Table 4.2          Action and Limit Level Exceedance Procedure for Coral Monitoring

 

Event

ET Leader

Action Level Exceedance

Step 1 - Inform the IEC, ER, Contractor, Project Proponent, EPD, and AFCD and discuss the most appropriate method of reducing sediment in the discharge (e.g. check and increase effectiveness of construction site drainage and sediment and other site run-off removal facilities)

Step 2 – Audit the implementation of mitigation measures on site.

Step 3 - If non-compliance continues, check and confirm the effectiveness of mitigation measures and repeat monitoring survey measurements.

Limit Level Exceedance

Undertake Steps 1-3. If further exceedance of Limit Level, suspend construction works until an effective solution is identified.  Once the solutions have been identified and agreed with all parties, construction works may commence.