2                                  Project Description

The Project will be located within the existing site of the CPPS.  A brief description of the construction and operation of the Project is provided in the following sections.

2.1                            Construction of the Project

2.1.1                      Demolition and Relocation of Certain Existing Facilities

While the existing generating units will remain in their current locations, some of their auxiliary and common facilities to the south of the generating units at CPB may be demolished or relocated within CPPS to provide space for the FGD, SCR and related facilities.  The following demolition / relocation works are envisaged to be required:

·       demolition of CPB Fuel Oil Day Tank (FODT);

·       demolition of Dangerous Goods (DG) Store;

·       re-routing of underground pipeworks;

·       relocation of CO2 storage tank;

·       relocation of the LPG storage tanks; and

·       relocation of the Intermediate Pressure Reduction Station (IPRS).

2.1.2                      Installation of the New Emissions Control Equipment and Facilities

New facilities to be installed for the Project will include the SCR and FGD equipment, reagent and by-product handling and storage facilities associated with the SCR and FGD operations.  An additional berthing facility for the loading and unloading of reagents and by-products will also be required.  These are described in the following sections.

Installation of SCR and FGD Facilities

The SCR and FGD facilities will be retrofitted to the CPB generating units.  The exact footprint of these facilities will be finalized upon design optimisation.

Provision of Reagent and By-product Handling and Storage Facilities

The major reagent and by-product handling facilities for FGD operations will include limestone storage facilities, limestone slurry tanks, gypsum dewatering and storage facilities, and handling and storage facilities for lower grade gypsum.  SCR systems will require urea as the ammonia supply reagent, urea storage facilities, dissolvers, urea solution storage tanks and urea-to-ammonia reactors will be required.

Provision of Additional Berthing Facility

The SCR systems could require about 40,000 tonnes per annum (tpa) of urea, while the FGD systems could consume about 150,000 tpa of limestone and generate about 257,000 tpa of gypsum as by-product.  The quantities of reagents required and by-product produced will be finalised during the design engineering phase.  An additional berthing facility will be needed for the loading and unloading of process reagents and by-product.

The provision of additional berthing is by extending the existing Heavy Load Berth to form a multi-purpose wharf, providing a straight quay with the potential to accommodate ships with a wide range of loaded draft requirements.  It is anticipated that the extension work will require some small-scale dredging for the foundations of the deck and for providing a sufficient turning basin for the different marine vessels’ loaded draft requirements.

The preliminary general arrangements of the proposed facilities are shown in Figures 2.1.

2.2                            Operation of the Project

The operations involved in the control of emissions from CPB are summarised in the following sections:

2.2.1                      Selective Catalytic Reduction Process

In the selective catalytic reduction (SCR) process, a nitrogen-based chemical reagent in the form of ammonia (NH3) is injected into the flue gas upstream of the SCR catalyst.  The ammonia will be generated from a urea-to-ammonia conversion system and will selectively react with nitrogen oxides (NOx) in the presence of a catalyst to form nitrogen (N2) and water vapour (H2O).  The reactions are essentially the conversion of various nitrogen oxides in the flue gas to nitrogen gas (N2).  The oxygen removed from the nitrogen oxides combines with hydrogen to form water (H2O).  The products of the reactions, nitrogen gas (N2) and water (H2O), are innocuous and exist naturally in the atmosphere in large quantities.

2.2.2                      Limestone Flue Gas Desulphurisation (LS FGD) Process

In a LS FGD system, the flue gas enters a large vessel (usually known as the ‘absorber’), where it is sprayed with or bubbles through limestone slurry in the absorber.   The calcium carbonate (CaCO3) from limestone in the slurry reacts with the sulphur dioxide (SO2) in the flue gas to form calcium sulphite (CaSO3).  The calcium sulphite initially formed in the absorber is nearly 100% oxidised to form gypsum (CaSO4, calcium sulphate) by the provision of oxidation air into the sulphite slurry in a separate vessel, or in-situ, depending on the technology design.  The gypsum generated can be commercially recycled.

The schematics of the emissions control systems are presented in Figure 2.2.

2.3                            Proposed Project Programme

Subject to timely agreement of a long-term environmental policy with the HKSAR Government and the successor regulatory regime, the currently envisaged project milestones are as follows:

 

Key Stage of the Project

Indicative Date

Finalisation of other major permitting requirements

2006

Completion of front-end engineering design

1st half of 2007

Commencement of relocation of existing facilities

1st half of 2007

Award of major contracts

2007

Commencement of retrofit site work

End 2007

Start-up of the retrofitted units

End 2009 to 2011