1                                  Introduction

1.1                            Background to the Study

The Castle Peak Power Company (CAPCO) has initiated a project for emission control at the Castle Peak Power Station “B” units (CPPSB) (“Project”), in response to the Hong Kong SAR Government (HKSARG)’s stated intent to reduce emissions in Hong Kong.  An Environmental Impact Assessment (EIA) Study Brief was issued for the Project by the Environmental Protection Department (EPD) in October 2005 (EIA Study Brief No. ESB-134/2005).  In compliance with one of the Study Brief requirements, a land contamination assessment will be carried out for the Project Areas (“the site”). 

 

To accommodate the new development, extensive demolition works are required to relocate a number of existing facilities, including:

·       CPB Fuel Oil Day Tank (FODT, hereafter referred to as the aboveground fuel oil day tank) and associated pipe works connecting with fuel oil pump house (FOPH) and oil interceptor;

·       Dangerous Goods (DG) stores; and

·       Intermediate Pressure Reduction Station (IPRS), LPG compound and CO2 storage tanks.

 

The preliminary Project Areas are shown in Figure 1.1a.

 

Environmental Resources Management (ERM) was commissioned by CAPCO to conduct a land contamination assessment of the site, in accordance with the Study Brief requirements.

 

Site inspection including the sampling and analysis will be conducted to identify potential sources of contamination from historical and current operations in this area. 

 

This report describes the Contamination Assessment Plan (CAP) for the land contamination assessment.

 

1.2                            Objective of the CAP

The purpose of the CAP is to provide information, guidance and instruction for characterising land contamination at the proposed Project Areas.  This CAP documents procedures for identifying land contamination, carrying out the site investigation and evaluating the results to identify the nature and extent of contamination at the site.  The specific tasks of the CAP include:

·       Review of the history of the Project Areas in relation to possible land contamination;

·       Identification of potential contamination and associated impacts, risks or hazards; and

·       Preparation of a plan for the actual contamination assessment, which includes a proposal on soil and, where appropriate, groundwater sampling and analysis, for agreement with the EPD prior to its implementation.

 

The findings of the site investigation will be evaluated and reported in the Contamination Assessment Report (CAR).  If the findings confirm that the site is contaminated, a Remediation Action Plan (RAP) will be prepared and submitted to EPD for approval.

 

1.3                            Environmental Legislation and Non-statutory Guidelines

The assessment of land contamination sources and the potential impacts will be carried out in accordance with the guidelines set out in the Environmental Protection Department’s (EPD) Practice Note for Professional Person (ProPECC) PN3/94 - Contaminated Land Assessment and Remediation; and EPD’s Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards, and Car Repair/Dismantling Workshop (Guidance Notes) and other relevant guidance notes.

 

Under the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), Annex 19 Guidelines for Assessment of Other Impacts, consideration should be given during development and redevelopment projects to a number of potentially contaminating historical land uses, which have the potential to cause, or have caused, land contamination.  This includes developing a CAP for the investigation where such land uses are identified, preparation of CAR after the investigation has been completed, and if contamination is confirmed, a RAP.

 

2                                  Site Appraisal

2.1                            Site Appraisal and Review of Historical Site Investigation Data

ERM conducted a walkthrough of the proposed Project Areas on 16 November 2005 and identified the areas of potential sources of contamination as follows.

 

Potential sources of contamination within the Project Areas:

·       An aboveground fuel oil day tank, aboveground steel structures of 4,680 tonnes capacity underlain and surrounded with a concrete bund.  Visual inspection of the concrete bund area showed no evidence of oil leakage or spillage.

·       Dangerous goods (DG) storage, two one-storey concrete buildings located on concrete paved ground.  Visual inspection of the concrete floor around the DG stores showed no evidence of oil leakage or spillage.

·       Intermediate pressure reduction station (IPRS), LPG compound and CO2 storage tanks.

 

Locations of these facilities are presented in Figure 1.1a.

 

The aboveground fuel oil day tank (FODT) was surrounded with reinforced-concrete slabs with bund walls.  The bund walls were designed to provide containment volumes of not less than the maximum operating capacity of the oil tank and the containment was fitted with drain channels connecting to a sump pit, where the oil/oily drainage will be further diverted via a pipeline to a nearby oil interceptor.  Visual inspection of the tank and containment area identified no apparent evidence of oil staining.

 

According to information provided by CAPCO, oil leakage at one of the pipelines connecting the FOPH and the FODT inside the pipeline trench was reported on 29 July 2004 and the oil spill was cleaned up and written report submitted to Marine Department on 10 August 2004.

 

2.2                            Potential Soil and Groundwater Contamination

Based on the review of site information and the walkthrough, the potential sources of soil and groundwater contamination include the oil and chemical storage and handling and oil transmission facilities, are described in Section 2.1.  The facilities in the Project Areas may be considered to be potential sources of land contamination due to the following reasons:

·       Leakage and/or spillage from the oil tank to the underlying soil and groundwater;

·       Leakage and/or spillage of chemicals during handling in the DG stores.

 

The likely contaminants associated with the fuel storage and transfer facilities include total petroleum hydrocarbons (TPH), benzene, toluene, ethylbenzene, xylene (BTEX) and polycyclic aromatic hydrocarbons (PAHs).  The likely contaminants associated with the chemicals (DG stores) storage include total petroleum hydrocarbons (TPH), volatile organic compounds (VOCs, including benzene, toluene, ethylbenzene, xylene, BTEX) and semivolatile organic compounds (SVOCs, including polycyclic aromatic hydrocarbons, PAHs). 

 

 

3                                  Proposal for Site Investigation

3.1                            Sampling Strategy

The soil and groundwater sampling plan presented in the following Sections aims to determine the presence and/or extent of soil and groundwater contamination in the proposed Project Areas.

 

3.1.1                      Sampling Location and Sampling Depths

The sampling locations and depths are recommended based on the findings of the site appraisal and have made reference to the guidelines presented in the Guidance Notes.

 

The proposed site investigation programme is described below and is summarised in Table 3.1a.

·       Conduct a utility scanning and excavation of inspection pits to 1.2m below ground level (m bgl) to ensure no interference with underground utilities;

·       Eight (8) boreholes (DH1 to DH8) shall be drilled to 2 m below the groundwater level, these include:

-          Four (4) boreholes (DH 4 to DH 7) located within the northern coal storage yard to the south of the fuel oil day tank, DG stores, FOPH, APS/ADCR building and IPRS;

-          One borehole (1) (DH 3) located north of the fuel oil day tank;

-          One (1) borehole (DH 8) located at the IPRS; and

-          Two (2) boreholes (DH 1 and DH 2) located within the proposed gypsum dewatering and storage facilities area in the western coal storage yard.

·       Four (4) trial pits (TP1 to TP4) located within the northern coal storage yard area for surface soil sampling;

·       Sampling of soil for on-site visual investigation and screening using photo-ionisation detector (PID) from sub-surface (around 0.5 m) and every 1.0 m until the end of drilling;

·       Three soil samples shall be collected from each borehole to ascertain the vertical distribution of any detected contamination ([1]).  It is proposed that samples be taken from the unsaturated zone to below the groundwater level (eg at between 0.5m to 1m bgl, at soil and groundwater interface, at 1m below groundwater level) or where there is visual evidence of contamination;

·       One soil sample shall be collected from each trial pit to provide additional information on the surface soil condition;

·       All eight boreholes will be converted into eight (8) temporary groundwater monitoring wells to facilitate groundwater sampling ([2]);

·       One (1) groundwater (GW) sample shall be collected from each monitoring well; and

·       Free-floating products in groundwater, if observed, will also be collected for laboratory analysis.

 

Figure 3.1a shows the proposed soil and groundwater sampling locations.

 

3.2                            Analytical Parameters

With respect to the nature of the substances stored and used at the fuel oil day tank (medium fuel oil), diesel storage and filling station (diesel oil), vehicle maintenance workshop (lubricant oils and solvent), dangerous goods store, where paints and solvents are stored, it is proposed that the soil and groundwater samples collected will be analysed for TPH (total petroleum hydrocarbons), benzene, toluene, ethylbenzene, xylene (BTEX), polycyclic aromatic hydrocarbons (PAHs) volatile organic compounds (VOCs), and semivolatile organic compounds (SVOCs). 

Summary of analytical parameters are presented in Table 3.1a.

 

TCLP tests and analysis of leachate for metal concentrations (as per Landfill Disposal Criteria for Contaminated Soil listed in the EPD’s Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards, Car Repair/Dismantling Workshops) for the material’s suitability for landfill disposal will be conducted for the samples confirmed to be contaminated.

 


Table 3.1a           Proposed Site Investigation Programme

Location

Rationale

Depth

Temporary Monitoring Well

# Soil
Samples

# Groundwater Samples

Analytical Parameters

Borehole/Monitoring Well/Trial Pits

 

 

 

 

 

DH1

Located in the northern part of the proposed long-term gypsum storage area

2 m below groundwater level

1

3

1

Soil: TPH, BTEX and PAHs

Groundwater: TPH, BTEX and PAHs

DH2

Located in the southern part of the proposed long-term gypsum storage area

2 m below groundwater level

1

3

1

DH3

Located up-gradient from the fuel oil day tank and up-gradient from all proposed project areas

2 m below groundwater level

1

3

1

Soil: TPH, VOCs (including BTEX) and SVOCs (including PAHs)

Groundwater: TPH, VOCs (including BTEX) and SVOCs (including PAHs)

DH4

Located within the north coal storage yard and also down-gradient from the fuel oil day tank

2 m below groundwater level

1

3

1

Soil: TPH, BTEX and PAHs

Groundwater: TPH, BTEX and PAHs

TP4

Located within the north coal storage yard and also down-gradient from the day tank

Up to 1.2 m below ground level

-

1

-

DH6

Located within the north coal storage yard

2 m below groundwater level

1

3

1

Soil: TPH, BTEX and PAHs

Groundwater: TPH, BTEX and PAHs

DH7

Located within the north coal storage yard

2 m below groundwater level

1

3

1

TP2

Located within the north coal storage yard

Up to 1.2 m below ground level

-

1

-

DH5

Located within the north coal storage yard and down gradient from the DG Stores

2 m below groundwater level

1

3

1

Soil: TPH, VOCs (including BTEX) and SVOCs (including PAHs)

Groundwater: TPH, VOCs (including BTEX) and SVOCs (including PAHs)

TP3

Located within the north coal storage yard and down gradient from the DG Stores

Up to 1.2 m below ground level

-

1

-

DH8

Located within the current Intermediate Pressure

Reduction Station to be demolished

2 m below groundwater level

1

3

1

Soil: TPH, BTEX and PAHs

Groundwater: TPH, BTEX and PAHs

TP1

Located within the north coal storage yard and down gradient from the current Intermediate Pressure Reduction Station

Up to 1.2 m below ground level

-

1

-

(To be selected on site)

 

 

1 Duplicate Soil Sample per 20 Soil Samples

1 Duplicate Groundwater Sample

As per samples

Trip Blank

 

 

 

Estimated 5 delivery trips (water samples)

Soil: TPH, VOCs (including BTEX) and SVOCs (including PAHs)

Groundwater: TPH, VOCs (including BTEX) and SVOCs (including PAHs)

Equipment Rinsate

 

 

 

Estimated 3 (with 3 rigs on-site) (water samples)

 

 

 

Total

30

17

 

 


3.3                            Sampling Method

A utility scan will be conducted prior to the commencement of any excavation/drilling.  At each of the sampling locations, a trial pit will be excavated to 1.2 m bgl.  Trial pits will be dug manually using hand tools and necessary concrete breaking hand operated mechanical tools to ensure no interference with underground utilities.  Sampling below trial pit levels, will be conducted using drilling rig.  Drilling rigs, drilling equipment that do not come in contact with samples and hand breakers will be steam cleaned prior to mobilisation to the site.  Prior to sampling, all sampling equipment and well materials will be steam cleaned, scrubbed with a non-phosphate soap solution, washed with tap water and rinsed with distilled water.  This procedure will be repeated after use at each sampling location to avoid potential cross contamination, and between samples to ensure that any contamination from the surface of the site does not affect deeper substrata or the groundwater.

 

In addition to taking samples for analysis, the strata log will be recorded.  This includes recording the general structure of the ground and the depth and thickness of each band of material.  The depths at which samples are taken will be recorded with a description of each sample such as grain size, colour, and wetness.  Extreme care will be exercised when toxic gases or hazardous materials are suspected.  Photographs will be taken during the site investigation and for each sample.

 

3.3.1                      Sample Collection

The soil or groundwater sampling will be undertaken following appropriate protocols so as to minimise the potential for cross-contamination between sampling locations and depths.  The soil sampling methodologies are based on methods developed by US Environmental Protection Agency (US EPA), as outlined below.

 

Decontamination Procedures

Sampling equipment used during the course of the site investigation programme will be decontaminated using the following procedures:

·       Manual washing and scrubbing with non-phosphate detergent;

·       Tap water and distilled water rinse; and

·       Air drying.

 

Where available, a steam cleaner or pressure washer will be used.

 

During the sampling and decontamination activities, disposable latex gloves will be worn to prevent transfer of contaminants from other sources.  Any disposable equipment such as latex gloves will be disposed of as general waste after each use.  Provisions will be made to containerise any decontamination fluids, although the volume of fluids to be produced is expected to be low.

 

Soil Sample Collection

Soil samples will be taken by ERM staff and placed into appropriate clean glass bottles or sampling containers (provided by the laboratory) immediately after collection.  Before sampling commences, the laboratory will be consulted on the particular sample size and preservation procedures that are necessary for each chemical analyses.  The sample containers will be laboratory cleaned, made of glass or other suitable materials with aluminium or teflon-lined lids, so that the container surface will not react with the sample or adsorb contaminants.  The containers will be labelled with the sampling location codes and the depths at which the samples are taken.  They will then be transferred to an icebox or cooler container.  Samples will be kept between 0 to 4°C but not frozen.

 

Groundwater, if encountered, will be sampled from the monitoring wells using disposable Teflon bailers.

 

Sampling Management

Samples will be dispatched to the analytical laboratory for analysis as soon as practicable following sampling.  All samples will be handled under chain of custody protocols and relinquished to the laboratory representative at the site or at a location specified by the laboratory.

 

3.4                            Analytical Method

The parameters as described in Section 3.2 will be analysed using the methods stated in Table 3.4a.

Table 3.4a      Analytical Methods for Contaminants in Soil and Groundwater Samples

Contaminant

Analytical Methods

TPH

·       US EPA 8260 & 8015

VOCs (incl. BTEX)/SVOCs (incl. PAHs)

·       US EPA Method 8260/8270

TCLP

·       EPA SW-846 (Method 1311)

 

 

3.5                            Quality Control and Quality Assurance (QC/QA)

Samples collected should be representative of field conditions.  At each sampling location, soil (and groundwater, if encountered) samples will be collected using pre-cleaned sampling equipment.  All sample containers will be provided by the contracted laboratory who guarantees their sterilisation and preservative contents.

 

Appropriate QC/QA samples will also be collected during the field investigation, including:

 

·       Equipment (rinsate) blanks (one per machine) for the full suite of target parameters, in order to assess the adequacy of the decontamination procedures;

·       Trip blanks (one per cooler/shipment) for the full suit of target parameters in order to assess the potential contamination of the sample handling and transportation processes; and

·       Groundwater and soil duplicates (one duplicate sample per 20 samples) for the full suite of analyses to assess the precision of the procedures.

 

Precision will be calculated as the relative percent difference (RPD) between the original sample and the blind duplicate.  For water and soil, the acceptance criteria for precision are 20% RPD and 30% RPD, respectively.  Accuracy will be assessed by analysis of blank samples to ensure that no bias is present in the analytical data.

 

 

3.6                            Analytical Laboratory

Analysis of samples will be carried out by an appropriate, HOKLAS-certified (or other equivalent scheme approved by the EPD) analytical laboratory.  The laboratory should maintain high standards of analytical and technical services for the detection of trace organic contaminants.  All analysis will be conducted according to standard procedures set by the US EPA, along with internal QC/QA procedures.

3.7                            Health and Safety

 

A health and safety risk assessment and health and safety management plan shall be developed for the site investigation works in accordance with CLP Power HK Ltd (CLP) and ERM’s internal requirements.  All personnel will attend safety training provided by CLP prior to commencing the works at the site.

 

4                                  Programme Schedule & Reporting

4.1                            Programme Schedule

It is anticipated that site investigation and laboratory analysis will be completed within three to four weeks from the date of approval of the CAP.  The CAR will be submitted to the EPD for approval after the completion of the laboratory analysis.

 

The overall assessment will comprise the following activities:

 

·       Required revision and endorsement of the CAP by EPD;

·       Mobilisation of the subcontractor and contracting analytical laboratory;

·       Field sampling programme;

·       Analytical programme/laboratory turnaround (normal turnaround time is expected two weeks);

·       Assessment and reporting of results in a CAR, including, if required, development of a remedial action plan (RAP).  The CAR will include all laboratory testing results of chemical analyses; and

·       In the event that landfill disposal is proposed for contaminated soil materials, prior agreement will need to be reached with the EPD and the application accompanied by the RAP and the TCLP test results.

 

No demolition works involving excavation will be conducted at the project area before the assessment and the necessary remediation works have been established.

 

4.2                            Assessment and Reporting

A CAR will be prepared after obtaining analytical results from the laboratory.  The report will present the findings of the CAP and site investigation assessment (including the methodology used during the soil and groundwater sampling and details of field observations such as visual observations made during the investigation).

 

There are no legislative standards requiring clean up of soil and groundwater contamination in Hong Kong.  The analytical results will be compared against recognized standards for soil and ground water contamination.  The remediation standards to be agreed with EPD should not be so high that it makes land decontamination operation unreasonably uneconomical.  A risk-based approach as a flexible and pragmatic approach, as the amount of decontamination work required would be determined on a case-by-case basis, taking into account the future land use of specific sites. 

 

CAPCO notes that Dutch “B” values are currently being adopted as the cleanup targets for most of the land decontamination cases in Hong Kong.  EPD has indicated during their discussions with CAPCO that there is no potable use of groundwater in Hong Kong, and therefore the evaluation of results for groundwater can be based on an approach more inclined towards that of a risk assessment.

 

The CAR will be prepared and submitted to the EPD.

 

If necessary, a RAP will be prepared in consultation with the EPD, with the objective of mitigating the site to an agreed upon condition.  Any proposed mitigation recommendations will be considered under several factors including nature of the contamination, degree of the contamination, the potential receiver, time allocation, treatment cost and availability of local expertise for undertaking the treatment in accordance with the ProPECC PN3/94 and other relevant guidance notes.  The RAP will also outline requirements for construction workers to follow to limit potential future exposures. 

 

The results of the sampling programme, the report, and the objectives of the RAP will be submitted to EPD.  It should be noted that no estimate of the time frame for any mitigation is presented at this time.



 

([1])  In accordance with the ProPECC PN 3/94 and the Guidance Notes.

([2])  Purpose made UPVC or HDPE slotted risers and blank pipes (50mm diameter) will be used for the groundwater wells.  The slotted risers will be installed from 2m below groundwater levels to 1-2 m above groundwater levels.  The risers will be connected with blank pipes up to approx. 0.5m above ground surface.  Voids between risers/pipes and the drill holes will be filled with clean gravel.  Wells will be purged (pumped or bailed) 5 times the volumes of the wells after installation to rid of dirt/potential cross contamination during well installation.