4.                       TERRESTRIAL ECOLOGICAL ASSESSMENT

 

4.1                   Introduction

 

4.1.1               This chapter assesses the impacts of the Project upon terrestrial ecology.  The Project consists of the provision of a drainage tunnel and collecting system for Northern Hong Kong Island as well as a discharge outlet at Cyber Port.  The discharge outlet  includes a stilling basin to release the surface runoff collected from the Hong Kong Island catchment to the Lamma Channel.

 

4.1.2               The objective of this assessment is to identify existing ecological resources in the Study Area, evaluate any impacts of the Project at both construction and operation phases, and, where required, to propose mitigation measures to minimize adverse impacts.  The assessment follows the criteria and guidelines as stated in Annexes 8 and 16 of the EIAO TM and the EIA Study Brief No. ESB-070/2001.

 

4.1.3               The assessment is mainly focused on the above-ground intake structures along the proposed Hong Kong West Drainage Tunnel.  The outlet structures of the tunnel and the impacts on the receiving water body are covered by the chapter for marine ecological assessment in this report.

 

4.1.4               The nature and scope of the Project are described in Chapter 2 of this Report.  In accordance with the EIA Study Brief No. ESB-070/2001, this section identifies and assesses the terrestrial ecological impact associated with the Designated Project described in Chapter 2.

 

4.1.5               Alternative alignments and design options were studied at the early stage of this assignment.  Findings in the study are summarized in Section 2.4 of this report.  The alignment and design option proposed in this report, as compared with other alignments and design options, has minimum predicted impact. 

 

4.1.6               There are no scheduled concurrent designated projects (DP) in the vicinity of the proposed tunnel portals, intakes or tunnel alignment during the construction and operation phases. 

 

4.2                   Legislation and Standards

 

4.2.1               The Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO) was used as a guideline for this Project.  Other relevant environmental legislation, guidelines and references include:

 

·               EIA Study Brief No. ESB-070/2001;

·               Environmental Impact Assessment Ordinance (Cap. 499)

·               Hong Kong Planning Standards and Guidelines (HKPSG) Chapter 10;

·               Forests and Countryside Ordinance (Cap. 96) and its subsidiary legislation the Forestry Regulations;

·               Wild Animals Protection Ordinance (Cap. 170);

·               Country Parks Ordinance (Cap. 208) and associated subsidiary legislation;

·               Ecological Baseline Survey For Ecological Assessment (EIAO Guidance Note No. 7/2002);

 

·               Town Planning Ordinance (Cap. 131), in particular, Town Planning Board Guidelines for Application

·               United Nations Convention on Biodiversity (1992);

·               PRC relevant Regulations and Guidelines, including Class 1 and Class 2  protected species in China and China Plant Red Data Book listing species of conservation importance.

 

4.3                   Assessment Methodology

 

4.3.1               The assessment area for terrestrial ecology included all areas within 500 m from the site boundary of the works areas. 

 

4.3.2               A four-month ecological baseline survey programme was conducted from August to November 2003 to fulfill the requirements as detailed in EIA study brief ESB-070/2001.  Results of the ecological baseline survey are described in Appendix B.  The ecological baseline surveys recorded ecological data within the assessment area and established the ecological profile for impact assessment.

 

4.4                   Key Findings of Field Surveys

 

4.4.1               Major habitats recorded within the study area include natural woodland, shrubland, fung shui woodland, urban plantation (including road, village, construction site, grave site and recreational park) and stream/nullah.  The ecological values of these habitats are evaluated and ranked in Appendix B (see Table 11-15 in Appendix B).  The overall ecological values are summarized in the table below for easy reference.

 

Table 4.1 Evaluation of habitats within the study area

 

Habitat

Overall Ecological Values

Natural Woodland

Medium to high

Shrubland

Low to Medium

Fung Shui Woodland

High

Urban Plantation

Low

Stream/nullah

Low to Medium

*Please refer to Tables 11-15 in Appendix B for further details of the evaluation.

 

4.4.2               Four floral species of conservation concern were recorded within the study area.  Species protected by Hong Kong Forestry Regulations include one shrub, Pavetta hongkongensis, one tree fern Sphaeropteris lepifera and one fern Angiopteris fokiensis.  One tree species Artocarpus hypargyreus protected in China is common in Hong Kong.  All of these species are located outside the works area of the proposed project.  The rare plant species Ulmus parvifolia recorded in fung shui wood is native to north China but considered an exotic locally.  Therefore it is not included with the four floral species of conservation concern in Table 4.2 below:

 

 

 

 

 

 

 

 

Table 4.2 Evaluation of floral species of conservation concern

 

Species

Growth Form

Location

Protection status

Distribution

Rarity

Pavetta hongkongensis

Shrub

TP789,

HKU1

Protected under Forestry Regulations in Hong Kong

Widely distributed in Hong Kong

Occasionally seen in Hong Kong

Artocarpus hypargyreus

Tree

HKU1

(and other woodland)

Category III nationally protected species in China, also listed as ‘vulnerable’ in the China Plant Red Data Book.

Widely distributed in Hong Kong

Occasionally seen in Hong Kong

Sphaeropteris lepifera

Tree fern

W5

Protected under Forestry Regulations in Hong Kong

Hong Kong Island

Rare

Angiopteris fokiensis

Fern

W5

Protected under Forestry Regulations in Hong Kong

Hong Kong Island and Tai Mo Shan

Rare

 

 

4.4.3               Fauna of conservation concern recorded during field surveys included Belly-banded Squirrel, Black Kite, Buzzard, Greater Necklaced Laughing Thrush, Hong Kong Cascade Frog (upstream of PFLR1(P) and W12(P)), Lesser Spiny Frog (P5(P)) and Greater Short-nosed Fruit Bat (two bats roosted at a Chinese Fan Palm near W12(P)) (Table 4.3).

 

4.4.4               Hong Kong Cascade Frog is protected under Wild Animals Protection Ordinance (Cap 170) and Lesser Spiny Frog is considered threatened in China due to a decline in populations of the species throughout its range (Fellowes et al. 2002).  Both species are considered of potential global concern (ibid.).

 

4.4.5               All bats are protected under WAPO in Hong Kong and Greater Short-nosed Fruit Bat is considered a local conservation concern (Fellowes et al. 2002).  Belly-banded Squirrel is protected under WAPO.

 

4.4.6               Black Kite and Buzzard are State Class 2 Protected Animals of China and both are listed in Appendix 2 of CITES (Wang 1998).  Black Kite is considered of potential global concern by China authorities (ibid.) but is not listed by IUCN World Conservation Union under any category of threat.  Greater Necklaced Laughingthrush is a rare resident and inhabits thick shrubland and forest in Hong Kong (Carey et al. 2001).  All birds are protected under WAPO in Hong Kong.


Table 4.3 Fauna species of conservation concern

Common Name

Latin name

Location

Protection Status

Distribution

Rarity

Greater short-nosed fruit bat

Cynopterus sphinx sphinx

Two individuals roosted at a Chinese Fan Palm near W12(P)

Wild Animals Protection Ordinance (Cap 170)

Widespread localities in the New Territories and Hong Kong Island

Uncommon to common in Hong Kong

Belly-banded Squirrel

Callosciurus erythraeus styani

Found in the woodland habitats adjacent to BR3(P)-BR4(P), BR5(P)-BR7(P), HKU1(P), W11(P), W10, W12(P) and PFLR1(P)

Wild Animals Protection Ordinance (Cap 170)

Scattered localities in the New Territories and Hong Kong Island

Uncommon in Hong Kong

Black Kite

Milvus lineatus

Record on all transects.

Wild Animals Protection Ordinance (Cap 170)

Class II Protected Animal in PRC

CITES Appendix II

Distribute widely in Hong Kong.

Common in Hong Kong

Buzzard

Buteo buteo

Record at Western Outlet Portal (Transect L)

Wild Animals Protection Ordinance (Cap 170)

Class II Protected Animal in PRC

CITES Appendix II

Distribute widely in Hong Kong.

Common/uncommon in Hong Kong

Greater Necklaced Laughing Thrush

Garrulax pectoralis

DG1(P)

Wild Animals Protection Ordinance (Cap 170)

 

Distribute widely in Hong Kong

Rare in Hong Kong

Hong Kong Cascade Frog

Amolops hongkongensis

45 m and 60 m upstream of PFLR1(P) and W12(P) respectively

Wild Animals Protection Ordinance (Cap 170)

Distribute widely in Hong Kong Island and the New Territories, not found on Lantau or other islands

Common in Hong Kong

 

Lesser Spiny Frog

Paa exilispinosa

P5(P)

Not protected

Distribute widely in Hong Kong

Fairly common in Hong Kong, considered potential global concern


4.5                          Impact Identification and Evaluation

 

4.5.1                      The significance of ecological impacts is evaluated based primarily on the criteria set forth in Table 1, Annex 8 of the TM-EIAO:

 

·                     habitat quality;

·                     species affected;

·                     size/abundance of habitats/organisms affected;

·                     duration of impacts;

·                     reversibility of impacts; and

·                     magnitude of environmental changes.

 

4.5.2                      Impacts are generally ranked as "minor", "moderate" or "severe", although in a few cases a ranking of "minimal" (less than "minor") may be given.  The ranking of a given impact will vary based on the criteria listed above.  For example, an impact might be ranked as "minor" if it affected only common species and habitats, or if it affected only small numbers of individuals or small areas, whereas it might be ranked as "severe" if it affected rare species or habitats, large numbers of individuals or large areas.  The major factors giving rise to a ranking are explained in the text.  As noted in Annex 16 of the TM-EIAO, a degree of professional judgment is involved in the evaluation of impacts.

 

4.5.3                      The Project consists of the provision of a drainage tunnel (Hong Kong West Drainage Tunnel) and collecting system for Northern Hong Kong Island as well as a discharge outlet at Cyber Port.  The discharge outlet includes a stilling basin to release the surface runoff arising from the Hong Kong Island catchment to Lamma Channel.  The tunnel is approximately 10 km in length, starting at Tai Hang near Causeway Bay, passing beneath different districts of the mid-levels of North-western Hong Kong Island such as Braemer Hill and Parker Hill.  Drop shafts (Intake Point) would be constructed along the tunnel alignment to collect and divert upland runoff from the upper reaches of the Northern Hong Kong Island catchment, away from developed areas, to the east-west stormwater tunnel.  The diverted runoff would be conveyed via the tunnel to the sea at a tunnel portal, which is located at the headland south of Sandy Bay.  Although part of the tunnel alignment would fall within the boundaries of Pok Fu Lam Country Park and Lung Fu Shan Country Park, no ground surface structures (portals and intakes) would be located within and thus no ground surface construction works would take place inside any of the country parks. 

 

4.5.4                      The construction activities at tunnel portals and intake shafts are detailed in Chapters 2 and 7.  Works would include site preparation and clearance, excavation, intake structures and tunnel portal structure construction, utilization of ancillary equipment at tunnel portals to support tunnel construction, material handling and rock drilling at portals and intakes, and blasting underground if unavoidable.  For the western portal at Kong Sin Wan, a temporary berthing point will be constructed for transportation of excavated spoil during the tunnel construction and delivery of supporting TBM (tunnel boring machines) materials and equipment by marine access. 

 

4.5.5                      By using the Tunnel Boring Machine (TBM) method, the construction of the tunnel would not cause significant impacts, including habitat loss or disturbance along most of the alignment. The two portals of the tunnel, and the 35 intake points along the tunnel would be the major source of impacts.   

 

4.5.6                      The 35 intake structures would be constructed on existing stormwater flow paths (mostly existing drainage culverts) to collect surface water.  Each would include three major components: a diversion structure on the ground surface, a drop shaft from the ground surface to the level of the tunnel, and a horizontal adit at the base of the shaft to take the flow into the tunnel.  By the application of “Raise Boring” at most of the intake locations, the adit and the drop shaft would be constructed from the tunnel beneath rather than from the ground surface.  The intake diversion structure would be the only ground surface structure visible at each intake point, which is mostly less than or around 100 m2 in area.  A works area larger than the diversion structure would be needed to accommodate works equipment.  The intake point works areas range from 150 m2 to 1,500 m2, but most would be below 1,000 m2.  The construction works for intake points are small-scale.  Even the maximum tentative construction programme for the deepest intake point is less than 12 months, and the ground surface works would take even less time.

 

4.5.7                      The Eastern Portal (Figure 2.3-8) is also the biggest water flow receiving point of the tunnel.  It would be established adjacent to an existing watercourse at the southern end of a car park immediately east of the Haw Par Mansion on the south side of Tai Hang Road.  Construction activities in the works area will include:

 

l        initial excavation/breaking to establish the portal;

l        excavation and construction of the stream diversion structure;

l        assembly and operation of the tunnel boring machine (TBM);

l        handling of the spoil;

l        supply of materials for construction of the stream diversion structure and tunnel; and

l        establishment and later removal of site offices.

 

4.5.8                      A much larger works area, in particular the existing car park, is therefore needed at Eastern Portal but will avoid rare plant Ulmus parvifolia and the fung shui woodland habitat.

 

4.5.9                      The western portal will be an engineered structure specifically designed to discharge tunnel flow into the sea while maximizing dissipation of the flow’s energy (Figure 2.3-35).  The Portal will also be the second site for assembly and operation of TBM, where a TBM will start construction of the tunnel alignment working from the western portal in an easterly direction (The TBM at Eastern Portal would work in an westerly direction).

 

4.5.10                  The portal will be constructed on an existing reclaimed area beneath the northern access road to Cyberport and the works area would cover mostly an engineering slope and the reclaimed land. 

 

                  Construction Impacts

 

                  Habitat loss

 

4.5.11                  Since the proposed drainage pipes would be installed as tunnels between the intake points the alignment itself would not cause habitat loss.  Habitat loss would therefore mainly result from the construction of the 35 intake points and the two portals and is considered permanent, while habitat loss at works areas is considered temporary as these sites would be reinstated after the construction has been completed.  Habitat loss was calculated by overlaying the existing alignment on the habitat map using ArcView GIS version 3.2a.

 

4.5.12                  The proposed project would cause a permanent loss of 0.16 ha of woodland, 0.70 ha of urbanised/disturbed, 0.04 ha of shrubland habitats and 85 m of natural stream, the temporary habitat loss would include 0.53 ha of woodland, 1.56 ha of urbanised/disturbed land, 0.11 ha of shrubland, 91 m of natural stream, and 384 m of nullah (Table 4.4).  As all the ground surface structures would be located outside the Pok Fu Lam Country Park and Lung Fu Shan Country Park, none of these habitat losses would occur inside any of the country parks.

 

Eastern Portal

 

4.5.13                  The Eastern Portal would have a works area of about 6,876 m2, which is only second to Western Portal in size.  A considerable portion (1,375 m2 in total, see Table 4.4) of this works area is urbanized/disturbed habitat (an existing car park). There would be a loss of over 1,000m2 of this habitat but the impact is ranked as minimal as similar habitat (i.e. urbanized/disturbed) would be reprovided. There is a stand of woodland inside the works area of which the majority (4,481 m2) is in the temporary works area and only a small fraction (37m2) in the permanent works area.  The woodland within the temporary works area would not be affected, so there would be only 37 m2 of permanent woodland loss and no temporary woodland loss.  This is confirmed in the landscape chapter of this report that within the temporary works area no tree would be felled and only one tree would be transplanted. The impact on woodland loss in Eastern Portal is thus ranked as minor. Compensation for the permanent woodland loss would be provided.  

 

4.5.14                  The total loss of stream habitat is limited in the present Project (91 m temporary loss in total and 85 m permanent loss in total).  The majority of the permanent loss would result from the modification of a section of stream course immediately upstream from the Eastern Portal location (54 m in length, about 68% of 85m of the total stream habitat permanent loss). This stream was semi-natural and partially channelised. Currently, this stream flows in its natural stream bed until it reaches the car park immediately east of the Haw Par Mansion where the stream flow is collected by underground drains which replace the natural stream bed.  The tunnel portal and the section of stream to be modified are located just upstream from the car park.  The modification is essential for adjusting the flow rate before the stream flow enters the drainage tunnel.  The width of the channel would expand progressively in this section (Figure 2.3-8).  In non-flood situations, the flow would still go into the drains beneath the car park.  But when the water depth exceeds a threshold level, the excess would flow into the tunnel opening.  The stream was surveyed for aquatic fauna.  According to the results of ecological baseline surveys in Appendix B, no rare or protected species was recorded within the works area at this site.  Some common stream organisms including macrobenthic stream fauna were recorded and Mosquito fish was the only fish species recorded.  In addition, recorded herpetofauna, butterfly and dragonfly species were also common and widespread in Hong Kong, and of low conservation concern.  Although no species of conservation concern were found at the Eastern Portal stream, the streambed is natural and a relatively large section of the stream habitat would be lost and consequently this impact is ranked minor to moderate and mitigation is recommended. There is also another 39m of the stream lied within the works area boundary. However, the engineers have confirmed that the section would not be disturbed during construction. Therefore, different from the case in intake points (see below), this section is not considered as temporary loss. 

 

Western Portal

 

4.5.15                  The Western Portal has the largest works area among all construction sites of the Project, i.e. over 8,000 m2.  But the entire works area is on urbanized/disturbed habitat (an engineered slope and reclaimed lands).  These are the only habitat types on the site and they are considered low in ecological value. No other habitats would be affected or disturbed. The impact is ranked as minimal as similar urbanized/disturbed habitat would be reprovided.  No mitigation is needed for the Western Portal. However, this site provides an opportunity for compensation planting and is one of the largest compensation areas for the project (619 m2).

 

Intake Points

 

4.5.16                  Among the 35 intake points, urbanised/disturbed habitat is the predominant habitat type to be affected, and 18 take points would encroach only one type of land habitat, i.e. urbanised/disturbed habitat. Only 16 intake points would encroach woodland habitats. There are also 2 intake points (including one from the 16 intake points affecting woodland, i.e. this intake point would encroach both shrubland and woodland habitats) would encroach shrubland habitat. Woodland habitats affected are mainly located alongside roads (Figures 4.1a-c). Impacts of loss of urbanised/disturbed and shrubland habitat are not considered as severe due to the limited ecological value, low wildlife abundance and small affected area of these habitats. 

 

Woodland

 

4.5.17                  Among the 35 intake points, 16 would include woodland habitats within the works area boundaries and constitute temporary and permanent woodland loss. Indeed, subject to the judgments by on-site engineers, most of the potentially affected woodlands might not be encroached during construction. Only 14 out of the 16 intake points would confirmedly result in a total of 1,559 m2 of permanent woodland loss. Due to the limited size of woodland to be permanently lost, and the temporary nature of the impact on most of the woodland to be affected, the construction impact on terrestrial habitats is ranked as minor.  However, due to the ecological value of woodland habitat, mitigation is required to compensate the impact of woodland loss. The four plant species protected in Hong Kong or in China and recorded during the study are located outside the site formation area and the temporary works area of the proposed intake points.  One exception is the single tree of Artocarpus hypargyreus recorded at HKU1.  If this tree would be affected by construction works, it will be transplanted.  The fung shui wood and the ‘rare’ species Ulmus parviflora will not be affected by the project. Therefore, potential impacts of the project to the these plant species are minimal.

 

Stream/nullah

 

4.5.18                  Besides in the Eastern Portal, the intake points will also cause loss of natural streams, but the loss is very small (31m out of the total 85m permanent loss of stream habitat, and all 91 m of the total temporary loss). These permanently lost sections of streams (31m) are scattered among 5 intake locations (Table 4.4) and all are close to roads, residential buildings, or existing drainage facilities. They would be modified into channels as part of the diversion structure of the intake points. Sections of streams lied within the temporary work areas are potentially disturbed by the construction works, depending upon the final works plan at these intake points. To adopt a conservative approach, all these sections of streams are considered temporarily lost. Dragonflies and amphibians were only recorded at a few of the proposed intake points. Dragonfly nymphs and amphibian larvae usually live in unpolluted aquatic habitats.  Most of the proposed intake points are however located on concrete nullahs with poor water quality.  These are of low ecological importance as dragonfly or amphibian habitats. 

 

4.5.19                  Two amphibian species of conservation concern, Hong Kong Cascade Frog and Lesser Spiny Frog, were recorded within the study area.  Hong Kong Cascade Frogs were only found at 45 and 60 m upstream of PFLR1(P) and W12(P) respectively, but not at the proposed works area of PFLR1(P) and W12(P).  Lesser Spiny Frogs and their tadpoles were recorded in the proposed work area of P5(P).  The stream at P5(P) has been modified to a concrete nullah, and is not the natural habitat of this species.  Construction works at PFLR1(P), W12(P) and P5(P) will not affect important habitats of Hong Kong Cascade Frog and Lesser Spiny Frog.

 

4.5.20                  The impact of loss/modification of stream and nullah in the study area is ranked minor. Compensation of these scattered stream habitat losses is thus not required.  However mitigation measures for temporary stream loss (e.g. reinstatement and by-pass channels) and translocation of frogs, in particular Hong Kong Cascade Frog and Lesser Spiny Frog, are needed. It is also necessary to translocate tadpoles, if any are present, at the same time.

 

4.5.21                  Frogs are not very mobile animals and are usually found at habitats with some moisture.  The dependence of frogs on humid environments means they are largely habitat-restricted.  Site formation may result in mortality of frogs due to their strong site fidelity.  Those frogs that leave the works areas and search for new habitats may risk death due to desiccation.  Although the project will mostly affect frog habitats of low ecological importance, precautionary mitigation measures are recommended to minimize the residual impact at the 7 intake points where frogs were found.  Precautionary mitigation measures are discussed in Section 4.6.1.

 

Shrubland

 

4.5.22                  Among the 35 intake points, only two would encroach shrubland habitat. Potential impacts to loss of shrubland are considered minor due to the limited area to be lost (1,092 m2 temporary loss and 400 m2 permanent loss from 35 intake points) (Table 4.4) and absence of rare/protected species potentially affected. 

 

Urbanised/disturbed

 

4.5.23                  This is the predominant habitat type to be affected in both the two portals and almost all intake points (32 out of the 35 intake points). At 18 intake points, urbanised/disturbed habitat would even be the only habitat type other than stream and nullah to be permanently encroached. A total of over 7,000 m2 permanent loss and over 15,000m2 temporary loss would result from the Project. (Table 4.4). Two rare fern species Tree Fern Sphaeropteris lepifera and Fern Angiopteris fokiensis were found during field surveys near Intake Point W5(P) (Figure 4.1-c), they were however located in recreational park outside the works areas for the Project and there would be no impact on the ferns.   Potential impacts to loss of urbanised/disturbed area are considered minimal due to the low ecological value of this habitat and similar habitat would be reprovided.

 

                  Dependent fauna

 

4.5.24                  The impact of the habitat loss to fauna depends on the habitat requirements of fauna in the study area and the quantity and quality of lost habitats.

 

4.5.25                  The areas of terrestrial habitat loss during the construction phase are small (temporary 0.53 ha and permanent 0.16 ha of woodland, temporary 0.11 ha and permanent 0.04 ha of shrubland) and are scattered over 35 intake points and 2 portals.  Therefore, habitat loss at each intake point will only account for small proportion of the daily home range of highly mobile animals such as avifauna (particularly raptors) and Belly-banded Squirrel.  Loss of habitats is mainly confined to roadside or urbanized/disturbed locations, which are generally of low ecological importance as wildlife habitats.  The impact from the loss of habitats to terrestrial fauna is ranked minor.  However, in order to minimize residual impact, it is recommended that habitats temporarily lost to construction work should be re-instated after completion of construction works.

 

                  Construction Noise and disturbance

 

4.5.26                  Noise and visual disturbance may occur during site formation and construction, potentially affecting the distribution and behavior of fauna of the adjacent habitats.  Due to the temporary and localized nature of the disturbance, and the disturbed nature of affected habitats, potential impacts to fauna from this source are ranked as minor.

 

4.5.27                  Construction works at W12(P) would not remove the roosts of Greater short-nosed Fruit Bats. However, due to the proximity of the roost to the works area (around 10m), it is possible that the roosting bats may leave the Chinese Fan Palm when construction work commences.  Since Chinese Fan Palm is common on Hong Kong Island, the bats could find new roost easily.  For example, Chinese Fan Palm was recorded at various locations within the Study Area, including Urban Plantation habitat within Area A (where the bat roost will be affected) and Area C, and Woodland within Area B and Area D.  Another 10 Chinese Fan Palms were seen near the intake point W12(P),.  Therefore alternative bat roosts are available over a wide range of areas and the bats can find new roost easily.  The impact to this bat species is therefore also ranked minor.

 

4.5.28                  Ecological impacts to the surrounding country parks including Pok Fu Lam Country Park and Lung Fu Shan Country Park are minimal as all of the intake points and works areas are located outside the country park boundaries. 

 

                  Surface Runoff

 

4.5.29                  Streams are breeding habitats for amphibians and dragonflies, and mortality of nymphs/larvae may result from sedimentation.  Most of the watercourses affected by this Project are concrete nullahs carrying polluted water.  However some natural streams within the Study Area will also be affected by the Project.  To prevent sedimentation in streams, site runoff should be collected and properly treated before discharging to the nearby drainage system.   With good site practice, the impact to aquatic fauna from this source is ranked minor.

 

                  Construction Dust

 

4.5.30                  Indirect construction impacts on habitat, and flora and fauna include dust generated during construction which may affect growth of vegetation and distribution of fauna.  Avifauna may temporarily avoid nesting at locations affected by dust generated during construction.  Due to the temporary, reversible, localized and small scale of the impacts, dust impacts to flora and fauna are considered minor.

 

4.5.31                  The construction stage impacts are summarised in Table 4.5.

 


Table 4.4         Estimated habitat loss

 

Habitat Loss (Permanent) (m2)

Habitat Loss (Temporary) (m2)

 

Intake point

Woodland

Urbanised/

Disturbed

Shrubland

Natural Stream (m)**

Woodland

Urbanised/

Disturbed

Shrubland

Natural Stream (m)**

Nullah (m)***

Woodland to be reinstated (m2)

E5(A)(P)

 

54

 

 

 

244

 

 

 

496

E5(B)(P)

 

208

 

 

 

272

 

 

 

MB16(P)

 

99

 

 

 

339

 

 

14

305

MBD2

 

158

 

 

 

773

 

 

26

269

E7(P)

 

572

 

 

 

138

 

 

 

543

THR2(P)

55

262

 

8

251

380

 

8

 

437

HR1

114

64

 

 

458

77

 

 

20

147

GL1(P)

 

211

 

 

 

186

 

 

 

148

DG1(P)

 

106

 

 

 

355

 

 

 

313

W0(P)

 

154

 

 

 

1321

 

 

 

0

BR3

10

 

246

 

153

 

747

35

 

691

BR4(P)

106

 

 

 

349

 

 

 

 

247

W1(P)

296

46

 

 

881

356

 

 

70

774

BR5(P)

102

 

 

 

451

 

 

9

16

295

BR6(P)

163

65

 

 

470

98

 

 

20

56

BR7(P)

 

107

 

 

29

143

 

 

13

318

W3(P)

 

239

 

 

 

593

 

 

51

450

B2(P)

74

25

 

 

239

48

 

 

 

297

MA13(P)&MA14(P)

152

 

 

 

766

 

 

 

10

688

MA15(P)

258

41

 

 

390

281

 

 

21

243

MA17(P)

 

48

 

 

 

202

 

 

 

0

M3(P)

 

131

 

 

 

490

 

 

8

470

TP789(P)

 

132

 

3

 

199

 

6

 

256

TP5 (P)

 

99

 

2

 

398

 

10

 

180

TP4(P)

 

100

 

 

63

346

 

 

20

320

W5(P)

 

63

 

 

 

233

 

 

9

0

RR1(P)

 

153

 

 

 

207

 

 

 

0

W8

 

101

 

 

 

49

 

 

 

0

P5(P)

 

25

154

 

 

28

345

 

14

336

W10

 

50

 

 

 

341

 

 

 

0

W11

102

17

 

 

389

264

 

 

35

443

HKU1(P)

6

151

 

 

41

401

 

 

20

396

PFLR1(P)

121

27

 

10

367

202

 

23

 

405

W12(P)

 

97

 

8

 

314

 

 

18

45

Eastern Portal*

37

1043

 

54

 

332

 

 

 

0

West Portal

 

2396

 

 

 

6019

 

 

 

619

Total (m2)

1596

7043

400

85

5296

15628

1092

91

384

10,187

Total (ha)

0.16

0.70

0.04

0.01

0.53

1.56

0.11

0.01

0.04

1.02

 

*There would be 4,481 m2 of woodland and 39m natural steam habitat within the temporary works area of Eastern Portal, which however will not be affected as confirmed by the engineers of the Project.

**natural stream = equal to or more than 50% natural substrate

***nullah = >50% concrete/man-made substrate, underground drains were not counted.

 

Table 4.5 Construction stage impacts

Impacts

Receiver

Habitat quality

Species affected

Size/abundance of habitats/organisms affected

Duration of impacts

Reversibility of impacts;

Magnitude of environmental changes

Severity

Mitigation Recommended

Habitat loss

Eastern Portal

Eastern Portal Woodland

Medium to high

Terrestrial fauna, including common species and species conservation importance (Black Kite)

Small, 37m2

 

Permanent within site formation boundary.

Temporary within works area.

Permanent loss, irreversible.

Temporary loss to be reinstated.

Minor

Minor

Yes

(see Section 4.6 below)

Natural stream/nullah

Low to medium

Mosquito fish Gambusia sp. (the only fish species recorded), and common stream macrobenthic,

Moderate, 54m.

Limited species affected

Moderate

Minor to Moderate

Yes

(see Section 4.6 below)

Urbanised/ disturbed

Low

Terrestrial fauna, including common species and species of conservation importance (Black Kite)

Moderate, over 1,000 m2

Limited species affected

Minor

Minimal

No

Western Portal

Urbanised/ disturbed

Low

Terrestrial fauna, including common species and species of conservation importance (e.g. Black Kite and Buzzard)

High over 8,000 m2

Limited species affected

Permanent within site formation boundary.

Temporary within works area.

Permanent loss, irreversible.

Temporary loss to be reinstated.

Minor

Minimal

No

All intake points

Woodland

Medium to high

Terrestrial fauna, including common species and species of conservation importance (e.g. Black Kite and Greater Necklaced Laughing Thrush)

Small size affected

 

Permanent within site formation boundary.

Temporary within works area.

Permanent loss, irreversible.

Temporary loss to be reinstated.

Minor

Minor

Yes

(see Section 4.6 below)

Natural stream/nullah

Low to medium

Common amphibian species and two spp. of conservation concern

(i.e. Hong Kong Cascade Frog and Lesser Spiny Frog)

Small size affected

 

Minor

Minor

Yes for the seven intake points where frogs were found during the field surveys.

Shrubland

Low to medium

Common species of terrestrial fauna

Small size affected

Minor

Minor

No

Urbanised/ disturbed

Low

Common species of terrestrial fauna

Small size affected

Minor

Minimal

No

Construction noise and disturbance

Wildlife species on adjacent habitats

NA

Terrestrial fauna, including common species and species of conservation importance (e.g. Greater short-nosed fruit bats and Belly-banded Squirrel)

Low abundance of fauna

Temporary

reversible

Minor

Minor

No other than good site practice

Construction dust

Vegetation

Wildlife species on adjacent habitats

NA

Terrestrial fauna, including common species and species of conservation importance (e.g. Greater short-nosed fruit bats and Belly-banded Squirrel)

Low abundance of fauna

Temporary

reversible

Minor

Minor

No other than good site practice

Surface runoff

Aquatic fauna

Low to medium

Common species of aquatic fauna and dragonflies

Low abundance of aquatic fauna

Temporary

Reversible,

Small scale earth works at intake points.

At eastern portal major earth works inside the tunnel and at the end of the stream course.

Minor

Yes (see Section 4.6 below)

 


Operation Impacts

 

4.5.32           Except the intake points themselves, all other structures of the drainage tunnel will be underground and the operation will not pose any observable impact to the surrounding habitats and the associated flora and fauna.  Low flow channel or dry weather flow channel is designed to cater for the flow in dry season and normal wet season such that the ecology at the downstream can be maintained. There will be no operation phase impact on stream/nullah habitats.  The potential operational impact on habitat and terrestrial and aquatic fauna is therefore ranked as minimal. 

4.6                   Impact Avoidance and Mitigation Measures

Construction Phase

 

4.6.1               The construction methods applied in the present Project would help avoid the majority of the environmental impacts, and in turn the ecological impacts, encountered in other similar projects.  Bored drilling method would be used to build the drainage tunnel.  This method, in which the only locations with ground surface works would be the two end points, is much more environmental friendly than the cut-and-cover method, in which ground surface works are needed along the entire alignment of the tunnel.   More details of the horizontal boring construction method are given in Section 7.11.

 

4.6.2               The construction of connecting channels to each intake point is a major task during the construction phase in addition to building the tunnel.  Instead of drilling from the ground surface at intake locations towards the tunnel as in some other projects, in the present Project the drilling of the connecting channels would start from the newly constructed drainage tunnel.  Except when the drilling work is reaching the intake locations, no ground surface works/facilities are needed at the majority of the intake points.  This would reduce the disturbance impacts (including noise and human activities) during the construction phase.  This method will minimize the extent of excavated materials from the surface level at the intake point locations and to the greatest extent minimize the risk of water quality impacts from site runoff during construction.

 

4.6.3               During the detailed design stage, the following issues should also be considered as possible to further minimise the impacts:

 

·               Adjustment of site boundary to minimise temporary loss of natural stream habitat during construction. 

·               Adjustment of site boundary to minimise use of woodland as temporary works area.  In particular, the woodland habitat in temporary works area of the Eastern Portal will be avoided, thereby greatly reducing the area of temporary loss of woodland habitat. 

·               Minimizing felling of large trees.  A tree survey was conducted at the intake points/portal areas especially for those encroaching woodland habitats.  Among the 563 existing trees with diameter at breast height (dbh) > 95mm within the works area, it is estimated that 410 trees will be retained, while about 63 trees will be felled, mostly composing of common native pioneer trees and fruit trees.

·               About 90 trees within the works areas will be transplanted.  The single Artocarpus hypargyreus recorded within the temporary works area of HKU1 would also be transplanted if found to be in the path of the works.

 

4.6.4               Standard site practices including the following, should be enforced to minimise the disturbance to the surroundings:

 

·         Treat any damage that may occur to large individual trees in the adjacent area using materials and methods appropriate for tree surgery.

·         Reinstate work sites/disturbed areas immediately after completion of the construction works, in particular, through on-site tree/shrub planting along the woodland and shrubland section within the temporary works area.  Tree/shrub species to be planted should be the same as those in the surrounding area.  Only native species should be planted.

·         Regularly check the work site boundaries to ensure that they are not exceeded and that no damage occurs to surrounding areas.

 

4.6.5               The permanent loss of 0.16 ha of woodland due to site formation and temporary loss of 0.53 ha of woodland within the works area would be mitigated by on site compensatory planting.  While loss of woodland at the temporary works area at the Eastern Portal would be avoided, reinstatement of the temporary works area together with planting a mixture of tree species at most of the temporary works areas at various intake points and the Western Portal would be adequate for compensating loss of woodland (refer to last column of Table 4.4 and Table 10.5 of Chapter 10).  As tree planting doubles as a landscape mitigation measure, and at some intake points the space available for planting would not be enough to fully compensate the woodland loss from the same location, trees will also be planted at some other intake points where there would be no woodland loss from the Project. This could help increase the compensation ratio.  A total of 1.02 ha would be planted with woodland species, reaching almost a 1.5:1 ratio for compensatory planting (approximately 1.5 tree would be planted for the loss of one tree).  Tree/shrub species used should be based on those in the surrounding areas, including those shown in Table 4.6, which are commonly recorded during the baseline surveys.

Table 4.6 Plant/shrub species for compensatory planting

 

Species

Growth Form

Species

Growth Form

Ficus microcarpa

Tree

Cinnamomum camphora

Tree

Litsea monopetala

Tree

Litsea glutinosa

Tree

Choerospondias axillaris

Tree

Schefflera octophylla

Tree

Gordonia axillaris

Tree

Ilex asprella

Shrub

Cratoxylum cochinchinense

Tree

Psychotria rubra

Shrub

Celtis tetrandra subsp. sinensis

Tree

Litsea rotundifolia

Shrub

Artocarpus hypargyreus

Tree

Rhodomyrtus tomentosa

Shrub

Machilus spp.

Tree

Rhaphiolepis indica

Shrub

 

4.6.6               The majority of the permanent stream habitat loss would come from the modification of a section of stream course (54 m) immediately upstream from the Eastern Portal and mitigation at this site is required. The tunnel portal is located at the end of the natural section of the stream (Figure 2.3-8).  The modification is essential for adjusting the flow rate before the stream flow, which is the largest stream along the tunnel alignment, enters the drainage tunnel.  The width of the channel would expand progressively in this section.  In non-flood situations, the flow would continue into an existing underground drain beneath the car park.  But when the water depth exceeds a threshold level, the excess flow would go into the tunnel opening.  Although only limited aquatic fauna were found in this stream during the ecological field survey (Mosquito fish was the only fish species found, see Appendix B), the stream course remains natural and has potential to develop a more diverse fauna.  The aim of the mitigation is mainly to provide living space within the modified section for aquatic communities to develop.  A low-flow channel would be provided within the channelised section to maintain a deeper water depth in the expanded channel, in particular during dry season (Figures 4.2 and 4.3).  And there would be a basin at the end of the channelised section.  Both structures could provide living space for aquatic life within the channelised section.  Furthermore, step chute in the form of a series of descending water pools would be constructed between the low flow channel and the undisturbed stream course.  There would also be openings for aquatic fauna between each chute step (pool).  These could work like a “ladder” to help avoid isolating the aquatic fauna in the channelised section from natural habitats.

 

4.6.7               Measures are also needed to maintain the flow of all affected streams/nullahs during the construction stage.  Temporary bypasses should be provided if the stream/nullah flows will be cut off by the construction works.  After the construction works are finished, sections of temporary loss should be reinstated.  Construction materials, wastes, and equipment should be cleared from the sites.

 

4.6.8               Surveys of amphibians at Eastern Portal, PFLR1(P), W12(P), MB16, E5(B)(P), TP789(P) and P5(P) prior to commencement of construction is recommended.  Frogs, including Hong Kong Cascade Frog and Lesser Spiny Frog, and tadpoles found at the works areas of these proposed intake points will be collected and translocated to nearby streams that will not be affected by the project before commencement of construction.  These procedures should be performed by experienced herpetologists.  A detailed translocation proposal will be submitted during the detailed design stage.

 

4.6.9               Measures should be taken to avoid site runoff entering into streams/nullahs and thus affecting freshwater and marine habitats.  In addition, site runoff should also be properly treated (by silt traps and grease traps) before discharging to the nearby drainage system to reduce the potential of suspended solid, organics and other contaminants entering the local stream and marine environment.

 

4.6.10           Construction phase mitigation measures are summarized in Table 4.7 below.

 

 

 

Table 4.7         Construction phase mitigation measures

 

Impacts

Mitigation Recommended

Habitat loss

Adjustment of site boundary to minimise temporary works area and loss of natural habitats.

Minimizing felling of trees and transplantation.

On site compensatory planting of native species.

Provision of living space, low flow channel and step chute within the modified section at the Eastern Portal.

Provision of temporary by-pass for water flows.

Sections of temporary loss of stream as well as work sites/disturbed areas to be reinstated immediately after completion of construction. Construction materials, wastes, and equipment should be cleared from the sites.

Translocation of frogs.

Disturbance & Surface runoff

Good site practice.

Treat any damage that may occur to large individual trees in the adjacent area.

Regularly check the work site boundaries.

Prevention of sediment and runoff to streams habitats, desilting runoff.

 

Operation Phase

 

4.6.11           No mitigation measure is required as the ecological impact is considered minimal.

4.7                   Residual Impacts

 

4.7.1               The residual ecological impacts include net loss of 85 m of stream course as a result of the construction and operation of the proposed project.  This impact is considered acceptable due to the small area involved, the scattered distribution of the loss and the low quality of the affected stream habitat.

 

4.8                   ENVIRONMENTAL AUDIT AND MONITORING

 

4.8.1               Besides the EM&A for site practices, no specific EM&A programme for terrestrial ecology would be required for the Project.

 

4.9                   Conclusion

 

4.9.1               Major habitats recorded within the study area include natural woodland, shrubland, fung shui woodland, urban plantation and stream/nullah.  The proposed construction would cause permanent losses of 0.16 ha of woodland, 0.70 ha of urbanised/disturbed land, 0.04 ha of shrubland habitats and 85 m of natural stream, and temporary losses of 0.53 ha of woodland, 1.56 ha of urbanised/disturbed land, 0.11 ha of shrubland, 91 m of natural stream, and 384 m of nullah.  This project will cause limited terrestrial ecological impacts.  The proposed construction methods will avoid or minimise impacts to the extent possible.  Remaining impacts are addressed by mitigation. Mitigation would be implemented to provide living space within the modified stream section for aquatic communities to develop. With the recommended mitigation measures in place, the residual ecological impacts are considered acceptable.  Permanent loss of 85m scattered stream habitats would constitute residual ecological impact which is considered acceptable due to the small area involved, the scattered distribution of the loss and the low naturalness of the stream sections concerned.

 

 

4.10               Reference

 

 

Carey, G.J., Chalmers, M.L., Diskin, D.A., Kennerley, P.R., Leader, P.J., Leven, M.R., Lewthwaite, R.W., Melville, D.S., Turnbull, M. and Young, L. 2001. The Avifauna of Hong Kong. Hong Kong Bird Watching Society, Hong Kong.

 

Fellowes J.R., Lau, M.W.N., Dudgeon, D. Reels, G.T., Ades, G.W.J., Carey, G.J., Chan, B.P.L., Kendrick, R.C., Lee, K.S., Leven, M.R., Wilson, K.P.D. and Yu, Y.T. 2002. Wild animals to watch: Terrestrial and freshwater fauna of conservation concern in Hong Kong. Memoirs of the Hong Kong Natural History Society 25: 123–160.

 

Wang, S.  1998.  China Red Data Book of Endangered Animals: Mammalia.  Science Press, Beijing.