2.1
This section presents the requirements, methodology,
equipment, monitoring locations, criteria and protocols for the monitoring and
audit of air quality impacts during the construction and operational phase of
the Project. Air quality monitoring (NO2 concentrations) underneath
the proposed Atrium Link Extension (ALE) during operational phase of the
Project, as presented in this section, would be proposed for the Interim
Scenario (i.e. without the implementation of WDII project and CWB project). However,
should the area underneath the ALE be resumed for the construction of WDII
project and hence not open to public use upon completion of the ALE, NO2
monitoring would no longer be considered necessary. For the Long-term Scenario
(i.e. with the implementation of WDII project and CWB project), details of operational
air quality monitoring programme will be discussed and arranged among TDC, CEDD
or/and HyD in due course.
2.2
The objectives of the air quality monitoring shall be:
· to identify the extent of construction dust impacts on sensitive receivers;
· to determine the effectiveness of mitigation measures to control fugitive dust emission from activities during construction phase;
· to audit the compliance of the Contractor with regard to dust control, contract conditions and the relevant dust impact criteria;
· to recommend further mitigation measures if found to be necessary;
· to comply with Action and Limit (A/L) Levels for air quality as defined in this Manual;
· to monitor NO2 concentration underneath the Atrium Link Extension.
2.3
The criteria against which ambient air quality monitoring
shall be assessed during construction phase are:
·
The Hong Kong Air Quality
Objectives (AQOs) for TSP, 24-hour TSP levels of
·
The statutory 1-hour TSP limit
of
2.4
During
operation phase, the air quality level underneath the Atrium Link Extension
shall be assessed against the Hong Kong Air Quality Objective (AQO) for NO2,
1-hour average NO2 level of 300 mg m-3.
2.5
These
levels are not to be exceeded at
Air Sensitive Receivers (ASRs).
2.6
1-hour and
24-hour TSP levels shall be measured to indicate the impacts of construction
dust. The TSP levels shall be measured by following the standard method as set
out in High Volume Method for Total Suspended Particulates, Part 50 Chapter 1 Appendix B,
Title 40 of the Code of Federal Regulations of the USEPA.
2.7
Dust laden air
shall be drawn through a high volume sampler (HVS) fitted with a conditioned,
pre-weighed filter paper, at a controlled rate.
After sampling for 24-hours, the filter paper with retained particles is
collected and returned to the laboratory for drying in a desiccator followed by
accurate weighing. 24-hour average TSP
levels are calculated from the ratio of the mass of particulates retained on
the filter paper to the total volume of air sampled.
2.8
All relevant data including temperature, pressure, weather conditions,
elapsed-time meter reading for the start and stop of sampler, identification
and weight of the filter paper, and other special phenomena and work progress
of the concerned site, etc, shall be recorded down in detail. A sample data sheet is shown in Appendix
A.
2.9
HVS in compliance with the following specifications shall be used for carrying
out the 1-hour and 24-hour TSP monitoring:
·
0.6 -
· equipped with a timing / control device with ± 5 minutes accuracy for 24 hours operation;
· installed with elapsed-time meter with ± 2 minutes accuracy for 24 hours operation;
·
capable of providing a minimum
exposed area of
· flow control accuracy: ± 2.5% deviation over 24-hour sampling period;
· incorporated with an electronic mass flow rate controller or other equivalent devices;
· equipped with a flow recorder for continuous monitoring;
· provided with a peaked roof inlet;
· incorporated with a manometer;
· able to hold and seal the filter paper to the sampler housing at horizontal position;
· easy to change the filter;
· capable of operating continuously for 24-hour period.
2.10
The ET shall be responsible for the provision of the monitoring equipment.
He shall ensure that sufficient number of HVSs with appropriate calibration kit
is available for carrying out the baseline, regular impacts monitoring and
ad-hoc monitoring. The HVSs shall be
equipped with an electronic mass flow controller and be calibrated against a
traceable standard at regular intervals, in accordance with requirements stated
in the manufacturers operating manual and as described below. All the equipment, calibration kit, filter
papers, etc, shall be clearly labelled.
2.11
The flow rate of
each HVS with mass flow controller shall be calibrated using an orifice
calibrator. Initial calibration of the
dust monitoring equipment shall be conducted upon installation and prior to
commissioning. One point flow rate
calibration shall be carried out every two months. Five-point calibration shall be carried out
every six months.
2.12
The flow-rate of the sampler before and after the sampling exercise with the
filter in position shall be verified to be constant and be recorded down on the
data sheet as mentioned in Appendix
A.
2.13 Nitrogen Dioxide over 1-hour average shall be measured to determine whether the air quality levels underneath the Atrium Link Extension comply with the Air Quality Objective. The NO2 levels shall be measured by automatic analyzer with data-logging feature designated by the USEPA as “reference” or “equivalent” methods in accordance with Title 40 of the Code of Federal Regulations Part 53. The ET shall be responsible for the provision of the monitoring equipment.
2.14
The worst affected
and accessible location has been identified for TSP dust monitoring during
construction phase and nitrogen dioxide monitoring during operational phase as
shown in Table 2.1 and illustrated
in Figure 2.1. Prior to the commencement of the EM&A programme, the
proposed air quality monitoring station shall be discussed and agreed with the
Engineer, the ET, IEC and EPD.
2.15
When alternative
monitoring locations are proposed, the monitoring locations shall be chosen
based on the following criteria:
· monitoring at sensitive receivers close to the major site activities which are likely to have air quality impacts;
· monitoring at the air sensitive receivers as defined in the Technical Memorandum;
· assurance of minimal disturbance to the occupants during monitoring.
Table 2.1 Air Quality Monitoring Station
Identification No. |
ASR ID in EIA Report |
Air Quality Monitoring Location |
Construction Phase |
||
AM1 |
A8 |
|
AM2 |
A4 |
Renaissance Harbour View Hotel |
Operation Phase |
||
AM3 |
- |
Area underneath the Atrium Link
Extension(1) |
Note: (1) The
appropriate NO2 monitoring location shall be discussed and agreed
with the Engineer, the ET, IEC and EPD
2.16
When positioning the
HVS samplers, the following points shall be noted:
· a horizontal platform with appropriate support to secure the samples against gusty wind shall be provided;
·
no two sampler shall be placed
less than
· the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
·
a minimum of
·
a minimum of
· no furnace or incinerator flue is nearby;
· airflow around the sampler is unrestricted;
·
the sampler is more than
· any wire fence and gate to protect the sampler, shall not cause any obstruction during monitoring;
· permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
· a secured supply of electricity is needed to operate the samplers.
2.17
Baseline monitoring
shall be carried out to determine the ambient 1-hour and 24‑hour TSP
levels at the monitoring locations prior to the commencement of the Project
works. During the baseline monitoring,
there shall not be any construction or dust generating activities in the
vicinity of the monitoring stations.
2.18
TSP baseline
monitoring shall be carried out for a continuous period of at least 14 days
under typical weather conditions with the 24-hour and three 1-hour ambient
measurements taken daily at each monitoring location. General meteorological conditions (wind
speed, direction and precipitation) and notes regarding any significant
adjacent dust producing sources shall also be recorded throughout the baseline
monitoring period.
2.19
The baseline
monitoring will provide data for the determination of the appropriate Action
levels with the Limit levels set against statutory or otherwise agreed limits.
2.20
Baseline checking of
ambient TSP levels shall be carried out every six months at each monitoring
location, when no dusty works activities are in operation. If the ET considers that significant changes
in the ambient conditions have arisen, a repeat of the baseline monitoring may
be carried out to update the baseline levels and air quality criteria, after
consultation and agreement with the ER, the IEC and the EPD.
2.21
No baseline
monitoring is generally required for operational phase of the Project.
2.22
The monthly schedule
of the compliance and impact monitoring programme shall be drawn up by the ET
one month prior to the commencement of the scheduled construction period. For regular impact monitoring, a sampling frequency
of at least once in every six-days shall be strictly observed at all of the
monitoring stations for 24-hour TSP monitoring.
1-hour TSP monitoring shall also be conducted at least three times in
every six days when the highest dust impacts are likely to occur. The impact monitoring programme is summarised
in Table 2.2.
Table 2.2 Impact Monitoring Programme (TSP)
Sampling duration |
Frequency |
1 hour |
3 times
every 6 days |
24 hours |
Once
every 6 days |
2.23
Upon the completion
of the Atrium Link Extension, a continuous NO2 monitoring shall be measured
for the first six months at the appropriate monitoring location underneath the
Atrium Link Extension.
2.24
Before commencing
the monitoring, the ET shall inform the IEC of the impact monitoring programme
such that the IEC can conduct an on-site audit to ensure the accuracy of the
impact monitoring results.
2.25
Action and Limit
levels that provide an appropriate framework for the interpretation of
monitoring results have to be agreed between ET, IEC, EPD and the Engineer
before commencement of the air monitoring.
The air quality monitoring data shall be checked against the agreed A/L
levels. Recommended A/L levels are listed
in Table 2.3.
Table 2.3 Proposed Action and Limit Levels for Impact Monitoring
Parameter |
Action Level (1) |
Limit Level |
TSP (24 hour average) |
·
BL £ ·
BL > |
|
TSP (1 hour average) |
·
BL £ ·
BL > |
|
NO2 (1 hour average) |
NO2
concentration (1 hour average) equal to or higher than 300 mg m-3. |
300 mg m-3 |
Note: (1) BL = Baseline level,
2.26 The principle upon which the Event and Action Plan is based on the prescription of procedures and actions associated with the measurement of certain defined levels of air pollution recorded by the environmental monitoring process and the agreed A/L levels. In cases where exceedance of these A/L levels occurs, the ET, the IEC, the ER and the Contractor shall strictly observe the relevant actions listed in Table 2.4 for Construction Phase and Table 2.5 for Operational Phase.
Table 2.5 Event / Action Plan for Air Quality (Operational Phase)
EVENT |
ACTION |
|
ET |
TDC |
|
Action Level
being exceeded in the monitoring station |
Notify
TDC;
Provide
details of AQO exceedance and monitoring condition to EPD. |
Liaise
with EPD to investigate mitigation proposals;
Implement
mitigation proposals, if required. |
Construction Phase
2.27
The EIA
Report recommended air quality control and mitigation measures during the
construction phase of the Project in accordance with the Air Pollution Control
(Construction Dust) Regulation and good site practices are summarised below.
·
skip hoist for material transport should be totally enclosed
by impervious sheeting;
·
every vehicle should be washed to remove any dusty materials
from its body and wheels before leaving a construction site;
·
the area where vehicle washing takes place and the section
of the road between the washing facilities and the exit point should be paved
with concrete, bituminous materials or hardcores;
·
where a site boundary adjoins a road, streets or other
accessible to the public, hoarding of not less than 2.4 m high from ground
level should be provided along the entire length except for a site entrance or
exit;
·
every stock of more than 20 bags of cement should be covered
entirely by impervious sheeting placed in an area sheltered on the top and the
3 sides;
·
all dusty materials should be sprayed with water prior to
any loading, unloading or transfer operation so as to maintain the dusty
materials wet;
·
the height from which excavated materials are dropped should
be controlled to a minimum practical height to limit fugitive dust generation
from unloading; and
·
The load of dusty materials carried by vehicle leaving a
construction site should be covered entirely by clean impervious sheeting to
ensure dust materials do not leak from the vehicle.
·
Instigation of an environmental monitoring and auditing
program to monitor the construction process in order to enforce controls and
modify method of work if dusty conditions arise.
Operational Phase
2.28
No
adverse air quality impact on the ASRs would be identified during operational
phase of the Project after re-diversion of some fresh air intakes at the Hong Kong
Convention and Exhibition Centre Phase I, Renaissance Harbour View Hotel and
Grand Hyatt Hotel (ASRs A4, A5 and A6) to the new air vent shaft provided for
Atrium Link Extension where fresh air intake locates at +55.8m PD.
2.29
EIA
assessment results indicated that while the air quality underneath the Atrium
Link Extension would comply with AQO in the Interim Scenario, exceedance would
be found in the Long-term Scenario. According to the current Draft Wan Chai North
Outline Zoning Plan, the planned land use underneath the Atrium Link Extension
is “Road”. The results showed that the air quality level underneath the Atrium
Link would comply with the In-tunnel Air Quality Guideline.
2.30 The implementation for the recommended air quality impact mitigation measures is presented in Appendix B.
Table 2.4 Event / Action Plan for Air Quality (Construction Phase)
Event |
Action |
|||
Action Level |
ET |
Contractor |
ER |
IEC |
Exceedance for one sample |
1.
Identify
source 2.
Notify
IEC, ER and Contractor within 1 working day after receiving the laboratory
results. 3.
Conduct
additional monitoring to investigate the causes. 4.
Report
the investigation results and if exceedance is due to contractor’s
construction works to the IEC, ER and Contractor. 5. Increase monitoring frequency to once per 2
days for 24-hour TSP and daily for 1-hour TSP until exceedance stops if
exceedances are considered related to contractor’s construction works and
report the results to IEC, ER and Contractor within 1 working day after
receiving the laboratory results. |
1.
Take
immediate action to avoid further exceedance and rectify any unacceptable
practice. 2.
Submit
air mitigation proposal to IEC and ER for agreement within 3 working days if
ET indicated that exceedance is related to the construction works 3.
Implement
agreed proposal within a time scale agreed with ER and IEC. |
1.
Confirm
receipt of notification of failure in writing. 2.
Notify
Contractor. 3.
Require
Contractor to submit air mitigation proposal. 4.
Ensure
remedial measures are properly implemented. |
1.
Review
monitoring data and investigation report submitted by ET. 2.
Review
Contractor’s air mitigation proposal and advise the ER accordingly. 3.
Supervise
and confirm in writing the implementation of remedial measures within 2
working days after receipt of the mitigation proposal. |
Exceedance for two or more consecutive samples |
1.
Identify
source 2.
Notify
EPD, IEC, ER and Contractor within 1 working day after receiving the
laboratory results 3.
Conduct
additional monitoring to investigate the causes. 4.
Report
the investigation results and if exceedances are due to contractor’s
construction works to EPD, IEC, ER and Contractor within 3 working days after
additional monitoring. 5.
Increase
monitoring frequency to daily for 24-hour TSP and 1-hour TSP if exceedances
are considered related to contractor’s construction works until exceedance
stops, and report the results to EPD, IEC, ER and Contractor within 1 working
day after receiving the laboratory results. 6.
If
exceedances continue after 1-week monitoring events, request ER to arrange
meeting with ER, IEC and contractor to discuss remedial actions. |
1.
Take
immediate action to avoid further exceedance and rectify any unacceptable
practice 2.
In
consultation with the IEC, submit air mitigation proposal to IEC and ER for
agreement within 3 working days of notification if ET indicated that
exceedances are related to construction works 3.
Implement
agreed proposal within a time scale agreed with ER and IEC. 4.
Amend
working methods if appropriate. |
1.
Confirm
receipt of notification of failure in writing. 2.
Notify
Contractor. 3.
Require
Contractor to submit air mitigation proposal. 4.
Ensure
remedial measures are properly implemented. |
1.
Review
monitoring data and investigation report submitted by ET. 2.
Discuss
amongst ER, ET and Contractor in order to formulate air mitigation proposal. 3.
Review
Contractor’s air mitigation proposal and advise the ER accordingly. 4.
Supervise
and confirm in writing the implementation of remedial measures within 2
working days after receipt of the mitigation proposal. |
Event |
Action |
|||
Limit Level |
ET |
Contractor |
ER |
IEC |
Exceedance
for one sample |
1.
Identify
source 2.
Notify
EPD, IEC, ER and Contractor within 1 working day after receiving the
laboratory results 3.
Conduct
additional monitoring to investigate the causes. 4.
Report
the investigation results and if exceedances are due to contractor’s
construction works to EPD, IEC, ER and Contractor within 3 working days after
additional monitoring. 5.
Increase
monitoring frequency to daily if exceedances are considered related to
contractor’s construction works until exceedance stops, and report the
results to EPD, IEC, ER and Contractor within 1 working day after receiving
the laboratory results. |
1.
Take
immediate action to avoid further exceedance and rectify any unacceptable
practice 2.
In
consultation with the IEC, submit air mitigation proposal to IEC and ER for
agreement within 3 working days of notification if ET indicated that
exceedances are related to construction works 3.
Implement
agreed proposal within a time scale agreed with ER and IEC. 4.
Amend
working methods if appropriate. |
1.
Confirm
receipt of notification of failure in writing. 2.
Notify
Contractor. 3.
Require
Contractor to submit air mitigation proposal. 4.
Ensure
remedial measures are properly implemented. |
1.
Review
monitoring data and investigation report submitted by ET. 2.
Discuss
amongst ER, ET and Contractor in order to formulate air mitigation proposal. 3.
Review
Contractor’s air mitigation proposal and advise the ER accordingly. 4.
Supervise
and confirm in writing the implementation of remedial measures within 2
working days after receipt of the mitigation proposal.. |
Exceedance
for two or more consecutive samples |
1.
Identify
source 2.
Notify
EPD, IEC, ER and Contractor within 1 working day after receiving the
laboratory results 3.
Conduct
additional monitoring to investigate the causes. 4.
Report
the investigation results and if exceedances are due to contractor’s
construction works to EPD, IEC, ER and Contractor within 3 working days after
additional monitoring. 5.
Increase
monitoring frequency to daily if exceedances are considered related to
contractor’s construction works until exceedance stops, and report the
results to EPD, IEC, ER and Contractor within 1 working day after receiving
the laboratory results. 6.
If
exceedances continue after 2 consecutive monitoring events, request ER to
arrange meeting with IEC and contractor to discuss remedial actions. |
1.
Take
immediate action to avoid further exceedance and rectify any unacceptable
practice 2.
In
consultation with the IEC, submit air mitigation proposal to IEC and ER for
agreement within 3 working days of notification if ET indicated that
exceedances are related to construction works 3.
Implement
agreed proposal within a time scale agreed with ER and IEC. 4.
Amend
working methods and proposal if appropriate. 5.
Stop
relevant portion(s) of works as required by ER, ET and IEC |
1.
Confirm
receipt of notification of failure in writing. 2.
Notify
Contractor. 3.
Require
Contractor to submit air mitigation proposal. 4.
Ensure
remedial measures are properly implemented. 5.
If
exceedances continue arrange meeting with Contractor, IEC and ET and to
consider what portion(s) of works should be further mitigated or have to
stop. |
1.
Review
monitoring data and investigation report submitted by ET. 2.
Discuss
amongst ER, ET and Contractor in order to formulate air mitigation proposal. 3.
Review
Contractor’s air mitigation proposal and advise the ER accordingly. 4.
Supervise
and confirm in writing the implementation of remedial measures within 2
working days after receipt of the mitigation proposal.. |