3.
NOISE
3.1.1
Noise impact is likely to arise
from some of the activities for the construction of KT13. The EIA recommended a
number of mitigation measures that should be implemented to reduce potential
impacts to acceptable limits. A monitoring programme is recommended for
baseline conditions and during the construction phase to evaluate the
performance of the proposed measures.
3.1.2
This section of the Manual
lists all the recommended mitigative and preventive measures in the EIA for the
control of construction noise, and the up to date requirements for baseline and
construction phase noise monitoring. The Contractor is required to implement
these listed measures in the EIA and to undertake noise monitoring as specified
in this section, in addition to complying with all noise control related
legislation.
3.2.1
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound pressure level (Leq). Leq(30 min) shall be used as
the monitoring parameter for the time period between 0700-1900 hours on normal
weekdays.
3.2.2
As
supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference. A sample data record
sheet is shown in Appendix B for reference.
3.3.1
As
referred to in the Technical Memorandum (TM) issued under the Noise Control
Ordinance (NCO), sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement, the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
3.3.2
Noise
measurements shall not be made in the presence of fog, rain, wind with a steady
speed exceeding 5ms-1 or wind with gusts exceeding 10ms-1.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s. Standard acoustical principles and practices
should be observed during monitoring.
3.3.3
The
Contractor’s ET leader is responsible for the provision of the monitoring
equipment. He shall ensure that sufficient noise measuring equipment and
associated instrumentation are available for carrying out the baseline
monitoring, regular impact monitoring and ad hoc monitoring. All the equipment
and associated instrumentation shall be clearly labelled.
3.4.1
The
locations of noise monitoring stations are shown in Table 3.1 and Figure 3.1. In case works is required for restricted
hours, monitoring locations may also include those relevant to the application
of Construction Noise Permit (CNPs) as advised by EPD.
3.4.2
The
status and locations of noise sensitive receivers may change after issuing this
manual. In this case, the Contractor’s ET leader shall propose updated
monitoring stations and seek approval from ER and agreement from the ICE and
EPD of the proposal.
Noise Monitoring Stations for Baseline and
Construction Monitoring
Noise Monitoring Stations |
Equivalent RNSRs in EIA |
Rationale |
N1 |
13b |
Closest to proposed work
under Section A |
N2 |
13d |
Closest to proposed
works under Section B |
N3 |
13f |
Closest to proposed work
for bypass culvert |
3.4.3
When
alternative monitoring stations are proposed, the monitoring locations should
be chosen based on the following criteria:
(a)
at
locations close to the major site activities which are likely to have noise
impacts;
(b)
close
to the noise sensitive receivers (N.B. For the purposes of this section, any
domestic premises, hotel, hostel, temporary housing accommodation, hospital,
medical clinic, educational institution, place of public worship, library,
court of law, performing art centre should be considered as noise sensitive
receiver); and
(c)
for
monitoring locations located in the vicinity of the sensitive receivers, care should
be taken to cause minimal disturbance to the occupants during monitoring.
3.4.4
The
monitoring station shall normally be at a point 1m from the exterior of the
sensitive receivers building facade and be at a position 1.2m above the ground.
If there is problem with access to the normal monitoring position, an
alternative position may be chosen, and a correction to the measurements shall
be made. For reference, a correction of +3dB(A) shall be made to the free field
measurements.
3.4.5
The
Contractor’s ET leader shall agree with the ER on the monitoring position and
the corrections adopted. Once the positions for the monitoring stations are
chosen, the baseline monitoring and the impact monitoring shall be carried out
at the same positions.
3.4.6
In
case the monitoring location’s windows are normally closed and operate their
air condition units, or has fixed windows and operate air conditioning units,
alternative locations shall be sought, bearing in mind the criteria listed in
Section 3.4.3.
3.5.1
The
ET Leader shall carry out baseline noise monitoring prior to the commencement
of the construction works. The baseline monitoring shall be carried out
continuously for a period of at least one week at interval of 5 minutes. The
A-weighted noise level Leq, L10 and L90 shall be recorded.
A schedule on the baseline monitoring shall be submitted to the ER for approval
before the monitoring starts.
3.5.2
The
survey period should be selected prior to the commencement of construction
activities in order to avoid other atypical noise sources. The proper
functioning of the logger shall be ensured during the monitoring period, and as
a minimum, the equipment shall be inspected for a period of not less that one
hour every two days to ensure its continued operation and to detail specific
noise sources audible at the monitoring location. The calibration of the logger
kit shall be as recommended by the manufacturer. Measurements shall be recorded
to the nearest 0.1 dB.
3.5.3
There
shall not be any construction activities in the vicinity of the stations during
the baseline monitoring.
3.6.1
Impact
monitoring shall be carried out at all the designated monitoring station in
Table 3.1 during the construction phase of the project. The monitoring
frequency for each station on a basis of each calendar week when noise
generating activities are underway is as follows:
•
one
set of Leq (30min) between 0700-1900 hours on normal weekdays.
3.6.2
General
construction work carried out during restricted hours is controlled by CNP
system under the Noise Control Ordinance (NCO).
3.6.3
The
Action and Limit Levels for Regular Monitoring are given in Table 3.2 and the
Event/Action Plan in Table 3.3.
3.7
Event and Action Plan for
Construction Noise
3.7.1
In
case of non-compliance with the construction noise criteria, more frequent
monitoring as specified in the Action Plan in Table 3.3 shall be carried out.
This additional monitoring shall be continued until the recorded noise levels
are rectified or proved to be irrelevant to the construction activities. The contractor’s
ET shall provide full documentation of his investigation on the cause of the
non-compliance and whether it can be traced to activities other than those
caused by the project, to the satisfaction of the ER and the IEC.
Action and Limit Levels for Construction Noise
|
Time
Period |
Action |
Limit |
Normal
hours |
0700-1900
hrs on normal weekdays |
When
one documented complaint is received |
75* dB(A) |
* Reduced to 70 dB(A) for schools and 65 dB(A)
during school examination periods.
3.8
Construction Noise Mitigation
Measures
3.8.1
To mitigate construction noise
impacts, gap-free noise barriers made of material at least 10 kg/m² shall be
installed at locations as indicated in Figure 3.2 shall be maintained
throughout the construction period. The Contractor shall also used quiet
powered mechanical equipment as well as conduct good site practices throughout
the construction period.
Table 3.3 Event/Action Plan for Construction Noise
Monitoring
EVENT
|
ACTION
|
|||
Contractor’s ET Leader
|
IEC |
ER |
Contractor |
|
|
|
|
|
|
Action Level |
1. Notify
IEC, Contractor and ER 2. Carry
out investigation 3. Report
the results of investigation to the IEC, Contractor and ER 4. Discuss
with the Contractor and formulate remedial measures 5. Double
monitoring frequency 6. Check
compliance to Action/Limit Levels after application of mitigation measures |
1. Review
the analysed results submitted by the Contract’s ET leader 2. Review
the proposed remedial measures by the Contractor and advise the ER
accordingly 3. Review
the implementation of remedial measures |
1. Confirm
receipt of notification of complaint in writing 2. Notify
Contractor 3. Require
Contractor to propose remedial measures for the analysed noise problem 4. Ensure
remedial measures are properly implemented |
1. Submit
noise mitigation proposals to ER and IEC 2. Implement
noise mitigation proposals |
|
|
|
|
|
|
|
|
|
|
Limit Level |
1. Notify
IEC, ER, EPD and Contractor 2. Identify
Source 3. Repeat
measurement to confirm findings 4. Increase
monitoring frequency 5. Carry
out analysis of Contractor’s working procedures to determine possible
mitigation to be implemented 6. Inform
IEC, ER and EPD the causes & actions taken for the exceedances 7. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results 8. If
exceedance stops, cease additional monitoring |
1. Discuss
amongst ER, Contractor’s ET leader and Contractor on the potential remedial
actions 2. Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly 3. Audit
the implementation of remedial measures |
1. Confirm
receipt of notification of failure in writing 2. Notify
Contractor 3. Require
Contractor to propose remedial measures for the analysed noise problem 4. Ensure
remedial measures are properly implemented 5. If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated |
1. Take
immediate action to avoid further exceedance 2. Submit
proposals for remedial actions to within 3 working days of notification 3. Implement
the agreed proposals 4. Resubmit
proposals if problem still not under control 5. Stop
the relevant portion of works as determined by the ER until the exceedance is
abated |
|
|
|
|
|