Table 7.4 Event / Action Plan for Air Quality
Event |
Action |
|||
Action Level |
ET |
Contractor |
ER |
IEC |
Exceedance for one sample |
1.
Identify
source 2.
Notify
IEC, ER and Contractor 3.
Conduct
additional monitoring to investigate the causes. 4.
Report
the investigation results and if exceedance is due to contractor’s
construction works to the IEC, ER and Contractor. 5.
Increase
monitoring frequency to once per 2 days for 24-hour TSP and daily for 1-hour
TSP until exceedance stops if exceedances are considered related to contractor’s
construction works and report the results to IEC, ER and Contractor. |
1.
Take
immediate action to avoid further exceedance and rectify any unacceptable
practice. 2.
Submit
air mitigation proposal to IEC and ER for agreement if ET indicated that
exceedance is related to the construction works 3.
Implement
agreed proposal within a time scale agreed with ER and IEC. |
1.
Confirm
receipt of notification of failure in writing. 2.
Notify
Contractor. 3.
Require
Contractor to submit air mitigation proposal. 4.
Ensure
remedial measures are properly implemented. |
1.
Review
monitoring data and investigation report submitted by ET. 2.
Review
Contractor’s air mitigation proposal and advise the ER accordingly. 3.
Supervise
and confirm in writing the implementation of remedial measures. |
Exceedance for two or more consecutive
samples |
1.
Identify
source 2.
Notify
EPD, IEC, ER and Contractor 3.
Conduct
additional monitoring to investigate the causes. 4.
Report
the investigation results and if exceedances are due to contractor’s
construction works to EPD, IEC, ER and Contractor within 3 working days after
additional monitoring. 5.
Increase
monitoring frequency to daily for 24-hour TSP and 1-hour TSP if exceedances
are considered related to contractor’s construction works until exceedance
stops, and report the results to EPD, IEC, ER and Contractor. 6.
If
exceedances continue after 1-week monitoring events, request ER to arrange
meeting with ER, IEC and contractor to discuss remedial actions. |
1.
Take
immediate action to avoid further exceedance and rectify any unacceptable
practice 2.
In
consultation with the IEC, submit air mitigation proposal to IEC and ER for
agreement within 3 working days of notification if ET indicated that
exceedances are related to construction works 3.
Implement
agreed proposal within a time scale agreed with ER and IEC. 4.
Amend
working methods if appropriate. |
1.
Confirm
receipt of notification of failure in writing. 2.
Notify
Contractor. 3.
Require
Contractor to submit air mitigation proposal. 4.
Ensure
remedial measures are properly implemented. |
1.
Review
monitoring data and investigation report submitted by ET. 2.
Discuss
amongst ER, ET and Contractor in order to formulate air mitigation proposal. 3.
Review
Contractor’s air mitigation proposal and advise the ER accordingly. 4.
Supervise
and confirm in writing the implementation of remedial measures. |
Event |
Action |
|||
Limit Level |
ET |
Contractor |
ER |
IEC |
Exceedance
for one sample |
1.
Identify
source 2.
Notify
EPD, IEC, ER and Contractor 3.
Conduct
additional monitoring to investigate the causes. 4.
Report
the investigation results and if exceedances are due to contractor’s
construction works to EPD, IEC, ER and Contractor within 3 working days after
additional monitoring. 5.
Increase
monitoring frequency to daily if exceedances are considered related to
contractor’s construction works until exceedance stops, and report the
results to EPD, IEC, ER and Contractor. |
1.
Take
immediate action to avoid further exceedance and rectify any unacceptable
practice 2.
In
consultation with the IEC, submit air mitigation proposal to IEC and ER for
agreement within 3 working days of notification if ET indicated that
exceedances are related to construction works 3.
Implement
agreed proposal within a time scale agreed with ER and IEC. 4.
Amend
working methods if appropriate. |
1.
Confirm
receipt of notification of failure in writing. 2.
Notify
Contractor. 3.
Require
Contractor to submit air mitigation proposal. 4.
Ensure
remedial measures are properly implemented. |
1.
Review
monitoring data and investigation report submitted by ET. 2.
Discuss
amongst ER, ET and Contractor in order to formulate air mitigation proposal. 3.
Review
Contractor’s air mitigation proposal and advise the ER accordingly. 4.
Supervise
and confirm in writing the implementation of remedial measures. |
Exceedance
for two or more consecutive samples |
1.
Identify
source 2.
Notify
EPD, IEC, ER and Contractor 3.
Conduct
additional monitoring to investigate the causes. 4.
Report
the investigation results and if exceedances are due to contractor’s
construction works to EPD, IEC, ER and Contractor within 3 working days after
additional monitoring. 5.
Increase
monitoring frequency to daily if exceedances are considered related to
contractor’s construction works until exceedance stops, and report the
results to EPD, IEC, ER and Contractor. 6.
If
exceedances continue after 2 consecutive monitoring events, request ER to
arrange meeting with IEC and contractor to discuss remedial actions. |
1.
Take
immediate action to avoid further exceedance and rectify any unacceptable
practice 2.
In
consultation with the IEC, submit air mitigation proposal to IEC and ER for
agreement within 3 working days of notification if ET indicated that
exceedances are related to construction works 3.
Implement
agreed proposal within a time scale agreed with ER and IEC. 4.
Amend
working methods and proposal if appropriate. 5.
Stop
relevant portion(s) of works as required by ER, ET and IEC |
1.
Confirm
receipt of notification of failure in writing. 2.
Notify
Contractor. 3.
Require
Contractor to submit air mitigation proposal. 4.
Ensure
remedial measures are properly implemented. 5.
If
exceedances continue arrange meeting with Contractor, IEC and ET and to
consider what portion(s) of works should be further mitigated or have to
stop. |
1.
Review
monitoring data and investigation report submitted by ET. 2.
Discuss
amongst ER, ET and Contractor in order to formulate air mitigation proposal. 3.
Review
Contractor’s air mitigation proposal and advise the ER accordingly. 4.
Supervise
and confirm in writing the implementation of remedial measures. |