6                                  Waste management

6.1                            Introduction

The Project involves the demolition of existing facilities and retrofitting of emissions control facilities to four existing 677MW generating units of CPB.  This section identifies the potential wastes arising from the Project and assesses the potential environmental impacts associated with waste handling and disposal.  The main issues are:

·       disposal of dredged sediments;

·       handling and treatment of contaminated soil;

·       disposal of construction and demolition (C&D) materials ([1]) arising from the demolition, excavation and construction works; and

·       management of by-products produced from the FGD process.

Opportunities for waste minimisation, recycling, storage, collection, transport and disposal have been examined and procedures for waste reduction and management have been proposed.

6.2                            Legislative Requirements and Evaluation Criteria

The following discussion on legislative requirements and evaluation criteria applies to both the construction and operational phases of the Project.

The criteria and guidelines for evaluating potential waste management implications are laid out in Annexes 7 and 15 of the EIAO-TM under the EIAO.

The following legislation covers, or has some bearing upon, the handling, treatment and disposal of wastes in Hong Kong, and will also be considered in the assessment.

·       Waste Disposal Ordinance (Cap 354);

·       Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C);

·       Land (Miscellaneous Provisions) Ordinance (Cap 28);

·       Public Health and Municipal Services Ordinance (Cap 132) - Public Cleansing and Prevention of Nuisances Regulation; and

·       Dumping at Sea Ordinance (Cap 466).

6.2.1                      Waste Disposal Ordinance (Cap 354)

The Waste Disposal Ordinance (WDO) prohibits the unauthorised disposal of wastes, with waste defined as any substance or article, which is abandoned.  Under the WDO, wastes can only be disposed of at a licensed site.  A breach of these regulations can lead to the imposition of a fine and/or a prison sentence.  The WDO also provides for the issuing of licences for the collection and transport of wastes.  Licences are not, however, currently issued for the collection and transport of construction waste or trade waste.

The Waste Disposal (Charges for Disposal of Construction Waste) Regulation defined construction waste as any substance, matters or things that is generated from construction work and abandoned, whether or not it has been processed or stockpiled before being abandoned, but does not include any sludge, screening or matter removed in or generated from any desludging, desilting or dredging works.

The Construction Waste Disposal Charging Scheme entered into operation on 1 December 2005.  Starting from 1 December 2005, the main contractor who undertakes construction work under a contract with value of $1 million or above is required to open a billing account solely for the contract.  Application should be made within 21 days after the contract is awarded.

For construction work under a contract with value less than $1 million, such as minor construction or renovation work, any person such as the owner of the premises where the construction work takes place or his/her contractor can open a billing account; the account can also be used for contracts each with value less than $1 million.  The premises owner concerned may also engage a contractor with a valid billing account to make arrangement for disposal of construction waste.

Under the new construction waste charging scheme, charging for disposal of construction waste started on 20 January 2006 and therefore will apply to this Project.

Depending on the percentage of inert materials in the construction waste, construction waste can be disposed at public fill, sorting facilities, landfills and outlying islands transfer facilities where different disposal cost would be applied.  The scheme encourages reducing, reusing and sorting of construction waste such that the waste producer can minimise their disposal fee.  Table 6.1 presents a summary of the government construction waste disposal facilities, types of waste accepted and disposal cost. 

Table 6.1        Government Waste Disposal Facilities for Construction Waste

Government Waste Disposal Facilities

Type of Construction Waste Accepted

Charge Per Tonne

Public fill reception facilities

Consisting entirely of inert construction waste

$27

Sorting facilities

Containing more than 50% by weight of inert construction waste

$100

Landfills

Containing not more than 50% by weight of inert construction waste

$125

Outlying Islands Transfer Facilities

Containing any percentage of inert construction waste

$125

6.2.2                      Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C)

Chemical waste as defined under the Waste Disposal (Chemical Waste) (General) Regulation includes any substance being scrap material, or unwanted substances specified under Schedule 1 of the Regulation, if such a substance or chemical occurs in such a form, quantity or concentration so as to cause pollution or constitute a danger to health or risk of pollution to the environment.

A person should not produce, or cause to be produced, chemical wastes unless he is registered with the EPD.  Producers of chemical wastes must treat their wastes, utilising on-site plant licensed by the EPD or have a licensed collector take the wastes to a licensed facility.  For each consignment of wastes, the waste producer, collector and disposer of the wastes must sign all relevant parts of a computerised trip ticket.  The system is designed to allow the transfer of wastes to be traced from cradle-to-grave.

The Regulation prescribes the storage facilities to be provided on site including labelling and warning signs.  To minimise the risks of pollution and danger to human health or life, the waste producer is required to prepare and make available written procedures to be observed in the case of emergencies due to spillage, leakage or accidents arising from the storage of chemical wastes as well as provide employees with training in such procedures.

6.2.3                      Land (Miscellaneous Provisions) Ordinance (Cap 28)

The inert portion of C&D materials (also called public fill) may be taken to public filling facilities.  Public filling areas usually form part of land reclamation schemes and are operated by the Civil Engineering and Development Department (CEDD) and others.  The Land (Miscellaneous Provisions) Ordinance requires that individuals or companies who deliver public fill to the public filling facilities obtain Dumping Licences from the CEDD.

Under the licence conditions, public filling areas will accept only inert building debris, soil, rock and broken concrete.  There is no size limit on rock and broken concrete, and a small amount of timber mixed with inert material is permissible.  The material should, however, be free from marine mud, household refuse, plastic, metal, industrial and chemical wastes, animal and vegetable matter and any other materials considered unsuitable by the public filling supervisor.

6.2.4                      Public Health and Municipal Services Ordinance (Cap 132) - Public Cleansing and Prevention of Nuisances Regulation

This Regulation provides a further control on the illegal dumping of wastes on unauthorised (unlicensed) sites.  The illegal dumping of wastes can lead to a fine and imprisonment.

6.2.5                      Dumping at Sea Ordinance (Cap 466)

This Ordinance came into operation in April 1995 and empowers the Director of Environmental Protection to control the disposal and incineration of substances and articles at sea for the protection of the marine environment.  Under the Ordinance, a permit from the Director of Environmental Protection is required for the disposal of regulated substances within and outside the waters of the Hong Kong SAR.  The permit contains terms and conditions that includes the following specifications:

·       Type and quantity of substances to be dumped;

·       Location of the disposal grounds;

·       Requirements of equipment for monitoring the disposal operations; and

·       The need for environmental monitoring.

Management of Dredged/Excavated Sediments for Marine Disposal

Marine disposal of any dredged/excavated sediment is subject to control under the Dumping at Sea Ordinance 1995.  The Ordinance has replaced the Dumping at Sea Act 1974 (Overseas Territories) Order 1975 (App. III p. DK1) in its application in Hong Kong SAR.  In addition, dredged/excavated sediment destined for marine disposal is classified based on its contaminant levels with reference to the Chemical Exceedance Levels (CEL), as stipulated in ETWBTC No. 34/2002: Management of Dredged/Excavated Sediment.  This Technical Circular includes a set of sediment quality criteria, as presented in Table 6.2, which includes heavy metals and metalloids, organic pollutants and a class of contamination level for highly contaminated sediment not suitable for marine disposal.

Table 6.2        Dredged/Excavated Sediment Quality Criteria for the Classification under the ETWBTC No 34/2002

Contaminants

Lower Chemical Exceedance Level (LCEL)

Upper Chemical Exceedance Level (UCEL)

Metals (mg kg-1 dry weight)

Cd

1.5

4

Cr

80

160

Cu

65

110

Hg

0.5

1

Ni (a)

40

40

Pb

75

110

Silver (Ag)

1

2

Zinc (Zn)

200

270

Metalloid (mg kg-1 dry weight)

Arsenic (As)

12

42

Organic-PAHs (mg kg-1 dry weight)

Low Molecular Weight (LMW) PAHs

550

3,160

High Molecular Weight (HMW) PAHs

1,700

9,600

Organic-non-PAHs (mg kg-1 dry weight)

Total PCBs

23

180

Organometallics (mgTBT l-1 in interstitial water)

Tributyl-tin (a)

0.15

0.15

Note:

(a)                 The contaminant level is considered to have exceeded the UCEL if it is greater than the value shown.

In accordance with ETWBTC 34/2002, the sediment is classified into three categories based on its contamination levels:

Category L :   Sediment with all contaminant levels not exceeding the LCEL.  The material must be dredged, transported and disposed of in a manner which minimises the loss of contaminants either into solution or by re-suspension.

Category M : Any one or more contaminants in the sediment exceed the - the LCEL and none exceeding the UCEL.  The material must be dredged and transported with care, and must be effectively isolated from the environment upon final disposal unless appropriate biological tests demonstrate that the material will not adversely affect the marine environment.

Category H :   Any one or more contaminants in the sediment exceed the exceeding the UCEL.  The material must be dredged and transported with great care, and must be effectively isolated from the environment upon final disposal.

Figure 6.1 summarises the sediment classification and disposal arrangements.  EPD will base on the sediment and biological test results to determine the most appropriate disposal site (eg open sea or confined marine disposal site).

 

Figure 6.1       Management Frameworks for Dredged/Excavated Sediment

Notes:

(a)   Most open sea disposal sites are multi-user facilities and as a consequence their management involves a flexibility to accommodate varying and unpredictable circumstances. Contract documents should include provisions to allow the same degree of flexibility should it be necessary to divert from one disposal site to another during the construction period of a contract.

(b)  Dedicated Sites will be monitored to confirm that there is no adverse impact.

(c)   For sediment requiring Type 2 or Type 3 disposal, contract documents should state the allocation conditions of Marine Fill Committee (MFC) and DEP. At present, East Sha Chau Mud Pits are designated for confined marine disposal.

(d)  If any sediment suitable for Type 3 disposal (Category H sediment failing the biological dilution test) is identified, it is the responsibility of the project proponent, in consultation with DEP, to identify and agree with him/her, the most appropriate treatment and/or disposal arrangement. Such a proposal is likely to be very site and project specific and therefore cannot be prescribed. This will not preclude treatment of this sediment to render it suitable for confined marine disposal.

(e)   The allocation of disposal space may carry a requirement for the project proponent to arrange for chemical analysis of the sediment sampled from 5% of the vessels en-route to the disposal site. For Category M and certain Category H sediment, the chemical tests will be augmented by biological tests. Vessel sampling will normally entail mixing five samples to form a composite sample from the vessel and undertaking laboratory tests on this composite sample. All marine disposal sites will be monitored under the general direction of the CEDD. However, exceptionally large allocations might require some additional disposal site monitoring. These will be stipulated at the time of allocation.

(f)    Trailer suction hopper dredgers disposing of sediment at the East Sha Chau Mud Pits must use a down-a-pipe disposal method, the design of which must be approved in advance by Director of the CEDD. The dredging contractor must provide equipment for such disposal.

Source: Appendix C, ETWBTC 34/2002

6.2.6                      Other Relevant Guidelines

Other ‘guideline’ documents, which detail how the works contractor should comply with the WDO and its associated regulations, are as follows:

·       Waste Disposal Plan for Hong Kong (December 1989), Planning, Environment and Lands Branch Government Secretariat, Hong Kong Government;

·       Chapter 9 Environment (1999), Hong Kong Planning Standards and Guidelines, Hong Kong Government;

·       New Disposal Arrangements for Construction Waste (1992), EPD & CEDD, Hong Kong Government;

·       Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), EPD, Hong Kong Government.

·       Works Branch Technical Circular (WBTC) No. 32/92, The Use of Tropical Hard Wood on Construction Site; Works Branch, Hong Kong Government;

·       WBTC No. 2/93, Public Dumps. Works Branch, Hong Kong Government;

·       WBTC No. 2/93B, Public Filling Facilities, Works Branch, Hong Kong Government;

·       WBTC No. 16/96, Wet Soil in Public Dumps; Works Branch, Hong Kong Government;

·       WBTC Nos. 4/98 and 4/98A, Use of Public Fill in Reclamation and Earth Filling Projects; Works Bureau, Hong Kong SAR Government.

·       Waste Reduction Framework Plan, 1998 to 2007, Planning, Environment and Lands Bureau, Government Secretariat, 5 November 1998;

·       WBTC Nos. 25/99, 25/99A and 25/99C, Incorporation of Information on Construction and Demolition Material Management in Public Works Sub-committee Papers; Works Bureau, Hong Kong SAR Government;

·       WBTC No. 12/2000, Fill Management; Works Bureau, Hong Kong SAR Government;

·       WBTC No. 19/2001, Metallic Site Hoardings and Signboards; Works Bureau, Hong Kong SAR Government;

·       WBTC Nos. 6/2002 and 6/2002A, Enhanced Specification for Site Cleanliness and Tidiness. Works Bureau, Hong Kong SAR Government;

·       WBTC No. 11/2002, Control of Site Crusher. Works Bureau, Hong Kong SAR Government;

·       WBTC No. 12/2002, Specification Facilitating the Use of Recycled Aggregates. Works Bureau, Hong Kong SAR Government;

·       ETWBTC No. 33/2002, Management of Construction and Demolition Material Including Rock; Environment, Transport and Works Bureau, Hong Kong SAR Government;

·       ETWBTC No. 34/2002, Management of Dredged/Excavated Sediment; Environment, Transport and Works Bureau, Hong Kong SAR Government;

·       ETWBTC No. 31/2004, Trip Ticket System for Disposal of Construction & Demolition Materials, Environment, Transport and Works Bureau, Hong Kong SAR Government; and

·       ETWBTC No. 19/2005, Environmental Management on Construction Sites; Environment, Transport and Works Bureau, Hong Kong SAR Government.

6.3                            Expected Waste Sources

6.3.1                      Construction Phase

During the construction phase, the main activities, which will result in generation of waste, include demolition, site formation, dredging, filling and concreting.

The typical waste types associated with these activities include:

 

·       Dredged marine sediment;

·       Contaminated soil;

·       C&D materials;

·       Chemical waste;

·       Sewage; and

·       General refuse.

Proper waste management is important to prevent and mitigate potential environmental impacts.

6.3.2                      Operational Phase

The following wastes are expected to be generated during the operational phase:

 

·       Gypsum generated from FGD processes;

·       Sludge from FGD wastewater treatment;

·       Industrial waste; and

·       General refuse.

6.4                            Assessment Methodology

The potential environmental impacts associated with the handling and disposal of waste arising from the construction and operation of the Project are assessed in accordance with the criteria presented in Annexes 7 and 15 of the EIAO-TM, which are summarised as follows:

·       estimation of the types and quantities of the wastes to be generated;

·       assessment of the secondary environmental impacts due to the management of waste with respect to potential hazards, air and odour emissions, noise, wastewater discharges and traffic; and

·       assessment of the potential impacts on the capacity of waste collection, transfer and disposal facilities.

6.5                            Waste Management Assessment

6.5.1                      Construction Phase

Dredged Marine Sediment

The existing Heavy Load Berth along the north-western waterfront of the Castle Peak Power Station will be extended to form a multi-purpose wharf and to provide the additional berthing facility required for future loading and unloading of the reagent and by-products of the new emission control system.  Dredging will be required for the development of the additional berthing facility.  The dredging works are expected to be carried out within about six weeks in early to mid 2007.  The exact extent and boundary of the dredging works is still being streamlined but the total area required to be dredged is currently estimated to be approximately 30,000 m2.  Due to the small dredging area, one dredger is expected to be employed for the dredging works.  The existing seabed level is about -6 mPD and the dredged level is expected to be up to a depth of –8.2 mPD with the estimated total dredged volume to be about 80,700 m3.  The proposed dredged area is shown in Figure 2.3.

Based on the existing sediment quality data published by EPD for the monitoring stations at Pillar Point and Urmston Road (NS3 and NS4), the sediment quality in the area is considered to be not contaminated.  To confirm no contamination of the marine sediment, vibrocore samples of sediment were taken at three locations evenly distributed within the area to be dredged based on the total area expected to be dredged.  The sampling locations are presented in Figure 2.3.  Detailed sampling plan and sampling method are presented in Sediment Quality Plan (SQP) which has been submitted to EPD (Annex D).

The results of the chemical analyses of the marine sediment are presented in Table 6.3.

As shown in Table 6.3, all the results are below their respectively LCEL/reporting limit at all sampling locations and all sampling depths.  The findings indicate that the marine sediment within the dredged area is likely to be uncontaminated but further sampling and testing in accordance with the detailed requirements of ETWBTC No. 34/2002 will be required for the actual allocation of sediment disposal site and the application for a dumping permit under the Dumping at Sea Ordinance (Cap 466) prior to the commencement of the dredging activities.  In the event that these further tests show the sediment to be uncontaminated, it would be suitable for disposal at open sea.  Should the sediment be found to be contaminated, confined marine disposal would be appropriate.  Based on a maximum daily dredging rate of about 5,200m3, about 8 barge trips per day will be required, assuming a carrying capacity of about 700 m3 per barge, for the disposal of the dredged sediment.


Table 6.3    Marine Sediment Testing Results

 

Sample Reference

Heavy Metals (mg kg-1)

Total PCBs (mg/kg)

PAHs (Low MW) (mg/kg)

PAHs (High MW) (mg/kg)

TBT in Interstitial Water (mg/L)

Drill-hole No.

Depth below Existing Seabed (m)

Cadmium
(Cd)

Chromium
(Cr)

Copper (Cu)

Nickel
(Ni)

Lead
(Pb)

Zinc
(Zn)

Mercury
(Hg)

Arsenic
(Ar)

Silver
(Ag)

From-To

 

 

 

 

 

 

 

 

 

Reporting Limits

0.1

1

1

1

1

10

0.05

1

0.1

2

55

170

0.015

LCEL

1.5

80

65

40

75

200

0.5

12

1

23

550

1700

0.15

UCEL

4

160

110

40

110

270

1

42

2

180

3160

9600

0.15

V1

0.00-0.90

0.2

35

18

21

54

83

0.13

12

0.1

<2

330

1700

<0.015

V1

0.90-1.70

0.1

28

15

18

36

72

0.10

12

<0.1

<2

330

1700

<0.015

V2

0.20-0.90

0.2

35

63

22

55

110

<0.05

12

0.4

<2

330

1700

<0.015

V2

0.90-2.20

0.1

35

46

20

45

97

0.17

12

0.2

<2

330

1700

<0.015

V3

0.05-1.10

0.2

30

37

19

46

110

0.14

10

0.4

<2

330

1700

<0.015

 


Table 6.3    Marine Sediment Testing Results (Continue)

 

Sample Reference

Chlorinated Pesticides (mg/kg)

Overall Sediment Classification (a)

Final Disposal (b)

 

Drill-hole

Depth below Existing Seabed (m)

Alpha-BHC

Beta BHC

Gamma BHC

Delta-BHC

Heptachlor

Aldrin

Heptachlor epoxide

Endosulfan 1

p, p'-DDT

p, p'-DDD

p, p'-DDE

Endosulfan sulfate

 

No.

From-To

 

 

 

 

 

 

 

 

 

 

 

 

 

Reporting Limits

0.01

0.01

0.01

0.01

0.01

0.01

0.01

0.01

0.01

0.01

0.01

0.01

 

 

 

V1

0.00-0.90

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

L

Type 1

 

V1

0.90-1.70

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

L

Type 1

 

V2

0.20-0.90

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

L

Type 1

 

V2

0.90-2.20

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

L

Type 1

 

V3

0.05-1.10

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

L

Type 1

 

Notes:

(a)     “L’ = little or no contamination (refer to Section 6.2.5).

(b)     Type 1 Disposal = Disposal at open sea (refer to Figure 6.1).


Contaminated Soil

To accommodate the new development, demolition works are required to demolish or relocate a number of existing facilities including:

·       CPB Fuel Oil Day Tank (FODT);

·       Dangerous Goods (DG) Store to the south of the FOPH;

·       Oil interceptor for FODT and APS Transformer Compound (West & East Ends);

·       Pipe works in trenches connecting between FODT to FOTPH;

·       Pipe works connecting with FOPH and oil interceptor;

·       Intermediate pressure reduction station (IPRS), LPG compound and CO2 storage tanks.

Potential leakage and/or spillage (if any) of oil from the operation of these facilities may cause land contamination to the underlying soil.

A Contamination Assessment Plan (CAP) has been prepared, submitted to and was approved by EPD in April 2006 (see Annex E).  It reviewed the historical land uses and existing conditions of the site and recommended a site investigation programme to determine if the site is contaminated and if so, the types and degree of contamination.  Site investigation was conducted at four trial pits and eight drillholes.  Based on the finding of the site investigation, total petroleum hydrocarbon (TPH) was found at 0.9 m below ground level at TP3.  However, since no contamination were found at the adjacent trail pits/boreholes, it is anticipated that the TPH contamination is localized at TP3.  The estimated amount of potentially contaminated soil within the Project boundary is 50 m3 (with a bulking factor of 1.2 applied to the in-situ volume).  Details of the finding of the site investigation were reported in the Annex E1 – Contamination Assessment Report (CAR).

The excavated contaminated soil will be treated onsite using bioremediation method.  The remediation actions involve excavation, testing, on-site treatment (i.e., biodegradation) and verification sampling and analysis.  The treated soils will be reused within the Project as far as possible or disposed of at the public fill bank at Tuen Mun Area 38.

The Remediation Action Plan (RAP) in Annex E details the measures required.

C&D Materials

Demolition Materials

Facilities to be demolished to provide space for installing FGD plants in this Project have been discussed above. 

The demolition and relocation works will take about 6.5 months and are scheduled to commence in the first half of 2007.

A total of about 835 tonnes of scrap metals will be produced from the demolition of FODT, LPG and CO2 tanks, pumps and the associated fixtures/ appendages such as pipeline, spiral stair and catwalk attached to the oil tanks.  The steel sheet of the circular roof and sidewall will be cut into small panels in regular size for easy transportation.  All the scrap steel will be transported off-site by barge/trucks for recycling.

A total of about 1,830 m3 uncontaminated reinforced concrete (after applying a bulking factor of 1.4) will be generated from demolition of the retaining walls of FODT, DG stores, LPG switch room and vaporiser room and LPG tank foundation.  These materials are not contaminated and will be separated from other wastes to avoid contamination.  The reinforced concrete (public fill) can be reused on-site or sent to public filling area at Tuen Mun Area 38 and/or other reclamation site for reuse.

Excavated Materials

Excavation works would be required for the construction of the foundations to support the new facilities.  A total of approximately 30,000 m3 (with a bulking factor of 1.2 applied) of non-contaminated excavated materials (assumed to be mainly soft materials) will be generated from the excavation for the foundations of new facilities.  The excavated soil will be temporarily stockpile onsite at the existing coal yard located to the north of the Stacker Reclaimer and is expected to be reused for the filling activities in this Project.

The portion of the existing coal yard to be used for the new FGD facilities (located south of existing ash sump and ACP Plant House) will need to be raised from the existing level of +5 to +6mPD to an approximate level of +7mPD.  Public fill material will still need to be imported even after reusing the excavated materials generated from the Project and therefore no surplus excavated materials is expected from the Project.

C&D Materials Arising from New Building Construction

C&D materials consisting of packing materials, plastics, metal, concrete, wood etc will be generated from the new building construction.  The main structures to be constructed at the site would be the CO2 tank, LPG tank, IPRS, FGD and SCR equipment, limestone and gypsum storage facilities and urea storage area.  The majority of these new facilities are steel structures and also pre-fabricated, and therefore the quantity of C&D materials generated is expected to be small.  These materials should be sorted on-site in order to minimise the amount of construction waste to be disposed of at landfills and the cost for disposal of the C&D materials arising from the Project.  Recyclables could be reused on site or sold to recyclers/recycling facilities.  Construction waste will be disposed of at the refuse transfer station at North West New Territories or directly to the WENT landfill by trucks.

Chemical Wastes

Chemical waste, as defined under the Waste Disposal (Chemical Waste) (General) Regulation, includes any substance being scrap material, or unwanted substances specified under Schedule 1 of the Regulation.  A complete list of such substances is provided under the Regulation; however, substances likely to be generated from the construction of the SCR and FGD plants and the associated building will, for the most part, arise from the maintenance of construction plant and equipment.  These may include, but need not be limited to the following:

·       Scrap batteries or spent acid/alkali from their maintenance;

·       Used paint, engine oils, hydraulic fluids and waste fuel;

·       Contaminated oily water from the flushing and cleaning of the light oil tanks and the oil/water separation sump prior to their demolition;

·       Spent mineral oils/cleaning fluids from mechanical machinery; and

·       Spent solvents/solutions, some of which may be halogenated, from equipment cleaning activities.

Chemical wastes may pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner as outlined in the Waste Disposal (Chemical Waste) (General) Regulation and the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.  These hazards may include:

·       Toxic effects to workers;

·       Adverse effects on air, water and land from spills; and

·       Fire hazards.

Oily water and oily sludge will be generated from the cleaning of the FODT and oil transfer pipelines to be demolished.  The amount of chemical waste that will arise from other construction activities will be highly dependent on the Contractor’s on-site maintenance activities and the quantity of plant and equipment utilised.  With respect to the nature of construction works, the number of construction plant and equipment to be used on site, it is estimated that about a few hundred litres of used lubricant oil will be generated during the construction period.  It is anticipated that the quantities of waste solvent and waste paint will be minimal.

With the incorporation of suitable arrangements for the storage, handling, transportation and disposal of chemical wastes under the requirements stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Waste, no adverse environmental and health impacts will result from the handling, transportation and disposal of chemical waste arising from the Project.

Sewage

Sewage will arise from the construction workforce and site office’s sanitary facilities.  These wastes should be managed properly to avoid any adverse water quality impact, odour and potential health risks to the workforce by attracting pests and other disease vectors.

It is estimated that about 900 construction workers will be working on site at the peak of the construction programme.  With a sewage generation rate of 0.15 m3 per worker per day, about 135 m3 of sewage will be generated per day.  It is expected that portable toilets will be provided for site workers and the existing sanitary facilities at the CPPS will not be used by any of the site workers.  A licensed contractor should be employed to remove the sewage and dispose of it to sewage treatment works operated by Drainage Services Department.  With the implementation of these waste management practices on-site, adverse environmental impacts are not expected.

General Refuse

The presence of a construction site with workers and associated site office will result in the generation of a variety of general refuse requiring disposal.  General refuse will mainly consist of food waste, aluminium cans and waste paper.

The storage of general refuse has the potential to give rise to adverse environmental impacts.  These include odour if the waste is not collected frequently (for example, daily), windblown litter, water quality impacts if waste enters water bodies, and visual impact.  The site may also attract pests, vermin, and other disease vectors if the waste storage areas are not well maintained and cleaned regularly.  In addition, disposal of wastes at sites other than approved landfills, can also lead to similar adverse impacts at those sites.

During the peak of construction programme, about 900 construction workers will be worked on site at any one time and the amount of general refuse to be generated is expected be about 585 kg per day based on a general refuse generation rate of 0.65 kg per worker per day.

Recyclable materials (i.e. paper, plastic bottle and aluminium can) should be separated and disposed of at the recycling bins in order to minimise the amount of general refuse to be disposed of at landfills.  General refuse generated from the construction workforce will be collected together with other general refuse generated from the existing CPB by contractor and subsequently sent to the refuse transfer station in North West New Territories or directly to WENT landfill for disposal.  With respect to the small quantity of general refuse to be generated, it is anticipated that no additional traffic will be generated due to its disposal.

Provided that the mitigation measures recommended in Section 6.6 are adopted, the environmental impacts caused by the storage, handling, transport and disposal of general refuse are expected to be minimal.

Summary

Table 6.4 summarised the waste arising during construction of the Project.

Table 6.4        Waste Arising During Construction Phase

Type

Estimated Quantity

Disposal / Treatment Site

Dredged Sediment

·     80,700 m3 (likely to be uncontaminated)

·          Disposal to open sea (if confirmed by further tests in accordance with ETWBTC No. 34/2002 to be uncontaminated); or

·          confined marine disposal (if confirmed by further tests to be contaminated)

Contaminated Soil

·     50 m3 (bulk)

On-site treatment (bioremediation) and the treated soil will be reused as fill materials with the Project or disposal of at public fill bank in Tuen Mun Area 38

Scrap Steel

·     835 tonnes

Off-site recycling

Public Fill

·     1,830 m3 (uncontaminated concrete)

·     30,000 m3 (bulk) (excavated soil)

Reuse on-site for site formation and backfilling

Construction Waste

·     minor

Refuse transfer station in North West New Territories or WENT Landfill

Chemical Waste

·     fuel oil day tank and oil separator sump demolition.

·     Less than one hundred litres per month from all construction activities.

Chemical Waste Treatment Centre and/or other licensed lube oil recycling facility

Sewage

·     135 m3/day (on average)

Provision of portable toilets and regular collection by contractor for off-site treatment

General Refuse

·     585 kg/day (on average)

Transported together with other general refuse generated from the existing CPPS to refuse transfer station in North West New Territories or WENT Landfill

6.5.2                      Operational Phase

Gypsum Generated from FGD Processes

The limestone FGD processes will generate two principal types of by-product or waste.  They are the gypsum and the sludge from treatment of the FGD wastewater.

Gypsum is a non-hazardous and non-toxic substance.  It is produced in the form of fine, white, crystalline powder consisting predominantly of calcium sulphate.  The quantity of gypsum generated will depend on a number of factors including the sulphur content of the fuel used and the operational profile of CPB.

Gypsum is a useful construction material in building industry and the demand for gypsum is high in both Hong Kong and Mainland China.

About 240,000 tonnes of commercial grade gypsum will be produced per year in addition to a small amount of lower grade gypsum at about 17,000 tonnes per year (i.e., 6.6% of the total gypsum generated).

Commercial Grade Gypsum : The commercial grade gypsum produced could be used for a number of purposes such as the production of plasterboard, cement, etc.  CAPCO can liaise with the overseas limestone supplier to take back the gypsum generated from the limestone FGD system at CPB.  Currently, the Hongkong Electric Company has entered into a buyback agreement with the overseas limestone supplier to take back the gypsum generated from the FGD process at the Lamma Power Station.  It is likely that the buyback agreement could also be feasible for the limestone FGD system at CPB.

Another feasible way to reuse the gypsum is to sell to cement manufacturers in PRD and East-Asia region.  The demand for gypsum from the cement and plasterboard sectors in Guangdong Province is likely to exceed the supply.  Many multi-national cement manufacturers have acquired sizable cement production plants in the East-Asia region and their potential demand for gypsum is therefore well in excess of the level of supply by CAPCO.  It is therefore likely that multi-national cement manufacturers could take all the FGD gypsum to be produced at CPB under a long-term arrangement to supply various cement plant around the region.

Barges will be employed to transport the commercial grade gypsum offsite.  One to two barge trips per week are anticipated for gypsum transport.

Lower Grade Gypsum: A small amount of lower grade gypsum (about 17,000 tonnes per year or 6.6% of the total gypsum generated) will also be generated as a result of the FGD process.  Despite its lower grade, the gypsum can still be reused for cement production.  Similar to the case of commercial grade gypsum, CAPCO can liaise with the limestone supplier to take back also the lower grade gypsum.  As a fallback option in the rare event of the lack of demand for lower grade gypsum, it can be disposed of at a designated area of the Tsang Tsui Ash Lagoons.  The dewatered gypsum will be transported by trucks.  Assuming 365 working days per year, 47 tonnes of lower grade gypsum (or about 20 m3 of lower grade gypsum based on a density of 2.3 tonne per cubic metre) will be generated per day.  Based on a carrying capacity of 7 m3 for each truckload, about three additional truck trips will be generated per day from the Project on the Lung Kwu Tan Road and Nim Wan Road for the transportation of lower grade gypsum.

Sludge from FGD Wastewater Treatment

The dewatered gypsum cake will need to be washed with fresh water to remove the soluble chlorides to meet the specification for commercial grade gypsum.  The wash water, containing excessive chlorides, will be treated in a chloride purge treatment system to remove the suspended solids and trace elements, to reduce the residual COD and to adjust the pH before it is discharging with the cooling water of the CPB to Urmston Road.

About 60 tonnes of sludge dry solids per day (or about 180 tonnes per day at 30% dry solids) will be generated from the chloride purge treatment system.  The typical quality of the sludge is presented in Table 6.5.

Table 6.5        Typical Chemical Composition of Chloride Purge Treatment Sludge

Component

Content

Calcium sulphate

40%

Calcium sulphite

1%

Calcium carbonate

4%

Inerts

20%

Flyash

5%

Others (surplus sludge from biological treatment system)

30%

Design optimisation of the FGD wastewater treatment system has commenced.  One of the key design optimisation objective is to minimise the influent throughput to the wastewater treatment system which would result in a lower quantity of sludge arising.  This would help to reduce the amount of sludge requiring disposal.  In addition, the feasibility of other disposal options such as off-take by the limestone supplier and gypsum off-taker to minimise the quantity of sludge to be disposed of at landfills would be further explored in the detailed design stage.

Industrial Waste

Most of the industrial waste generated from the maintenance of the limestone FGD system will be scrap metal, which can be recycled.  It is therefore anticipated that no adverse environmental impacts will result from the handling and disposal of the industrial waste to be generated from the operation of the FGD system.

General Refuse

CAPCO will deploy the existing CPB staff to manage the new emission control system and it is not anticipated to have significant increase of number of staff.  Hence, no additional general refuse will be generated from the workforce.

Summary

Table 6.6 summarises the waste arising during the operation of the Project.

Table 6.6        Waste Arising During Operational Phase

Type

Estimated Quantity

Disposal / Treatment Site

Gypsum

·     Commercial grade gypsum : 240,000 tonnes per year

·     Lower grade gypsum : 17,000 tonnes per year

·     Commercial grade gypsum : To be collected by the limestone supplier or sold to plasterboard and/or cement manufacturers

·     Lower grade gypsum : To be collected by the limestone supplier or sold to cement manufacturers.  As a fall-back option, disposal at a designated area of Tsang Tsui Ash Lagoons may be considered

Sludge

·     60 tonnes dry solid per day or about 180 tonnes per day at 30% dry solids

·     Minimising the influent throughput to the wastewater treatment system which would result in a lower quantity of sludge arising;

·     Feasibility of other disposal options to be further explored in detailed design stage

Industrial waste

·     Few kg of scrap metal per month

·     To be collected by recyclers/recycling facilities

6.6                            Mitigation Measures

There are no major waste management issues associated with the operation of the new emission control system.  This section recommends the mitigation measures to avoid or minimize potential adverse environmental impacts associated with handling, collection and disposal of waste arising from the construction of the new emission control system. 

It is the Contractor’s responsibility to ensure that only licensed chemical waste collectors are used for collection and transportation of chemical waste to the licensed disposal facility and that appropriate measures are taken to minimize adverse environmental impacts, including windblown litter and dust from the transportation of wastes.  In addition, the Contractor must ensure that all the necessary waste permits are obtained for the construction and operational phases.

6.6.1                      Dredged Sediments

According to the requirements stipulated in ETWBTC No. 34/2002, the dredged sediment should be disposed of only at designated disposal sites allocated by the Marine Fill Committee (MFC) based on the findings of further sediment quality tests.  A dumping licence should also be obtained from EPD prior to the commencement of the dredging works. 

Regardless of the sediment disposal method and site, the Contractor should:

·       Dredge the sediments using closed grabs;

·       Use split barges of not less than 750 m3 capacity when transporting the sediment to the disposal site;

·       Regularly maintain the barge hoppers to ensure that they are capable of rapid opening and discharge at the designated disposal site; and

·       Monitor the barge load against loss of materials during transportation.

6.6.2                      Contaminated Soil

For excavated contaminated soil, mitigation measures recommended in the RAP, Annex E should be implemented.

6.6.3                      Excavated Materials

Wherever practicable, excavated materials should be segregated from other wastes to avoid contamination thereby ensuring that it can be re-used onsite avoiding the need for disposal at landfills.

Management of Waste Disposal

Construction Waste Disposal Charging Scheme was launched on 1 December 2005 and the charging for disposal of construction waste was commenced on 20 January 2006.

The Contractor should open a billing account with EPD in accordance with the Waste Disposal (Charges for Disposal of Construction Waste) Regulation for the payment of disposal charges.  Every waste load transferred to Government waste disposal facilities such as public fill, sorting facilities, landfills or transfer station would required a valid “chit” which contains the information of the account holder to facilitate waste transaction recording and billing to the waste producer.  A trip-ticket system will be established in accordance with the ETWBTC No. 31/2004 to monitor the reuse of surplus excavated materials offsite and disposal of C&D waste and general refuse at transfer station/landfills, and to control fly-tipping.  The billing “chit” and trip-ticket system will be included as one of the contractual requirements and implemented by the contractor.   CAPCO will also conduct regular audits of the waste management measures implemented on site as described in the Waste Management Plan.

A recording system (similar to summary table as shown in Annex 5 and Annex 6 of Appendix G of ETWBTC No. 19/2005) for the amount of waste generated, recycled and disposed of (including the disposal sites) should be established during the construction stage.

Measures for the Reduction of C&DM Generation during Planning and Design Stages

The various waste management options can be categorized in terms of preference from an environmental viewpoint.  The options considered to be more preferable have the least impacts and are more sustainable in the long term.  Hence, the waste management hierarchy is as follows:

·       Avoidance and minimization, that is, reduction of waste generation through changing or improving practices and design;

·       Reuse of materials, thus avoiding disposal (generally with only limited reprocessing);

·       Recovery and recycling, thus avoiding disposal (although reprocessing may be required); and

·       Treatment and disposal, according to relevant law, regulations, guidelines and good practice.

This hierarchy should be used to evaluate the waste management options, thus allowing maximum waste reduction and reduced disposal costs.  Records of quantities of wastes generated, recycled and disposed (locations) shall be kept.

Measures for the Reduction of C&DM Generation during Construction

All C&D materials will be reused within the Project.  Public fill and construction waste should be segregated and stored in different containers or skips to facilitate reuse or recycling of materials and their proper disposal of construction waste.  Specific areas of the work site should be designated for such segregation and temporary storage if immediate use is not practicable.

The construction waste should be collected by Contractor and transported to landfills for disposal.    

The use of wooden hoardings should not be allowed.  An alternative material, which can be reused or recycled, for example, metal (aluminium, alloy, etc) should be used.

To reduce the potential dust impact, C&D materials should be wetted as quickly as possible during excavation works.

6.6.4                      Chemical Waste

The Contractor should register as a chemical waste producer with the EPD.  Chemical waste, as defined by Schedule 1 of the Waste Disposal (Chemical Waste) (General) Regulation, should be handled in accordance with the Code of Practice on the Packaging, Handling and Storage of Chemical Wastes as follows:

Containers used for storage of chemical wastes should:

·       be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed;

·       have a capacity of less than 450 L unless the specifications have been approved by the EPD; and

·       display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations.

The storage area for chemical wastes should:

·       be clearly labelled and used solely for the storage of chemical waste;

·       be enclosed on at least 3 sides;

·       have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest;

·       have adequate ventilation;

·       be covered to prevent rainfall entering (water collected within the bund must be tested and disposed of as chemical waste, if necessary); and

·       be arranged so that incompatible materials are appropriately separated.

Disposal of chemical waste should be:

·       via a licensed waste collector; and

·       to a facility licensed to receive chemical waste, such as the Chemical Waste Treatment Centre which also offers a chemical waste collection service and can supply the necessary storage containers.

6.6.5                      Sewage

The sewage sludge from the portable toilet should be collected by a reputable collector on a regular basic. 

6.6.6                      General Refuse

General refuse should be stored in enclosed bins or compaction units separately from construction and chemical wastes.  General refuse should be removed from the site, separately from construction and chemical wastes, on a daily basis to minimise odour, pest and litter impacts.  Burning of refuse on construction site is prohibited by law.

Aluminium cans are often recovered from the waste stream by individual collectors if they are segregated and made easily accessible.  As such, separate, labelled bins for their deposit should be provided if feasible.  Materials recovered will be re-used on site or sold for recycling.

6.6.7                      Staff Training

Training will be provided to workers on the concepts of site cleanliness and on appropriate waste management procedures, including waste reduction, reuse and recycling at the beginning of the Contract.

6.7                            Residual Environmental Impacts

With the implementation of the recommended mitigation measures, no residual impacts are anticipated from the construction and operation of the Project.

6.8                            Environmental Monitoring and Audit

6.8.1                      Construction Phase

Joint site audits by the CAPCO and the contractor should be undertaken on a weekly basis.  Particular attention should be given to the contractor’s provision of sufficient spaces, adequacy of resources and facilities for on-site sorting and temporary storage of C&D materials.  The C&D materials to be disposed of from the site should be visually inspected.  The C&D waste to be disposed of at refuse transfer stations or landfills should contain no as practicable observable inert or reusable/recyclable C&D materials (e.g. soil, broken rock, metal, and paper/cardboard packaging, etc).  Any irregularities observed during the weekly site audits should be raised promptly to the contractor for rectification.

6.8.2                      Operational Phase

No adverse environmental impact will arise with the implementation of good waste management practices and therefore, no environmental monitoring and audit programme is required.

6.9                            Conclusion

6.9.1                      Construction Phase

The key potential impacts during the construction phase are related to management of dredged sediments, demolition materials, excavated materials and construction waste.

About 80,700 m3 of marine sediment will be dredged in connection with the provision of the additional berthing facility.  The final disposal site for the material will be determined by the MFC and a dumping licence will be obtained from EPD prior to the commencement of the dredging works with reference to the results of further tests to be undertaken in accordance with the detailed requirements of ETWBTC No. 34/2002.

An estimated total of 50 m3 total petroleum hydrocarbon (TPH) contaminated soil will be excavated and the material should be remediated by using bioremediation method, as discussed in Section 7 and the RAP in Annex E.  The treated soil will be reused within the Project or disposed of at the public fill bank in Tuen Mun Area 38.

A total of about 835 tonnes of scrap steel will be produced during demolition of oil tanks and the associated fixtures/ appendages.  All the scrap steel will be delivered off-site by barge/truck for recycling. 

A total of about 30,000 m3 of uncontaminated excavated soil will be generated from the demolition and construction works.  All excavated soil will be reused for the backfilling on-site.

Small quantities of chemical wastes (less than 100 litres per month), sewage (a maximum of 135 m3 per day) and general refuse (a maximum of 585 kg per day) will be generated during the construction phase.

With the implementation of the recommendations in Section 6.6, the potential environmental impacts arising from storage, handling, collection, transport and disposal of wastes should be able to meet the criteria specified in the EIAO-TM.  No unacceptable waste management impact is anticipated.

6.9.2                      Operational Phase

Commercial grade gypsum (about 240,000 tonnes per year) can be recycled in PRD and East-Asia regional market.  Similarly the lower grade gypsum (about 17,000 tonnes per year) can also be reused for cement production.  The sludge from FGD wastewater treatment (about 180 tonnes at 30% dry solids per day) will be generated.  Design optimization of FGD wastewater system has been commenced and one of the key objectives is to minimize the influent throughput to the wastewater treatment system as a result in lowering the quantity of sludge arising.  This would help to reduce the amount of sludge requiring disposal.  Alternative disposal options such as off-take by the limestone supplier and gypsum off-taker and incineration of the sludge will be explored in the detailed design stage.

With the implementation of the recommended mitigation measures, the potential environmental impacts associated with the storage, handling, collection, transport and disposal of a small quantity of industrial waste and general refuse arising from the operation of the Project will meet the criteria specified in the EIAO-TM and no unacceptable waste management impact is anticipated.



([1])   "C&D materials" refers to materials arising from any land excavation or formation, civil/building construction, road works, building renovation or demolition activities.  It includes various types of reusable materials, building debris, rubble, earth, concrete, timber and mixed site clearance materials.  When sorted properly, materials suitable for land reclamation and site formation (known as public fill) should be reused at a public filling area or other land formation/reclamation projects.  The rock and concrete can be crushed and processed to produce rock fill or aggregate for various civil and building engineering applications.  The remaining construction waste (comprising timer, paper, plastics and general refuse) are to be disposed of at landfills.