4                                            WATER QUALITY ASSESSMENT

4.1                                      Introduction

The project involves installation of FGD plants to the two existing coal-fired Units L4 and L5 and demolition of two existing light oil tanks on formed land. When the FGD plants are in operation, limestone slurry is introduced to react with flue gas for removal of SO2 in the FGD plants before emission to the atmosphere.  As a result, wastewater filtrated from the reacted limestone slurry, i.e. gypsum slurry, will be produced and it will be directed to the existing wastewater treatment system.

This section examines the potential water quality impact induced by the project and suggests the applicable mitigation measures to minimise the adverse impacts, if any, on the water quality.

4.2                                      Legislation and Standards

The regulatory requirements and standards to protect water quality are as follows:

·          Water Pollution Control Ordinance (WPCO);

·         Technical Memorandum Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM);

·         Environmental Impact Assessment Ordinance (Cap. 499. S.16), Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), Annexes 6 and 14;

·         WPCO Licence on Decantrate Tower of the Ash Lagoon; and,

·         Practice Note for Professional Persons on Construction Site Drainage (PN 1/94)

 

4.2.1    Water Pollution Control Ordinance (WPCO)

The WPCO is the legislation for the control of water pollution and water quality in Hong Kong.  Under the WPCO, Hong Kong waters are divided into 10 Water Control Zones (WCZs). Each WCZ has a designated set of statutory Water Quality Objectives (WQOs). The WQOs set limits for different parameters that should be achieved in order to maintain the water quality within the WCZs.

The Project is located in the Southern WCZ.  The boundary for the WCZ is shown in Figure 4.1.  The WQOs for the marine waters of the Southern WCZ, which are presented in Table 4.1, are applicable as evaluation criteria for assessing compliance of any effects from the discharges of the Project.

Table 4.1        Water Quality Objectives for the Southern Water Control Zones

Water Quality Objectives

Part or parts of Zone

A.      ESTHETIC APPEARANCE

 

(a)    Waste discharges shall cause no objectionable odours or discolouration of the water.

Whole Zone

(b)    Tarry residues, floating wood, articles made of glass, plastic, rubber or of any other substance should be absent.

Whole Zone

(c)     Mineral oil should not be visible on the surface. Surfactants should not give rise to a lasting foam.

Whole Zone

(d)    There should be no recognisable sewage-derived debris

Whole Zone

(e)    Floating, submerged and semi-submerged objects of a size likely to interfere with the free movement of vessels, or cause damage to vessels, should be absent.

Whole Zone

(f)      Waste discharges shall not cause the water to contain substances which settle to form objectionable deposits.

Whole Zone

B.      BACTERIA

 

(a)    The level of Escherichia coli should not exceed 610 per 1000 mL, calculated as the geometric mean of all samples collected in one calendar year.

Secondary Contact Recreation Subzones and Fish Culture Subzones

(b)    The level of Escherichia coli should not exceed 180 per 100 mL, calculated as the geometric mean of all samples collected from March to October inclusive in one calendar year. Samples should be taken at least 3 times in a calendar month at intervals of between 3 and 14 days.

Bathing Beach Subzones

C.     DISSOLVED OXYGEN

 

(a)    Waste discharges shall not cause the level of dissolved oxygen to fall below 4 milligrams per litre for 90% of the sampling occasions during the year; values should be calculated as the water column average (arithmetic mean of at least 3 measurements at 1 metre below surface, mid-depth, and 1 metre above seabed). In addition, the concentration of dissolved oxygen should not be less than 2 milligrams per litre within 2 metres of the seabed for 90% of the sampling occasions during the year.

Marine waters excepting Fish Culture Subzones

(b)    The dissolved oxygen level should not be less than 5 milligrams per litre for 90% of the sampling occasions during the year; values should be calculated as water column average (arithmetic mean of at least 3 measurements at 1 metre below surface, mid-depth and 1 metre above seabed). In addition, the concentration of dissolved oxygen should not be less than 2 milligrams per litre within 2 metres of the seabed for 90% of the sampling occasions during the year.

Fish Culture Subzones

(c)     Waste discharges shall not cause the level of dissolved oxygen to be less than 4 milligrams per litre.           

Inland waters of the Zone

D.         pH

 

(a)    The pH of the water should be within the range of 6.5-8.5 units. In Marine waters addition, waste discharges shall not cause the natural pH range to be excepting Bathing extended by more than 0.2 units.       

Beach Subzones; Mui Wo (A), Mui Wo (B), Mui Wo (C), Mui Wo (E), Mui Wo (F) Subzones

(b)    The pH of the water should be within the range of 6.0-9.0 units.

Mui Wo (D) Sub-zone and other inland waters.

(c)     The pH of the water should be within the range of 6.0-9.0 units for 95% of samples. In addition, waste discharges shall not cause the natural pH range to be extended by more than 0.5 units.

Bathing Beach Subzones

E.      TEMPERATURE

 

(a)    Waste discharges shall not cause the natural daily temperature range to change by more than 2.0 degrees Celsius.

Whole Zone

F.      SALINITY

 

Waste discharges shall not cause the natural ambient salinity level to change by more than 10%.

Whole Zone

G.     SUSPENDED SOLIDS

 

(a)    Waste discharges shall neither cause the natural ambient level to Marine waters be raised by 30% nor give rise to accumulation of suspended solids which may adversely affect aquatic communities.

 

(b)    Waste discharges shall not cause the annual median of suspended solids to exceed 20 milligrams per litre.

Beach Subzones; Mui Wo (A), Mui Wo (B), Mui Wo (C), Mui Wo (E), Mui Wo (F) Subzones

(c)     Waste discharges shall not cause the annual median of suspended solids to exceed 25 milligrams per litre.

Mui Wo (D) Subzone and other Inland Waters

H.     AMMONIA

 

The ammonia nitrogen level should not be more than 0.021 milligram per litre, calculated as the annual average (arithmetic mean), as unionised form.

Whole Zone

I.   NUTRIENTS

 

(a)  Nutrients shall not be present in quantities sufficient to cause excessive or nuisance growth of algae or other aquatic plants.

Marine waters

(b)  Without limiting the generality of objective (a)      above, the level of inorganic nitrogen should not exceed 0.1 milligram per litre, expressed as annual water column average (arithmetic mean of at least 3 measurements at 1 metre below surface, mid-depth and metre above seabed).

Marine waters

J.   5-DAY BIOCHEMICAL OXYGEN DEMAND

 

Waste discharges shall not cause the 5-day biochemical oxygen demand to exceed 5 milligrams per litre.                                                                                                                  Inland waters of thedemand to exceed 5 milligrams per litre.

Inland Waters of the Zone

K.  CHEMICAL OXYGEN DEMAND

 

Waste discharges shall not cause the chemical oxygen demand to exceed 30 milligrams per litre.                                                                                                                  Inland waters of theexceed 30 milligrams per litre

Inland Waters of the Zone

L. DANGEROUS SUBSTANCES

 

(a)  Waste discharges shall not cause the concentrations of dangerous substances in marine waters to attain such levels as to produce significant toxic effects in humans, fish or any other aquatic organisms, with due regard to biologically cumulative effects in food chains and to toxicant interactions with each other.

Whole Zone

(b)  Waste discharges of dangerous substances shall not put a   risk to any beneficial uses of the aquatic environment.

Whole Zone

4.2.2    Technical Memorandum for Effluent Discharges into Drainage and Sewerage Systems, Inland and Coastal Waters

All discharges from the Lamma Power Station, including those from the emission control facilities, are required to comply with the Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM) issued under Section 21 of the WPCO.  The TM defines discharge limits for different types of receiving waters.  Under the TM, effluents discharged into the drainage and sewerage systems, inshore and coastal waters of the WCZs are subject to pollutant concentration standards for particular discharge volumes.  Any new discharges within a WCZ are subject to licence conditions and the TM acts as a guideline for setting discharge standards for inclusion in the licence.

For the discharges from the Lamma Power Station it is appropriate to make reference to Table 10a Standards for Effluents Discharged into the Inshore Waters of Southern, Mirs Bay, Junk Bay, North Western, Eastern Buffer and Western Buffer Water Control Zones.  Existing WPCO discharge licences have been issued for a number of wastewater discharges from the existing power station, including the cooling water systems, oil separators and wastewater treatment plant.

4.2.3    Environmental Impact Assessment Ordinance (Cap. 499. S.16), Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM)

Annexes 6 and 14 of the EIAO-TM provide general guidelines and criteria to be used in assessing water quality issues.

The EIAO-TM recognises that it may not be possible to achieve compliance with the WQOs in the vicinity of a wastewater discharge.  In this area, where the initial dilution of pollutants takes place, there may be greater water quality impacts than would be allowed by the WQOs.  Such an area may be termed a ‘mixing zone’ and within this area exceedence of the WQOs would not be deemed to be an adverse impact.  In general, the criteria for acceptance of a ‘mixing zone’ are that it must not impair the integrity of the water body as a whole and must not damage the ecosystem or impact marine sensitive receivers.

Whilst the technical circulars are non-statutory, they are generally accepted as best guidelines in Hong Kong and have been adopted as relevant for this assessment.

4.2.4    WPCO Licence on Decantrate Tower of the Ash Lagoon

The WPCO licence was issued to HEC in order to restrict the quality and quantity of the effluent of FGD Wastewater Treatment Plant (WWTP) discharged into the ash lagoon.  The effluent discharge limits are applied for two situations, i.e. normal plant operation and during plant maintenance.  Tables 4.2 and 4.3 present the details.

Table 4.2        Effluent Discharge Limits for FGD WWTP during Normal Plant Operation

Parameters

Unit

Maximum

Flow Rate

cu.m day-1

200

pH

(pH units)

6-9

Temperature

oC

40

Suspended Solids

mg L-1

30

COD

mg L-1

80

BOD

mg L

20

Iron

mg L

4

Barium

mg L

1.5

Mercury

mg L

0.005

Cadmium

mg L

0.005

Other Toxic Metals (individually)

mg L

0.4

Total Toxic Metals

mg L

0.8

Cyanide

mg L

0.1

Phenols

mg L

0.2

Sulphide

mg L

5

Total Phosphorus

mg L

8

Total Nitrogen

mg L

400

 

Table 4.3        Effluent Discharge Limits for FGD WWTP during Plant Maintenance

Parameters

Unit

Maximum

Flow Rate

cu.m day-1

500

pH

(pH units)

6-9

Temperature

oC

40

Suspended Solids

mg L-1

30

COD

mg L-1

80

BOD

mg L

20

Iron

mg L

4

Barium

mg L

1.5

Mercury

mg L

0.003

Cadmium

mg L

0.003

Other Toxic Metals (individually)

mg L

0.4

Total Toxic Metals

mg L

0.8

Cyanide

mg L

0.1

Phenols

mg L

0.2

Sulphide

mg L

5

Total Phosphorus

mg L

8

Total Nitrogen

mg L

150

 

4.2.5    Practice Note for Professional Persons on Construction Site Drainage (PN 1/94)

The ProPECC (PN 1/94) issued by EPD provides some basic environmental guidelines for the handling and disposal of construction site discharges to prevent or minimise construction impacts on water quality.

4.3                                      Assessment Methodology

The retrofit methodology (see Section 1.5) has been reviewed to assess the remoteness of the proposed project to existing and committed Water Sensitive Receivers.  The WSRs were identified according to guidance provided in Hong Kong Planning Standards and Guidelines (HKPSG).

Construction stages, sequence and duration were reviewed to identify activities likely to impact upon identified WSRs and other water courses.  Following the identification of WSRs and potential water quality impacts, the scale, extent and severity of potential net (i.e. unmitigated) construction /operational impacts were evaluated, taking into account all potential cumulative effects including those of adjacent projects, with reference to the WPCO criteria.

Where net water quality impacts exceed the appropriate WPCO criteria, practical water pollution control measures/mitigation proposals will be identified to ensure compliance with reference to the WPCO criteria.  Water quality monitoring and audit requirements will be subsequently developed, if necessary, to ensure the effectiveness of the water pollution control and mitigation measures.

4.4                                      Baseline Conditions and Water Quality Sensitive Receivers

4.4.1    Existing Conditions

Construction will be carried out on formed land where the drainage system has been well established.  During construction activities, the primary sources of water quality impacts will be from pollutants in site run-off. Pollutants, mainly suspended sediments, may also enter receiving waters if the run-off is not adequately controlled on-site.  The potential sources of impacts to water quality may be readily controlled by appropriate on-site measures to minimise potential impacts as discussed in Section 4.6.

4.4.2    Water Quality Sensitive Receivers

In order to evaluate the water quality impacts resulting from the construction and/or operation of the FGD plants on Lamma Island, the water sensitive receivers (WSRs) have been identified in accordance with the HKPSG, which provides criteria for identifying environmental factors influencing the proposed development.

The identified water quality sensitive receivers close to (i.e. within 3 km) the Power Station and around Lamma Island (Figure 4.2) include:

      Gazetted Bathing Beaches: Hung Shing Ye Beach and Lo So Shing Beach.

      Water Intakes: HEC Lamma Power Station Intake.

      Fish Culture Zones: Lo Tik Wan Fish Culture Zone and Sok Kwu Wan Fish Culture Zone.

      Sites of Ecological Interest: Pak Kok (corals present), Shek Kok Tsui (corals present), Luk Chau (corals present), Ha Mei Wan (fish spawning ground) and southern Lamma waters (Finless Porpoise, Chinese White Dolphin, green turtles nesting site and proposed marine park).  SW Lamma 1 and SW Lamma 2, which are situated to the south of the works area (Figure 4.2), have been selected to assess any potential water quality impacts of this Project on the southern Lamma waters.  As long as the impact on this part of the water is acceptable, the impact on the other parts of the southern Lamma waters will be less and therefore also acceptable.

Table 4.4 shows that the site is remote (i.e. > 1 km) from the WSRs except for the HEC Lamma Power Station Intake.

Table 4.4        Distance of the Site from the Water Quality Sensitive Receivers

Water Quality Sensitive Receivers

Minimum Distance

ID

 

from the Site (m)

 

Pak Kok (Coral)

3,020

SR1

Shek Kok Tsui (Coral)

1,800

SR2

Luk Chau (Coral)

3,110

SR3

Lo Tik Wan Fish Culture Zone

2,330

SR4

HEC Lamma Power Station Intake

200

SR5

Hung Shing Ye Beach

1,360

SR6

Lo So Shing Beach

2,010

SR7

Sok Kwu Wan Fish Culture Zone

2,480

SR8

Ha Mei Wan (Fish Spawning Ground)

1,500

SR9

SW Lamma 1

2,660

SR10

SW Lamma 2

3,920

SR11

4.4.3    FGD Waste Water Treatment (WWT) System

The existing WWT system is designed to treat the effluent from FGD plants by alkalization, precipitation and neutralization process without removal of heavy metals apart from zinc and manganese.  The plant capacity has been designed based on 5x350MW FGD with a total capacity of 54 m3 hr-1 (2 streams each of 27 m3 hr-1) which can also cater for supernatant from wastewater sludge centrifuge and other on-load equipment drains. The schematic diagram of the FGD WWT is illustrated in Figure 4.3 and the design capacity of the WWT Plant is calculated as follows:

 

Constant flow from 5 x 350MW (5 x 6.3 m3 hr-1):

31.5 m3

Supernatant from wastewater sludge centrifuge:

16 m3

Other on-load equipment drains:

6.5 m3

Total:

54 m3

Wastewater from FGD process is conveyed to the underground wastewater storage sump pits equipped with agitator for temporary storage.  When high level is reached, the wastewater is pumped to the pH adjustment and coagulation tanks where caustic soda is dosed to bring the pH to 9-10 for precipitation of metals as hydroxides.  After the pH adjustment and coagulation tank, the wastewater is dosed with a polymer and is brought to a thickener for settlement of suspended solids.

The water overflow from the thickeners is conveyed to a primary treated water storage tank for further neutralization by hydrochloric acid to decrease the pH to 6-9.  In case the pH is not correct or the turbidity of the wastewater is above a preset limit, it would be recycled back to the storage sump pit for re-treatment.

The underflow sludge is conveyed to two centrifuge feed tanks for temporary storage before feeding into the centrifuges for dewatering.  Dried sludge ejected from the centrifuges is temporarily stored and discharged to barge through conveyors.  The sludge is then taken away by contractor for reuse in the building industry.

Neutralized wastewater is temporarily stored in Rejected Treated Water Storage Tanks and then is discharged to the existing Ash Lagoon.  The Ash Lagoon will have sufficient capacity to store treated effluent from the FGD treatment process.  The discharge point for effluent from the ash lagoon decantrate tower is presented in Figure 4.4. Its quantity and quality is closely monitored in accordance with the WPCO licence on Decantrate Tower of the Ash Lagoon.

The decanted water from the Ash Lagoon is then discharged through the Cooling Water Outfall into the marine water.  The effluent of the Ash Lagoon is also monitored. 

The details of the monitoring results are presented in Section 4.5.2.

4.5                                      Water Quality Impact Assessment

4.5.1    Construction Phase

Potential sources of impacts to water quality from the construction activities are:

      Construction runoff; and

      Sewage effluents generated from the workforce.

Construction Runoff

Construction runoff from site areas may contain high loading of suspended solids (SS) and contaminants. Potential water pollution sources from construction site runoff include:

a)      Runoff and erosion from site surfaces, earth working areas and stockpiles;

b)      Used water from purging of the Light Oil Tanks; and

c)      Fuel, oil, solvents and lubricants from maintenance of machinery and equipment.

Construction runoff may cause physical, biological and chemical effects. Its physical effect can cause blockage of drainage channels due to the deposits of increasing SS from the site.  Chemical and biological effects are however highly dependent on its chemical and nutritional contents.  Runoff containing significant amount of concrete and cement-derived materials would lead to increasing turbidity and discoloration, elevation in pH, and accretion of pH solids.

There will be no wastewater generated by the demolition of oil tanks.  The excavated top soil will not be stored on site and will be removed offsite soon after the excavation due to limited site works area.

Excavation is necessary for the construction of the piled foundations of FGD booster fans, gas-gas heaters, gas ducts supports and the shallow foundation of the Switchgear and Equipment Building.  It is anticipated that the construction runoff will not be significant.  In addition, the existing storm drains could catch the runoff to prevent the run-off reaching the nearby marine water. With good practice of work, as stated in ProPECC PN1/4, and appropriate mitigation measures, the construction runoff should be minimal and unacceptable water quality impacts due to surface runoff are not expected.

Sewage Effluents generated from the Workforce

Sewage effluents will arise from the sanitary facilities provided for the on-site workforce.  The characteristics of sewage would include high levels of 5-day Biochemical Oxygen Demand (BOD5), Ammonia and E.coli counts.

The existing toilet facilities of the Power Station will be provided for use by the workforce.  Additional sanitary facilities are therefore not required. Based on the above, adverse impacts to water quality as a result of the sewage effluent generated by the workforce are not expected to occur.

4.5.2    Operational Phase

Potential source of impacts to water quality from the operation of the FGD plants are as a result of filtrate generated from the dewatering of gypsum slurry.

The limestone slurry is introduced to react with flue gas for removal of SO2. Water will filter out from the gypsum slurry after passing through the hydrocyclones.  It is then retained in the reclaimed water tanks before discharging to the existing wastewater treatment plant (WWTP). The influent is characterised as pH of 5-6 and SS of approximately 7% of the whole volume.

In line with the existing practice adopted for the Units L6, L7 & L8 FGD plants, operational plant effluent from the proposed FGD plant will be reused as far as possible for preparation of limestone slurry, conditioning of PFA for offsite transportation, etc. to minimise discharge to the existing WWTP.

The WWTP is equipped with a number of storage tanks/pits and recirculation lines to temporary store the effluent for re-treatment if the action limit is triggered.  Chemical tanks are usually sized based on 14 days usage for 5 x 350MW FGD Plants whereas the transfer/dosing pumps are with 100% standby capacity.  The sizing of the storage pits/tanks are listed in Table 4.5.

Table 4.5        WWTP Plant Design Capacity

Equipment Capacity

Size

Design

Wastewater Storage Sump Pit

120 m3 x 2

2x50% for 5x350MW

Rejected Treated Water Storage Tanks

260 m3 x 2

2x50% for 5x350MW

Referring to the past record (October 2004 to September 2005) at the sampling point of the Rejected Treated Water Storage Tank (Table 4.6), the effluent generated is well below the licence limit. Note that not all parameters require monitoring in accordance with the WPCO licence.  In addition, there is no normal and emergency plant maintenance discharge so far.

Table 4.6        Monitoring Records of FGD Wastewater Treatment Plant Discharge to Ash Lagoon

 

Daily Average

Concentration (Daily Average)

Month

Volume

pH

S.S.

Ba

Hg

Cd

Fe

TP

TN

CN

 

(m3 day-1)

 

(mg L-1)

(mg L-1)

(mg L-1)

(mg L-1)

(mg L-1)

(mg L-1)

(mg L-1)

(mg L-1)

Licence

Limit

200

6-9

30

1500

5

5

4000

8

400

0.1

Oct 2004

43.4

8.3

17.7

69

<0.5

<1

240

<0.1

53

<0.01

Nov 2004

19.1

8.4

17.8

22

<0.5

<1

300

<0.1

200

<0.01

Dec 2004

24.9

8.1

18.7

31

<0.5

<1

440

0.2

150

0.02

Jan 2005

44.7

8.3

15.1

24

<0.5

<1

<50

0.2

130

<0.01

Feb 2005

26.6

8.3

18.4

138

<0.5

2

<50

<0.1

115

0.04

Mar 2005

53.6

8.3

19.3

280

<0.5

2

100

0.2

285

0.02

Apr 2005

56.1

8.4

19.1

741

<0.5

2

110

0.6

315

<0.01

May 2005

57.0

8.4

19.0

340

1.4

3.8

130

0.2

320

0.02

Jun 2005

42.1

8.4

17.9

313

<0.5

<1

<50

0.1

148

<0.01

Jul 2005

78.3

8.4

19.5

307

<0.5

<1

<50

<0.1

145

0.01

Aug 2005

89.8

8.4

18.6

273

<0.5

3

260

0.2

117

<0.01

Sep 2005

52.7

8.5

19.3

30

<0.5

<1

<50

0.3

87

<0.01

As the L4 & 5 FGD would adopt the same wet limestone-gypsum process, similar properties of effluent would be generated with the following properties and the expected influent and effluent are given in Table 4.7.

Table 4.7        Expected Influent and Effluent Characteristics on FGD Wastewater Treatment Plan

Constituents

Units

Designed Influent for 5x350MW FGD

Expected Influent for 5x350MW FGD

Effluent at sampling point

pH

pH

5~6

5~6

6~9

Temperature

°C

46

43~44

≤40

Suspended

mg/L

71,800

64,400~66,200

≤30

Solids

 

 

 

 

Current design capacity of the existing WWTP is 54 m3 hr-1, which is designed to cater for effluent from 5 FGD plants each with a maximum effluent discharge rate of 6.3 m3 hr-1.  As the existing WWTP has spare capacity to cater for the additional wastewater produced from the proposed retrofit project, it is expected that effluent from the WWTP to the Ash Lagoon will meet the requirements in the WPCO licence for the Ash Lagoon Decantrate Tower.

The decanted water discharged from the Ash Lagoon is closely monitored.  The monitoring results of the decanted water discharged from the Ash Lagoon to the Cooling Water Outfall from October 2004 to September 2005 is presented in Table 4.8. 

Table 4.8        Monitoring Records of Ash Lagoon Discharged to Cooling Water Outfall

Month

Volume

SS

Ba

Hg

Cd

Fe

TP

TN

CN

 

(m3 day-1)

(mg L-1)

(mg L-1)

(mg L-1)

(mg L-1)

(mg L-1)

(mg L-1)

(mg L-1)

(mg L-1)

Licence

Limit

20,000

30

200

1

1

600

5.0

20

0.01

Oct 2004

18589.7

19.0

62

<0.5

<1

190

<0.1

0.4

<0.01

Nov 2004

18581.3

18.9

22

<0.5

<1

360

<0.1

0.3

<0.01

Dec 2004

18594.2

19.6

33

<0.5

<1

410

0.1

0.5

<0.01

Jan 2005

7203.9

20.3

23

<0.5

<1

<50

0.1

0.1

<0.01

Feb 2005

0

*

*

*

*

*

*

*

*

Mar 2005

0

*

*

*

*

*

*

*

*

Apr 2005

0

*

*

*

*

*

*

*

*

May 2005

0

*

*

*

*

*

*

*

*

Jun 2005

7506.0

17.9

32

<0.5

<1

<50

0.2

2.1

<0.01

Jul 2005

14106.1

18.7

40

<0.5

<1

90

<0.1

1.3

<0.01

Aug 2005

14087.4

20.5

30

<0.5

<1

190

0.2

0.6

<0.01

Sep 2005

3756.0

16.1

27

<0.5

<1

50

<0.1

0.9

<0.01

Notes:

* No sampling was taken due to no discharge.

The monitoring results show that the concentrations of the effluent from Ash Lagoon are well below the limit.  In overall, the effluent from Ash Lagoon is better in quality than that from the FGD WWTP.  It has been shown that the additional flow from the FGD plants is in compliance with the license and is environmentally acceptable.  On the basis of the above results and the fact that the discharge point of the cooling water outfall for the ash lagoon decantrate is directed away from WSRs (see Figure 4.4), effluent from the Cooling Water Outfall is not expected to pose any unacceptable adverse impacts on the WSRs.

Based on the above, no unacceptable impacts to WSRs are expected to occur as a result of either the construction or operation of the FGD Retrofit.

4.6                                      Mitigation Measures

4.6.1                                Construction Phase

General

Any construction effluent discharge should be diverted away from embayed water such as the eastern waters of the working site where bathing beaches are found.

Construction Runoff

Exposed soil areas should be minimised to reduce the contamination of runoff and erosion.  As mentioned in Section 4.5.1, excavation is necessary for the construction of the piled foundations of FGD booster fans, gas-gas heaters, gas ducts supports and the shallow foundation of the Switchgear and Equipment Building only.  Silt removal facilities, channels and manholes should be maintained and the deposited silt and grit should be removed regularly to ensure they are functioning properly at all times.  Temporary covers (i.e. tarpaulin) should also be provided to minimise the generation of high SS runoff.

A licensed waste collector will be standby on-site to collect the waste oils and other chemical waste collected from the demolition of oil tank and oil separator as well as the used water from diesel oil tank purging.  The used water will then be transported to a facility licensed to receive chemical waste, such as Chemical Waste Treatment Centre at Tsing Yi.

In addition, control measures, including implementation of excavation schedules, lining and covering of excavated stockpiles and contaminated soil treatment areas, shall be implemented to minimize contaminated stormwater run-off from the site.  The contaminated run-off water as well as leachate/seepage resulting from the contaminated soil stockpiles and treatment shall be collected and treated to meet the WPCO requirements prior to discharge.

Sewage Effluents

The existing toilet of the Power Station will be provided for the construction workforce. No additional sanitary facilities will be required and hence adverse impact is not anticipated.

Groundwater Discharge

According to the Land Contamination Assessment (Section 2), exceedances of TPH were detected in several groundwater samples.  As groundwater is not used for either domestic or industrial purposes at the Site and in the adjacent areas, remediation of TPH in the groundwater of the Site is not considered necessary.  Groundwater extraction is not anticipated during the demolition and/or construction programmes as the proposed excavations are at levels well above the site groundwater table.  However, if groundwater is encountered during the demolition and/or construction programmes and groundwater dewatering from the work areas is required, the extracted groundwater will be collected, appropriately stored on-site and recharged back to the underlying ground. 

4.6.2                                Operational Phase

As mentioned in Section 4.5.2, the operational plant effluent from the FGD plants should be reused as much as possible in order to minimise discharge to the WWTP.  Maintenance of the WWTP should be performed regularly to ensure the effluent from the WWTP would not exceed the current requirements stipulated in the WPCO license for Ash Lagoon.

Any operational effluent discharge should be discharged to the Ash Lagoon and the decanted water is then discharged through the Cooling Water Outfall, which is away from embayed water such as the eastern waters of the working site where bathing beaches are found

4.7                                      Summary of Environmental Outcomes and Conclusion

The potential water quality impacts from the retrofit of FGD plants have been assessed.  Assessment results indicate that no unacceptable water quality impacts will arise from the construction activities provided that the recommended mitigation measures are implemented.

The operation of the FGD plants will not result in adverse water quality impacts on the water quality sensitive receivers as the existing WWTP has adequate capacity to deal with the additional FGD effluent.

4.7.1                                Environmental Monitoring and Audit (EM&A) Requirements

Due to the small scale of the demolition and construction works of the Project, and no adverse impacts predicted, no EM&A is required for the Construction Phase.

Since the Project will not have any unacceptable water quality impacts, no additional EM&A activities are required, besides those already in place, such as those required by the operation of the existing WWTP at Lamma Power Station.