitoring programme
currently applied in the existing golf course will be extended to the
proposed third golf course as well.
Based on this three-tier approach to environmental protection, water
quality impacts are not anticipated. |
Golf course/During the operation phase |
Golf Course Operator |
|
|
Ö |
|
|
|
Marine Ecology |
|
|
|
|
|
|
|
|
Biological
methods will also be applied at Holes 5 and 6. The proposed biological insecticide
and fungicide products are all registered by |
Golf course/During the operation phase |
Golf Course Operator |
|
|
Ö |
|
|
Table 4.2 |
Monitoring of the
natural colonies at Site C, Site D2 (on the bedrock |
Site C, B2, the bedrock at Site D2 and the Control Site/ during the
first two years of operation phase |
All Contractor |
|
|
Ö |
|
|
Table 4.2 |
During operation phase,
the seagrass monitoring would be conducted in
conjunction with the coral monitoring at Site D2 (natural corals on bedrock). Seagrasses
at Site D3, and at Site D2 (if seagrasses are found
at Site D2 during the baseline survey), would be monitored during the first
two years of the operation phase. The monitoring schedule during the first
three months would be monthly. After that, the monitoring schedule
would be changed to semi-annually, i.e. once in dry season and once in
wet season. The extent of the seagrass beds, the
coverage percentage and health conditions of seagrasses
will be recorded. The need of any further monitoring will be reviewed
according to the monitoring results after the second year monitoring. |
Site D3 and D2/during the first two years of operation phase |
All Contractor |
|
|
Ö |
|
*
All recommendations and requirements resulted during the course of EIA Process,
including ACE and/or accepted public comment to the proposed project.
**
D=Design, C=Construction, O=Operation
N/A
Not applicable
Table 15.5 Implementation
Schedule of Fisheries Impact Measures
EIA Ref |
EM&A Ref |
Environmental Protection Measures* |
Location / Timing |
Implementation Agent |
Implementation Stages** |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
|
|
Construction phase |
|
|
|
|
|
|
|
|
In addition to the temporary drainage system which would collect
site runoff for re-use for irrigation, site runoff would also be controlled
by general site practices during the construction period. |
Work site / During the
construction period |
All Contractor |
|
Ö |
|
|
|
|
Silt curtains will be deployed during dredging for the
desalination plant. With the
deployment of silt curtains around the construction area, adverse water
quality impacts associated with the dredging and back-filling would be controlled. |
Work site / During the
construction period |
All Contractor |
|
Ö |
|
|
|
|
The majority of the heavy construction
works, in particular, the cut and fill earth works, would be conducted
within the 2005-2006 dry season. |
Work site / During the
construction period |
All Contractor |
|
Ö |
|
|
|
|
Monitoring during construction is not required. |
|
|
|
|
|
|
|
|
Operational Phase |
|
|
|
|
|
|
|
|
Monitoring during operation is not required. |
|
|
|
|
|
|
*
All recommendations and requirements resulted during the course of EIA Process,
including ACE and/or accepted public comment to the proposed project.
**
D=Design, C=Construction, O=Operation
N/A
Not applicable
Table 15.6 Implementation
Schedule of Landscape and Visual Impact Measures
EIA Ref |
EM&A Ref |
Environmental Protection
Measures* |
Location / Timing |
Implementation Agent |
Implementation Stages ** |
Relevant Legislation &
Guidelines |
||
D |
C |
O |
||||||
Landscape and Visual Impact - Construction Phase |
||||||||
Table 12.13 |
|
MC1 Site offices and
construction yards: -
Site offices and the construction yard shall be
decommissioned after construction. Haul roads shall be decommissioned and restored with hydroseeding works after construction. |
All site offices |
All contractors |
|
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MC2 Height of site
offices: The height of site offices shall be controlled in order to avoid
visual impacts. |
All site offices |
All contractors |
|
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MC3 Hoarding and
screening: Where practical the site offices areas, construction yards and
storage areas shall be screened using olive green coated hoarding or
vegetation around the peripheries of the works area until the completion of
relevant construction phases. |
All site office and construction yard areas. |
All contractors |
|
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MC4 Construction
plant and building material: -
Shall be orderly and carefully stored in order to
appear neat and avoid visibility from outside where practical; -
Excess materials shall be removed from site as
soon as practical; All construction plant shall be removed from site upon completion of
construction works. |
In all construction yards. |
All contractors |
|
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MC5 Construction
light: -
To be oriented away from the viewing location of VSRs; and -
All lighting shall have frosted diffusers and
reflective covers. While construction at night might be required from time to time, this
should be controlled and minimised. |
All construction lights. |
All contractors |
|
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MC6 Vegetation: -
Temporary construction sites shall be restored to
standards as good as, or better than, the original condition. In this
respect, areas that are not covered by golf course grassing works shall be
hydro seeded; -
The potential for soil erosion shall be reduced at
the construction stage by minimizing the extent of vegetation disturbance on
site and providing a protective cover over exposed ground; and No plant or building materials shall be stored under the dripline of retained trees and no vehicle movement or
other construction activities like washing, concrete mixing etc shall be
carried out under the dripline of trees. |
All temporary construction sites. |
All contractors |
|
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MT1 Compensation for losses: -
The tree compensation to tree loss ratio shall be
between 1:2 and 1:3; At least 700 new trees shall have be of
light standard or larger size. |
As shown on mitigation measures plans. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MT2 The majority of compensation species shall comprise species that
already occurs within the LIA boundaries; |
General. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MT3 Where practical, trees that require removal shall be transplanted on
Site; |
General. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MT4 New trees shall be planted in groups in order to screen visual
impacts and to provide additional shade at the administration building, rain
shelters and halfway houses. |
As shown on mitigation measure plans. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MT5 Tree Planting on
Slopes: ·
New slopes with a gradient larger than 30o
shall have whip tree
planting. ·
Such
whip trees shall comprise tree species with shrub-like characteristics, such
as Gordonia axillaries (大頭茶) and Raphiolepis indica (車輪梅). |
General. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MT6 Tree planting works at the hill where the desalination plant will be
located shall be carefully positioned in order to represent its original
profile. |
At the desalination plant. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MT7 Tree Preservation: -
No tree shall be transplanted or felled without
prior approval by relevant Government departments in accordance with WBTC
24/94, WBTC 14/2002 and ETWB 2/2004; -
All trees that are marked for retention shall be
fenced off with a Transplant preparation works shall be carried as soon as possible
after commencement of construction. Rootball and
crown pruning shall be carried out over at least 1 month. |
All areas with existing trees |
All contractors |
Ö |
Ö |
|
WBTC 24/94 WBTC 14/2002 ETWB 2/2004 |
Table 12.13 |
|
MT8 Buffer Areas -
For streams the width of the buffer zones will be No construction activities will be allowed in the buffer zones,
except for site formation works, which are required for the construction of
bridge footings. |
At streams |
All contractors |
Ö |
Ö |
|
|
Table 12.13 |
|
MS1 Bulk hydroseeding: Bulk site formation works shall be followed with bulk hydroseeding as soon as practical. |
General. |
All contractors |
|
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MS2 Grassing: · In the case of
golf course areas, grassing shall be carried out as soon as practical after
sanding and shaping; and · Sanding, shaping
and grassing works shall be phased in sections. |
At proposed grassing areas. |
All contractors |
|
Ö |
|
EIAO Guidance Note No. 8/2002 |
|
|
MS3 Restoration: ·
In the case of residual areas that were disturbed
during construction, which
will not be part of the golf course areas, detailed site formation works and shaping
shall be followed by hydroseeding and shrub
planting as soon as practical; and ·
The hydroseeding mix
shall be composed of the following grass species: Erograstic
curvula Lolium Perenne Neyraudia reynaudiana Pennisetum purpureum; and the following shrub / small tree species: Gordonia axillaries, Rhaphiolepis
indica and Rhodomyrtus tomentosa. |
At all residual areas. |
All contractors |
|
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
ME1 Screening: -
Bridges and pumping stations shall be screened by
tree and shrub planting; and Retaining wall shall be covered with climber plants. |
All bridges and pumping stations. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
ME2 Abutments
of bridges shall be surfaced with stone of volcanic origin with a colour and texture similar to that of rock in the
surrounding landscape; |
All bridges. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
ME3 Above-ground walls and foundations
of pumping stations shall be surfaced with stone of volcanic origin with a colour and texture similar to that of rock in the
surrounding landscape. |
All pumping stations. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
ME4 Above-ground covers of pumping
stations shall have an olive green coating. |
All pumping stations. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
ME5 The desalination plant shall be
located within the hill behind the pier. Slope cutting of this hill shall
have a natural appearance with hydroseeding cover. |
As shown on the mitigation measure plans. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
ME6 Water tanks shall be located below
surface level. Above-ground components shall be coated in olive green. |
All water tanks. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MB1 Extensions of the clubhouse shall
have a surface cover that is in visual harmony with the clubhouse itself. |
All new extensions of the clubhouse. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MB2 Shrub planting shall be implemented
in front of the new golf cart parking area in order to screen low-level
views. |
The new golf cart parking area. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MB3 Tree and shrub planting shall be
implemented on the peripheries of the maintenance building and its
extensions. |
At the maintenance building. |
All contractors |
Ö |
Ö |
|
EIAO Guidance Note No. 8/2002 |
Table 12.13 |
|
MB4 Halfway houses and rain shelters
shall be surfaced with either stone or beige and olive green paint. |
At all halfway houses and rain shelters. |
All contractors |
|
Ö |
|
EIAO Guidance Note No. 8/2002 |
Landscape and Visual Impact
- Operational Phase |
||||||||
|
|
N/A |
|
|
|
|
|
|
*
All recommendations and requirements resulted during the course of EIA Process,
including ACE and/or accepted public comment to the proposed project.
**
D=Design, C=Construction, O=Operation
N/A
Not applicable
Table 15.7
Implementation Schedule of Cultural Heritage Mitigation Measures
EIA Ref |
EM&A Ref |
Environmental Protection
Measures* |
Location / Timing |
Implementation Agent |
Implementation Stages ** |
Relevant Legislation &
Guidelines |
|||
D |
C |
O |
|||||||
Construction Phase |
|||||||||
Table 13.4 |
|
Wan Chai Archaeological
Site - Archaeological Watching Brief |
Site formation and construction works |
All Contractors |
|
Ö |
|
EIAO |
|
Table 13.4 |
|
Grave #1 – Preservation in-situ - Fenced off three metre buffer zone around the grave |
Site formation and construction works |
All Contractors |
|
Ö |
|
EIAO |
|
Table 13.4 |
|
Grave #5 - Preservation by record; and recovery of
structural elements (if required by AMO) |
Construction phase (prior to commencement of works) |
All Contractors |
|
Ö |
|
EIAO |
|
Table 13.4 |
|
Grave #20 - Preservation by record; and recovery of
structural elements (if required by AMO) |
Construction phase (prior to commencement of works) |
All Contractors |
|
Ö |
|
EIAO |
|
Table 13.4 |
|
Any, as of yet unidentified graves at Kap Lo Kok. If a grave is found works will stop in
the immediate vicinity of the grave until it can be inspected by AMO staff. |
Site formation and construction works |
All Contractors |
|
Ö |
|
EIAO |
|
Operational Phase |
|||||||||
|
|
N/A |
|
|
|
|
|
|
|
*
All recommendations and requirements resulted during the course of EIA Process,
including ACE and/or accepted public comment to the proposed project.
**
D=Design, C=Construction, O=Operation
N/A
Not applicable
Table 15.8
Implementation Schedule of Land Contamination Mitigation Measures
EIA Ref |
EM&A Ref |
Environmental Protection
Measures* |
Location / Timing |
Implementation Agent |
Implementation Stages ** |
Relevant Legislation &
Guidelines |
||
D |
C |
O |
||||||
Land Contamination - Construction Phase |
||||||||
|
|
Since the exact
cut areas on site during construction by the Contractor have not been
determined at this stage, the Contractor should implement the suitable
precautions and preventive measures for the discovery of buried or abandoned
ordnance during the construction. Moreover, it is recommended that standard
good practice should be implemented during the construction phase in order to
minimize any potential exposure to contaminated soils or groundwater. These
measures include: · The Contractor should sweep the area of
intended excavation with a metal detector to check any ordnance underneath
the ground prior to any excavation. · For any detection of metals under the
ground, the Contractor should cease work immediately before confirming the
identity of the cause. For any suspect of artillery ordnance, Hong Kong
Police Force should be informed. · The use of bulk earth-moving excavator
equipment would minimise construction workers’
potential contact with the contaminated materials; · Exposure to any contaminated materials can
be minimised by the wearing of appropriate clothing
and personal protective equipment such as gloves (when interacting directly
with suspected contaminated material), providing adequate hygiene and washing
facilities and preventing smoking and eating during such activities; · Stockpiling of contaminated soil should be
avoided. If this cannot be avoided, the stockpile of contaminated materials
should be segregated from the uncontaminated ones. Moreover, the contaminated
materials should be properly covered with waterproof material (e.g. tarpaulin
sheet) to avoid leaching of contaminants, especially during rainy season. · Vehicles containing any excavated
materials should be suitably covered to limit potential dust emissions or
contaminated wastewater run-off, and truck bodies and tailgates should be
sealed to prevent any leakage during transport or during wet conditions; · Only licensed waste haulers should be used
to collect and transport any contaminated material to an appropriate disposal
site and procedures should be developed to ensure that illegal disposal of
waste does not occur; · Necessary waste disposal permits should be
obtained, as required, from the appropriate authorities, in accordance with
the Waste Disposal Ordinance (Cap 354),
Waste Disposal (Chemical Waste)
(General) Regulation (Cap 35), as required; · Records of the quantities of wastes
generated and disposed of should be maintained; · Adequate washing facilities should be
provided on site; and · In accordance with good construction
practice, silt traps should be used to reduce the impact to drainage caused
by suspended solids arising from disturbed ground, or any construction
materials such as cement and gravel. Groundwater should be disposed of in
accordance with the Water Pollution Control
Ordinance (Cap 358). |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
Waste Disposal Ordinance (Cap 354), Waste Disposal
(Chemical Waste) (General) Regulation (Cap 35); Water Pollution Control Ordinance
(Cap 358). |
|
|
Based on preliminary
site investigation, the site is considered as a potentially land contaminated
site as hotspots of contamination of lead and sulphur
were identified. Further
investigation for land contamination at this site is therefore required and
is detailed in the Contamination Assessment Plan ( |
Work site / During the
construction period |
All Contractors |
|
Ö |
|
Waste Disposal Ordinance (Cap 354), Waste Disposal
(Chemical Waste) (General) Regulation (Cap 35); Water Pollution Control Ordinance
(Cap 358). |
|
||||||||
Land Contamination - Operational Phase |
||||||||
|
|
Prevention
of Contamination Impact In order to prevent the chemicals from contaminating
the land, a Turfgrass Management Plan ( As present in the water quality assessment section,
four main chemicals are used for existing golf courses,
they are nitrogenous fertilizers, herbicides, fungicides and insecticides.
The approach should be to minimize application of fertilizers and this is
also driven by economic requirements to minimize recurrent costs. Healthy growth rates are achieved when
the grass is not over fertilized or over watered. A balanced programme allows the grass to stand up to wear and
develop disease resistance. In line with existing practice, the following
mitigation measures will be implemented: ·
Nutrient
status will be monitored every 6 months of the year through the aid of soil
and leaf tissue tests. Tests help determine the optimum nutrient provisions
for turf grass. ·
A
slow release fertilizer will be used to help minimize the amount of nitrate
leached from the soil. ·
Applying
low quantity of fertilizer is recommended to minimize the leaching due to the
active uptake. ·
Applications
will not be made if heavy rain is forecast to minimize the significant
nitrogen runoff. |
Golf course/During the operation phase |
Golf Course Operator |
|
|
Ö |
Waste Disposal Ordinance (Cap 354), Waste Disposal
(Chemical Waste) (General) Regulation (Cap 35); Water Pollution Control Ordinance
(Cap 358). |
|
|
Routine soil testing for nutrients as described in
the All fertilizers and pesticides will be
well-documented including following details: ·
Location
of applications; ·
Type
of fertilizer applied; ·
Amount
applied in kg per hectare; ·
Date
of applications; and ·
Product
applied. |
Golf course/During the operation phase |
Golf Course Operator |
|
|
Ö |
|
|
|
Spillages In the event
that any spillages occur on the golf courses, the following actions would be
taken: ·
Make
every effort to contain the spillage responsibly and safely; ·
Block
drainage downstream flows and divert upstream flows where practicable; ·
Notify
Environmental Protection Department; ·
Collect
samples of downstream water for analysis; ·
Continue
sampling until the impact of the spillage can no longer be detected. |
Golf course/During the operation phase |
Golf Course Operator |
|
|
Ö |
|
|
|
The
extent of the contamination (e.g. volume of the contaminated soil) should be
identified and confirmed by taken samples of contaminated soil for testing.
Remediation action should also be carried out and completed within 3 to 6
months. |
Golf course/During the operation phase |
Golf Course Operator |
|
|
Ö |
|
*
All recommendations and requirements resulted during the course of EIA Process,
including ACE and/or accepted public comment to the proposed project.
**
D=Design, C=Construction, O=Operation
N/A
Not applicable