Table 14.1 Summary
of Key Environmental Outcomes / Benefits
Area/Issue |
Environmental Outcomes / Benefits and Mitigation Measures |
Purpose and Scope of the Project |
The
purpose of the Project is to upgrade and expand the existing The
Project comprises various construction works for: civil infrastructure,
utilities, primary life support systems, municipal facilities, area
development, parkwide systems, hard/ soft landscape
& area theming, attractions venues,
installation of rides, merchandise/ retail facilities, food and beverage
facilities and back of house facilities (refer to Section 2.4 for details). |
Design options selection |
The
majority of the works comprise redevelopment works within the existing park
footprint to minimise impacts on other areas. A funicular
railway through a tunnel and operating by cables driven by electricity is
proposed to minimize the construction and operation environmental impacts due
to establishment of a new visitor transportation link between the Lowland
area and the Headland area. The
revised design is all in tunnel, resulting in less noise, ecological, and landscape and visual impacts than
the
previously proposed viaduct section. A new
access road from Tai Shue Wan to the Headland area
would no longer be implemented because of the likely ecological impacts
arising from construction. The tall shrubland between Nam Long Shan Road and Tai Shue Wan is preserved in the current Park expansion
scheme to reduce ecological impacts. Previous
schemes to develop different levels at the hillside on Nam Long Shan would
not be implemented, which would reduce long term long energy consumption
arising from the operation of passenger lifting devices for transporting
visitors between different levels. The service
reservoir proposed near the summit of Nam Long Shan has been relocated to the
|
Construction Method |
An enclosed
conveyor belt system is proposed for rapidly conveying the excavated material
from the excavation site for the new Barges are to be employed for
transporting majority of the surplus C&D material from the site formation
for the Blasting is proposed for rock
excavation at the |
Noise |
NSRs at Traffic noise associated with the operation phase of the Project was assessed for both the “with redevelopment” and “without redevelopment” scenarios on weekday and Sunday. Modelling results indicated that the increase in overall traffic noise levels predicted at all representative NSRs except 1-2/F of NSR PTS1 and 1-4/F of PTS2 would be less than 1dB(A). However, the predicted noise levels at 1-2/F of NSR PTS1 and 1-4/F PTS2 would comply with the noise criteria of 65dB(A) and 70 dB(A) for school and residential dwelling respectively. Thus, no mitigation measure is required. The assessment results also indicated that predicted noise
levels at all NSRs arising from the fixed plants of
the Project would comply with the EIAO-TM criteria. No mitigation measures
would be necessary. Noise impacts from loudspeakers for nightly lagoon shows would comply with the noise
criterion as set out in the EIAO-TM with all the proposed
mitigation measures in place. To ensure compliance with the EIAO-TM noise criteria,
monitoring of entertainment noise is considered necessary during nighttime show. A
noise review study will be conducted in detailed design stage to verify the EIA predictions. |
Landscape and Visual |
Excavation of “The Summit” at Nam Long
Shan and construction of “The Waterfront” will affect existing
landscape resources, landscape characters and visual sensitive
receivers. The impacts would be
acceptable with the implementation of recommended mitigation measures. Visual impacts from the funicular railway viaduct structure have been avoided by placing the entire railway in tunnel. Visual impacts from the proposed
reservoir have been reduced by relocating the reservoir to an area within the
footprint of the Impact of day-time glare would be
avoided through the adoption of suitable building forms and materials. Night-time glare would be essentially
“designed out” by carefully considering a reasonable level of functional and
thematic lighting with due consideration of possible light pollution and
night-time glare to the surroundings.
With careful consideration in the design stage and adoption where
necessary of suitable design features, there would be no residual day-time or night-time glare impact. |
Ecology |
Ecological impacts (including habitat loss, impact on plant species of conservation interest and disturbance impacts to habitats and associated communities arising from the excavation works at Nam Long Shan) would be minor and acceptable with the implementation of recommended mitigation measures. No adverse impact on coral and other marine communities would be expected during the construction and operation phase of the Project. Loss of tall shrubland
habitat has been avoided by placing the funicular railway entirely in tunnel,
rather than a section running on viaduct structure, and by relocating the
reservoir to an area within the footprint of the Loss of tall shrubland
habitat would be compensated by a greater area of planting (using natural
species) at an area within and adjacent to the Park. Loss
of marine ecological resources is avoided as there would not be any
marine-based construction works for this Porject. |
Waste management implications |
Construction
waste arisings have been identified based on the
proposed construction activities and would comprise C&D material, general
refuse and chemical waste. Provided
that the identified waste arisings are to be
handled, transported and disposed of using approved methods and the recommended
good site practices are to be strictly followed, adverse environmental
impacts would not be expected during the construction phase. The
handling, collection, transportation and disposal practices of waste
generated during the operational phase would follow the existing arrangements
currently in operation at the Park. |
Land Contamination |
Based
on the desk-top study and the findings of site
inspection, no
sign of contamination is noted in the existing Site investigation
conducted at CBD in March 2006 indicated that elevated TPH concentrations
were identified at 2 sampling locations near the underground storage tanks
whereas elevated levels of arsenic/tin were also identified at five sampling
locations. Excavation and landfill
disposal is recommended for TPH contaminated soil, with quantity of ~ For a conservative
approach, cement solidification/stabilization treatment is recommended for
the heavy metals contaminated soil (~ It is proposed that site investigation works should be
conducted at the HKSM site as soon as possible prior to the commencement of
site clearance/ construction works. No adverse residual impact in respect of land contamination would be anticipated if necessary remediation works are carried out at the identified contaminated land in the HKSM and CBD sites.
|
Air quality |
No adverse dust impacts would be expected on the ASRs within (e.g. visitors) or in the vicinity of the Park with the implementation of effective dust suppression measures. The operation of the proposed Project would not incur adverse air quality impacts to the nearby ASRs. |
Water quality |
Water
quality impacts from construction activities would be controlled by
implementing the recommended mitigation measures. Additional types of operation discharge from the future operations at
the redeveloped Park is not expected.
Operational improvements would be implemented to ensure control of
discharges within statutory limits. Upgrading
of the existing foul sewerage system within the Park will be required to
prevent sewage overflow and/or emergency bypass as a result of capacity
constraint of the sewerage system. |
Sewerage and Sewage Treatment Implication |
The performance assessment results under the peak flow
condition have identified The Aberdeen PTW was assessed to be adequate to convey the
total catchment flows both
with and without the Project. |
Cultural Heritage |
The HKSM and the City Bus Depot
sites were assessed to be of low archaeological potential. An archaeological Investigation will need to
be undertaken prior to the construction phase to verify the absence or
presence of archaeological deposits. The construction works would not affect a historical
grave located in the Lowland section of |
Hazard to Life |
A Quantitative Risk Assessment study for the explosives related activities for the Project has been carried out. The risk level for the original Base Case was found to be unacceptable and therefore a new blasting strategy has been developed in consultation with Mines Division of CEDD. A number of additional risk control measures were identified and were included in this revised Base Case. For the revised Base Case, the level of offsite societal risk is within the acceptable limit, and since no area of individual risk greater than 10-5 per year could affect the public, therefore the risk level of the revised Base Case is considered acceptable. |