2.1 The major works activity for the Atrium Link Extension will comprise the following:
Construction
and demolition of the temporary footbridge;
Demolition
of the existing Atrium Link;
Construction
and demolition of a temporary working platform;
Construction
of foundations and pile caps for the Atrium Link Extension; and
Construction
of superstructure for the Atrium Link Extension.
2.2 Construction works are expected to commence in May 2006 and to be completed by March 2009. Upon completion of the proposed ALE, Halls 1 and 2 at Level 2 and Level 5 of the Phase II development will be extended by 7,200 m2 each while Hall 3 at Level 7 will be extended by 5,000 m2. Related circulation and support areas of these Halls will be correspondingly enlarged. The total gross floor area of the Extension, including circulation and support areas, will be about 49,100 m2.