4.                   water quality impact

 

Introduction

 

4.1        This section evaluates the potential water quality impacts that are likely to be generated during the construction and operation phases of the proposed Project. Appropriate mitigation measures were identified, where necessary, to mitigate the potential water quality impacts to acceptable levels.

Environmental Legislation, Policies, Plans, Standards and Criteria

 

Environmental Impact Assessment Ordinance (EIAO), Cap.499, S.16

 

4.2        The Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) is issued by the EPD under Section 16 of the EIAO.  It specifies the assessment method and criteria that need to be followed in this Study.  Reference sections in the EIAO-TM provide the details of the assessment criteria and guidelines that are relevant to the water quality impact assessment, including:

·         Annex 6 Criteria for Evaluating Water Pollution

·         Annex 14 Guidelines for Assessment of Water Pollution

 

Marine Water Quality Objectives

 

4.3        The Water Pollution Control Ordinance (WPCO) Cap.358 provides Water Control Zones (WCZ).  Corresponding statements of Water Quality Objectives (WQO) are stipulated for different water regimes (marine waters, inland waters, bathing beaches subzones, secondary contact recreation subzones and fish culture subzones) in the WCZ based on their beneficial uses. A summary of WQOs for Victoria Harbour WCZ is given in  Table 5.1Table 5.1Table 5.1Table 5.1Table 5.1Table 5.1Table 54.1.

Table 5.1Table 45.1 Summary of Water Quality Objectives for Victoria Harbour WCZ

 

Parameters

Objectives

Sub-Zone

Offensive Odour, Tints

Not to be present

Whole zone

Visible foam, oil scum, litter

Not to be present

Whole zone

Dissolved Oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg/L for 90% of samples

Marine waters

Depth-averaged DO

Not less than 4.0 mg/L for 90% of samples

Marine waters

pH

To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2

Marine waters

Salinity

Change due to human activity not to exceed 10% of ambient

Whole zone

Temperature

Change due to human activity not to exceed 2 oC

Whole zone

Suspended solids (SS)

Not to raise the ambient level by 30% caused by human activity

Marine waters

Unionised Ammonia (UIA)

Annual mean not to exceed 0.021 mg/L as unionised form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

Total Inorganic Nitrogen (TIN)

Annual mean depth-averaged inorganic nitrogen not to exceed 0.4 mg/L

Marine waters

Toxic substances

Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms.

Whole zone

Human activity should not cause a risk to any beneficial use of the aquatic environment.

Whole zone

Source: Statement of Water Quality Objectives (Victoria Harbour (Phases One, Two and Three) Water Control Zone).

 

 

Hong Kong Planning Standards and Guidelines (HKPSG)

 

4.4        The HKPSG, Chapter 9 (Environment), provides additional information on regulatory guidelines against water pollution for sensitive uses such as aquaculture and fisheries zones, bathing waters and other contact recreational waters.

Water Supplies Department Water Quality Objectives

 

4.5        Besides the WQO set under the WPCO, the Water Supplies Department (WSD) has also specified a set of seawater quality objectives for water quality at seawater intakes.  The list is shown in Table 5.2Table 5.2Table 5.2Table 5.2Table 5.2Table 54.2.  The relevant criteria for suspended solids (SS) are the target limit of 10 mg/L.

Table 5.2Table 54.2    WSD Standards at Sea Water Intakes

 

Parameter (in mg/L unless otherwise stated)

WSD Target Limit

Colour (HU)

< 20

Turbidity (NTU)

< 10

Threshold Odour Number (odour unit)

< 100

Ammoniacal Nitrogen

< 1

Suspended Solids

< 10

Dissolved Oxygen

> 2

Biochemical Oxygen Demand

< 10

Synthetic Detergents

< 5

E. coli (no. / 100 ml)

< 20,000

 

Cooling Water Intake Standards

 

4.6        Based on the information provided by the individual cooling water intake operators, no specific requirement on seawater quality at the cooling water abstraction points was identified.

Technical Memorandum

 

4.7        Besides setting the WQOs, the WPCO controls effluent discharges into any WCZ through a licensing system.  The Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS), issued under Section 21 of the WPCO, gives guidance on permissible effluent discharges based on the type of receiving waters (foul sewers, storm water drains, inland and coastal waters). The limits control the physical, chemical and microbial quality of effluent.  Any sewage from the proposed construction activities should comply with the standards for effluent discharged into the foul sewers, inshore waters or marine waters of the Victoria Harbour WCZ, shown in Table 1, Table 9a and Table 9b, respectively, of the TM-DSS.


Practice Note

 

4.8        A practice note for professional persons has been issued by the EPD to provide guidelines for handling and disposal of construction site discharges. The ProPECC PN 1/94 “Construction Site Drainage” provides good practice guidelines for dealing with ten types of discharge from a construction site.  These include surface runoff, groundwater, boring and drilling water, bentonite slurry, water for testing and sterilisation of water retaining structures and water pipes, wastewater from building construction, acid cleaning, etching and pickling wastewater, and wastewater from site facilities.  Practices given in the ProPECC PN 1/94 should be followed as far as possible during construction to minimise the water quality impact due to construction site drainage.  For operational stage effluent handling, treatment and disposal, reference should be made to ProPECC PN 5/93.

Assessment Criterion for Coral Impact

 

4.9        According to Pastorok and Bilyard [1] and Hawker and Connell [2], a sedimentation rate higher than 0.1 kg/m2/day would introduce moderate to severe impact upon corals.  This criterion has been adopted in recently approved EIA studies such as Eastern Waters MBA Study [3], West Po Toi MBA Study [4] and Tai Po Gas Pipeline Study [5].

Baseline Conditions

 

4.10      The marine water quality monitoring data routinely collected by EPD were used to establish the baseline condition.  The EPD monitoring stations in Victoria Harbour include VM1, VM2, VM4, VM5, VM6 and VM7 (Figure 54.1).  A summary of EPD monitoring data collected in 2002 and 2003 is presented in Table 5.3Table 5.3Table 5.3Table 5.3Table 5.3Table 54.3 and Table 54.4 respectively for VM5, VM6 and VM7 which are the closest monitoring stations to the Macau Ferry Terminal (MFT).  As the Harbour Area Treatment Scheme (HATS) Stage I was commissioned in late 2001, the data shown in Table 5.3Table 5.3Table 5.3Table 5.3Table 5.3Table 54.3 and Table 54.4 represent the situation after the commissioning of HATS Stage 1.

Table 5.3Table 54.3    Summary Statistics of 2002 Marine Water Quality in the Vicinity of the Macau Ferry Terminal

 

Parameter

 

EPD Monitoring Station

WPCO WQOs (in marine waters)

VM5

VM6

VM7

Temperature (oC)

 

23.1

(16.3 - 27.4)

23.1

(16.3 - 27.4)

23.2

(16.4 - 27.5)

Not more than 2 oC in daily temperature range

Salinity (ppt)

 

31.8

(29.1 - 33.3)

31.8

(28.7 - 33.2)

31.7

(28.7 - 33.2)

Not to cause more than 10% change

Dissolved Oxygen (DO)

(% saturation)

 

81.0

(65 – 104)

77.0

(67.0 – 92.0)

79.0

(68.0 – 103.0)

-

Bottom

73.0

(34 – 103)

69.0

(20.0 – 89.0)

71.0

(47.0 – 85.0)

-

DO (mg/L)

 

5.7

(4.6 – 6.9)

5.5

(4.7 – 6.3)

5.6

(4.6 – 7.0)

Not below 4 mg/L for 90% of the samples

Bottom

5.2

(2.4 – 6.8)

4.9

(1.4 – 6.3)

5.1

(3.3 – 6.4)

Not below 2 mg/L for 90% of the samples

pH value

 

8.0

(7.6 – 8.2)

7.9

(7.7 – 8.2)

7.9

(7.6 – 8.3)

6.5 - 8.5 (± 0.2 from natural range)

Secchi disc (m)

 

2.0

(1.0 – 3.0)

1.9

(1.0 – 2.5)

1.7

(1.0 – 3.0)

-

Turbidity (NTU)

 

10

(7.0 - 14.3)

10.4

(7.0 – 14.6)

10.2

(7.3 – 15.6)

-

Suspended Solids (SS) (mg/L)

 

6.0

(3.2 – 13.3)

7.0

(3.4 – 17.0)

6.0

(3.9 – 10.1)

Not more than 30% increase

Silica (as SiO2)

(mg/L)

 

0.7

(0.1 – 1.4)

0.7

(0.2 – 1.4)

0.7

(0.3 – 1.3)

-

5-day Biochemical Oxygen Demand (BOD5) (mg/L)

 

1.2

(0.5 – 2.4)

1.2

(0.7 – 2.3)

1.3

(0.5 – 3.1)

-

Nitrite Nitrogen (NO2-N)  (mg/L)

 

0.03

(0.01 – 0.05)

0.03

(0.01 – 0.05)

0.03

(0.01 – 0.05)

-

Nitrate Nitrogen (NO3-N) (mg/L)

 

0.10

(0.04 – 0.17)

0.10

(0.04 – 0.21)

0.11

(0.06 – 0.21)

-

Ammonia Nitrogen (NH3-N) (mg/L)

 

0.19

(0.05 – 0.42)

0.20

(0.06 – 0.42)

0.21

(0.06 – 0.41)

-

Unionised Ammonia (UIA) (mg/L)

 

0.006

(0.003 – 0.010)

0.006

(0.003 – 0.010)

0.007

(0.003 – 0.011)

Not more than annual average of  0.021 mg/L

Total Inorganic Nitrogen (TIN) (mg/L)

 

0.31

(0.13 – 0.64)

0.33

(0.20 – 0.65)

0.34

(0.20 – 0.66)

Not more than annual water column average of  0.4 mg/L

Total Nitrogen (Total-N) (mg/L)

 

 

0.52

(0.30 – 0.90)

0.53

(0.36 – 0.84)

0.54

(0.46 – 0.87)

-

Ortho-Phosphate (Ortho-P) (mg/L)

 

0.022

(0.007 – 0.040)

0.023

(0.009 – 0.040)

0.023

(0.009 – 0.038)

-

Total Phosphorus (Total-P) (mg/L)

 

0.05

(0.03 – 0.08)

0.05

(0.03 – 0.07)

0.05

(0.04 – 0.07)

-

Chlorophyll-a

(µg/L)

 

4.8

(0.6 – 18.9)

4.2

(0.4 – 16.2)

4.2

(0.7 – 19.8)

-

E. coli

(cfu/100 mL)

 

4,500

(630 – 42,000)

5,000

(600 – 19,000)

4,600

(1,500 – 60,000)

-

Faecal Coliform

(cfu/100 mL)

 

11,000

(1,400 – 70,000)

13,000

(2,000 – 70,000)

12,000

(4,100–180,000)

-

Note:    1.   Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: Surface, mid-depth, bottom.

2.       Data presented are annual arithmetic means of depth-averaged results except for E. coli and faecal coliforms that are annual geometric means.

3.       Data in brackets indicate the ranges.

 

Table 5.4Table 45.4    Summary Statistics of 2003 Marine Water Quality in the Vicinity of the Macau Ferry Terminal

 

Parameter

 

EPD Monitoring Station

WPCO WQOs (in marine waters)

VM5

VM6

VM7

Temperature (oC)

 

23.4

(171 - 27.5)

23.5

(17.3 - 27.6)

23.5

(17.2 - 27.8)

Not more than 2 oC in daily temperature range

Salinity (ppt)

 

32.1

(29.4 - 33.4)

32.0

(29.8 - 33.3)

31.0

(21.7 - 33.3)

Not to cause more than 10% change

Dissolved Oxygen (DO)

(% saturation)

 

75

(61 – 88)

74

(58 – 85)

76

(61 – 91)

-

Bottom

71

(53 – 88)

69

(44 – 85)

72

(55 – 91)

-

DO (mg/L)

 

5.3

(4.1 – 6.9)

5.3

(3.9 – 6.7)

5.4

(4.1 – 6.9)

Not below 4 mg/L for 90% of the samples

Bottom

5.0

(3.7 – 6.9)

4.9

(3.1 – 6.7)

5.1

(3.8 – 6.8)

Not below 2 mg/L for 90% of the samples

pH value

 

8.1

(8.0 – 8.2)

8.0

(7.9 – 8.2)

8.1

(7.9 – 8.2)

6.5 - 8.5 (± 0.2 from natural range)

Secchi disc (m)

 

2.3

(1.5 – 4.1)

2.3

(1.5 – 4.0)

2.1

(1.3 – 3.2)

-

Turbidity (NTU)

 

8.6

(5.4 - 11.0)

8.8

(5.4 – 12.2)

8.9

(4.7 – 14.2)

-

Suspended Solids (SS) (mg/L)

 

4.7

(5.7 - 7.5)

5.1

(2.4 – 9.8)

5.8

(2.8 – 13.3)

Not more than 30% increase

Silica (as SiO2)

(mg/L)

 

0.8

(0.3 – 1.4)

0.9

(0.2 – 1.4)

1.0

(0.5 – 3.2)

-

5-day Biochemical Oxygen Demand (BOD5) (mg/L)

 

1.4

(0.7 – 2.2)

1.1

(0.5 – 2.0)

1.2

(0.6 – 2.4)

-

Nitrite Nitrogen (NO2-N)  (mg/L)

 

0.03

(0.01 – 0.05)

0.03

(0.01 – 0.05)

0.04

(0.01 – 0.14)

-

Nitrate Nitrogen (NO3-N) (mg/L)

 

0.11

(0.04 – 0.21)

0.11

(0.04 – 0.19)

0.16

(0.05 – 0.58)

-

Ammonia Nitrogen (NH3-N) (mg/L)

 

0.20

(0.07 – 0.34)

0.20

(0.09 – 0.34)

0.21

(0.11 – 0.31)

-

Unionised Ammonia (UIA) (mg/L)

 

0.009

(0.005 – 0.014)

0.009

(0.005 – 0.015)

0.009

(0.005 – 0.016)

Not more than annual average of 0.021 mg/L

Total Inorganic Nitrogen (TIN) (mg/L)

 

0.33

(0.22 – 0.50)

0.34

(0.25 – 0.50)

0.40

(0.28 – 0.93)

Not more than annual water column average of 0.4 mg/L

Total Nitrogen (Total-N) (mg/L)

 

 

0.52

(0.33 – 0.65)

0.52

(0.35 – 0.64)

0.58

(0.44 – 1.15)

-

Ortho-Phosphate (Ortho-P) (mg/L)

 

0.036

(0.02 – 0.050)

0.037

(0.02 – 0.050)

0.037

(0.02 – 0.050)

-

Total Phosphorus (Total-P) (mg/L)

 

0.06

(0.03 – 0.08)

0.06

(0.0 4 – 0.07)

0.06

(0.04 – 0.08)

-

Chlorophyll-a

(µg/L)

 

4.0

(0.3 – 22.7)

3.5

(0.4 – 16.7)

3.3

(0.3 – 15.6)

-

E. coli

(cfu/100 mL)

 

 

5,200

(640 – 42,000)

3,000

(250 – 14,000)

5,900

(500 – 22,000)

-

Faecal Coliform

(cfu/100 mL)

 

12,000

(2,500 – 100,000)

7,000

(1,100 – 26,000)

14,000

(1,200–60,000)

-

Note:       1.   Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: Surface, mid-depth, bottom.

2.       Data presented are annual arithmetic means of depth-averaged results except for E. coli and faecal coliforms that are annual geometric means.

3.       Data in brackets indicate the ranges.

 

4.11      Full compliance with the WQO for depth-averaged and bottom dissolved oxygen (DO), depth-averaged total inorganic nitrogen (TIN) and unionised ammonia (UIA) was achieved at VM5, VM6 and VM7 in 2002.

4.12      In 2003, full compliance with the WQO for depth-averaged and bottom DO, depth-averaged UIA was achieved at VM5, VM6 and VM7.  The compliance for depth-averaged TIN was achieved at VM5 and VM6 only.  At VM7, the annual mean of depth averaged TIN marginally exceeded the WQO (reference: EPD Publication “Marine Water Quality in Hong Kong 2003”).

Marine Sensitive Sites

 

4.13      Figure 54.2 shows the existing marine sensitive sites that may be affected by the Project. Key marine sensitive sites include:

·         Saltwater intakes and cooling water intakes along the seafront of Victoria Harbour

·         Coral and bird nesting sites at Green Island and Little Green Island

·         Egretry site at Stonecutters Island

·         Various typhoon shelters and Public Cargo Working Areas (PCWA)


Assessment Methodology

 

4.14      Construction Phase

 

The potential impacts from construction activities for the proposed expansion of the existing helipad have been reviewed and assessed in Sections 45.17 15 to 45.1917.  Water pollution control measures are recommended in Sections 45.1825  to 45.32 24 to ensure that any effluent discharged from the Project site would comply with the criteria of WPCO.

Operational Phase

 

The locations of the existing marine refuelling facilities and proposed new helicopter refuelling facilities are shown in Figure 4.1.  Background information including description and operational details of the refuelling facilities are provided in Chapter 2 as well as Sections 4.6 to 4.13.  The physical and chemical properties of jet fuel are described in Sections 4.15 to 4.16 and Section 5.21.  Identification of hazardous scenarios during operational phase covers storage, transfer and transhipment of fuel within the MFT site.  The possible fuel spillage events, spill quantities and occurring frequency have been identified in Table 4.6.  Two possible spill locations at the MFT have been identified in the hazard assessment, which are the fuel unloading point and the fuel storage tank as shown in Figure 4.3. 5454.  coastal developmentlikely likely Risks of fuel spillage will be minimised through design and operational practice.  Mitigation measures are recommended in Section 4.7 to prevent and contain spillages from the Project.  Potential water quality impacts in case of fuel spillage will be managed through the emergency contingency plan derived under this Project as well as the Maritime Oil Spill Response Plan  (MOSRP) developed by the Marine Department (MD). Identification and Evaluation of Water Quality Impacts

 

Construction Phase Water Quality Impact

 

Construction Activities

 

4.15      The proposed structural reinforcement for the new landing pad on the roof-top of the Inner Pier of the MFT would be carried out using existing pile caps on site and new piles supported by the pier level.  Marine piling works would not be required and no dredging of marine sediment would be carried out for the Project.  The aluminium design for the proposed new landing/take-off pad would be built on the existing rooftop of the MFT Inner Pier.  The aluminium trusses would be built offsite and then transported to the MFT Pier by barge.  The aluminium trusses would then be fixed on site and connected to the existing pile cap.  There would not be any demolition of existing structures for the expansion works.  Excavation works would not be required.  It is also expected that the installation of aluminium trusses at the existing pile cap would not impose any water quality concern during construction and operational stages. The effects on water quality from the possible provision of segregation facilities and measures to accommodate domestic helicopter services and the possible expansion of the existing helipad would be expected to be minimal with the implementation of proper site drainage and good site practices.

Sewage from Workers

 

4.16      Based on the Sewerage Manual, Part I, 1995 of the Drainage Services Department (DSD), the sewage production rate for construction workers is estimated at 0.35 m3 per worker per day. For every 10 construction workers working simultaneously at the construction site, about 3.5 m3 of sewage would be generated per day.  The sewage should not be allowed to discharge directly into the surrounding water body without treatment.  Existing toilets within the MFT site could be made available for use as necessary.  Sufficient chemical toilets should be provided for workers as necessary. 

Construction Runoff and Drainage

 

4.17      It is important that proper site practice and good site management be followed to prevent contaminated run-off from entering the surrounding waters.  With the implementation of appropriate measures to control run-off and drainage from the construction site, disturbance of water bodies would be avoided and deterioration in water quality would be minimal. Thus, unacceptable impacts on the water quality are not expected, provided that the recommended measures described in Sections 4.1825  to 4.32 24 are properly implemented.

Operational Phase Impact due to Fuel Spillage

 

During the operational phase, the likelihood of major spill events occurring would be very low.  The water quality impact due to fuel spillage is considered to be adequately addressed by the established MOSRP.  Risks of fuel spillage will be minimised through design and operational practice as discussed in Section 4.7.

keroseneskerosene [6]The properties of helicopter fuel are given in Table 5.5.  In the remote case that spillage occurs, the associated water quality impact is considered minor and would be transient only. Helicopter fuel, which consists of light oil, is non-persistent and would not result in marine pollution [7].  The fuel would evaporate to the atmosphere in less than 24 hours under typical temperate climate in Hong Kong [8]. 

Table 5.5                                                                                                                                                                                           Properties and Characteristics of Helicopter Fuel 6

 

Oil Type

Specific Gravity

Persistence

Light to medium distillate

< 0.85

Non-persistent

 

Figure 5.1 shows the locations of existing marine sensitive sites.  Two possible spill locations at the MFT have been identified in the hazard assessment, which are the fuel unloading point and the fuel storage tank as shown in Figure 4.3.  The hazard assessment also considered spillage during marine transport within 500m from the MFT site.  The distance between the fuel transportation route and coastal development would likely be maximized to reduce any potential hazard impact.  Thus, within 500m from the MFT site, a fuel delivery barge would likely approach the MFT from the north.  

Key marine sensitive receivers would be the saltwater and cooling water intakes along the seafront of the Victoria Harbour, in particular the WSD saltwater intakes at Sheung Wan and Central Water Front that are closest to the possible spill locations. These intakes are however well below the sea surface level and therefore would not be easily damaged by the surface oil slick.  Impacts on the egretry at Stonecutters Island, coral and bird nesting sites at Green Island, which are more than 2 km away from the Site, would be considered insignificant. As under the influence of strong currents in Victoria Harbour, any residual fuel patch remaining after the necessary oil response and clean up operations under the MOSRP would likely have dissipated before reaching these distant receivers.   

In case of any fuel spillage, the WSD saltwater intakes at Sheung Wan and Central Water Front should be given priority for protection.  In any case, it is important to predict the movement of the spill in order to decide which sensitive receivers should be protected during the spill event. Surface currents would dominate the movement of the spill unless the winds are extremely strong.  The wind will cause the slick to move at approximately 3% of the wind speed, in the direction of the wind 6.  The surface flow patterns of marine water in the Study Area in summer and winter under typical tidal conditions are illustrated in Appendix 5.1.  As shown in Appendix 5.1, the water within the Study Area would in general flow either to the east or to the west depending on the tide condition. Priority should be given to protect the sensitive sites downstream of the spill location.   

Mitigation Measures

 

Construction Phase
 
Construction Site Runoff and General Construction Activities

 

4.18      The practices outlined in ProPECC PN 1/94 Construction Site Drainage should be adopted where applicable, to minimise the potential water quality impacts from construction site runoff and various construction activities. 

4.19      There is a need to apply to EPD for a discharge licence for discharging effluent from the construction site, if any. The discharge quality is required to meet the requirements specified in the discharge licence. Any wastewater generated from the works areas should be treated so that it satisfies all the standards listed in the TM-DSS.  It is anticipated that the wastewater generated from the works areas, if any, would be of small quantity.

4.20      Good site practices should be adopted to collect the rubbish and litter on the construction sites so as to prevent the rubbish and litter from spreading from the site area.  It is recommended to clean the construction site on a regular basis.  Scavenging service for collecting any materials/waste loss form the site into the sea should be provided on a need basis.

Sewage from Workforce

 

4.21      The presence of construction workers generates sewage.  The construction workers can make use of the existing toilet facilities within the MFT, as necessary. If required, sufficient portable chemical toilets should be provided in the works areas, and a licensed collector should be deployed for appropriate disposal and maintenance of the toilets on a regular basis. 

4.22      Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the nearby environment during the construction phase of the Project.  Regular environmental audit on the construction site can provide an effective control of any malpractices and can achieve continual improvement of environmental performance on site.  It is anticipated that sewage generation during the construction phase of the Project would not cause water pollution problem after undertaking all required measures.

Accidental Spillage of Chemicals

 

The contractor must register as a chemical waste producer if chemical wastes would be produced from the construction activities. The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations, in particular the Waste Disposal (Chemical Waste) (General) Regulation, should be observed and complied with for control of chemical wastes.

4.23      Any service shop and maintenance facilities should be located within a bunded area, and sumps and oil interceptors should be provided. Maintenance of equipment involving activities with potential for leakage and spillage should only be undertaken within the areas appropriately equipped to control these discharges.

 

Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance. The Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes. General requirements are given as follows:

·Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport.

·Chemical waste containers should be suitably labelled, to notify and warn the personnel who are handling the wastes, to avoid accidents.

·Storage area should be selected at a safe location on site and adequate space should be allocated to the storage area.

 

Operational Phase

 

Handling of Site Drainage and Effluent

 

4.24      For handling, treatment and disposal of operational stage effluent, the practices outlined in ProPECC PN 5/93 should be adopted where applicable.  The following relevant recommendations should be followed:

·         Drainage outlets provided in open areas and areas subjected to a substantial amount of wind-blown rain should be connected to storm drains.

·         Drainage outlets provided in covered areas, including covered podiums and other roofed areas, should be discharged to foul sewers.

·         Surface water drainage should be provided for discharging storm water from open surfaces.  Such drainage as normally collected in open surface channels should be led to storm water drains via silt removal facilities.  Runoff in channels of building platforms should pass through a gully pit with necessary gratings to prevent objects from entering the storm water drains.

 

Emergency Contingency Plan
 

To provide a mechanism to minimise the impact of fuel spill, an emergency contingency plan has been formulated in Sections 5.535 to 5.641 below.

Communication Facilities

 

Good communications or telecommunications are vital for efficient management of the spill response.  It is important to ensure that vessels, helicopters and site supervisors are equipped with proper telecommunication equipment such as portable radiotelephones and cellular telephones so that they can talk to each other for managing the responses to the ever-changing conditions of a spill.

 

 

 

 

 

 

 

 

 

 

 

 

 

Communication Paths and Reporting Procedures

 

The supervisor(s) of the refuelling facility (in case of fuel spill from MFT) or operator(s) of the relevant fuel delivery vessel (in case of fuel spill from ship) should closely communicate with the MD and other relevant departments.  A list of key personnel contacts should be provided to the refuelling facility/vessel operator(s) for effective communication.  The list of contacts should include the telephone numbers of responsible personnel in the MD and other relevant parties such as the Water Services Department (WSD), Agricultural, Fisheries and Conservation Department (AFCD), as well as the owners or operators of the individual cooling water intakes that are potentially affected by the Project.  Close communication with WSD and individual intake operators is considered to be one effective means to minimize any impact on the intake systems.  Should it appear necessary, WSD and/or individual intake operators may consider shutting down the relevant pumping station for a short period of time in order to minimize any adverse impacts.  If any potential impact on the coral and bird nesting sites at Green Island or the egretry site at Stonecutters Island is foreseen, AFCD should be informed. The telephone list should be updated at regular intervals to incorporate any future sensitive sites.

Any spill event should be reported to the pollution control unit of the MD at the earliest opportunity.  The refuelling facility/vessel operator(s) should record as much of the information listed below as possible. 

Date and time of spillage event/sighting of the fuel spill

Location (Position in Latitude/Longitude, and/or description using recognised names)

Source of spill

Cause of spill

In case of a ship spill, the name and type of vessel(s) involved, information on whether grounding or collision has occurred should be provided. 

If the spill is released from an oil storage installation (OSI), the name and location of the OSI should be provided.

Type and estimated quantity of oil spilled and likelihood of further spillage

Description of the oil slicks, including direction of movement, length, breadth and appearance

Action, both taken and intended, to combat pollution and to prevent further spillage

Whether the leak or spill has been stopped at the source

Name of person reporting the incident and how he can be re-contacted

This information should be provided to the MD for effective management of the spill event under the MOSRP.

 

Spill Cleanup

 

Any spill event will be systematically responded through the MOSRP.   The guidelines for cleaning up of oil spills are given in Section 5.5 of the MOSRP.  The clean up operation is to be carried out by the MD with the support from other relevant departments or organizations as described in the MOSRP.  The Project Proponent should consider maintaining some anti-oil pollution equipment on site, such as floating oil booms, absorbent materials and skimmers, as supplements to MD’s equipment for efficient oil response. 

The operation staff of the Project should not be directly involved in any oil combating activity, unless the relevant personnel are protected by appropriate safety clothing/equipment and are fully trained with the oil combating knowledge as discussed in Section 6 of the MOSRP so as to minimize the potential safety and health risks.

Training

 

It is important that periodic training should be provided for the operation staff of the Project to get familiar with the oil response and clean up procedures derived in the MOSRP, as well as the communication paths and reporting procedures in the event of fuel spill.

Evaluation of Residual Impacts

 

4.25      With the implementation of appropriate mitigation measures recommended in Sections 4.1825 to 4.24, no adverse residual impact would be expected during both construction phase and operational phase.

Conclusion

 

4.26      The construction phase water quality impact would be temporary and localised during construction.  No unacceptable residual water quality impacts would be expected from the Project, provided that all the recommended mitigation measures are properly implemented.

 


4.         water quality impact. 4-1

Introduction. 4-1

Environmental Legislation, Policies, Plans, Standards and Criteria. 4-1

Baseline Conditions. 4-3

Marine Sensitive Sites. 4-6

Assessment Methodology. 4-7

Identification and Evaluation of Water Quality Impacts. 4-7

Mitigation Measures. 4-7

Evaluation of Residual Impacts. 4-8

Conclusion. 4-9

 

 

List of Tables

Table 4.1           Summary of Water Quality Objectives for Victoria Harbour WCZ

Table 4.2           WSD Standards at Sea Water Intakes

Table 4.3           Summary Statistics of 2002 Marine Water Quality in the Vicinity of the Macau Ferry Terminal

Table 4.4           Summary Statistics of 2003 Marine Water Quality in the Vicinity of the Macau Ferry Terminal

 

List of Figures

Figure 4.1          Locations of EPD Monitoring Stations

Figure 4.2          Existing Marine Sensitive Sites

 

 



[1]      Pastorok, R.A. and Bilyard, G.R. (1985).  “Effects of sewage pollution on coral-reef communities.”  Marine Ecology Progress Series 21: 175-189.

[2]      Hawker, D. W. and Connell, D. W. (1992).  “Standards and Criteria for Pollution Control in Coral Reef Areas” in Connell, D. W and Hawker, D. W. (eds.), Pollution in Tropical Aquatic Systems, CRC Press, Inc.

[3]      Hyder (1997). Sand Dredging and Backfilling of Borrow Pits at the Potential Eastern Waters Marine Borrow Area, EIA Report, CED, 1997.

[4]      ERM-Hong Kong, Limited (2001).  Focused Cumulative Water Quality Impact Assessment of Sand Dredging at the West Po Toi Marine Borrow Area Final Report.

[5]      ERM-Hong Kong, Limited (2003). The Proposed Submarine Gas Pipelines from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai Po Gas Production Plant, Hong Kong, EIA Report, The Hong Kong and China Gas Company Limited, 2003