Table 2.6 Event / Action Plan for Construction Noise
Event |
Action |
|||
|
ET |
Contractor |
ER |
IEC |
Action Level |
1.
Identify
source. 2.
Notify
IEC, ER and Contractor. 3.
Conduct
additional noise monitoring to investigate the causes. 4. Report the investigation
results to the IEC, ER and Contractor. 5. Discuss with Contractor for
their formulation of remedial measures if the exceedance is related to
construction works. 6.
Conduct
additional monitoring to check mitigation effectiveness. |
1.
Take
immediate action to avoid further exceedance. 2.
Submit
noise mitigation proposals to ET, ER and IEC. 3.
Implement
noise mitigation proposals. |
1.
Confirm
receipt of notification of failure in writing. 2.
Notify
Contractor. 3.
Require
Contractor to propose remedial measures for the analysed noise problem. 4.
Ensure
remedial measures are properly implemented. |
1.
Review
the analysed results submitted by the ET. 2.
Review
the proposed remedial measures by the Contractor and advise the ER
accordingly. 3.
Supervise
and confirm in writing the implementation of remedial measures |
Limit Level |
1.
Identify
source. 2.
Notify
EPD, IEC, ER and Contractor. 3.
Conduct
additional noise monitoring and analyse Contractor’s working procedures to
determine possible cause of exceedance. 4.
Provide
interim report to EPD, IEC and ER on the causes and proposed actions to be
taken for the exceedances if exceedance is related to construction works 5.
Assess
effectiveness by additional monitoring and report to EPD, IEC, ER and
Contractor the results. 6.
If
exceedance stops, cease additional monitoring. |
1.
Take
immediate action to avoid further exceedance. 2.
Submit
proposals for remedial actions to ET, ER and IEC within 3 working days of
notification. 3.
Implement
the agreed proposals. 4.
Resubmit
proposals if problem still not under control. 5.
Stop
the relevant portion of works as determined by the ER until the exceedance is
abated. |
1.
Confirm
receipt of notification of failure in writing. 2.
Notify
Contractor. 3.
Require
Contractor to propose remedial measures for the analysed noise problem. 4.
Ensure
remedial measures are properly implemented. 5.
If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated. |
1.
Discuss
amongst ER, ET and Contractor on the potential remedial actions. 2.
Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly. 3.
Supervise
and confirm in writing the implementation of remedial measures. |