ID
No. |
Nature/ Type |
Landscape and Visual Mitigation Measure |
Funding / Implementation |
Management / Maintenance |
||
|
|
|
||||
CM-01 |
Design/
Construction Planning |
Temporary
Tree Nurseries
- Due to accessibility difficulties, new large trees are prone to be damaged
when being transported within the Park.
Small on-site temporary tree nurseries may be set up at various
locations at an early stage to allow small trees to grow during the construction
period. By the time these trees are
needed at the end of the construction for each Phase, they will have matured
and grown. They will require minimal
pruning and suffer much less damage during transplanting, as the moving
distance from an on-site rather than off-site nursery will be much
smaller. These trees may also be
positioned as visual mitigation during the construction period. |
|
N/A |
||
CM-02 |
Design/
Construction Planning |
No-intrusion
zone - To
maximize protection to existing trees, ground vegetation and the associated
under-storey habitats, construction contracts may designate ‘no-intrusion
zones’ to various areas of the site where no construction activities will
take place. Simple but durable
boundary fences may be set up around each zone. The contractor shall instruct their staff
and their subcontractors not to enter the zones, even for non-direct
construction activities, such as lunch break, resting, urination etc. The construction contract may require the
contractors to derive contractually enforceable mechanism to monitor its
staff and its subcontractors and to penalize violators. |
|
N/A |
||
CM-03 |
Design/
Construction Planning |
Hoarding – Two generic types of
hoarding or boundary fencing for construction shall be considered. One type should be graphical and thematic,
and visually ‘impermeable’ to block view into the construction. It shall be used for areas in close contact
with visitors and for areas where visual intrusion is a critical concern. The other should be subtle, camouflaged and
more ‘permeable’ so that they fit into the surrounding existing
landscape. It will be used for areas
to be viewed at a distance. |
|
N/A |
||
CM-04 |
Site
Practice |
Hill
Fire Prevention
- Burning shall be strictly prohibited onsite to prevent hill-fire. Welding activities shall be properly
monitored and followed up. Smoking
shall only be permitted in designated areas.
The Contractor shall include in the safety plans ways to prevent hill
fire, to patrol, to ensure good house keeping, to combat hill fire, and to
develop an evacuation plan. The
construction Contract shall refer the local laws and shall include
enforceable clauses to require the Contractor to compensate loss of existing
trees (even outside the Park boundary) due to hill fires where due to the
negligence of the Contractor. |
|
N/A |
||
CM-05 |
Site
Practice |
Appearance
of Construction Workers
- A recent example from the expansion project of the |
|
N/A |
||
CM-06 |
Site
Practice |
Dust and
Erosion Control for Exposed Soil - The cutting of Nam Long Shan is at a prominent
location on top of the hill highly visible from surrounding areas. Slope cutting shall be planned and carried
out with well-planning and with caution to suppress dust. Exposed soil shall be covered or
‘camouflaged’ and watered often. Areas
that are expected to be left with bare soil for a long period of time shall
be hydroseeded and covered with suitable protective fabrics. Due to the exposed nature of the site,
additional measures may be necessary during windy conditions. Existing vegetation, including trees,
surrounding the work site should be also be watered periodically during dry
periods to remove dust accumulated on foliage. Silt and erosion shall be controlled by
ground barriers around the slope cutting area. |
|
N/A |
||
CM-07 |
Site Supervision |
Quarterly
Report on Existing Trees
– To ensure protection to existing trees to be retained or transplanted
during construction, the construction contract may require the Contractor to
provide a quarterly photographic report on such trees. |
|
N/A |
||
CM-08 |
Site
Supervision |
Inspection/
Supervision by Relevant Resident Site Staff – Due to the special nature of the project, Ocean
Park and the main contractor should employ sufficient resident landscape
architects and landscape inspectors of works to ensure a due consideration of
landscape and visual impacts and mitigations throughout the construction
period. |
|
N/A |
||
CM-09 |
Design/
Construction Planning |
Construction
Plant/ Machinery –
To minimize the visual intrusion of construction activities to tourists and
visitors, a suitable color scheme of construction machines and plants shall
be adopted if available. Construction
machines and plants shall be cleaned on a regular basis. . |
|
N/A |
||
CM-10 |
|
(Not
used) |
|
|
||
CM-11 |
|
(Not
used) |
|
|
||
CM-12 |
Design/
Construction Planning |
Irrigation
Water – A
large amount of fresh water will be required for planting new
vegetation. Some planting may be
carried out in advance when irrigation network is not complete. Some planting, such as hillside planting,
is not even intended to be served by permanent irrigation systems. The Contractor should plan reliable water
source and distribution networks, including possible temporary water tanks
and water trucks, for irrigation. |
|
N/A |
||
CM-13 |
Design/
Construction Planning |
The
barging point and The conveyor belt system – The removal of excavated material from the |
|
N/A |
||
CM-14 |
Site
Practice |
Construction
Light – All
security floodlights for construction sites shall be equipped with adjustable
shield , frosted diffusers and reflective covers, and be carefully controlled
to minimize light pollution and night-time glare to the nearby
residences. The Contractor should
consider other security measures, such as infrared cameras, which impose
lower impacts. |
|
N/A |
||
|
|
|
||||
OM-01 |
Design/
Construction Planning |
Large-size
Plants – The
completed Park will seek to provide an ‘immediate’ greening effect for
enjoyment. Wherever technically
possible, such as in flat areas, use trees in ‘Semi-mature’ and
‘Heavy-standard’ sizes’. |
|
|
||
OM-02 |
Design/
Construction Planning |
Tree
Transplanting –Trees
of high to medium survival rate after transplanting to be affected by the
works shall be transplanted. Where practicable, trees shall be directly
transplanted to permanent onsite locations. |
|
By
others if outside |
||
OM-03 |
Design/
Construction Planning |
Tree
Compensation Ratio
– The proposed redevelopment of the Park is an expansion of the developed
area of the Park and a reduction in the natural or undeveloped portion of the
Park. For the |
|
By
others if outside |
||
OM-04 |
Design/
Construction Planning |
Balanced
Woodland Mix - Some
areas of the development will require special, exotic planting, such as large
palm trees in |
|
By AFCD
if outside |
||
OM-05 |
Design/
Construction Planning |
Hardy
Plants – There
is a substantial variation of vegetation coverage and density on the existing
site. Careful consideration on sun
orientation, altitude, wind direction, proximity to sea, and other
microclimate factors to select correct species of plants will be
necessary. Proposed vegetation,
including that in thematic areas, shall be of species that tolerate the
exposed and salty environment of the site.
|
|
By
others if outside |
||
OM-06 |
Design/
Construction Planning |
Minimize
Impacts on Existing Vegetation – Removal of existing vegetation should be
minimized through careful planning and master layout on park facilities. Some of the proposed works, such as
roadworks along |
|
By
others if outside |
||
OM-07 |
Design/
Construction Planning |
On-structure
Planting – A
substantial portion of planting in the Waterfront will be on-structure/
on-slab, over the proposed car park.
Sufficient soil depth, structural loading, and drainage should be
allowed. Minimum |
|
|
||
OM-08 |
Design/
Construction Planning |
Reuse of
Existing Soil – Existing topsoil shall be reused where
possible for new planting areas within the project. The construction program shall consider
using the soil removed from one phase for backfilling another. Suitable storage ground, gathering ground
and mixing ground may be set up onsite as necessary. |
|
|
||
OM-09 |
Design/
Construction Planning |
Trees
for Landform Change
- The |
|
|
||
OM-10 |
|
Not
used. |
|
|
||
OM-11 |
Site
Supervision |
Establishment
Period – Most
construction contracts in Hong Kong require the Contractor to carry out
routine horticultural operations, including watering, pruning, weeding, pest
control, replacement of dead plants etc. to ensure healthy establishment of
new planting during a 12 month establishment period. This Period also serves as a kind of
warranty/ guarantee on the quality of the plants supplied and installed by
the Contractor. There will be a
significant fraction of woodland/ hillside/ slope planting that requires
planting of whips or seedlings. The
quality of these small plants is sometimes difficult to assess in one growing
season. The 12 month establishment
period will incentivize the Contractor to provide quality materials and
uphold good maintenance. |
|
|
||
OM-12 |
Design/
Construction Planning |
Irrigation
Water – Some
hillside planting may not be intended to be served by permanent irrigation
system. The Contractor should plan
reliable water source and distribution networks, including possible temporary
water tanks and water trucks, to ensure sufficient watering during the
Establishment Period. |
|
|
||
OM-13 |
Design/
Construction Planning |
Enhancement
along Public Roads in Wong Chuk Hang – The proposed roadwork outside the new |
|
By HyD/
LCSD if outside |
||
OM-14 |
Design/
Construction Planning |
Boundary
with Neighbors
– Boundary features and boundary fence walls, especially those to be shared
with neighboring development such as the Hong Kong Country Club, shall be
carefully designed. |
|
|
||
OM-15 |
Design/
Construction Planning |
Overall
Lighting Strategy –
Theme park design would carefully consider a reasonable level of functional
and thematic lighting with due consideration of possible light pollution and
night-time glare to the surroundings. Consideration
shall be made by the lighting designers to the following measures: -
lighting shall be designed with due consideration of mounting height and
direction of light fixtures so as not to point directly towards any sensitive
receiver -
lighting shall be arranged with due consideration of reflectance so as to
avoid glare effect - lighting shall be regularly monitored
during operation - lights
located adjacent or in proximity to neighbors shall be carefully designed to
prevent possible light intrusion -
lighting operation schedule shall specify only lights necessary for security
to be left on after business hours - paving
materials should be selected as necessary to reduce potential glare from
surface reflectance -
particular attention should be paid to the use of lighting having a high
intensity or harsher tone (e.g. metal halide lamps) - lights
shall generally be models having precise cut-off range (such as full cut-off
optics where available and practicable) and if necessary be fitted with
adjustable anti-glare shields. |
|
|
||
OM-16 |
Design/
Construction Planning |
|
|
|
||
OM-17 |
Design/
Construction Planning |
Retaining
Wall Design – Some
portion of the proposed redevelopment will be built against the
hillside. Leveled platforms will be
created and in association with retaining walls. The layout and treatment of retaining walls
shall be an integral part of the proposed park facilities. Other treatments, such as planting in front
of walls, that are sympathetic to the surroundings may also be considered. |
|
|
||
OM-18 |
Design/
Construction Planning |
Appearance
and Greening for Non-thematic Elements – The appearance of individual park facilities
and elements is mostly determined by designed themes. However, for non-thematic elements that are
not of ‘utility’ nature, such as water tanks, sympathetic design on the form,
color, and texture shall be provided to attain a visual balance for the
overall site and also to accentuate thematic elements. Planting, such as turf, low groundcovers
and climbers, may also be planted on top of these elements to provide
greening and aesthetic effect. |
|
|
||
OM-19 |
Design/
Construction Planning |
Overall
Greening Strategy
– Woodland mix planting with native trees and shrubs would be adopted
where practicable. |
|
|
||