3 KEY FINDINGS OF THE ENVIRONMENTAL IMPACT ASSESSMENT
Construction Phase
3.1 Dust emission
from the site is an area of the concern for the construction phase of the
Project. TSP would be generated from
construction activities. In view of limited scale of construction area and no
dusty construction activities such as excavation and site formation, the
predicted TSP level at the ASRs were low and within the acceptable criteria,
with the incorporation of dust control measures stipulated in the Air Pollution Control (Construction Dust)
Regulation. These dust mitigation measures and good site practices shall be
incorporated into the contract clauses. Environmental monitoring and audit programme was also recommended to monitor the effectiveness of implementation of recommended
dust suppression measures during construction.
Operational Phase
3.2 Two assessment
scenarios of operation phase of the Project, Long-term Scenario and Interim
Scenario, have been assessed. For the
Long-term Scenario, cumulative air quality impact arising from vehicular
emissions from existing and planned roads with Central Reclamation Phase III
(CRIII), Central-Wanchai Bypass (CWB) & Wanchai Development Phase II (WDII); tunnel portal
emissions from the CWB westbound slip road; portal emission from Atrium Link
Extension, planned deckovers along Road P2 and deckover over Expro Drive; and
vent shaft emission from CWB Central Ventilation Building was assessed. For the Interim Scenario, cumulative air
quality impact arising from vehicular emissions from existing roads, portal
emission from Atrium Link Extension and deckover over
3.3 For Long-term Scenario,
results indicated that all representative ASRs except some fresh air intakes at
Renaissance Harbour View Hotel (ASR A4), Hong Kong
Convention and Exhibition Centre Phase I (ASR A5) and Grand Hyatt Hotel (ASR
A6) would satisfy the Air Quality Objective (AQO). Other than ASRs A4, A5 and
A6, the concentrations of 1-hour average NO2, 24-hour average NO2
and 24-hour average RSP of other representative ASRs were predicted to range
from 59 to
3.4 In view of the proposed deckover,
the background air quality outside the planned CWB eastbound tunnel would be different
comparing with the condition predicted in the WDII EIA Study. However, the
impact to the air quality in CWB tunnel would be alleviated as the design of
3.5 For Interim Scenario,
results indicated that the air quality at all representative ASRs and the area
underneath the Atrium Link Extension would satisfy the AQO. The concentrations of 1-hour average
NO2, 24-hour
average NO2 and 24 hour average RSP were predicted to range from 56 to
Construction Phase
3.6 The nearest NSR (i.e. NSR N2 – Causeway Centre), which rely on openable window for ventilation, is located about 250 m away from the nearest worksite. In addition, Causeway Centre is substantially screened by two office buildings (i.e. Great Eagle Centre and Harbour Centre) in between. Based on the nature of the major construction works for the Project, the maximum SWL of the construction activities throughout the construction period would be estimated to be about 127 dB(A) by assuming all typical construction plants operated concurrently as a conservation estimation. Taking into account the noise reduction provided by the large separation distance and the screening from the nearby office buildings, the construction noise levels at NSR N2 would be about 64 dB(A) which would be well within the EIAO-TM daytime construction noise criteria of 75dB(A).Therefore, noise arising from the construction activities of the proposed Project would not have significant impact on the NSRs located in the vicinity of the proposed work areas. To minimize noise emissions, however, good site practices and environmental audit are recommended during the construction stage of the Project.
Operational Phase
3.7 In terms of operation noise impacts, the closest distance between proposed plant room and the nearest NSR (Causeway Centre) identified are about 250m. And, the nearest NSR is located behind two office buildings. Based on preliminary design information, the total SWL of the equipment in the plant rooms was estimated to be 116 dB(A) as a conservative assumption. Taking into account the separation distance and the noise reduction provided by surrounding office buildings, the predicted noise levels at NSR N2 would be about 43 dB(A) which is comply with both daytime and nighttime criteria of 65 dB(A) and 55 dB(A) respectively. Adverse operation noise impact of the fixed plant on Causeway Centre would not be anticipated. However, appropriate noise reduction measures are recommended to minimize noise emissions.
Construction Phase
3.8 Short-term water quality impact could be associated with the proposed construction works. Impacts may result from the surface runoff from construction sites, sewage from on-site construction workers, wastewater from general construction activities and seabed disturbance from marine piling and marine pile extraction. Impacts could be controlled to comply with relevant standards in the Water Pollution Control Ordinance (WPCO) standards by implementing the recommended mitigation measures. Double layers of silt curtain are recommended to be installed around the marine piling and marine pile removal works. Good site practices and water pollution control measures are also recommended to minimize the water quality impacts. Therefore, unacceptable residual impacts on water quality would be unlikely. Monitoring of water quality is recommended to verify the effectiveness of the mitigation measures.
3.9 Hydrodynamics modelling was
conducted to evaluate the flushing impact on the ALE sea channel due to the
installation of marine piles for supporting the temporary working platform(s)
and temporary footbridge in the sea channel between Phase I and Phase II of the
HKCEC during the construction period.
The modelling exercise was carried out based on
a fully calibrated and verified model to ensure the model performance. Alternative layouts of temporary working
platform(s) were considered in the hydrodynamics modelling.
The modelling results concluded that the recommended
layout (Option 2) would cause the least impact on the flushing capacity of the
sea channel. Hydrodynamic modelling results indicated that the installation of
temporary piles in the sea channel would inevitably reduce the flushing
capacity of the sea channel. The impact
is however considered only temporary and the overall influence on the flushing
capacity of the sea channel during the construction period was predicted to be
less than 5% under the recommended option. Given that the marine piles would last for a maximum of three years and
would be removed after construction of the ALE, it is anticipated the overall
impact on the water quality inside the channel would be insignificant. Refuse collection
vessel is recommended to be mobilized on a need basis to collect any floating
refuse trapped at the ALE sea channel during the construction period.
Operational Phase
3.10 It is proposed that the sewage arising
from the proposed ALE to be discharged to the existing
3.11 It is proposed to discharge the additional stormwater
runoff arising from the proposed ALE to the existing
Construction Phase
3.12 Waste types generated by
the construction and demolition activities for the Atrium Link Extension are
likely to include C&D material, general refuse from the workforce and
chemical wastes from the maintenance of construction plant and equipment.
Provided that these identified waste arisings are to
be handled, transported and disposed of using approved methods and that the
recommended good site practices are to be strictly followed, adverse
environmental impacts would not be expected during the construction phase.
Operational Phase
3.13 The main waste
types generated during the existing operation of the pedestrian link between
Phase I and Phase II of the HK Convention and Exhibition Centre are general
refuse generated on site by the public and staff. These include waste paper, food wrappings and
beverage containers. It is estimated there would be a 5-7% increase ratio in
future operation of the establishment. The handling, collection, transportation
and disposal practices of the identified waste arisings
in the future are anticipated to follow the existing arrangements currently in
operation at the HKCEC.
Construction Phase
3.14 There will be some
Moderate residual impacts due to the
construction of the proposed HKCEC Atrium Link Extension:
LR1 – Urban Waterfront and Harbour
Mitigation measures will not be
able to deal with the fact the construction will cover a significant area of
the waterfront and the sea. The residual landscape impact during construction
will be Moderate.
VSR
With such close distance and prevailing view towards the New Wing
(Phase II) and the Harbour, the hotels will still
have much view to the construction even with mitigation measures. No matter how
much temporary screen is provided, the construction still cannot be ‘hidden’
from the hotels. The residual visual impact during construction will be
Moderate.
VSR1B – Wan Chai Waterfront
Even with mitigation measures, tourists enjoying and taking photos of
the waterfront will still have much view to the construction, which is visually
incompatible. It will be impossible and impractical to ‘hide’ the construction
in such an open area. The residual visual impact during construction will be
Moderate.
3.15 Key recommended
landscape and visual mitigation measures include visual screening for adjacent
hotels and HKCEC “New Wing” (Phase II) and “Old Wing” (Phase I), due
consideration for construction site and related activities, transplanting of
existing affected trees to adjacent open space and protection of existing
unaffected trees.
Operational Phase
3.16 There
will be only one Moderate residual impact due to the operation of the proposed
HKCEC Atrium Link Extension for the scenario with all possible waterfront
developments (e.g. Road P2, CWB and WDII currently under review):
VSR1B – Wan
Chai Waterfront
With Road P2 and
WDII, mitigation measures will not be able to deal with the significant
increase in covered vehicular surface, inducing Moderate visual impact during
operation.
3.17 Key recommended
landscape and visual mitigation measures include, most importantly, the
creation of cascaded roofs to be landscaped with various in-situ planting and
potted planting (30% of the roof area as planting area for the project will be
achieved) and the improvement of the existing covered space underneath the
proposed Atrium Link Extension with due consideration on sensitive façade
treatment, hard landscape, soft landscape, finishes, and lighting
elements. Other mitigation measures
include suitable appearance design for building service elements, transplanting
of existing affected trees to adjacent open space, provision of visual screens,
interior layout rearrangements, and the reinstatement of existing footpaths
along
Environmental Monitoring and Audit
3.18 Environmental monitoring and audit
(EM&A) requirements have been specified in an EM&A Manual. The EM&A
Manual contains full details of proposed baseline and compliance monitoring
programme, as well as performance specifications, audit requirements and
monitoring procedures.