Table 4.2 Action and
Limit Level Exceedance Procedure for Coral Monitoring
Event |
ET
Leader |
Action
Level Exceedance |
Step
1 -
Inform the IEC, ER, Contractor, Project Proponent, EPD, and AFCD and discuss
the most appropriate method of reducing sediment in the discharge (e.g. check
and increase effectiveness of construction site drainage and
sediment and other site run-off removal facilities) Step
2 –
Audit the implementation of mitigation measures on site. Step 3 - If non-compliance continues, check and confirm
the effectiveness of mitigation measures and repeat monitoring survey
measurements. |
Limit
Level Exceedance |
Undertake Steps 1-3. If further exceedance of
Limit Level, suspend construction works until an effective solution is
identified. Once the solutions have
been identified and agreed with all parties, construction works may commence. |