6.
6.1
Introduction
6.1.1
The potential air quality
impacts associated with the construction and operation of the proposed Project
are assessed according to the requirements stipulated in Section 3.4.1 of the
Environmental Impact Assessment Study Brief (ESB-070/2001) and presented in the
following section. The major components of the Project are described in detail
in Chapter 2.
6.1.2
The proposed preferred alignment
of the Project, comprising a tunnel section and above ground (intake shafts and
portals), will cover areas where existing and future residential development
will be located. There is potential for residents to be affected by air quality
impacts during the construction stage.
6.1.3
This section presents an assessment
of air quality impact associated with the construction and operation of the Project.
As the proposed tunnel section will be constructed using a TBM (tunnel boring
machine), limited construction nuisance is expected. If appropriate mitigation
measures are not followed and implemented, it will result in potential dust
nuisance due to the proximity to nearby sensitive receivers. Higher impacts are
expected at both portals as they are two main discharge locations for the
excavated material and temporary storage before disposal. The air quality
impacts due to the operation of the Project are considered to be minor.
6.1.4
Odour is not expected to be an
issue since the stream bed sediments will be left in place and are unlikely to
be contaminated as there are no known sources of effluents being discharged
into these streams.
6.2
Air Quality Assessment Criteria
6.2.1
The principal legislation
regulating air emissions in Hong Kong is the Air Pollution Control Ordinance
(APCO) [Cap 311] and its subsidiary regulations. Ten air control zones,
covering the entire HKSAR, have been declared under APCO. A set of Air Quality
Objectives (AQOs) applicable to all air control zones have also been
established. The AQOs for hourly, daily and annual concentrations of four major
pollutants are shown in Table 6.1.
Table 6.1
Hong Kong Air
Quality Objectives (AQOs)
Pollutants |
Concentration in |
||
1 hourA |
24 hourB |
1 yearC |
|
Nitrogen Dioxide (NO2) |
300 |
150 |
80 |
Sulphur Dioxide (SO2) |
800 |
350 |
80 |
Total Suspended Particulates
( |
500E |
260 |
80 |
Respirable Suspended
Particulates (RSP)D |
-- |
180 |
55 |
Notes: Concentrations measured at 298K (25°C)
and 101.325 kPa (one atmosphere)
A 1
hour criteria not to be exceeded more than 3 times per year.
B 24
hour criteria not to be exceeded more than once per year.
C Arithmetic
means.
D Respirable
suspended particulates means suspended particulates in air with a nominal
aerodynamic diameter of 10 micrometer (µm) or smaller
E This
control limit is a criterion listed in 1.1(b) Annex 4 of the TM on EIA Process
for evaluating construction dust assessment.
6.3
Air Sensitive Receivers
6.3.1
Air
sensitive receivers (ASRs) of the development include any existing or planned
residential areas, schools and parks etc in the vicinity of the development
including residents of development itself. Potential representative ASRs
outside of the development area have been identified from location plans and
the information of tentative future development plans.
6.3.2
The
representative ASRs that are outside the proposed development for use in the
construction phase assessment are mainly high-rise residential building and
schools. They are listed in Table 6.2 and shown in Figures 5.1-5.32
(Noise chapter).
Table 6.2
Details of Representative
Air Sensitive Receivers
|
Figure
no. |
Descriptions |
Status |
Approximate
distance to RASRs (m) |
Eastern Portal |
5.1 |
|
|
|
EP/1 |
|
Blk B Lai Sing Court |
Residential |
40 |
EP/2 |
|
Future Residential Development (Tower 1, The Legend) |
Residential |
10 |
EP/3 |
|
True Light Middle School of Hong Kong |
School |
30 |
Western Portal |
5.2 |
|
|
|
WP/1 |
|
Point Breeze |
Residential |
140 |
WP/2 |
|
Aegean Terrace |
Residential |
80 |
Intake shafts B2(P) |
5.3 |
|
|
|
B2(P)/1 |
|
Borrett Mansions |
Residential |
32 |
B2(P)/2 |
|
Carmel School |
School |
73 |
B2(P)/3 |
|
Glory Mansion |
Residential |
29 |
B2(P)/4 |
|
Grand House |
Residential |
33 |
Intake shafts BR3(P) |
5.4 |
|
|
|
BR3(P)/1 |
|
Greenville Garden Block D |
Residential |
66 |
Intake shafts BR4(P) |
5.5 |
|
|
|
BR4(P)/1 |
|
Kennedy Court |
Residential |
92 |
BR4(P)/2 |
|
St. James' Primary School |
School |
122 |
BR4(P)/3 |
|
Grandview Tower |
Residential |
111 |
Intake shafts BR5(P) |
5.6 |
|
|
|
BR5(P)/1 |
|
Sakura Court |
Residential |
75 |
BR5(P)/2 |
|
Camelot Height |
Residential |
68 |
BR5(P)/3 |
|
HK Tang King Po College |
School |
123 |
Intake shafts BR6(P) |
5.7 |
|
|
|
BR6(P)/1 |
|
16 Caronia |
Residential |
12 |
BR6(P)/2 |
|
Man Yuen Garden |
Residential |
39 |
BR6(P)/3 |
|
15 Carionia |
Residential |
75 |
Intake shafts BR7(P) |
5.7 |
|
|
|
BR7(P)/1 |
|
16 Caronia |
Residential |
12 |
BR7(P)/2 |
|
15 Caronia |
Residential |
15 |
BR7(P)/3 |
|
12 B Bowen Road |
Residential |
53 |
BR7(P)/4 |
|
Monticello |
Residential |
60 |
BR7(P)/5 |
|
Man Yuen Garden |
Residential |
72 |
Intake shafts DG1(P) |
5.8 |
|
|
|
DG1(P)/1 |
|
Rosaryhill School |
School |
54 |
DG1(P)/2 |
|
Blk C Villa Monte Rosa |
Residential |
29 |
DG1(P)/3 |
|
Evergreen Villa |
Residential |
51 |
Intake shafts E5(A)(P) |
5.9 |
|
|
|
E5(A)(P)/1 |
|
Buddist Li Ka Shing Care & Attention Home for
the Elderly |
Elderly Home |
5 |
E5(A)(P)/2 |
|
Blk 10, 135 |
Residential |
20 |
E5(A)(P)/4 |
|
Blk 10, 135 |
Residential |
23 |
Intake shafts E5(B)(P) |
5.9 |
|
|
|
E5(B)(P)/1 |
|
Blk 9 Aurizon |
Residential |
21 |
E5(B)(P)/2 |
|
Blk 1 Cavendish Heights |
Residential |
15 |
Intake shafts E7(P) |
5.10 |
|
|
|
E7(P)/1 |
|
Marymount Secondary School |
School |
8 |
E7(P)/2 |
|
French International School |
School |
77 |
E7(P)/3 |
|
117 Blue Pool Road |
Residential |
2 |
E7(P)/4 |
|
Blk J Villa Dorada |
Residential |
24 |
E7(P)/5 |
|
Blk 1 Green Lane Court |
Residential |
24 |
Intake shafts GL1(P) |
5.11 |
|
|
|
GL1(P)/1 |
|
Green Lane Hall |
Residential |
20 |
Intake shafts HKU(P) |
5.12 |
|
|
|
HKU1(P)/1 |
|
WSD Staff Quarters |
Residential |
36 |
Intake shafts HR |
5.13 |
|
|
|
HR1/1 |
|
Shuk Yuen Terrace |
Residential |
39 |
HR1/2 |
|
16-20 Broom Road |
Residential |
23 |
Intake shafts M3(P) |
5.14 |
|
|
|
M3(P)/1 |
|
May Fair |
Residential |
45 |
Intake shafts MA13(P)&MA14(P) |
5.15 |
|
|
|
MA13(P) & MA14(P)/1 |
|
The Harbour View |
Residential |
17 |
MA13(P) & MA14(P)/2 |
|
Magazine Gap Towers |
Residential |
26 |
MA13(P) & MA14(P)/3 |
|
Magazine Heights |
Residential |
41 |
Intake shafts MA15(P) |
5.15 |
|
|
|
MA15(P)/1 |
|
The Harbour View |
Residential |
9 |
MA15(P)/2 |
|
Magazine Gap Towers |
Residential |
86 |
MA15(P)/3 |
|
Rose Gardens |
Residential |
38 |
MA15(P)/4 |
|
Magazine Court |
Residential |
66 |
Intake shafts MA17(P) |
5.16 |
|
|
|
MA17(P)/1 |
|
Blk A Grenville House |
Residential |
42 |
MA17(P)/2 |
|
Magazine Court |
Residential |
45 |
MA17(P)/3 |
|
Rose Gardens |
Residential |
85 |
Intake shafts MB16(P) |
5.17 |
|
|
|
MB16/1 |
|
Clement Court |
Residential |
15 |
MB16/2 |
|
81 Perkins Road |
Residential |
20 |
MB16/3 |
|
83 Perkins Road |
Residential |
20 |
Intake shafts MBD2 |
5.18 |
|
|
|
MBD2/1 |
|
Amber Lodge |
Residential |
15 |
Intake shafts P5(P) |
5.19 |
|
|
|
P5(P)/1 |
|
24 Po Shan Road |
Residential |
7 |
P5(P)/2 |
|
23 Po Shan Road |
Residential |
38 |
P5(P)/3 |
|
Haddon Court |
Residential |
50 |
Intake shafts PFLR(P) |
5.20 |
|
|
|
PFLR(P)/1 |
|
Honey Court |
Residential |
14 |
PFLR(P)/2 |
|
Pokfulam Heights |
Residential |
19 |
Intake shafts RR1(P) |
5.21 |
|
|
|
RR1(P)/1 |
|
Primrose Court |
Residential |
15 |
RR1(P)/2 |
|
Scenic Heights |
Residential |
21 |
RR1(P)/3 |
|
Ying Wa Girl's School |
School |
60 |
RR1(P)/4 |
|
Peaksville Court |
Residential |
29 |
Intake shafts THR2(P) |
5.22 |
|
|
|
THR2(P)/1 |
|
Hong Chi Lions Morninghill School |
School |
7.5 |
THR2(P)/2 |
|
Hong Kong Japanese School |
School |
30 |
THR2(P)/3 |
|
Wan Chui Chuen |
Residential |
12 |
THR2(P)/4 |
|
Marymount Primary School |
School |
46 |
Intake shafts TP4(P) |
5.23 |
|
|
|
TP4(P)/1 |
|
Tregunter Tower 1 |
Residential |
32 |
TP4(P)/2 |
|
Tregunter Tower 2 |
Residential |
26 |
Intake shafts TP5(P) |
5.23 |
|
|
|
TP5(P)/1 |
|
Tavistock II |
Residential |
50 |
Intake shafts TP789(P) |
5.24 |
|
|
|
TP789(P)/1 |
|
Tavistock |
Residential |
42 |
TP789(P)/2 |
|
Branksome |
Residential |
45 |
Intake shafts WO(P) |
5.25 |
|
|
|
WO(P)/1 |
|
Sir Ellis Kadoorie Secondary School (Edward Hall) |
School |
18 |
WO(P)/2 |
|
Goodview Garden |
Residential |
25 |
WO(P)/3 |
|
Kui Yuen |
Residential |
30 |
Intake shafts W1(P) |
5.26 |
|
|
|
W1(P)/1 |
|
74 Bamboo Grove |
Residential |
60 |
W1(P)/2 |
|
Blk B Merry Garden |
Residential |
25 |
W1(P)/3 |
|
St James's Primary School |
School |
64 |
W1(P)/4 |
|
Caine Terrace |
Residential |
18 |
Intake shafts W3(P) |
5.27 |
|
|
|
W3(P)/1 |
|
Regent on the Park |
Residential |
63 |
W3(P)/2 |
|
Carmel School |
School |
158 |
W3(P)/3 |
|
Green Villa |
Residential |
95 |
Intake shafts W5(P) |
5.28 |
|
|
|
W5(P)/1 |
|
Raimondi College |
School |
6 |
W5(P)/2 |
|
Raimondi Primary School |
School |
8 |
W5(P)/3 |
|
Caritas House |
Residential |
14 |
W5(P)/4 |
|
Canossa Hospital |
Hospital |
70 |
Intake shafts W8(P) |
5.29 |
|
|
|
W8/1 |
|
Blk1, 80 Robinson Road |
Residential |
5 |
W8/2 |
|
Bonham Court |
Residential |
8 |
W8/3 |
|
Hong Kong Institute of Technology |
School |
1 |
Intake shafts W10(P) |
5.30 |
|
|
|
W10/1 |
|
Future Residential Development |
Residential |
17 |
W10/2 |
|
Blk 2 Po Shan Rd |
Residential |
18 |
W10/3 |
|
University Lodge |
School |
51 |
W10/4 |
|
Blk A-B University Heights |
Residential |
38 |
Intake shafts W11(P) |
5.31 |
|
|
|
W11(P)/1 |
|
17 Hatton Road |
Residential |
29 |
W11/(P)/2 |
|
Block B
Hatton Place |
Residential |
56 |
Intake shafts W12(P) |
5.32 |
|
|
|
W12(P)/1 |
|
Sylvanbrook |
Residential |
4 |
W12(P)/2 |
|
94A Pok Fu Lam Road |
Residential |
2 |
W12(P)/3 |
|
Blk A La Clare Mansion |
Residential |
27 |
6.4
Baseline Air Quality
Meteorology and Topography
6.4.1
The Study Area is situated in
the northwest of Hong Kong Island. It comprises the fringes of the urban area
and Country Parks. The project area is surrounded by series of hills, they are
Jardine’s Lookout, Mount Nicholson, Mount Cameron, Wan Chai Gap, Mount Gough
and Victoria Peak with peaks ranging from 300 m to 550 m.
6.4.2
Figures 6.1 a to d illustrates
the wind conditions at North Point, Central Plaza, Star Ferry Central and Green
Island of Hong Kong Observatory in year 2002 which are close to the Project and
will be taken as an indication of the conditions. Most of time, dominant wind
directions are come from East and Northeast directions. The wind pattern
characteristic is the result of blocking effect of hills over western parts of
the New Territories and Hong Kong Island. Topographic barriers also create
eddies that change the direction and speed of the air.
Existing Conditions
6.4.3
Table 6.3
Air Pollutants Maximum
Concentrations at Central/Western
Pollutant |
Averaging Time |
AQO (µg/m³) |
2002 (µg/m³) |
2001 (µg/m³) |
2000 (µg/m³) |
Sulphur Dioxide - SO2 |
1 hour |
800 |
395 |
274 |
416 |
24 hours |
350 |
105 |
103 |
92 |
|
1 year |
80 |
20 |
21 |
18 |
|
Nitrogen Dioxide - NO2 |
1 hour |
300 |
239 |
280 |
326 |
24 hours |
150 |
123 |
144 |
170 |
|
1 year |
80 |
46 |
54 |
53 |
|
Total Suspended Particulate - |
1 hour |
N/A |
- |
- |
- |
24 hours |
260 |
129 |
165 |
258 |
|
1 year |
80 |
61 |
69 |
71 |
|
Respirable Suspended
Particulate - RSP |
1 hour |
N/A |
216 |
242 |
349 |
24 hours |
180 |
152 |
155 |
200 |
|
1 year |
55 |
41 |
54 |
50 |
Notes:
N/A means data is not
available.
Concentrations with
exceedance of AQOs are bolded
6.4.4
The measurement results show
that both short term maximum values (one hour and 24 hours) and long term
maximum values (1 year) are all in compliance with the respective AQO both in
years 2001 and 2002.
6.4.5
Sulphur dioxide levels in Hong
Kong are below the long term AQO because of the enforcement of the Air
Pollution Control (Fuel Restriction) regulations for stationary sources and the
Air Pollution Control (Vehicle Fuel) Regulation for mobile sources. Decrease of
traffic volume of diesel vehicles in Hong Kong has probably contributed to the
nitrogen dioxide decreases in the past few years. For
6.4.6
For the purpose of this air
quality assessment, the usual practice of adopting the latest annual average
results of the nearest air quality monitoring station for the background air
pollution levels will be used.
Future Air Quality
6.4.7
It is less likely that air
quality of the area will deteriorate further due to the development of the
Project.
6.5
Impact Assessment and Mitigation
6.5.1
According to the schedule of
works, the deepest intake shafts (site clearance, formation and excavation)
will be finished within a period of about less than 12 months. Dust generating activities such as
drilling and muck shift will be mainly conducted through Eastern and Western
portal during construction period.
The remaining works are mainly on adit lining and finishing works on
intakes and portals. It has been
assumed that the dust emissions during the excavation of intake shafts will be
minimal owing to the small works area and excavated spoil will be collected
inside the tunnel for the majority of the intake locations (raise boring
method) and transported out from either portal for proper disposal. This should not create unacceptable
impact on residents nearby. For
only six intakes (W8, W5, RR1, THR(2), WO and HR1) formed by reserve circulation drill
method, materials will be excavated in slurry mud, therefore, emission to air
will be minimal.
Construction Phase
6.5.2
The principal potential source
of air quality impact arising from the construction of Project will be fugitive
dust. The temporary dust nuisance from construction activities, measurable as
6.5.3
The nuisance from emission of
construction vehicles at intake shafts is likely to be negligible because it is
anticipated that the number of these vehicles will be relatively small for the
area involved.
6.5.4
No on-site concrete batching plant will be erected. Any
concrete to be used will be transported to the work site. When construction
tenders/contracts are prepared, these documents will clearly specify that the
Contractor shall not erect or operate on-site concrete batching plant.
6.5.5
Bored-tunnels divided into two sections
from Tai Hang Road to Aberdeen Tunnel and Aberdeen Tunnel to Pok Fu Lam are proposed
to be constructed as the key components of the proposed Project. The estimated
volumes of spoil generated within the alignment have been estimated from
engineering drawings produced at this stage. An approximate estimate of
material volumes is given in Table 6.4.
Table 6.4 Estimated
Total Quantity of Spoil Generated during the
Construction of TBM
Tunnel, Intake Shafts and Adits
|
|
Length (m) |
|
|
||
Construction activities |
External diameter (m) |
Granite & Volcanic Rock (m³) |
Soil (m³) |
Granite & Volcanic Rock (m³) |
Soil (m³) |
|
TBM Tunnel |
|
|
|
|
|
|
Tai Hang Road to Aberdeen Tunnel |
7 |
4,360 |
- |
167,707 |
0 |
|
Aberdeen Tunnel to Pok Fu Lam |
8 |
6,000 |
- |
308,675 |
0 |
|
Intake Shafts + Ventilation pipes |
2.3 |
3,080 |
359 |
12,790 |
1,491 |
|
Adits |
2.3 |
7,556 |
0 |
313,77 |
0 |
|
|
|
|
Total |
520,549 |
1,491 |
|
Table 6.5 Proposed
Excavation Programme (TBM tunnel, Adits and Intake Shafts)
Proposed excavation programme |
Duration |
Estimate starting date |
Expected finished date |
||
TBM procurement & assembly |
14 months |
May 2007 |
June 2008 |
||
Tunnel excavation and lining |
26 months for TBM with diameter 6.25m
(Eastern Portal) |
June
2008 |
July 2010 |
||
25.5 months for TBM with internal
diameter 7.25m (Western Portal) |
June 2008 |
Aug 2010 |
|||
|
|
Eastern Portal |
Western Portal |
||
|
|
Start |
Finish |
Start |
Finish |
TBM removal |
2-4 weeks |
Sept 10 |
Sept 10 |
Aug 09 |
Sept 10 |
Drill & Blast (Adits) |
8.5 months for longest adit |
Sept 08 |
Apr 11 |
Sept 08 |
Apr 11 |
Shaft excavation by raise boring /
reverse circulation drill method |
2 months for deepest shaft |
Aug 08 |
Mid May 11 |
Aug 08 |
June 11 |
Adits lining |
2 months |
Sept 08 |
Apr 11 |
Sept 08 |
Apr 11 |
Finishing (Eastern & Western Portal
& Intake Shafts) |
4.5 months |
Apr 11 |
Jul 11 |
May 11 |
Sept 11 |
Landscaping Works & Correction of
Defects |
3.5 months |
End Jul 11 |
Mid Nov 11 |
Mid Sept 11 |
Mid Nov 11 |
|
|
55
months |
55
months |
6.5.6
The proposed excavation
programme is shown in Table 6.5. Based on this programme, estimated total quantity
of spoil generated to be transported out of Eastern and Western portals during
construction are approximate 185,073 m³ and 336,967 m³ respectively from Jun 2008
- May 2011. Based on the average truck load capacity of 6m³, it is estimated
that the maximum number of loaded trucks will be approximate 10 vehicles per hour
(5in/5out) at Eastern Portal. For
Western Portal, excavated spoil will be transported by barge. Details of
estimation are shown in Tables 6.6a and 6.6b. Given such a small number of
truck trips for transportation, dust nuisance is expected to be insignificant
if the standard site good housekeeping practice is in place.
Table 6.6a Estimated
Spoil Generated Breakdown from Eastern Portal
for 24 hours TBM
operation resume
Eastern Portal |
Construction Period & Duration |
Total volume, m³ |
m³/month |
m³ / day by truck |
Bored tunnel (Tai Hang Road to Aberdeen
Tunnel) |
June 2008 to July 2010 (26 months) |
167,707 |
6,450 |
215 |
Adits (Granite & Volcanic Rock) |
September 2008 to April 2011 (31.5 months) |
13,741 |
436 |
15 |
Adits (Soil) |
- |
- |
- |
|
Intake Shafts & Ventilation Pipes
(Granite & Volcanic Rock) |
August 2008 to May 2011 (33.5 months) |
3,165 |
95 |
3 |
Intake Shafts & Ventilation Pipes
(Soils) |
460 |
14 |
0.5 |
|
Total |
|
185,073 |
6,995 |
233.5 |
Table 6.6b Estimated
Spoil Generated Breakdown from Western Portal
for 24 hours TBM operation
resume
Eastern Portal |
Construction Period & Duration |
Total volume, m³ |
m³/month |
m³ / day by barge |
Bored tunnel (Aberdeen Tunnel to Pok Fu
Lam) |
June 2008 to August 2010 (26.5 months) |
308,674 |
11,648 |
388 |
Adits (Granite & Volcanic Rock) |
September 2008 to April 2011 (31 months) |
17,636 |
569 |
19 |
Adits (Soil) |
- |
- |
- |
|
Intake Shafts & Ventilation Pipes
(Granite & Volcanic Rock) |
August 2008 to June 2011 (34 months) |
9,625 |
283 |
10 |
Intake Shafts & Ventilation Pipes
(Soils) |
1,032 |
30 |
1 |
|
Total |
|
336,967 |
12,530 |
418 |
6.5.7
For Western portal, spoil
generated will be delivery to barges by means of a covered conveyor belt. As a result, the number of vehicles
entering the site will be reduced hugely and no vehicle-generated air pollution
problems will arise. However, dust may be emitted from the transfer points of
the conveyor. Proper design and maintenance of the conveyor will reduce dust
emissions from the transfer points to ensure low dust impact.
6.5.8
The remaining construction
activities are not expected to produce any dust nuisance to the air sensitive
receivers. Landscaping areas within the Project will not involve significant
movement of earth materials; hence dust impacts are expected to be
insignificant.
Mitigation Measures
6.5.9
In order to comply with the Air
Pollution Control Ordinance (APCO), the Contractor should undertake at all
times to prevent dust nuisance as a results of his activities. The Contractor
will be required to follow all the requirements for dust control stipulated in
the Air Pollution Control (Construction Dust) Regulation. Dust suppression
measures shall be implemented and shall be incorporated into the Contract
Specification, the following fugitive dust suppression measures are to be
implemented during the construction phase.
Dust Mitigation Measures
(i)
The Contractor shall undertake
at all times to prevent dust nuisance as a result of his activities. Effective
dust suppression measures should be installed to minimize air quality impacts,
at the boundary of the site and at any sensitive receivers.
(ii)
No blasting shall be carried out
when the strong wind signal or tropical cyclone warning signal No. 3 or higher
is hoisted (unless prior permission of the Commissioner of Mines is obtained).
(iii)
Effective water sprays shall be
used during the delivery and handling of all sand, aggregate and other similar
materials, when dust is likely to be created, to dampen all stored materials
during dry and windy weather. Watering of exposed surfaces shall be conducted
as often as possible depending on the circumstances.
(iv)
A watering programme of once
every 2 hours in normal weather conditions, and hourly in dry/windy conditions.
(v)
Any stockpile of dusty material
cannot be immediately transported out of the Site shall be either: a) covered
entirely by impervious sheeting; b) placed in an area sheltered on the top and
the three sides; or c) sprayed with water or a dust suppression chemical so as
to maintain the entire surface wet.
(vi)
Should a conveyor system be
used, the Contractor shall implement the following precautionary measures.
Conveyor belts shall be fitted within windboards. Conveyor transfer points and
hopper discharge areas shall be enclosed to minimize dust emission. All
conveyors under control of the Contractor, and carrying materials which have
the potential to create dust, shall be totally enclosed and fitted with belt
cleaners.
(vii) Any dusty materials being discharge to vehicle from a conveying system
at fixed transfer point, a three-sided roofed enclosure with a flexible curtain
across the entry shall be provided. Exhaust fans shall be provided for this
enclosure and vented via a suitable fabric filter system.
(viii) The heights from excavated spoils are dropped should be minimise to
reduce the fugitive dust arising from unloading/loading.
(ix)
The Contractor shall confine
haulage and delivery vehicles to designated roadways inside the site. If in the
opinion of the Engineer, any motorised vehicle is causing dust nuisance, the
Engineer may require that the vehicle be restricted to a maximum speed of 15 km
per hour while within the site area.
(x)
Areas within the site where
there is a regular movement of vehicles shall have an approved hard surface, be
kept clear of loose surface materials and / or be regularly watered.
(xi)
Wheel cleaning facilities shall
be installed for both portals and used by all vehicles leaving the site. No
earth, mud, debris, dust and the like shall be deposited on public roads. Water
in the wheel cleaning facility shall be changed at frequent intervals and
sediments shall be removed regularly. The Contractor shall submit details of
proposals for the wheel cleaning facilities to the Engineer prior to
construction of the facility. Such wheel cleaning facilities shall be usable
prior to any earthwork excavation activity on site. The Contractor shall
provide a hard-surfaced road between any cleaning facility and the public road.
(xii) Chemical wetting agents shall only be used on completed cuts and fills
to reduce wind erosion.
(xiii) No vehicle exhausts
shall be directed towards the ground or downwards to minimize dust nuisance.
(xiv) Ventilation system, equipped with proprietary filters, should be
provided to ensure the safe working environment inside the tunnel. Particular
attention should be paid to the location and direction of the ventilation
exhausts. The exhausts should not be allowed to face any sensitive receivers
directly. Consideration should also be given to the location of windows, doors
and direction of prevailing winds in relation to the nearby sensitive
receivers.
(xv) In the event of any spoil or debris from construction works being
deposited on adjacent land, or stream, or any silt being washed down to any
area, then all such spoil, debris or material and silt shall be immediately
removed and the affected land and areas restored to their natural state by the
Contractor to the satisfaction of the Engineers.
6.5.10
In addition, based on the Air Pollution Control (Construction Dust)
Regulation, any works involved regulatory and notifiable works, such as
stockpiling, loading and unloading of dusty materials, shall take precautions
to suppress dust nuisance. Examples of dust suppression methods are:
·
The working area of any
excavation or earthmoving operation shall spray with water or a dust
suppression chemical immediately before, during and immediately after the
operation so as to maintain the entire surface wet;
·
Exposed earth shall be properly
treated by compaction, turfing, hydroseeding, vegetation planting or sealing
with latex, vinyl, bitumen or other suitable surface stabiliser within six
months after the last construction activity on the construction site or part of
the construction site where the exposed earth lies;
·
Any stockpile of dusty materials
(greater than 20 m³) shall be either covered entirely by impervious sheeting or
placed in an area sheltered on the top and three sides; and sprayed with water
or a dust suppression chemical so as to maintain the entire surface wet; and
·
Other suitable dust control
measures as stipulated in the Air Pollution Control (Construction Dust)
Regulation, where appropriate, should be adopted.
6.6
Operation Impact Assessment
6.6.1
None
of area will likely be subject to adverse air quality impact due to the
operation of the proposed Project.
6.7
Concurrent Projects and Potential
Cumulative Impacts
6.7.1
There are no scheduled concurrent public works in the
vicinity of the proposed tunnel portals, intakes or tunnel alignment. The
northern access road to Cyberport is complete before commencement of
construction for this Designated Project. No cumulative construction impact is
expected from this Designated Project.
6.8
Monitoring and Audit Requirements
6.8.1
An Environmental Monitoring & Audit (EM&A)
program in respect of dust issues will be carried out to monitor compliance
with acceptable levels of air quality indicators and to ensure that the
proposed mitigation measures are implemented and that they are effective. Otherwise,
it is likely that some nearest air sensitive receivers would suffer
unacceptable impact.
6.8.2
Suggested monitoring locations are EP/1 (Lai Sing
Court) at Eastern portal and WP/2 (Aegean Terrace) at Western portal. These two
representative sensitive receivers are very close to the construction works
areas and hence, the most likely being impacted if dust suppression measures
are not properly implemented.
6.8.3
No
monitoring is required during operation phase.
6.9
Conclusion
6.9.1
The
construction dust impact assessment has identified Air Sensitive Receivers
(ASRs) within the Study Area. It has also identified those works that have
potential to generate substantial dust impact to the nearby ASRs.
6.9.2
The
transportation of earth material by trucks over site haul roads for both
portals is likely to be the dominant dust generation during the excavation of
the construction stage. With implementation of the recommended dust suppression
measures and backed up by a proper designed EM&A programme, the
construction of Project is expected to comply with the AQOs.