Table 7.8 Possible Remediation Options and
Preliminary Remediation Programme For
HKSM Site
Scenario |
Possible Quantity of Contaminated Soil (1) |
Possible Remediation Options (2) |
Preliminary Remediation Programme |
Scenario 1 |
No contaminated soil |
Nil |
Nil |
Scenario 2 |
Small volume of contaminated soil |
Landfill disposal |
3 to 5 months (3) |
Scenario 3 |
Large volume of contaminated soil which requires for the set-up of on-site/off-site
treatment plant |
Option 1 – On-site treatment by biopiling
and/or cement solidification/stabilisation |
12 to 18 months |
Option 2 – Off-site treatment by biopiling
and/or cement solidification/stabilisation |
12 to 18 months |
Notes:
(1) Small volume of contaminated soil is
expected to be a few hundreds cubic meters while the large volume of
contaminated soil is likely more than a thousand cubic meters.
(2) A complete comparison of the pros and cons of all possible
remediation options (plus recommendation) to be provided in the future RAP
submission so as to justify the proposed remediation options and determine the
best feasible option for contaminated soil treatment.
(3) Application of
landfill disposal to Facilities Management Group of EPD is normally required 3
months before disposal. Such application would be made as soon as possible if
excavation and landfill disposal is confirmed for soil remediation.