2.
AIR QUALITY
2.1.1
The
EIA concluded that while potential air quality impacts may arise as a result of
transporting dusty materials and construction activities during construction
phase, suitable mitigation and preventive measures will minimize these impacts.
This section describe the requirements and methodology for the baseline and
construction phase air quality monitoring for the audit of the performance of
the proposed mitigation and preventive measures in the EIA.
2.2.1
1-hour
and 24-hour Total Suspended Particulates (TSP) levels shall be measured by
following the standard high volume sampling (HVS) method as set out in the
Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. Upon approval of the ER, 1-hour TSP levels, that
indicate short event impacts, can be measured by direct reading methods which
are capable of producing comparable results to that taken by the high volume
sampling method.
2.2.2
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and other special phenomena and work progress of the
concerned site etc. shall be recorded in detail. A sample data sheet is shown
in Appendix B.
2.3.1
High
volume samplers (HVS) in compliance with the following specifications shall be
used for carrying out the TSP monitoring:
(a)
0.6-1.7
m3/min (20-60 SCFM) adjustable flow range;
(b)
equipped
with a timing/control device with +/- 5 minutes accuracy for 24 hours
operation;
(c)
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
(d)
capable
of providing a minimum exposed area of 406 cm2 (63 in2);
(e)
flow
control accuracy: +/- 2.5% deviation over 24-hr sampling period;
(f)
equipped
with a shelter to protect the filter and sampler;
(g)
incorporated
with an electronic mass flow rate controller or other equivalent devices;
(h)
equipped
with a flow recorder for continuous monitoring;
(i)
provided
with a peaked roof inlet;
(j)
incorporated
with a manometer;
(k)
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
(l)
easy
to change the filter; and
(m)
capable of operating continuously for 24-hr period.
2.3.2
The
Contractor’s ET leader is responsible for provision of the monitoring equipment.
He shall ensure that sufficient number of HVSs
with an appropriate calibration kit are available for carrying out any
baseline checks, regular impact monitoring and ad hoc monitoring. The HVSs shall be equipped with an electronic mass flow controller
and be calibrated against a traceable standard at regular intervals. All the
equipment, calibration kit, filter papers, etc. shall be clearly labelled.
2.3.3
Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognised primary standard and be calibrated
annually. The calibration data shall be properly documented for future
reference. All the data should be converted into standard temperature and
pressure condition.
2.3.4
The
flow-rate of the sampler before and after the sampling exercise with the filter
in position shall be verified to be constant and be recorded down in a data
sheet as shown in Appendix B.
2.3.5
If
the Contractor’s ET leader proposes to use a direct reading dust meter to
measure 1-hr TSP levels, he shall submit sufficient information to the ER to
prove that the instrument is capable of achieving a comparable result as that
the HVS and may be used for the 1-hr sampling. The instrument should also be
calibrated regularly, and the 1-hr sampling shall be determined periodically by
HVS to check the validity and accuracy of the results measured by direct
reading method.
2.3.6
Wind
data monitoring equipment shall also be provided and set up at conspicuous
locations for logging wind speed and wind direction near to the dust monitoring
locations. The equipment installation location shall be proposed by the
Contractor’s ET leader and agreed with the ER. For installation and operation
of wind data monitoring equipment, the following points shall be observed:
(a)
the
wind sensors should be installed on masts at an elevated level 10m above ground
so that they are clear of obstructions or turbulence caused by the buildings;
(b)
the
wind data should be captured by a data logger and be downloaded for processing
at least once a month;
(c)
the
wind data monitoring equipment should be re-calibrated at least once every six
months; and
(d)
wind direction should be divided into 16 sectors of
22.5 degrees each.
2.3.7
In
exceptional situations, the Contractor’s ET leader may propose alternative
methods to obtain representative wind data upon approval from the ER and
agreement from the ER and agreement from the IEC.
2.4
Laboratory Measurement/Analysis
2.4.1
A
clean laboratory with constant temperature and humidity control, and equipped
with necessary measuring and conditioning instruments, to handle the dust
samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The laboratory should be HOKLAS accredited or
other internationally accredited laboratory.
2.4.2
If
a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for
carrying out the laboratory analysis, the laboratory equipment shall be approved
by the ER and in consultation with the IEC. Measurement performed by the
laboratory shall be demonstrated to the satisfaction of the ER and the IEC. The
IEC shall conduct regular audit to the measurement performed by the laboratory
to ensure the accuracy of measurement results. The Contractor’s ET leader shall
provide the ER with one copy of the Title 40 of the Code of Federal
Regulations, Chapter 1 (Part 50), Appendix B for his
reference.
2.4.3
Filter
paper of size 8"x10" shall be labelled before sampling. It shall be a
clean filter paper with no pin holes, and shall be conditioned in a humidity
controlled chamber for over 24-hr and be pre-weighed before use for the
sampling.
2.4.4
After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper is then returned to the laboratory
for reconditioning in the humidity controlled chamber followed by accurate
weighing by an electronic balance with a readout down
to 0.1 mg. The balance shall be regularly calibrated against a traceable
standard.
2.4.5
All
the collected samples shall be kept in a good condition for 6 months before
disposal.
2.5.1
The
dust monitoring locations are shown in Table 2.1 and Figure 2.1. The status and locations of dust sensitive
receivers may change after issuing this manual. If such cases exist, the
Contractor’s ET leader shall propose updated monitoring locations and seek
approval from ER and agreement from the IEC.
Air Quality Monitoring Stations
Air Quality Monitoring Station |
Description |
ASR 14 (A1) |
Ho Pui Village |
ASR 15 (A2) |
Ma On |
2.5.2
When
alternative monitoring locations are proposed, the following criteria, as far
as practicable, should be followed:
(a)
at
the site boundary or such locations close to the major dust emission source;
(b)
close
to the sensitive receptors; and
(c)
take
into account the prevailing meteorological conditions.
2.5.3
The
Contractor’s ET leader shall agree with the ER on the position of the HVS for
installation of the monitoring equipment. When positioning the samplers, the
following points shall be noted:
(a)
a
horizontal platform with appropriate support to secure the samplers against
gusty wind should be provided;
(b)
no
two samplers should be placed less than 2 metres apart;
(c)
the
distance between the sampler and an obstacle, such as buildings, must be at
least twice the height that the obstacle protrudes above the sampler;
(d)
a
minimum of 2 metres separation from walls, parapets and penthouses is required
for rooftop samplers;
(e)
a
minimum of 2 metres separation from any supporting structure, measured
horizontally is required;
(f)
no
furnace or incinerator flue is nearby;
(g)
airflow
around the sampler is unrestricted;
(h)
the
sampler is more than 20 metres from the dripline;
(i)
any
wire fence and gate, to protect the sampler, should not cause any obstruction
during monitoring;
(j)
permission
must be obtained to set up the samplers and to obtain access to the monitoring
stations; and
(k)
a
secured supply of electricity is needed to operate the samplers.
2.6.1
Baseline
monitoring shall be carried out at all of the designated monitoring locations
for at least 14 consecutive days prior to the commissioning of the construction
works to obtain daily 24-hr TSP samples. 1-hr sampling shall also be done at
least 3 times per day while the highest dust impact is expected. Before
commencing the baseline monitoring, the ET leader shall inform the IEC of the
baseline monitoring programme such that the IEC can conduct an on-site audit to
ensure accuracy of the baseline monitoring results. Table 2.2 summarises
the parameters, frequency and duration for baseline monitoring.
2.6.2
During
the baseline monitoring, there should not be any construction or dust
generation activities in the vicinity of the monitoring stations.
2.6.3
In
case the baseline monitoring cannot be carried out at the designated monitoring
locations during the baseline monitoring period, it should be carried out at
alternative locations which can effectively represent the baseline conditions
at the impact monitoring locations. The alternative baseline monitoring
locations shall be approved with the ER and with the IEC.
2.6.4
In
exceptional cases, when insufficient baseline monitoring data or questionable
results are obtained, agreement with EPD should be sought on an appropriate set
of data to be used as a baseline reference and submit to ER for approval.
Air Quality Monitoring Locations, Parameters, Frequency and Duration for Baseline
Location |
Parameters |
Frequency |
Duration |
A1 |
24‑hour TSP |
Daily |
Two consecutive
week (total 14 days) |
A2 |
(All Locations) |
||
|
1-hour TSP |
Three times daily
during time of peak dust levels |
|
|
(All Locations) |
2.6.5
Ambient
conditions may vary seasonally and shall be reviewed at three monthly
intervals. If the ER or Contractor’s ET leader considers that the ambient
conditions have changed and a repeat of the baseline monitoring is required to
be carried out for obtaining updated baseline levels, the monitoring should be
at times when the contractor's activities are not generating dust, at least in
the proximity of the monitoring stations. Should a change in ambient conditions
be determined, the baseline levels and, in turn, the air quality criteria,
should be revised. The revised baseline levels and air quality criteria should
be agreed with the IEC and EPD.
2.7.1
The
Contractor’s ET leader shall carry out impact monitoring during the course of
the Works. For regular impact monitoring, the sampling frequency of once in
every six-days shall be performed at all designated monitoring stations for
24-hr TSP monitoring. For 1-hr TSP monitoring, the sampling frequency of three
times in every six-days should be undertaken when the highest dust impact
occurs. Before commencing the impact monitoring, the ET leader shall inform the
IEC of the impact monitoring programme such that the IEC can conduct on-site
audit to ensure accuracy of the impact monitoring results. All the locations
listed in Table 2.1 shall be monitored.
2.7.2
The
specific time to start and stop the 24-hr TSP monitoring shall be clearly
defined for each location and be strictly followed by the operator.
2.7.3
In
case of non-compliance with the air quality criteria, more frequent monitoring
exercise, as specified in the Action Plan in Section 2.8, shall be
conducted within 24 hours after the result is obtained. This additional
monitoring shall be continued until the excessive dust emission or the deterioration
in air quality is rectified.
2.8
Event and Action Plan for Air
Quality
2.8.1
The
baseline monitoring results form the basis for determining the air quality
criteria for the impact monitoring. The Contractor’s ET leader shall compare the
impact monitoring results with air quality criteria set up for 24-hour TSP and
1-hour TSP. Table 2.3 shows the air quality criteria and Action and Limit
levels to be used. Should non-compliance of the air quality criteria occurs,
the Contractor’s ET, the ER and the Contractor shall undertake the relevant
action in accordance with the Action Plan in Table 2.4.
Action and Limit Levels for Air Quality
Parameters |
Action |
Limit |
24-Hour TSP Level in μg/m³ |
For baseline level ≤ 200
μg/m³, For baseline level > 200
μg/m³, Action level = Limit level |
260 |
1-Hour TSP Level in μg/m³ |
For baseline level ≤ 384
μg/m³, For baseline level > 384
μg/m³, Action level = Limit level |
500 |
Event/Action Plan for Air Quality
EVENT |
ACTION |
|||
Contractor’s ET leader |
IEC |
ER |
Contractor |
|
ACTION LEVEL |
|
|||
1. Exceedance for one sample |
1. Identify
source 2. Inform
IEC, ER and Contractor 3. Repeat
measurement to confirm findings 4. Increase
monitoring frequency to daily |
1. Check
monitoring data submitted by Contractor’s ET leader 2. Check
Contractor’s working method |
1. Notify
Contractor |
1. Rectify
any unacceptable practice 2. Amend
working methods if appropriate |
2. Exceedance for two or more consecutive samples |
1. Identify
source 2. Inform
IEC, ER and Contractor 3. Repeat
measurement to confirm findings 4. Increase
monitoring frequency to daily 5. Discuss
with IEC, Contractor and ER on remedial actions required 6. If
exceedance continue, arrange meeting with IEC, ER
and Contractor 7. If
exceedance stops, cease additional monitoring |
1. Checking
monitoring data submitted by Contractor’s ET leader. 2. Check
Contractor’s working method 3. Discuss
with Contractor’s ET leader and Contractor on possible remedial measures 4. Advise
the ER on the effectiveness of the proposed remedial measures 5. Supervise
implementation of remedial measures |
1. Confirm
receipt of notification of failure in writing 2. Notify
Contractor 3. Ensure
remedial measures properly implemented |
1. Submit
proposals for remedial actions to IEC and ER within 3 working days of
notification 2. Implement
the agreed proposals 3. Amend
proposal if appropriate |
LIMIT LEVEL |
|
|||
1. Exceedance for one sample |
1. Identify
source 2. Inform
IEC, ER, EPD and Contractor 3. Repeat
measurement to confirm findings 4. Increase
monitoring frequency to daily 5. Assess
effectiveness of Contractor’s remedial actions and kept IEC, EPD and ER
informed of the results |
1. Check
monitoring data submitted by Contractor’s ET leader 2. Check
Contractor’s working method 3. Discuss
with Contractor’s ET leader and Contractor on possible remedial measures 4. Advise
the ER on the effectiveness of the proposed remedial measures 5. Audit
implementation of remedial measures |
1. Confirm
receipt of notification of failure in writing 2. Notify
Contractor 3. Ensure
remedial measures properly implemented |
1. Take
immediate action to avoid for the exceedance 2. Submit
proposals for remedial actions to IEC and ER within 3 working days of
notification 3. Implement
the agreed proposals 4. Amend
proposal if appropriate |
2. Exceedance for two or more consecutive samples |
1. Notify
IEC, ER, Contractor and EPD 2. Identify
source 3. Repeat
measurement to confirm findings 4. Increase
monitoring frequency to daily 5. Carry
out analysis of Contractor’s working procedures to determine possible
mitigation to be implemented 6. Arrange
meeting with IEC, Contractor and ER to discuss the remedial actions to be
taken 7. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results 8. If
exceedance stops, cease additional monitoring |
1. Discuss
amongst ER, Contractor’s ET leader and Contractor on the potential remedial
actions 2. Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly 3. Audit
the implementation of remedial measures |
1. Confirm
receipt of notification of failure in writing 2. Notify
Contractor 3. In
consultation with IEC, agree with the Contractor on the remedial measures to
be implemented 4. Ensure
remedial measures properly implemented 5. If
exceedance continues, consider what portion of the
work is responsible and instruct the Contractor to stop that portion of work
until the exceedance is abated. |
1. Take
immediate action to avoid for the exceedance 2. Submit
proposals for remedial actions to IEC and ER within 3 working days of
notification 3. Implement
the agreed proposals 4. Resubmit
proposals if problem still not under control 5. Stop
the relevant portion of works as determined by the ER until the exceedance is abate. |
2.9.1 The EIA report has recommended dust and odour control and mitigation measures. The Contractor shall be responsible for the design and implementation of these measures. The suggested dust and odour control/mitigation measures are described below.
Dust Mitigation
Measures
2.9.2 The following dust control measures as part of good construction site practice should be incorporated in the Contract Specification and implemented to minimize dust nuisance arising from the works to within acceptable levels:
(i) The Contractor shall frequently clean and water the site to minimize fugitive dust emissions.
(ii) Effective water sprays shall be used during the delivery and handling of aggregate and other similar materials, when dust is likely to be created and to dampen all stored materials during dry and windy weather.
(iii) Watering of exposed surfaces shall be conducted as often as possible depending on the circumstances.
(iv) Areas within the site where there is a regular movement of vehicles shall be regularly watered as often as necessary for effective suppression of dust or as often as directed by the Engineer.
(v) Where dusty materials are being discharged to vehicle from a conveying system at fixed transfer point, a three-sided roofed enclosure with a flexible curtain across the entry shall be provided. Exhaust fans shall be provided for this enclosure and vented to a suitable fabric filter system.
(vi) The Contractor shall restrict all motorized vehicles within the site, excluding those on public roads, to a maximum speed of 15 km per hour and confine haulage and delivery vehicles to designated roadways inside the site.
(vii) Wheel cleaning facilities shall be installed and used by all vehicles leaving the site. No earth, mud, debris, dust and the like shall be deposited on public roads. Water in the wheel cleaning facility shall be changed at frequent intervals and sediments shall be removed regularly. The Contractor shall submit details of proposals for the wheel cleaning facilities to the Engineer prior to construction of the facility. Such wheel cleaning facilities shall be usable prior to any earthwork excavation activity on site. The Contractor shall provide a hard-surfaced road between any cleaning facility and the public road.
(viii) All site vehicular exhausts shall be directed vertically upwards or directed away from ground.
(ix) Any materials dropped on paved roads shall be cleaned up immediately to prevent dust nuisance.
Odour Mitigation Measures
(x) Any odourous excavated material shall be placed away from sensitive receivers. The material shall be removed within 1 day.
(xi) Any odourous material stockpiled shall be of the shortest duration. Also, all stockpiled materials shall be stored in covered skips. Any leachate from these storage skips shall be collected in covered tanks or buckets and removed from site with toilet waste by licensed collectors for discharging to government sewer.
2.9.3
If
the above measures are not sufficient to restore the air quality to acceptable
levels upon the advice of Contractor’s ET leader, the Contractor shall liaise with the Contractor’s ET leader on some other
mitigation measures, endorsed by IEC and propose to ER for approval, and
implement the mitigation measures.