8.1
Potential air quality impacts associated with the
construction and operation phases of the Project are presented in this
section. Representative Air Sensitive
Receivers (ASRs) have been identified.
The potential air quality impacts on these receivers likely to result
from the construction and operation of the Project have been identified and
evaluated. Potential impacts have been
avoided wherever possible and appropriate mitigation measures have been
proposed to minimise the potential air quality impact.
Environmental Legislation, Standards
and Guidelines
8.2
The criteria for evaluating air quality impacts and the
guidelines for air quality assessment are set out in Annex 4 and Annex 12 of
the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).
Air Quality Objective & EIAO-TMs
8.3
The Air Pollution Control Ordinance (APCO) provides the
statutory authority for controlling air pollutants from a variety of
sources. The Hong Kong Air Quality
Objectives (AQOs), which must be satisfied, stipulate the maximum allowable
concentrations over specific periods for typical pollutants. The relevant AQOs are listed in Table 8.1.
Table 8.1
Pollutant |
Maximum Concentration (µg m-3) (1) |
|||
Averaging Time |
||||
1 hour (2) |
8 hour (3) |
24 hour (3) |
Annual (4) |
|
- |
- |
260 |
80 |
|
Respirable Suspended
Particulates (RSP) (5) |
- |
- |
180 |
55 |
|
800 |
- |
350 |
80 |
Nitrogen Dioxide (NO2) |
300 |
- |
150 |
80 |
Carbon Monoxide (CO) |
30,000 |
10,000 |
- |
- |
Photochemical Oxidants (as Ozone, O3)
(6) |
240 |
- |
- |
- |
Note:
(1)
Measured at 298 K and 101.325 kPa.
(2)
Not to be exceeded more than three times per year.
(3)
Not to be exceeded more than once per year.
(4)
Arithmetic mean.
(5)
Suspended particulates in air with a nominal aerodynamic
diameter of
(6)
Photochemical oxidants are determined by measurement of
ozone only.
8.4
The EIAO-TM stipulates that the hourly TSP level should not
exceed
Air Pollution Control (Construction Dust) Regulation
8.5
Notifiable and regulatory works are under the control of Air
Pollution Control (Construction Dust) Regulation. Notifiable works are site formation,
reclamation, demolition, foundation and superstructure construction for
buildings and road construction.
Regulatory works are building renovation, road opening and resurfacing
slope stabilisation, and other activities including stockpiling, dusty material
handling, excavation, concrete production, etc.
This Project is expected to include notifiable works. Contractors and site agents are required to
inform EPD on carrying out construction works and to adopt dust reduction
measures to reduce dust emission to the acceptable level.
Description of the Environment
8.6
The Project site is located within the existing
8.7
The potential air quality pollutant sources in the study
area include traffic road emissions and industrial emissions from Wong Chuk
Hang.
8.8
There is no EPD air quality monitoring station located in
the vicinity of the Project site, so the background pollutant concentrations to
be adopted for the Project site have therefore been derived from data for
“Rural/ New Development” areas such as Shatin, Tai Po and Yuen Long, as
recommended in the EPD “Guideline on Assessing the ‘Total’ Air Quality
Impacts”.
8.9
The latest five years (1999 – 2003) average monitoring data
for similar type of development area including Shatin, Tai Po, Yuen Long, Tap
Mun and Tung Chung (adopted to represent the background air quality in this
project) are presented in Table 8.2.
Table 8.2 Background Air
Pollutant Concentration for the Study Area
Parameters |
Concentration (mg/m3) |
TSP |
75 (1) |
RSP |
50 (1) |
Nitrogen Dioxide |
43 (1) |
|
15 (1) |
8.10
The two main project sites would be on northern (The
Waterfront) and southern (The Summit) sides of Nam Long Shan. The study area for air quality impact
assessment was defined by a distance of
8.11
The air quality impacts at ground floor of the
representative ASRs, which is the average height of the human breathing zone,
were assessed in the study. Assessment
heights of
Table 8.3 Summary of
Representative Air Sensitive Receivers
ASR |
Description |
Land Uses |
Existing / Planned NSR |
No. of storey |
Ground Level (mPD Level |
Assessment Height (mAG) |
Horizontal Separation from Site Boundary (m) |
AL1 |
|
Hospital |
Existing |
8 |
32 |
1.5, 5, 10 |
300 |
AL2 |
|
Hospital |
Existing |
8 |
10.2 |
1.5, 5, 10 |
240 |
AL3 |
Wong Chuk Hang San Wai |
Residential |
Existing |
2 |
10 |
1.5, 5, 10 |
160 |
AL4 |
Wong Chuk Hang San Wai |
Residential |
Existing |
2 |
10 |
1.5, 5, 10 |
80 |
AL5 |
The Hazelton |
Residential |
Existing |
3 |
22 |
1.5, 5, 10 |
40 |
AL6 |
Country Villa |
Residential |
Existing |
3 |
22 |
1.5, 5, 10 |
25 |
AL7 |
Bay Villas |
Residential |
Existing |
3 |
34 |
1.5, 5, 10 |
25 |
AL8 |
Island View |
Residential |
Existing |
2 |
22 |
1.5, 5, 10 |
140 |
AL9 |
Manly Villa |
Residential |
Existing |
3 |
92 |
1.5, 5, 10 |
80 |
AL10 |
Old Teaching Block ( |
Educational Institution |
Existing |
4 |
10.2 |
1.5, 5, 10 |
80 |
AL11 |
Inspectorate Married Quarters |
Residential |
Existing |
10 |
25.5 |
1.5, 5, 10 |
40 |
AL12 |
Open Area of |
Residential |
Existing |
-(1) |
6 |
1.5, 5, 10 |
15 |
AL13 |
|
Recreational |
Existing |
-(1) |
9 |
1.5, 5, 10 |
80 |
AL14 |
Proposed |
Commercial |
Planned |
-(1) |
8 |
1.5, 5, 10, 20(3), 40(3) 60(3),
70(3), 80(3) 100(3) |
-(2) |
AL15 |
Office near Cable Car Station (2) |
Commercial |
Existing |
-(1) |
18 |
1.5, 5, 10, 20(3), 40(3) 60(3),
70(3), 80(3) 100(3) |
-(2) |
AL16 |
Tennis Court adjacent to |
Recreational |
Existing |
-(1) |
17.7 |
1.5, 5, 10 |
10 |
AL17 |
The |
Recreational |
Existing |
-(1) |
17.6 |
1.5, 5, 10 |
10 |
AL18 |
|
Educational Institution |
Planned |
6 |
19.5 |
1.5, 5, 10 |
445 |
AL19 |
Woodgreen Estate |
Residential |
Existing |
3 |
27.5 |
1.5, 5, 10 |
170 |
AL20 |
|
Residential |
Existing |
3 |
21.9 |
1.5, 5, 10 |
180 |
AL21 |
|
Residential |
Existing |
3 |
27.8 |
1.5, 5, 10 |
100 |
Note:
(1)
N/A
(2)
ASR located within
(3)
Additional assessment heights were selected for assessing SO2
emission from chimneys.
Identification of Pollutant Sources
Construction Phase
8.12
Potential impacts arising from the construction of the
proposed Project would include dust and gaseous emissions from construction
plant and vehicles. It is anticipated that dust would be generated from
activities such as stockpiling, blasting, demolition, excavation, materials handling, vehicular movements on
unpaved haul roads and wind erosion from the site. However, the only major dusty activities
would be site formation, excavation works and blasting.
8.13
The proposed construction works at The Waterfront and The
Summit would be carried out in phases and the associated construction
activities are described as follows:
The Waterfront
8.14
There are 6 main construction sites at The Waterfront. The main construction activities include site
clearance, demolition, site formation, piling works and superstructure
construction. The major dusty
construction activities would be excavation and site formation. The tunnel excavation works for the funicular
railway, however, would take place mostly within the tunnel and so should not
result in dust major impacts. For the
other sites, the periods planned for excavation/ site formation are as follows
(refer to construction programme, Appendix
2.2).
Birds of
Whisker’s Harbour – May
2008
Back of House – April to
May 2008
8.15
As the construction works are phased, it can be seen that
the major dusty construction activities at these sites would not take place
concurrently, except for site formation at Whisker’s Harbour and Back of
House. However, the overlapping period
would last for only one month. The
cumulative dust impact is therefore of short-term nature, and with the
implementation of appropriate dust suppression measures, would be unlikely to
cause adverse impacts.
The
8.16
Apart from excavation of the summit itself and the spoil
handling facility/ barging point located at Tai Shue Wan (both addressed below),
there are 6 construction sites at the
Polar Adventure – May
2008 to July 2008
Killer Whale Stadium –
May 2009 to November 2009
Marine World – January 2009
to March 2009
8.17
As the construction works are phased, the major dusty
construction activities at different sites would not take place
concurrently. Therefore, cumulative dust
impact is not expected. With the
adoption of dust suppression measures and provision of a buffer zone between
the construction areas and the visitor areas, adverse construction dust impacts
are not expected.
8.18
Excavation of the
8.19
However, in order to avoid dust impact to the Park visitors,
blasting would take place only in the early morning prior to the opening of the
Park. Therefore Park visitors would not
be affected by dust from blasting. In
addition, the closest ASRs are located at a considerable distance from the site
(at least
8.20
The excavated rock will need to be removed from the site
after blasting. In view of the potential
for dust impacts along the transportation route, a tunnel will be formed and
excavated material will be fed down the drop shaft and conveyed along a
horizontal adit (the so-called “glory-hole” excavation method). From the entrance to the tunnel adit,
excavated material will be transported by covered conveyor belt system to a
marine barging point with enclosed tipping hall at
Operational Phase
8.21
The major air pollutant sources during operational phase of
the Project would be vehicular emissions (in particular NO2 and respirable
suspended particulates, RSP) from additional traffic induced by the operation of the new park. Emissions from existing roads and industrial
emissions from the existing Wong Chuk Hang industrial buildings, as well as
from the hospitals within
Construction Phase
8.22
As the construction activities would be phased, it is
expected that, with implementation of dust suppression measures as stipulated
in the Air Pollution Control (Construction Dust) Regulation and proposed
mitigation measures stipulated in section 8.42 - 8.46, significant dust impact
would not arise. A qualitative approach to evaluate the air quality impact pertinent to
the construction of the Project is therefore adopted.
Operational Phase
8.23
Potential air quality impacts have been considered for two
scenarios: (i) future operation of
Emission Inventory
Vehicle Emissions from Open Roads
8.24
The peak hourly traffic flows induced from the operation of
the Project occurring within 15 years of the park without development or
redeveloped park opening, i.e. Year 2026 traffic flows, were used to predict
the worst case scenario in the future.
8.25
A sensitivity test was conducted to determine whether the
worst air quality scenario would occur on a weekday or on a Sunday/ Public Holiday. The worst case was determined in terms of the
traffic flow and emission factors, for major roads in the year 2026 with
redeveloped park and the park without development (refer to Appendices
8.26
The vehicular emission factors (Fleet Average Emission
Factors – EURO4 Model) for the year 2026 were adopted for assessment of the
future scenarios (park without development and re-developed park). The composite emission factors for the road
links were calculated as the weighted average of the emission factors of
different types of vehicle. As emission
factors beyond 2011 are not available, the 2011 vehicle emission factors have
been used for traffic beyond 2011 as a worst-case scenario. Details for the calculations of the composite
emission factors for each road link are given in Appendices
8.27
All major roads within
8.28
According to information provided by the Traffic
Consultants, there was no queue found on Sunday/ Public Holidays. Therefore, emission from idling vehicles near
the
Emissions
from Portal and Ventilation Shaft of
8.29
The proportion of traffic emissions expelled from the
portals and the vent shaft(s) of a vehicular tunnel depends on the ventilation
design of the tunnel. Aberdeen Tunnel is a
Table 8.4 Details of
Tunnel Length |
|
Carriageway |
|
Height of Ventilation
Shaft |
|
Intake Volume of each
Ventilation Shaft |
|
Exhaust Volume of each
Ventilation Shaft |
|
Exit Direction |
Upward |
Exit Velocity |
|
Portal Emission for
each carriageway direction |
29.41% * |
Note: * Calculated based on the given flow rate from
Aberdeen Tunnel Management Company.
Emission
from
8.30
Emissions from the industrial buildings at Wong Chuk Hang
and hospitals at Nam Long Shan area would contri
8.31
The emission factor for NOX was based on AP42
(USEPA 1998: Table
Dispersion Modelling
Vehicle
Emissions from Open Roads
8.32
The CALINE4 dispersion model was used to calculate the
hourly NO2, 24-hour NO2 and 24-hour RSP
concentrations. For calculation of the
NO2 concentrations, the vehicular emission factor for NOx was used
and the conversion factor from NOx to NO2 was assumed (conventionally)
to be 20%.
8.34
The worst-case scenario of neutral meteorological conditions
was assumed in the CALINE4 model.
·
Wind speed:
·
Wind direction: 360 wind direction
·
Surface roughness:
·
Mixing height:
·
Temperature
8.35
Portal emissions from the Aberdeen Tunnel were calculated
based on the procedures in Section III of the Permanent International
Association of Road Congress Report (PIARC), 1991. It was assumed that emissions would emerge as
an air jet along the axis of the road so that only the well-diluted parts
gradually shear off. The pollutants were
assumed to be ejected as a volume source in the model, with two-thirds of the
total emissions dispersed in the first
Chimney Emissions and Ventilation
Shaft Emissions from
8.36
Emissions (NO2 & SO2) from
chimneys and emissions (NO2) from the ventilation shafts of the
Aberdeen Tunnel were modelled as point sources employing the Industrial Source
Complex Short-Term (ISCST3) dispersion model.
The meteorological conditions used in the ISC3 model were the same as
those used in the CALINE4 model.
Concentration Calculation
8.37
To obtain the cumulative pollutant concentrations, a set of
360 values was derived from both the CALINE4 model and the ISCST3 model at each
receptor location (one value for each of the 360 wind directions). The highest value among the 360 wind
directions of each set values were identified and then added together
(regardless of wind direction), the resulting value was considered to be the
highest predicted pollutant concentration level at the receptor.
8.38
Background pollutant concentrations were added to the
results calculated above to produce the worst-case concentrations.
8.39
The construction activities
would be phased, and the blasting activities
would be undertaken in early morning before the opening of the Park. The
conveyor system would be operated in enclosed area. With the implementation of standard dust
suppression measures as stipulated in the Air Pollution Control (Construction Dust)
Regulation and recommended measures in Section 8.42, there would be no adverse
dust impacts on the ASRs in the vicinity of the construction sites. Additionally, an
environmental monitoring and audit programme will be implemented during
construction to ensure all the proposed mitigation measures would be properly
in place.
8.40
The predicted average NO2, RSP and SO2
concentrations at the representative ASRs are summarized in Tables 8.5 to 8.7. The predicted
concentrations are the cumulative result of emissions from:
·
Open road sections
·
Aberdeen Tunnel portals
·
·
Chimney emissions in the Wong Chuk Hang and Nam Long Shan
Area.
Table 8.5 Predicted Air Pollutant Concentrations at Representative ASRs
for the Future Scenario (Year 2026, Redeveloped Park)
141 |
82 |
63 |
||
139 |
82 |
63 |
||
133 |
79 |
62 |
||
155 |
88 |
65 |
||
152 |
87 |
64 |
||
145 |
84 |
64 |
||
185 |
100 |
69 |
||
180 |
98 |
68 |
||
169 |
93 |
67 |
||
150 |
86 |
64 |
||
147 |
85 |
64 |
||
138 |
81 |
63 |
||
158 |
89 |
65 |
||
149 |
85 |
64 |
||
132 |
79 |
62 |
||
173 |
95 |
67 |
||
145 |
84 |
63 |
||
124 |
76 |
61 |
||
145 |
84 |
63 |
||
135 |
80 |
62 |
||
120 |
74 |
60 |
||
99 |
65 |
57 |
||
99 |
65 |
57 |
||
97 |
64 |
57 |
||
77 |
57 |
54 |
||
77 |
57 |
54 |
||
76 |
56 |
54 |
||
100 |
66 |
57 |
||
98 |
65 |
57 |
||
94 |
64 |
57 |
||
84 |
60 |
55 |
||
84 |
59 |
55 |
||
83 |
59 |
55 |
||
116 |
72 |
60 |
||
113 |
71 |
59 |
||
106 |
68 |
58 |
||
130 |
78 |
61 |
||
128 |
77 |
61 |
||
124 |
75 |
61 |
||
126 |
76 |
61 |
||
125 |
76 |
61 |
||
120 |
74 |
60 |
||
112 |
71 |
59 |
||
110 |
70 |
59 |
||
105 |
68 |
58 |
||
102 |
67 |
58 |
||
101 |
66 |
58 |
||
98 |
65 |
57 |
||
89 |
61 |
56 |
||
89 |
61 |
56 |
||
88 |
61 |
56 |
||
284 |
140 |
82 |
||
261 |
130 |
79 |
||
200 |
106 |
71 |
||
148 |
85 |
64 |
||
146 |
84 |
64 |
||
139 |
81 |
63 |
||
164 |
91 |
66 |
||
161 |
90 |
66 |
||
152 |
86 |
64 |
||
153 |
87 |
65 |
||
126 |
76 |
61 |
||
107 |
69 |
58 |
Notes:
(1) Value in bold type indicates that the NO2
concentration exceeds the HKAQO.
(2) Background NO2
concentration of 43 mg/m3 and RSP concentration
of 50 mg/m3 are
included.
126 |
76 |
61 |
||
125 |
76 |
61 |
||
119 |
73 |
60 |
||
136 |
80 |
62 |
||
132 |
79 |
62 |
||
127 |
77 |
61 |
||
163 |
91 |
66 |
||
159 |
89 |
65 |
||
148 |
85 |
64 |
||
135 |
80 |
62 |
||
132 |
79 |
62 |
||
124 |
75 |
61 |
||
145 |
84 |
64 |
||
137 |
81 |
62 |
||
120 |
74 |
60 |
||
160 |
90 |
66 |
||
134 |
79 |
62 |
||
115 |
72 |
60 |
||
134 |
79 |
62 |
||
125 |
76 |
61 |
||
110 |
70 |
59 |
||
92 |
63 |
56 |
||
91 |
62 |
56 |
||
90 |
62 |
56 |
||
72 |
55 |
54 |
||
72 |
54 |
54 |
||
71 |
54 |
54 |
||
81 |
58 |
55 |
||
81 |
58 |
55 |
||
80 |
58 |
55 |
||
73 |
55 |
54 |
||
73 |
55 |
54 |
||
72 |
55 |
54 |
||
89 |
62 |
56 |
||
89 |
61 |
56 |
||
88 |
61 |
56 |
||
117 |
73 |
60 |
||
116 |
72 |
60 |
||
112 |
70 |
59 |
||
114 |
71 |
59 |
||
112 |
71 |
59 |
||
108 |
69 |
59 |
||
102 |
67 |
58 |
||
101 |
66 |
58 |
||
96 |
64 |
57 |
||
94 |
63 |
57 |
||
93 |
63 |
57 |
||
91 |
62 |
56 |
||
83 |
59 |
55 |
||
83 |
59 |
55 |
||
81 |
58 |
55 |
||
230 |
118 |
75 |
||
212 |
111 |
73 |
||
166 |
92 |
67 |
||
129 |
77 |
62 |
||
127 |
77 |
61 |
||
121 |
74 |
61 |
||
142 |
83 |
63 |
||
139 |
81 |
63 |
||
132 |
79 |
62 |
||
145 |
84 |
64 |
||
118 |
73 |
60 |
||
96 |
64 |
57 |
Notes:
(1) Value in bold type indicates that the NO2
concentration exceeds the HKAQO.
(2) Background NO2
concentration of 43 mg/m3 and RSP concentration
of 50 mg/m3 are
included.
Table 8.7 Predicted SO2 concentrations at Representative ASRs
for Future Scenario
104 |
||
105 |
||
107 |
||
114 |
||
160 |
||
332 |
||
440 |
||
386 |
||
217 |
||
134 |
||
134 |
||
135 |
||
135 |
||
173 |
||
204 |
||
204 |
||
191 |
||
129 |
Note: Background concentration of SO2
concentration =
8.41
As indicated in Tables
8.5 & 8.6, the NO2
& RSP concentrations at all representative ASRs in the future scenarios
(with or without development of the Park) would comply with the AQO
limits. The contour plots for hourly and
daily average NO2 and daily average RSP are only provided for the
future scenario (
8.42
As shown in Table 8.7, the worst
hit SO2 impact
at the ASRs within the
Mitigation of Adverse Environmental
Impacts
8.43
To ensure compliance with the guideline level and AQO, the
Air Pollution Control (Construction Dust) Regulation should be implemented and
good site practices should be incorporated into the contract clauses to
minimize construction dust impact. A
number of practical measures are listed below:
§ Use of regular watering,
with complete coverage, to reduce dust emissions from exposed site surfaces and
unpaved roads, particularly during dry weather.
§ Use of frequent watering
for particularly dusty construction areas, temporary stockpiles and areas close
to ASRs.
§ Side enclosure and
covering of any aggregate or dusty material storage piles to reduce
emissions. Where this is not practicable
owing to frequent usage, watering shall be applied to aggregate fines.
§ Open stockpiles shall be
avoided or covered. Where possible,
prevent placing dusty material storage piles near ASRs.
§ Restricting heights from
which materials are dropped, as far as practicable to minimise the fugitive
dust arising from unloading/ loading.
§ Tarpaulin covering of all
dusty vehicle loads transported to, from and between site locations.
§ Use of vehicle wheel and
body washing facilities at the exit points of the site.
§ Provision of wind shield
and dust extraction units or similar dust mitigation measures at the loading
points, and use of water sprinklers at the loading area where dust generation
is likely during the loading process of loose material, particularly in dry seasons/
periods.
§ Imposition of speed
controls for vehicles on unpaved site roads.
Ten kilometres per hour is the recommended limit.
§ Dusty activities should
be re-scheduled if high-wind conditions are encountered.
§ Where possible, routing
of vehicles and positioning of construction plant should be at the maximum
possible distance from ASRs.
§ Implementation of an environmental
monitoring and auditing program to monitor the construction process in order to
enforce controls and modify method of work if dusty conditions arise.
Drilling & Blasting
8.44
The following mitigation measures would be adopted for
drilling & blasting activities:
§ Watering on the exposed
area after blasting.
§ Use of vacuum extraction
drilling methods.
§ Carefully sequenced
blasting.
§ Firing of explosive would be carried out in the
morning prior to opening of the Park.
Crushing Plant
8.45
The following mitigation measures would be adopted for
temporary crusher:
§ Water sprays on the
crusher.
§ Fabric filters installed
for the crushing plant.
§ When transferring materials
from crusher to the conveyors, chutes or dust curtains would be used for
controlling dust.
Barging Point & Conveyor Belt System
8.46
To ensure negligible dust emission from the barging point
and conveyor belt system, the following measures would be adopted:
§ The conveyors would be
placed within a totally enclosed structure (see Figure 3.5 and 3.6).
§ Profiled steel cladding
would be provided at two sides of loading point.
§ Dust suppression sprays
would be installed and operated in strategic locations at the feeding inlet and
outlet.
§ The barging
point would be placed within a totally enclosed structure incorporating an
enclosed chute for material transfer to the barge. Flexible curtain would hang on the enclosed
chute to prevent dust emission when excavated materials/rocks are transported
into the barge.
8.47
Some areas of the Park would remain open for visitors during
the construction period. Therefore,
suitable buffer zones from
major construction activities should be provided where
practical and the works areas should be fenced off with hoarding
during the construction phase. It is
recommended to erect hoarding of a height not less than
Operational Phase
8.48
No adverse air quality impact are expected to arise from the
additional traffic induced due to operation of redeveloped Ocean Park,
therefore mitigation measures would not be required.
Evaluation of Residual
Impacts
8.49
With the implementation of the Air Pollution Control
(Construction Dust) Regulation and proposed mitigation measures, adverse
residual impact is not expected.
Operational Phase
8.50
No adverse residual impact is expected during the
operational phase.
Environmental Monitoring
and Audit
8.51
An Environmental Monitoring and Audit (EM&A) programme
is recommended to be established to check compliance with legislative
requirements. All the recommended
mitigation measures should be incorporated into the EM&A programme for implementation
during construction. Details are provided
in a stand-alone EM&A Manual.
8.52
The assessment concluded that the project would not result
in unacceptable traffic emission impacts, and so no mitigation measures are
required. Hence, there would be no
EM&A requirement for the operational phase of the Project.
8.53
With the implementation of effective dust suppression
measures, no adverse construction dust impact would be expected in the vicinity
of the project. Similarly, visitors in
the park should not be affected.
8.54
Cumulative emissions from nearby pollutant sources such as
chimneys, and road traffic on nearby roads as well as emissions from the
Aberdeen Tunnel were assessed. The air
quality impact due to operation of the future