6                                            Noise

6.1                                      Introduction

This Section presents the potential noise impacts associated with the demolition of oil tanks, retrofitting of Flue Gas Desulphurisation (FGD) plant to two existing 350MW coal-fired generating units L4 and L5 of Lamma Power Station, construction of equipment building and the cumulative noise impacts associated with operation of proposed FGD plant and existing units.

6.2                                      Relevant Legislation and Guidelines

6.2.1                                Construction Noise

The principal legislation relating to the control of construction noise is the Noise Control Ordinance (Cap. 400) (NCO).  Various Technical Memoranda (TMs), which stipulate control approaches and criteria, have been issued under the NCO.  The following TMs are applicable to the control of noise from construction activities:

·           Technical Memorandum on Noise from Percussive Piling (PP-TM);

·           Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM); and

·           Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM).

Apart from the above, the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) also provides means to assess construction noise impacts.  The Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), issued under the EIAO, provides guidelines and noise criteria for evaluating construction noise impacts.

General Construction Works

Under the EIAO, noise impact arising from general construction works during normal working hours (i.e. 0700 to 1900 hours on any day not being a Sunday or public holiday) at the openable windows of buildings is to be assessed in accordance with the noise criteria as given in the EIAO-TM.  The EIAO-TM noise standards are presented in Table 6.1.

Table 6.1        EIAO-TM Daytime Construction Noise Standard (Leq, 30 min dB(A))

Use

Noise Standard

Domestic Premises

75

Educational Institutions (normal periods)

Educational Institutions (during examination periods)

70

65

When assessing a CNP application for the use of Powered Mechanical Equipment (PME) during restricted hours, the Noise Control Authority will compare the ANLs, as promulgated in GW-TM, and the CNLs (after accounting for factors such as barrier effects and reflections) associated with the proposed PME operations.  The ANLs are related to the noise sensitivity of the area in question and different Area Sensitivity Ratings have been established to reflect the background characteristics of different areas.  The relevant ANLs are shown in Table 6.2.

The Noise Control Authority will consider a well-justified Construction Noise Permit (CNP) application, once filed, for construction works within restricted hours as guided by the relevant Technical Memorandum issued under the NCO.  The Noise Control Authority will take into account adjoining land uses and any previous complaints against construction activities at the site before making a decision in granting a CNP.  Nothing in this EIA Report shall bind the Noise Control Authority in making his decision.  The Noise Control Authority may include any conditions in a CNP that it considers appropriate.  Failure to comply with any such conditions may lead to cancellation of the CNP and prosecution action under the NCO.

 

Table 6.2        Acceptable Noise Levels (ANL, Leq, 5 min dB(A))

Time period

Area Sensitivity Rating

 

A

B

C

All days during the evening (1900-2300 hours) and general holidays (including Sundays) during the day and evening (0700-2300 hours)

60

65

70

All days during the night-time (2300-0700 hours)

45

50

55

In addition to the general controls on the use of PME during restricted hours, the EPD has implemented a more stringent scheme via the DA-TM.  The DA-TM regulates the use of five types of Specified Powered Mechanical Equipment (SPME) and three types of Prescribed Construction Work (PCW), which are non-PME activities, in primarily densely populated neighbourhoods called Designated Areas (DAs).  The SPME and PCW are:

SPME:

·         hand-held breaker;

·         bulldozer;

·         concrete lorry mixer;

·         dump truck; and

·         hand-held vibratory poker.

PCW:

·         erection or dismantling of formwork or scaffolding;

·         loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material; and

·         hammering.

A CNP will be required for works during the time between 1900 and 0700 hours and any time on a general holiday, including Sunday, and the noise criteria for evaluating noise impact laid down in relevant TM issued under the NCO must be met.

As the study area is located outside a designated area, the noise criteria stipulated under the DA-TM are not applicable in this study.

6.2.2                                Operational Noise

The EIAO-TM and Technical Memorandum on Noise From Places Other than Domestic Premises, Public Places or Construction Sites (IND-TM) specifies the applicable Acceptable Noise Levels (ANLs) for the cumulative noise impacts from the operation of Project and existing power station equipment.  The ANLs are dependent on the Area Sensitivity Rating (ASR) and the time of the day and are presented in Table 6.3.

 

Table 6.3        ANLs to be used as Operation Noise Criteria

Time Period

LAeq 30min (dB(A))

ASR “A”

ASR “B”

ASR “C”

Daytime 0700-1900

60

65

70

Evening 1900-2300

60

65

70

Night-time 2300-0700

50

55

60

Fixed Plant Noise

Fixed plant noise is controlled under Section 13 of the NCO and the predictions will be undertaken in accordance with the IND-TM.  The criteria noise limits are set out in the EIAO-TM as follows:

·           the total fixed source noise level at the facade of the nearest NSR is at least 5 dB(A) lower than the appropriate ANL (as shown in Table 6.3) as specified in the Technical Memorandum on Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM);  or,

·           where the prevailing noise level in the area is 5 dB(A) or more below the appropriate ANL, the total fixed source noise level must not exceed this noise level. 

The criteria noise limits stipulated in the IND-TM are dependent on the Area Sensitivity Rating (ASR) of the NSRs as shown in Table 6.3.

As the site is located in a rural area and no influencing factors affect the NSRs, an ASR “A” has been assumed for the NSRs located at Ko Long and Hung Shing Ye.  With the inclusion of façade correction, the measured prevailing noise level will be higher than the (ANL-5) criterion, and therefore the (ANL – 5) criterion, i.e. 45 dB(A) LAeq, 30min for night-time period will be considered as the stipulated noise limit for the assessment of operational noise impact.  Detail of the noise measurement will be further discussed in Section 6.3.3.

In any event, the Area Sensitive Rating assumed in this Report is for indicative assessment only given that there are currently no influencing factors assumed in the vicinity of the NSRs.  It should be noted that fixed noise sources are controlled under Section 13 of the NCO.  At the time of investigation, the Noise Control Authority shall determine noise impact from concerned fixed noise sources on the basis of prevailing legislation and practices being in force, and taking account of contemporary conditions / situations of adjoining land uses.  Nothing in this Report shall bind the Noise Control Authority in the context of law enforcement against all the fixed noise sources being  assessed.

6.3                                      Baseline Environmental Conditions and Noise Sensitive Receivers

6.3.1                                Noise Sensitive Receivers

Settlement on the northern end of Lamma Island is largely concentrated around the harbour at Yung Shue Wan and in the adjacent villages of Yung Shue Long, Sha Po, Ko Long, Wang Long and Tai Wan San Tsuen.  These residences are shielded from plant noise to varying degrees by the intervening hill (Kam Lo Hom) which defines the plant’s northern site boundary.  The villages of Long Tsai Tsuen and Hung Shing Ye, although lie outside the area which is shielded by the hill (Kam Lo Hom), are shielded from the new plants by the existing plants.  The most affected NSRs are identified and summarised in Table 6.4 and the locations of the NSRs are shown in Figure 6.1.  No planned NSRs are identified within the study boundary. 

Table 6.4        Identified Noise Sensitive Receivers

NSR

Location

Type of Use

NSR 1

Hung Shing Ye / Tai Wan To

Residential Use (3-storey)

NSR 2

Ko Long

Residential Use (3-storey)

6.3.2                                Baseline Environmental Conditions

The proposed Project is located at the northern section of the existing Lamma Power Station.  The residential buildings located to the north and north-east of the Lamma Power Station are screened by the existing equipment units and natural topography.  Background noise is generally low and there are no private vehicles or industrial facilities within the Study Area.  The major noise source is identified as the community noise from the residents and the construction of the extension to the existing Lamma Power Station.

6.3.3                                Baseline Community Noise Monitoring

Existing local acoustic environment at the NSRs is currently affected by the construction activities of extension works conducted at the Lamma Power Station, and therefore to allow a worst case scenario, the ambient noise levels at the NSRs are made reference to Sections 6.3.3 and 6.3.4 of the Lamma Extension EIA Report ([1]).  The ambient noise levels were contributed by the operational noise from the existing Lamma Power Station and the ambient community noise. 

With reference to the noise monitoring conducted in 1997, the noise data collected at Tai Wan To (TWT) were considered to be a more stringent representation of the background as the results were manually screened to eliminate certain particular extraneous noise sources present in the environment.  The background noise levels are summarised in Table 6.5. 

Table 6.5        Seasonal Background Noise at TWT in 1997

Period

LAeq(1), 30min dB(A)

 

Summer

Winter

Daytime

52

49

Night-time

49

45

Remark:

(1)                                         The measured noise levels were not affected by the construction noise from the Lamma Extension, and therefore the noise levels represent a quieter ambient condition and a more stringent noise limit for the operational assessment.

(2)                                         There is no major change on site condition/environment of the study area so that the        background noise levels obtained in 1997 can still be applicable

6.4                                 Construction Noise Assessment

6.4.1                                Potential Sources of Impact

The major construction activities associated with the Project that may cause noise impacts to the NSRs are:

·       Demolition of two existing Nos. 4 & 5 Light Oil tanks, each of 50m3; and

·       Retrofit of FGD plants to two existing 350MW coal-fired Units L4 & L5 of the Lamma Power Station.

According to planned project programme, the demolition and retrofit works will be carried out in phases without overlapping.

6.4.2                                Evaluation of Impacts

The proposed Project is in small scale.  Additionally, in the view that the residential developments are shielded from construction noise to varying degrees by the intervening hill (Kam Lo Hom) and the existing plants, and considerable separation distance between the NSR and the Project, the noise generated during the construction stage is not expected to be a concern.  In accordance with the EIA Study Brief, a quantitative construction noise assessment is therefore not required. 

The normal working hours of the contractor will be between 0700 and 1900 hours from Monday to Saturday (except public holidays).  Should evening and night works between 1900 and 0700 hours or on public holidays (including Sunday) be required, the contractor should submit a CNP application and will be assessed by the Noise Control Authority.  Conditions stipulated in CNPs should be strictly followed.

6.4.3                                Mitigation Measures

In accordance with the EIA Study Brief, the following good site practice and noise management are recommended to ensure that construction noise is controlled within the relevant criteria:

·           Use of quiet plants should be considered for replacing the use of noisy plant;

·           Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction works;

·           Machines and plant that may be use intermittently, such as vibratory poker, should be shut down between work periods or should be throttled down to a minimum;

·           Plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from nearby NSRs; and

·           Mobile plant should be sited as far away from NSRs as possible.

6.5                                 Operational Noise Assessment

6.5.1                                Potential Sources of Impact

Additional equipments to be installed for the existing FGD plant at Lamma Power Station are given below:

·         Two sets of FGD absorbers and associated duct works;

·         Two sets of booster fans;

·         Two sets of gas-gas heater;

·         FGD switchgear and equipment building; and

·         Gypsum dewatering system comprising two sets of hydrocyclones and belt filter.

With reference to the operation mode of existing FGD units in Lamma Power Station, the potential noise sources and their sound power levels are presented in Table 6.6. 

To minimise the noise impact to the environment, most of the noise sources associated with the retrofit project will be housed within individual acoustic enclosure.

Table 6.6        Noise data Collected from Existing FGD Units

Equipment

No. of Unit for Each FGD Unit

Sound Power Level(1) per unit, dB(A) (with the provision of mitigation measures)

Mitigation Measures(2) Provided to the equipment

Absorber

1

107

-

Absorber Recirculation Pump

4

88

In enclosure

Oxidation Air Blower

2

100

In enclosure

Booster Fan

1

99

In enclosure

Booster Fan Motor

1

90

In enclosure

Gas-Gas Heater (untreated side)

1

95

Reinforced lagging

Gas-Gas Heater (treated side)

1

85

-

Total Sound Power Level

112 for L4 & L5 FGD Units

 

Remark:

(1) Sound Power Levels of the equipment were provided by the FGD Suppliers.

(2) Mitigation measures will also be provided for the future equipment of the proposed Project.

 

The figures presented in above Table 6.6 are guarantee figures from existing units provided by the FGD suppliers.  For the new L4 & L5 FGDs, same guarantee would also be included in the FGD Supply Contract and the suppliers are required to provide enclosures to ensure noise emission comply with the above requirements.

 

The equipment that will be installed inside the switchgear equipment building and the gypsum dewatering house are of low noise levels.  Certain equipment will also be fully enclosed inside concrete structures, and hence the equipment are of negligible noise impact and need not be included in the assessment.

6.5.2                                Assessment Methodology

The methodology for the noise impact assessment is in accordance with the procedures outlined in the ISO 9613([2]) and IND-TM, which is issued under the NCO and the EIAO-TM.  The assessment will take into account the distance attenuation, atmospheric absorption and barrier correction.    

6.5.3                                Evaluation of Impacts

Based on the noise data collected from the existing operating units in the Lamma Power Station, the facade noise levels at the identified NSRs (Hung Shing Ye/Tai Wan To) are predicted and summarised in Table 6.7.  Results indicate that the identified NSRs will be subject to noise level of up to 38 dB(A), which will comply with the stipulated noise criterion of 45 dB(A).  For the NSR at Ko Long, which is located the north of the proposed plants, the existing buildings and terrain act as barriers and significantly reduce the noise levels due to the new plant, and therefore these NSRs will be subject to even lower noise level than the NSRs at Hung Shing Ye and Tai Wan To.   

Table 6.7        Predicted Facade Noise Levels at Hing Shing Ye/Tai Wan To and Ko Long

NSR

Total Sound Power Level, dB(A)

Horizontal Distance to the NSRs(1), m

Correction Factor, dB(A)

Predicted Facade Noise Level, dB(A)

 

 

 

Distance

Barrier(2)

Facade

Air absorption(3)

 

NSR1

112

1071

68.6

-5

+2.5

-3.0

38.0

NSR2

112

348

58.8

-20

+2.5

-1

35

Remark:

(1) For a worst case scenario assessment, the distance from the nearest plant to the NSR is used to assess the operational noise impact at the NSRs

(2) A negative correction of 5 dB(A) has been included for the NSR screened by the existing equipment units and 20 dB(A) has been included for the NSRs screened by the existing equipment units and natural topography (Kam Lo Hom).

(3) A sound absorption by the atmosphere (assumed at 500 Hz, 20°C, RH 70%) has been accounted for in accordance with ISO 9613-1 Acoustics – Attenuation of Sound During Propagation Outdoors – Part 1: Calculation of the Absorption of Sound by the Atmosphere. 

As NSR 1 will be subject to highest facade noise level, the cumulative operational noise levels from the existing Lamma Power Station, Extension Plant and proposed Project at NSR 1 are predicted and summarised in Table 6.8.

Table 6.8        Predicted Cumulative Noise Levels at Hung Shing Ye / Tai Wan To

Period

Existing Plant and Extension Plant(1),         Leq, 30min dB(A)

New L4 and L5,           Leq, 30min dB(A)

Cumulative Noise Impact, (Leq, 30min dB(A)

Daytime

54.7 (summer)

38.0

55

 

52.2 (winter)

38.0

52

Night-time

49.5 (summer)

38.0

50

 

49.5 (winter)

38.0

50

Remark:

 

 

 

(1) Reference was made from the prediction results (Table 6.5b) of Environmental Impact Assessment of a 1,800 MW Gas-Fired Power Station at Lamma Extension, February 1999, ERM-Hong Kong.

The additional equipment to be installed will have insignificant contribution when compared with the cumulative operational noise of the Lamma Power Station.  Therefore, the plant noise associated with the retrofit plant is not expected to give rise unacceptable environmental impacts.    

6.5.4                                Mitigation Measures

The noise assessment indicated that, based on a worst-case scenario, the predicted facade noise levels will comply with the daytime, evening and night-time noise criterion at all NSRs.  In addition, most of the noise sources associated with the retrofit project will be housed within individual acoustic enclosure to minimise the noise impact to the environment (Table 6.6).  Hence, no further mitigation measures are required. 

6.6                                      Environmental Monitoring and Audit

In view of the anticipated insignificant noise impact in both construction and operational phases, additional noise monitoring work for this Project is considered not necessary. 

6.7                                      Conclusion

The proposed Project is in small scale.  Additionally, in the view that the residential developments are shielded from construction noise to varying degrees by the intervening hill (Kam Lo Hom) and the existing plants, and considerable separation distance between the NSR and the Project, it is envisaged that the construction noise of the Project will not be a concern for the NSRs located at a considerable distance from the proposed site.  However, in order to ensure that the construction noise levels at the NSRs controlled within the relevant criteria, good site practice and noise management is recommended during the construction phase. 

Based on a worst-case scenario, the operational noise levels due to additional equipment will comply with the noise criterion and will have insignificant contribution to the cumulative operational noise of the Lamma Power Station.  Therefore, the plant noise associated with the retrofit plant is not expected to give rise to unacceptable environmental impacts.    

In addition, most of the noise sources associated with the retrofit project will be housed within individual acoustic enclosure to minimise the noise impact to the environment. 

In view of the anticipated insignificant noise impact in both construction and operational phases, additional noise monitoring work for this Project is considered not necessary.



([1]) Environmental Impact Assessment of a 1,800 MW Gas-Fired Power Station at Lamma Extension, February 1999, ERM-Hong Kong.

([2])           ISO 9613 Acoustics - Attenuation of Sound during Propagation Outdoors.