10.1
EM&A Requirement
The assessments presented in the preceding sections
have predicted that the implementation of the Project is not expected to give
rise to any adverse environmental impacts.
A focused EM&A programme is considered appropriate to ensure that
the proposed mitigation measures are effectively implemented and the quality of
the surrounding environment is not prejudiced.
10.1.1
Construction Phase
In general, in view of the nature and small scale of the Project, no
environmental monitoring is required during construction except water quality
monitoring during dredging works and dolphin monitoring during underwater
percussive piling works, the details of which is provided in the following
section.
Joint environmental audit at the site by CAPCO staff and the Contractor
is recommended during construction to ensure the implementation of proper
handling and treatment of the construction waste generated from the
Project. Details of water quality
monitoring and dolphin monitoring are described as below.
Water Quality Monitoring
Monitoring Parameters
The parameters to be measured
in situ include:
· dissolved oxygen
(DO) (% saturation and mg L-1);
· temperature;
· turbidity (NTU);
and
· salinity (‰or ppt).
The only parameter to be
measured in the laboratory includes suspended solids (SS) (mg L-1).
In addition to the water
quality parameters, other relevant data should also be measured and recorded in
field logs, including the location of the sampling stations and grab dredger at
the time of sampling, water depth, time, weather conditions, sea conditions,
tidal state, current direction and speed, special phenomena and work activities
undertaken around the monitoring and works area that may influence the
monitoring results.
Monitoring Equipment and
Methodology
For water quality monitoring, the
following equipment should be supplied and used by the environmental
contractor.
·
Dissolved
Oxygen and Temperature Measuring Equipment - The instrument should be a portable,
weatherproof dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and should be operable from a DC power
source. It should be capable of
measuring: dissolved oxygen levels in the range of 0–20 mg L-1 and
0-200% saturation; and a temperature of 0-45 degrees Celsius.
It should have a membrane electrode with automatic
temperature compensation complete with a cable of not less than 35 m in
length. Sufficient stocks of spare
electrodes and cable should be available for replacement where necessary (for
example, YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument).
Turbidity Measurement Equipment - Turbidity should be measured in situ by the nephelometric
method. The instrument should be
portable and weatherproof using a DC power source complete with cable, sensor
and comprehensive operation manuals.
It should have a photoelectric sensor capable of measuring turbidity
between 0 - 1000 NTU (for example, Hach model 2100P
or an approved similar instrument). The cable should not be less than 25m in
length. The meter should be calibrated in order to establish the relationship
between NTU units and the levels of suspended solids. The turbidity measurement should be
carried out on a split water sample from the same water sample collected for
suspended solids analysis.
·
Salinity
Measurement Instrument
- A portable salinometer capable of measuring
salinity in the range of 0-40 ppm should be provided
for measuring salinity of the water at each monitoring location.
·
Water
Depth Detector - A
portable, battery-operated echo sounder should be used for the determination of
water depth at each designated monitoring station. A detector affixed to the bottom of the
work boat, if the same vessel is to be used throughout the monitoring
programme, is preferred.
·
Current
Velocity and Direction
– No specific equipment is recommended for measuring the current velocity and
direction. However, the
environmental contractor should seek approval of their proposed equipment with
the client prior to deployment.
·
Positioning
Device - A hand-held
or boat-fixed type digital Global Positioning System (GPS) with way point
bearing indication or other equipment instrument of similar accuracy, should be
provided and used during water quality monitoring to ensure the monitoring
vessel is at the correct location before taking measurements. GPS or the equivalent instrument,
calibrated at appropriate checkpoint (e.g. Quarry Bay Survey Nail at Easting
840683.49, Northing 816709.55) should be provided and used to ensure the
monitoring station is at the correct position before taking measurement and
water samples.
·
Water
Sampling Equipment -
A water sampler, consisting of a transparent PVC or glass cylinder of not less
than two litres, which can be effectively sealed with cups at both ends, should
be used (Kahlsico Water Sampler 13SWB203 or an
approved similar instrument). The
water sampler should have a positive latching system to keep it open and
prevent premature closure until released by a messenger when the sampler is at
the selected water depth.
All in
situ monitoring instruments should be checked, calibrated and certified by
a laboratory accredited under HOKLAS or any other international accreditation
scheme before use, and subsequently re-calibrated at monthly intervals
throughout all stages of the water quality monitoring. Responses of sensors and electrodes
should be checked with certified standard solutions before each use. The turbidity meter should be calibrated
to establish the relationship between turbidity readings (in NTU) and levels of
SS (in mg L-1) where possible.
For the on-site calibration of field
equipment, the BS 1427: 1993, Guide to Field
and On-Site Test Methods for the Analysis of Waters should be
observed. Sufficient stocks of
spare parts should be maintained for replacements when necessary. Backup monitoring equipment should also
be made available so that monitoring can proceed uninterrupted even when
equipment is under maintenance, calibration etc.
Water samples for SS measurements should
be collected in high density polythene bottles, packed in ice (cooled to 4° C without
being frozen), and delivered to a HOKLAS laboratory as soon as possible after
collection.
All laboratory work should be carried out
in a HOKLAS accredited laboratory.
Water samples of about 1,000 mL should be
collected at the monitoring and control stations for carrying out the
laboratory determinations. The determination
work should start within the next working day after collection of the water
samples. The SS laboratory
measurements should be provided to the client within 2 days of the sampling
event (48 hours). The analyses
should follow the standard methods as described in APHA Standard Methods for the Examination of Water and Wastewater, 19th Edition, unless otherwise specified
(APHA 2540D for SS).
The submitted information should include
pre-treatment procedures, instrument use, Quality Assurance/Quality Control
(QA/QC) details (such as blank, spike recovery, number of duplicate samples
per-batch etc), detection limits and accuracy. The QA/QC details should be in
accordance with requirements of HOKLAS or another internationally accredited
scheme.
Monitoring Stations
The monitoring station locations have been established to identify
potential impacts to water quality sensitive receivers which are shown in Figure 5.2.
Prior to, during and after the dredging works,
water quality sampling will be undertaken at stations situated around the
dredging area. The monitoring at
those stations is to ensure the dredging works of the Project do not affect the
sensitive areas nearby (shown in Figure 10.1).
·
C1 is a Control Station (during ebb tide) located to
the north of the dredging area, which is not supposed to be influenced by the
construction works;
·
C2 is a Control Station (during flood tide) located to the
south of the dredging area with the same coordinates as EPD routine monitoring
station NM3, which is not supposed to be influenced by the construction works;
·
SR1 and SR2
represent Lung Kwu Sheung
Tan Beach and Lung Kwu Tan Beach respectively,
located to the north of the dredging area;
·
SR3, SR4 and SR5 represent the Castle Peak Power
Station Intake, the Shiu Wing Steel Mill Intake and
the EcoPark Intake, located to the south of the
dredging area;
·
SR6, SR7 and SR8 represent the eastern boundary of Sha Chau and
·
G1, and G2
are regarded as a Gradient Station in-between the dredging area and the
The suggested co-ordinates of these monitoring
stations are listed in Table 10.1.
The monitoring stations will be sampled during
Baseline Monitoring (prior to the dredging works), Impact Monitoring (during
any works related to the dredging works) and Post Project Monitoring (after
completion of the dredging).
Table
10.1 Co-ordinates
of Baseline, Impact & Post Project Monitoring Stations (HK Grid)
Station |
Easting |
Northing |
C1 |
806561 |
829624 |
C2 |
811762 |
823728 |
SR1 |
808295 |
828795 |
SR2 |
809242 |
827496 |
SR3 |
809444 |
826076 |
SR4 |
810241 |
825355 |
SR5 |
810763 |
825047 |
SR6 |
806198 |
827886 |
SR7 |
806959 |
824749 |
SR8 |
807571 |
822187 |
G1 |
807729 |
826440 |
G2 |
808608 |
824832 |
Monitoring Frequency
For baseline, impact and post-project monitoring,
monitoring should be undertaken 3 days per week, at mid-flood and mid-ebb
tides, with sampling/ measurement at the designated stations. The intervals between 2 consecutive sets
of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Level, in which case
monitoring frequency should be increased.
The tidal range for each of the flood and ebb tide should not be less
than 0.5m.
The water quality sampling will be undertaken within
a 3-hour window of 1.5 hour before and 1.5 hour after mid flood and mid-ebb
tides. The environmental contractor
will be responsible for liaison with the engineering contractor to confirm whether
dredging works are being undertaken during the water quality sampling.
Each station will be sampled and measurements will be
taken at three depths, 1 m below the sea surface, mid depth and 1m above the
sea bed. For stations that are less
than 3 m in depth, only the mid depth sample should be taken.
Replicate in-situ
measurements and sample collected from each independent sampling event are
required for all parameters to ensure a robust statistically interpretable
dataset.
Baseline Monitoring:
Baseline Monitoring will comprise sampling 3 days a week, at mid-flood
and mid-ebb tides, for at least 4 weeks prior to the commencement of the
dredging works. The monitoring will
be undertaken at twelve locations in total (two control, five impact and two
gradient monitoring stations), as shown on Figure 10.1. The baseline monitoring schedule should
be provided to EPD for agreement at least 2 weeks prior to commencement of the
baseline monitoring work.
Impact Monitoring:
Impact Monitoring will comprise sampling 3 days a week, at mid-flood and
mid-ebb tides, during the dredging works.
Samples should be taken at the same location as the Baseline Monitoring
Stations. The monitoring schedule
should be provided to EPD for agreement prior to commencement of the monitoring
work.
Post Project Monitoring:
Post Project Monitoring will comprise sampling on 3 days a week, at
mid-flood and mid-ebb tides, for at least 4 weeks after completion of the
dredging works at the same location as the Baseline Monitoring Stations.
Compliance /
Action Event Plan
Water quality monitoring results will be evaluated
against Action and Limit levels shown in Table
10.2.
Table 10.2 Action
and Limit Levels for Water Quality (based on the Results of the Baseline
Report)
Parameter |
Action Level |
Limit Level |
SS in mg L-1 (depth-averaged a) c |
95%-ile of baseline data, and 20% exceedance of value at
any impact station compared with corresponding data from control stations at
the same tide of the same day d, e, f |
99%-ile of baseline data, and 30% exceedance of value at
any impact station compared with corresponding data from control stations at
the same tide of the same day and specific sensitive receiver water quality
requirements d, e, f |
DO in mg L-1 b |
Surface and Middle 5%-ile of baseline data for surface and middle layer Bottom 5%-ile of baseline data for bottom
layers |
Surface and Middle 4mg L-1 or 1%-ile of baseline for surface and middle
layer Bottom 2mg L-1 or 1%-ile of baseline
data for bottom layer |
Turbidity in NTU (depth-averaged a) c |
95%-ile of baseline data, and 20% exceedance of value at
any impact station compared with corresponding data from control stations at
the same tide of the same day d. e |
99%-ile of baseline data, and 30% exceedance of value at any impact station compared with
corresponding data from control stations at the same tide of the same day d,
e |
Notes: (a)
“Depth-averaged”
is calculated by taking the arithmetic means of reading of all three depths. (b)
For
DO, non-compliance of the water quality limits occurs when monitoring result
is lower than the limits. (c)
For
SS and turbidity, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits. (d)
An exceedance of Action Level and Limit Level is defined as
exceeding both criteria. The
comparison of the results of impact stations and control stations will aid to
determine the background influence to the water quality sensitive receivers. (e)
C1
is regarded as the Control Station during ebb tide, whereas C2 is regarded as
the Control Station during flood tide. (f)
For
WSD and Black Point/Castle Peak Power Station intakes, the specific SS
criteria are not greater than 20 mg L-1 and 764 mg L-1. |
Actions to be taken in the event that the Action or
Limit Levels are exceeded are shown in
Table 10.3.
Table 10.3 Event
and Action Plan for Water Quality
EVENT |
ACTION |
|||
ET |
IEC |
CAPCO |
Contractor |
|
Action Level being exceeded by one sampling day |
1. Repeat in-situ
measurement to confirm findings; 2. Identify
source(s) of impact; 3. Inform the IEC
and the Contractor and CAPCO; 4. Check
monitoring data, all plant, equipment and the Contractor’s working methods; 5. Discuss
mitigation measures with the IEC and the Contractor; |
1. Discuss with
the ET and the Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by the Contractor and advise the
CAPCO accordingly; 3. Assess the
effectiveness of the implemented mitigation measures. |
1. Discuss with the
IEC on the proposed mitigation measures; 2. Make agreement on
the mitigation measures to be implemented. |
1. Inform
the CAPCO and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with the ET and the IEC and propose mitigation measures to the IEC and the
CAPCO; 6. Implement
the agreed mitigation measures. |
Action Level being exceeded by more than one consecutive
sampling days |
1. Repeat
in-situ measurement to confirm findings; 2. Identify
source(s) of impact; 3. Inform
the IEC and the Contractor and CAPCO; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with the IEC and the Contractor; 6. Ensure
mitigation measures are implemented; |
1. Discuss
with the ET and the Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by the Contractor and advise the
CAPCO accordingly; 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss with
the IEC on the proposed mitigation measures; 2. Make
agreement on the mitigation measures to be implemented; 3.
Assess
effectiveness of the implemented mitigation measures; |
1. Inform
the CAPCO and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with the ET and the IEC and propose mitigation measures to the IEC and CAPCO
within 3 working days; 6. Implement
the agreed mitigation measures. |
Limit Level being exceeded by one consecutive sampling day |
1. Repeat
in-situ measurement to confirm findings; 2. Identify
source(s) of impact; 3. Inform
the IEC, the Contractor and the DEP; 4. Check
monitoring data, all plant, equipment and the Contractor’s working methods; 5. Discuss
mitigation measures with the IEC, the CAPCO and the Contractor; 6. Ensure
mitigation measures are implemented; |
1. Discuss with
the ET / Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by the Contractor and advise the
CAPCO accordingly; 3. Assess the
effectiveness of the implemented mitigation measures. |
1. Discuss
with the IEC, the ET and the Contractor on the proposed mitigation measures; 2. Request
the Contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; 4. Assess
the effectiveness of the implemented mitigation measures. |
1. Inform
the Engineer and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with the ET, the IEC and the CAPCO and propose mitigation measures to the IEC
and the CAPCO within 3 working days; 6. Implement
the agreed mitigation measures. |
Limit Level being exceeded by more than
one consecutive sampling days |
1. Repeat in-situ
measurement to confirm findings; 2. Identify
source(s) of impact; 3. Inform the
IEC, the Contractor and DEP; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with the IEC, the CAPCO and the Contractor; 6. Ensure
mitigation measures are implemented; |
1. Discuss with
ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by the Contractor and advise the
CAPCO accordingly; 3. Assess the
effectiveness of the implemented mitigation measures. |
1. Discuss with
the IEC, the ET and the Contractor on the proposed mitigation measures; 2. Request
Contractor to critically review working methods; 3. Make
agreement on the mitigation measures to be implemented; 4. Assess
effectiveness of the implemented mitigation measures; 5. Consider and
instruct, if necessary, the Contractor to slow down or to stop all or part of
the marine work until no exceedance of Limit Level. |
1. Inform the
CAPCO and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check all
plant and equipment; 4. Consider
changes of working methods; 5. Discuss with
the ET, the IEC and the CAPCO and propose mitigation measures to the IEC and
the CAPCO within 3 working days; 6. Implement
the agreed mitigation measures; 7. As directed
by the CAPCO, slow down or stop all or part of the construction activities. |
A letter report should be provided to CAPCO that
should include the monitoring results in addition to operating practices of the
dredging works during sampling (including position, quantity of dredged volume
per day) and an interpretation of monitoring results. The monitoring data should be provided
graphically to show the relationship between the Control and the Impact
monitoring stations and compliance or non-compliance with respect to the Action
and Limit Levels.
The reports to be provided by the environmental
contractor/ET should include one Baseline Monitoring Report; Weekly Impact
Monitoring Reports; and one Post Project Monitoring Report.
The ET should prepare and submit a Baseline
Environmental Monitoring Report at least 1 month before commencement of impact
monitoring. Copies of the Baseline
Environmental Monitoring Report will be submitted to the following: the
Contractor, the IEC, the CAPCO and the EPD. The ET will liaise with the relevant
parties on the exact number of copies required.
A Monthly Impact Monitoring Report should be prepared
by the ET and submitted to the Contractor, the IEC, the CAPCO and the EPD
within 10 working days at the end of each reporting month.
The Post-Project Monitoring Report should be prepared
by the ET and submitted to the Contractor, the IEC, the CAPCO and the EPD
within one week of completion of the Post Project Survey.
The format of the reports should follow that
specified in Technical Memorandum on EIA
Process (EIAO, Cap. 499, S16), as
appropriate.
Dolphin Monitoring
Visual dolphin monitoring should be conducted during
the underwater
percussive piling works to evaluate
whether there have been any effects on the animals. A
dolphin exclusion zone within a radius of 500 m from the works area during the
construction phase. The exclusion zone
around the work area should be scanned for at least 30 minutes prior to the
commencement of piling. If
cetaceans are observed in the exclusion zone, underwater percussive piling should be delayed until they have left the area.
The observer should stand at a location (eg the piling barge) that allows for an observation height
of 4 to 5 m above water level at the observer’s eye level and relatively unobstructed
forward visibility. Observation by
the observer should be conducted by searching with Fujinon
7X50 marine binoculars or equivalent, scanning the area with the naked eye and
occasional binocular check. The
observer should remain alert at all times during the entire observation
period.
A sighting record should be filled in immediately at
the initial sighting with data on the time, position, distance and bearing of
the sighting. All other information
on sea state, weather conditions (ie wind speed
according to the Beaufort Scale), as well as notes on dolphin appearance,
behaviour, direction of movement, response to boat and any other relevant
information can be completed at the end of the sighting.
When dolphins are spotted within the exclusion zone,
construction works should cease and should not resume until the observer
confirms that the zone has been continuously clear of dolphins for a period of
30 minutes (thereby adequately spanning the approximate maximum dive time of
the dolphins of 4 minutes). Dolphin
sighting position, data on sighting angle, distance to the group, group size
and behaviour should be recorded.
The dolphin surveys will be required solely during underwater percussive piling works. Daily monitoring should be conducted till
the completion of underwater
percussive piling works.
10.1.2
Operational Phase
CAPCO implements a comprehensive environmental monitoring programme for
the operations of the existing Castle Peak Power Station (CPPS) and it is
considered that no additional EM&A activities are required for the
emissions control operations.
The current operational environmental monitoring programmes for the CPPS
that are relevant to the Project include:
Air
·
Operation and maintenance
of Continuous Emission Monitoring (CEM) System at the stack to continuously
monitor the flue gas;
·
Transmission of the on-line
CEM data to EPD's office through a telemetry system;
·
Operation and maintenance
of an ambient air monitoring network at San Hui,
Butterfly Estate and Lung Kwu Tan in Tuen Mun and Tin Shui Wai;
·
Reporting of the stack
sampling result, emission data and validated CEM data to EPD; and
·
Reporting of the ambient
air monitoring and dust monitoring results to EPD.
Water
·
Monitoring of the quality of
effluents discharged from the CPPS and ash lagoon;
·
Monitoring of the quality
of marine water around the ash lagoon; and
·
Reporting of the wastewater
and marine water monitoring results to EPD.
10.2
Implementation
Schedule
Mitigation measures discussed in the preceding sections are summarised
in the Implementation Schedule in Table
10.4.
Table 10.4 Implementation
Schedule
EIA Ref. |
Environmental
Protection Measures |
Location/Duration of Measures/Timing of Completion
of Measures |
Implementation Agent |
Implementation Stage |
Relevant Legislation & Guidelines |
|||
Des |
C |
O |
Dec |
|||||
AIR QUALITY –CONSTRUCTION PHASE |
||||||||
S3.6.1 |
·
The area at which
demolition work takes place should be sprayed with water prior to, during and
immediately after the demolition activities so as to maintain the entire
surface wet |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
Air Pollution Control (Construction Dust) Regulation |
S3.6.1 |
·
Dust screens or sheeting should be provided to enclose the structure
to be demolished to a height of at least 1 m higher than the highest level of
the structure; |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
Air Pollution Control (Construction Dust) Regulation |
S3.6.1 |
·
Any dusty materials should be wetted with water to avoid any fugitive
dust emission; |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
Air Pollution Control (Construction Dust) Regulation |
S3.6.1 |
·
All temporary stockpiles should be wetted or covered by tarpaulin
sheet to prevent fugitive emissions; |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
Air Pollution Control (Construction Dust) Regulation |
S3.6.1 |
·
All the dusty areas and roads should be wetted with water; |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
Air Pollution Control (Construction Dust) Regulation |
S3.6.1 |
·
All the dusty materials transported by lorries should be covered
entirely by impervious sheet to avoid any leakage; and |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
Air Pollution Control (Construction Dust) Regulation |
S3.6.1 |
·
The falling height of fill materials should be controlled. |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
Air Pollution Control (Construction Dust) Regulation |
AIR QUALITY –
OPERATIONAL PHASE Since the Project will
significantly reduce SO2 and NOx
emissions and further reduce particulate emissions from CPB, no
mitigation measures are required. |
||||||||
NOISE –
CONSTRUCTION PHASE The predicted noise levels are within the stipulated
noise criterion as a result of the considerable
separation distance plus topography and existing building structures at CPB
located between the NSR and the Project. Mitigation measures are not required. |
||||||||
NOISE –
OPERATIONAL PHASE The predicted noise levels are below the daytime and
night-time criteria as a result of the considerable
separation distance plus topography and existing building structures at CPB
located between the NSR and the Project. Mitigation measures are not required. |
||||||||
WATER QUALITY –
CONSTRUCTION PHASE |
||||||||
Marine-based Construction Activities |
||||||||
S5.8.1 |
·
Silt curtains should be deployed around
the closed grab dredger to contain suspended solids within the construction
site during dredging. |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.1 |
·
A daily dredging rate of a closed grab
dredger (with a minimum grab size of 8 m3) should be less than
5,200 m3 day-1, with reference to the maximum rate for
dredging, which was derived in the EIA. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.1 |
·
Mechanical grabs should be designed and
maintained to avoid spillage and should seal tightly while being lifted. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.1 |
·
Barges or hoppers should have tight
fitting seals to their bottom openings to prevent leakage of material. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.1 |
·
Loading of barges or hoppers should be
controlled to prevent splashing of dredged material to the surrounding water. |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.1 |
·
Barges or hoppers should not be filled to
a level which will cause overflow of materials or pollution of water during
loading or transportation. |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.1 |
·
Excess material should be cleaned from
the decks and exposed fittings of barges or hoppers before the vessel is
moved. |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.1 |
·
Adequate freeboard should be maintained
on barges to reduce the likelihood of decks being washed by wave action. |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.1 |
·
All vessels should be sized such that
adequate clearance is maintained between vessels and the seabed at all states
of the tide to ensure that undue turbidity is not generated by turbulence
from vessel movement or propeller wash. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.1 |
·
The works should not cause foam, oil,
grease, litter or other objectionable matter to be present in the water
within and adjacent to the works site. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
- |
Land-based - Construction Runoff |
||||||||
S5.8.2 |
·
At the start of site establishment,
perimeter cut-off drains to direct off-site water around the site should be
constructed and internal drainage works and erosion and sedimentation control
facilities implemented. Channels,
earth bunds or sand bag barriers should be provided on site to direct stormwater to silt removal facilities. The design of efficient silt removal
facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
S5.8.2 |
·
All the surface runoff or extracted ground
water contaminated by silt and suspended solids should be collected by the
on-site drainage system and diverted through the silt traps prior to
discharge into storm drain. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
S5.8.2 |
·
All exposed earth areas should be
completed as soon as possible after earthworks have been completed, or alternatively,
within 14 days of the cessation of earthworks, where practicable. If excavation of soil cannot be
avoided during the rainy season, or at any time of year when rainstorms are
likely, exposed slope surfaces should be covered by tarpaulin or by other
means. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
S5.8.2 |
·
All drainage facilities and erosion and sediment
control structures should be regularly inspected and maintained to ensure
proper and efficient operation at all times and particularly following
rainstorms. Deposited silt and
grit should be removed regularly and disposed of by spreading evenly over
stable, vegetated areas. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
S5.8.2 |
·
Measures should be taken to reduce the
ingress of site drainage into excavations. If the excavation of trenches in wet
periods is necessary, they should be dug and backfilled in short sections
wherever practicable. Water
pumped out from trenches or foundation excavations should be discharged into
storm drains via silt removal facilities. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
S5.8.2 |
·
Open stockpiles of construction materials
(for example, aggregates, sand and fill material) of more than 50 m3
should be covered with tarpaulin or similar fabric during rainstorms. Measures should be taken to prevent the
washing away of construction materials, soil, silt or debris into any
drainage system. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
S5.8.2 |
·
Manholes (including newly constructed
ones) should always be adequately covered and temporarily sealed so as to
prevent silt, construction materials or debris being washed into the drainage
system. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
S5.8.2 |
·
Precautions to be taken at any time of year
when rainstorms are likely, actions to be taken when a rainstorm is imminent
or forecasted, and actions to be taken during or after rainstorms are
summarised in Appendix A2 of ProPECC PN 1/94. Particular attention should be paid to
the control of silty surface runoff during storm
events, especially for areas located near steep slopes. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
S5.8.2 |
·
Oil interceptors should be provided in
the drainage system and regularly emptied to prevent the release of oil and
grease into the storm water drainage system after accidental spillages. The interceptor should have a bypass
to prevent flushing during periods of heavy rain. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
S5.8.2 |
·
All temporary and permanent drainage
pipes and culverts provided to facilitate runoff discharge should be
adequately designed for the controlled release of storm flows. All sediment traps should be regularly
cleaned and maintained. The
temporary diverted drainage should be reinstated to the original condition
when the construction work has finished or the temporary diversion is no
longer required. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
Wastewater from Site Facilities |
||||||||
S5.8.2 |
·
Sewage from toilets should be collected
by a licensed waste collector. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.2 |
·
Vehicle and plant servicing areas,
vehicle wash bays and lubrication bays should, as far as possible, be located
within roofed areas. The drainage
in these covered areas should be connected to foul sewers via a petrol
interceptor. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.2 |
·
Oil leakage or spillage should be contained
and cleaned up immediately. Waste
oil should be collected and stored for recycling or disposal, in accordance
with the Waste Disposal Ordinance. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal
Ordinance |
Storage and Handling of Oil, Other Petroleum Products and Chemicals |
||||||||
S5.8.2 |
·
Waste streams classifiable as chemical
wastes should be properly stored, collected and treated for compliance with Waste Disposal Ordinance or Disposal (Chemical Waste) (General)
Regulation requirements. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste
Disposal Ordinance Disposal
(Chemical Waste) (General) Regulation |
S5.8.2 |
·
All fuel tanks and chemical storage areas
should be provided with locks and be sited on paved areas. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal (Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes |
S5.8.2 |
·
The storage areas should be surrounded by
bunds with a capacity equal to 110% of the storage capacity of the largest tank
to prevent spilled oil, fuel and chemicals from reaching the receiving
waters. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal (Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes |
S5.8.2 |
·
The Contractors should prepare guidelines
and procedures for immediate clean-up actions following any spillages of oil,
fuel or chemicals. |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
- |
S5.8.2 |
·
Surface run-off from bunded
areas should pass through oil/grease traps prior to discharge to the stormwater system. |
Within the construction site/Throughout
the construction period |
Contractor |
|
ü |
|
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
WATER QUALITY –
OPERATIONAL PHASE |
||||||||
Limestone FGD Absorber Effluent |
||||||||
S5.9.2 |
It has predicted that the marine works and structures
will have minimal effects on hydrodynamics and water quality. Mitigation measures are not considered
to be necessary. |
- |
- |
|
|
|
|
- |
S5.9.2 |
The high degree of mixing inherent in the coastal
margin or coastal zone will result in rapid dilution of the effluent to
non-significant concentrations, and therefore mitigation measures are
considered unnecessary. |
- |
- |
|
|
|
|
- |
Storage and Handling of Oil, Other Petroleum Products and Chemicals |
||||||||
S5.9.3 |
·
Waste streams classifiable as chemical
wastes should be properly stored, collected and treated for compliance with Waste Disposal Ordinance or Disposal (Chemical Waste) (General)
Regulation requirements. |
Within the Project
Site/Throughout the operational years |
CLP Power (as CAPCO operator) |
|
|
ü |
|
Waste
Disposal Ordinance Disposal
(Chemical Waste) (General) Regulation |
S5.9.3 |
·
All fuel tanks and chemical storage areas
should be provided with locks and be sited on paved areas. |
Within the Project
Site/Throughout the operational years |
CLP Power (as CAPCO operator) |
|
|
ü |
|
Waste Disposal (Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes |
S5.9.3 |
·
The storage areas should be surrounded by
bunds with a capacity equal to 110% of the storage capacity of the largest
tank to prevent spilled oil, fuel and chemicals from reaching the receiving
waters. |
Within the Project
Site/Throughout the operational years |
CLP Power (as CAPCO operator) |
|
|
ü |
|
Waste Disposal (Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes |
S5.9.3 |
·
The Contractors should prepare guidelines
and procedures for immediate clean-up actions following any spillages of oil,
fuel or chemicals. |
Within the Project
Site/Throughout the operational years |
CLP Power (as CAPCO operator) |
|
|
ü |
|
- |
S5.9.3 |
·
Surface run-off from bunded
areas should pass through oil/grease traps prior to discharge to the stormwater system. |
Within the Project
Site/Throughout the operational years |
CLP Power (as CAPCO operator) |
|
|
ü |
|
EPD Practice
Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94) |
WASTE MANAGEMENT – CONSTRUCTION PHASE There are no major waste management
issues associated with the operation of the new emission control system. This section recommends the mitigation
measures to avoid or minimize potential adverse environmental impacts
associated with handling, collection and disposal of waste arising from the
construction of the new emission control system. It is the Contractor’s
responsibility to ensure that only licensed chemical waste collectors are
used for collection and transportation of chemical waste to the licensed
disposal facility and that appropriate measures are taken to minimize adverse
environmental impacts, including windblown litter and dust from the
transportation of wastes. In
addition, the Contractor must ensure that all the necessary waste permits are
obtained for the construction and operational phases. |
||||||||
Dredged Sediments |
||||||||
S6.6.1 |
Dredged sediments should be
disposed of only at designated disposal sites allocated by the Marine Fill
Committee (MFC) based on the findings of further sediment quality tests. A dumping licence should also be
obtained from EPD prior to the commencement of the dredging works. |
Within designated disposal
site/prior to commencement of the dredging works |
Contractor |
|
ü |
|
|
Dumping at Sea Ordinance |
S6.6.1 |
Regardless of the disposal
method and site, the Contractor should: ·
Dredge the
sediments using closed grabs; ·
Use split barges
of not less than 750 m3 capacity when transporting the sediment to
the disposal site; ·
Regularly
maintain the barge hoppers to ensure that they are capable of rapid opening
and discharge at the designated disposal site; and ·
Monitor the barge
load against loss of materials during transportation. |
Within the dredging area
/Throughout the dredging works period |
Contractor |
|
ü |
|
|
Dumping at Sea Ordinance |
C&D Materials |
||||||||
Management of Waste Disposal |
||||||||
S6.6.3 |
·
The contractor should open a billing account with EPD in accordance
with the Waste Disposal (Charges for
Disposal of Construction Waste) Regulation for the payment of disposal
charges. Every waste load
transferred to government waste disposal facilities such as public fill,
sorting facilities, landfills or transfer station would required a valid
“chit” which contain the information of the account holder to facilitate
waste transaction recording and billing to the waste producer. A trip-ticket system should also be
established in accordance with Works
Bureau Technical Circular No. 21/2002 to monitor the disposal of solid
wastes at transfer station/landfills, and to control fly-tipping. The billing “chit” and trip-ticket
system should be included as one of the contractual requirements and
implemented by the contractor. |
Within the construction site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal (Charges for Disposal of
Construction Waste) Regulation, December 2005 ETWBTC No 31/2004, Trip Ticket System for
Disposal of Construction and Demolition Materials |
S6.6.3 |
·
A recording system for the amount of waste generated, recycled and
disposed of (including the disposal sites) should be established during the
construction stage. |
Within the construction site/Throughout the construction period |
Contractor |
|
ü |
|
|
ETWBTC No 31/2004, Trip Ticket System for
Disposal of Construction and Demolition Materials |
S 6.6.3 |
Measures for the Reduction of C&DM
Generation during Planning and Design Stages The various waste management options can be categorized in terms of
preference from an environmental viewpoint. The options considered to be more
preferable have the least impacts and are more sustainable in the long
term. Hence, the waste management
hierarchy is as follows: · Avoidance and minimization, that is, reduction of
waste generation through changing or improving practices and design; · Reuse of materials, thus avoiding disposal
(generally with only limited reprocessing); · Recovery and recycling, thus avoiding disposal
(although reprocessing may be required); and · Treatment and disposal, according to relevant law,
regulations, guidelines and good practice. This hierarchy should be used to evaluate the waste management
options, thus allowing maximum waste reduction and reduced disposal
costs. Records of quantities of
wastes generated, recycled and disposed (locations) should be kept. |
Within the construction site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal Ordinance WBTC No. 25/99 Incorporation of Information on
Construction and Demolition Material management in PWSC Papers |
S6.6.3 |
Measures for the Reduction of C&DM
Generation during Construction · C&D materials will be reused as far as possible
within the Project. Public fill
and construction waste should be segregated and stored in different
containers or skips to facilitate reuse or recycling of materials and their proper
disposal of construction waste.
Specific areas of the work site should be designated for such
segregation and temporary storage if immediate use is not practicable. · The construction waste should be collected by
Contractor and transported to landfills for disposal. · The use of wooden hoardings should not be
allowed. An alternative material,
which can be reused or recycled, for example, metal (aluminium, alloy, etc)
should be used. · To reduce the potential dust impact, C&D
materials should be wetted as quickly as possible during excavation works. |
Within the construction site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal Ordinance WBTC 32/92, The Use of Tropical Hard Wood on
Construction Site WBTC No. 2/93, Public Dumps |
Chemical Waste The Contractor should register
as a chemical waste producer with the EPD. Chemical waste, as defined by Schedule 1 of the Waste Disposal (Chemical Waste) (General) Regulation, should be
handled in accordance with the Code of Practice on the Packaging, Handling
and Storage of Chemical Wastes as follows: |
||||||||
S6.6.4 |
Containers used for storage
of chemical wastes should: ·
be suitable for
the substance they are holding, resistant to corrosion, maintained in a good
condition, and securely closed; ·
have a capacity
of less than 450 L unless the specifications have been approved by the EPD;
and ·
display a label
in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal (Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes |
S6.6.4 |
The storage area for chemical
wastes should: ·
be clearly
labelled and used solely for the storage of chemical waste; ·
be enclosed on at
least 3 sides; ·
have an
impermeable floor and bunding, of capacity to
accommodate 110% of the volume of the largest container or 20% by volume of
the chemical waste stored in that area, whichever is the greatest; ·
have adequate
ventilation; ·
be covered to
prevent rainfall entering (water collected within the bund must be tested and
disposed of as chemical waste, if necessary); and ·
be arranged so
that incompatible materials are appropriately separated. |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal (Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes |
S6.6.4 |
Disposal of chemical waste
should be: ·
via a licensed
waste collector; and ·
to a facility
licensed to receive chemical waste, such as the Chemical Waste Treatment
Facility which also offers a chemical waste collection service and can supply
the necessary storage containers |
Within the construction
site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal (Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes |
Sewage |
||||||||
S6.6.5 |
· The sewage sludge from the
portable toilet should be collected by a reputable collector on a regular
basic. |
Within the construction site/Throughout the construction period |
Contractor |
|
ü |
|
|
- |
General Refuse |
||||||||
S6.6.6 |
· General refuse should be stored in enclosed bins or
compaction units separately from construction and chemical wastes. |
Within the construction site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal Ordinance |
S6.6.6 |
· General refuse should be removed from the site,
separately from construction and chemical wastes, on a daily basis to
minimise odour, pest and litter impacts.
|
Within the construction site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal Ordinance |
S6.6.6 |
· Burning of refuse on construction site is prohibited
by law. |
Within the construction site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal Ordinance |
S6.6.6 |
· Aluminium cans are often recovered from the waste
stream by individual collectors if they are segregated and made easily
accessible. As such, separate,
labelled bins for their deposit should be provided if feasible. Materials recovered will be re-used on
site or sold for recycling. |
Within the construction site/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal Ordinance |
Staff Training |
||||||||
S6.6.7 |
·
Training should be provided to workers on the concepts of site
cleanliness and on appropriate waste management procedures, including waste
reduction, reuse and recycling at the beginning of the Contract. |
Within the construction site/Throughout the construction period |
Contractor |
|
ü |
|
|
- |
LAND
CONTAMINATION The following control measures should be implemented
during the excavation of potentially contaminated soil and potentially
contaminated groundwater: |
||||||||
Handling of potentially
contaminated soil to be excavated |
||||||||
Annex E |
·
Potentially
contaminated soil should be treated in accordance with the remediation
actions specified in the Remediation Action Plan (RAP) of this EIA Report and
the treated soil should be reused within the Project Site as far as possible. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD’s Guidance Notes for Investigation and Remediation
of Contaminated Sites of petrol Filling Stations, Boatyards and Car
Repairing/Dismantling Workshops |
Annex E |
·
The temporary stockpile of excavated
potentially contaminated materials should be contained in a container covered
by HDPE sheet on top |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD’s Guidance Notes for Investigation and
Remediation of Contaminated Sites of petrol Filling Stations, Boatyards and
Car Repairing/Dismantling Workshops |
Annex E |
·
Bioremediation by applying nutrient to
the soil should be employed for the on-site treatment of excavated materials
potentially contaminated by TPH. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD’s Guidance Notes for Investigation and
Remediation of Contaminated Sites of petrol Filling Stations, Boatyards and
Car Repairing/Dismantling Workshops |
Annex E |
·
If disposal of the treated excavated soil
to the public fill bank is required, vehicles containing any excavated
materials should be suitably covered to limit potential dust emissions or
wastewater run-off, and truck bodies and tailgates will be sealed to minimise
the risk of a discharge during transportation or during wet conditions. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD’s Guidance Notes for Investigation and
Remediation of Contaminated Sites of petrol Filling Stations, Boatyards and
Car Repairing/Dismantling Workshops |
Annex E |
·
Records of the quantities of soil
generated for off-site disposal will be maintained. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
EPD’s Guidance Notes for Investigation and
Remediation of Contaminated Sites of petrol Filling Stations, Boatyards and
Car Repairing/Dismantling Workshops |
Handling of potentially
contaminated groundwater |
||||||||
Annex E |
·
As groundwater is not used for either
domestic or industrial purposes at the site or in the adjacent areas,
remediation of groundwater is not considered to be necessary for the Project
to proceed. If groundwater is
encountered during the construction of foundations, the groundwater
abstracted or collected will be recharged back to the site. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Water Pollution Control Ordinance |
Annex E |
·
The FODT and the oil separator serving it
should be cleaned prior to demolition. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Water Pollution Control Ordinance |
Annex E |
·
Oily water and sludge collected from the
cleaning should be treated at the on-site wastewater treatment facility. Oily water and sludge collected from
the cleaning should be collected and disposed of as chemical waste at
Government chemical waste treatment facility. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal Ordinance (Cap 354) and
Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C) |
Annex E |
·
Only licensed waste contractors should be
used to collect and transport any chemical waste. The necessary waste disposal permits
will be obtained, as required, from the appropriate authorities, in
accordance with the Waste Disposal Ordinance (Cap 354) and Waste
Disposal (Chemical Waste) (General) Regulation (Cap 354C), as required. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Waste Disposal Ordinance (Cap 354) and
Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C) |
In order to minimise the contacts of the workers with
the contaminated materials and to ensure safe work environments during the
remediation works, the following safety measures are proposed |
||||||||
Annex E |
·
Prior to commence any remediation work, a
health and safety risk assessment should be performed for the remediation
work to identify potential work related hazards and prepare appropriate
control measures. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Heath and safety controls as stipulated under the Factories and Undertakings Ordinance and Occupational Safety and
Health Regulation |
Annex E |
·
Appropriate Personal Protective Equipment
(PPE) such as safety hat, chemical protective gloves, masks (for both dust
and vapour), eye goggles, protective clothing and protective footwear should
be provided to staff who would be involved in the tank cleaning and
contaminated area (FODT and TP3) remediation works. No works should be allowed without the
suitable PPE. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Heath and safety controls as stipulated under the Factories and Undertakings Ordinance and Occupational Safety and
Health Regulation |
Annex E |
·
The workers should inspect and check
their PPE before, during and after use.
In cases where any of the PPE is impaired, the workers should stop
work immediately and inform their supervisor. The workers should not be allowed to
re-start their work until the impaired PPE is replaced. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Heath and safety controls as stipulated under the Factories and Undertakings Ordinance and Occupational Safety and
Health Regulation |
Annex E |
·
The workers should always maintain basic
hygiene standard (e.g. hand wash before leaving the contaminated work
area). The workers should also be
responsible for cleaning and storing their own PPE in a secure place before
leaving the site. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Heath and safety controls as stipulated under the Factories and Undertakings Ordinance and Occupational Safety and
Health Regulation |
Annex E |
·
Eating, drinking and smoking should be
strictly prohibited within the contaminated site area. |
Within the contaminated area /Throughout
the construction period |
Contractor |
|
ü |
|
|
Heath and safety controls as stipulated under the Factories and Undertakings Ordinance and Occupational Safety and
Health Regulation |
Annex E |
·
The designated site management representatives
must be informed if any workers feel uncomfortable physically or mentally
during the remediation works. All
workers should leave the work areas and the work should be temporarily
suspended until the reason for the uncomfortable feeling has been identified. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Heath and safety controls as stipulated under the Factories and Undertakings Ordinance and Occupational Safety and
Health Regulation |
Annex E |
·
The works should be stopped or
discontinued when Typhoon Signal No. 3 or Rainstorm Warning signals are
hoisted. All stockpile materials
(if any) should be covered immediately by tarpaulin or other similar protective
and waterproof materials. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Heath and safety controls as stipulated under the Factories and Undertakings Ordinance and Occupational Safety and
Health Regulation |
Annex E |
·
Bulk earth-moving excavator equipment
should be used to minimise construction workers’ potential contact with
contaminated materials. |
Within the contaminated area
/Throughout the construction period |
Contractor |
|
ü |
|
|
Heath and safety controls as stipulated under the Factories and Undertakings Ordinance and Occupational Safety and
Health Regulation |
ECOLOGICAL IMPACT
– CONSTRUCTION AND OPERATIONAL PHASES In accordance with the guidelines in the EIAO-TM on marine ecology impact assessment,
the general policy for mitigating impacts to marine ecological resources, in
order of priority, are: |
||||||||
Measures for
Marine Mammals |
||||||||
S8.9 |
The
following recommendations should be considered to minimize potential construction
and operation impacts on dolphins and porpoises. ·
All vessel operators
working on the Project construction or operation should be given a briefing,
alerting them to the possible presence of dolphins in the area, and the
guidelines for safe vessel operation in the presence of cetaceans. If high speed vessels are used, they
should be required to slow to 10 knots when passing through a high density
dolphin area (west Lantau, Sha
Chau and Lung Kwu Chau); ·
The vessel operators should
be required to use predefined and regular routes, as these will become known
to dolphins using these waters; ·
The vessel operators should
be required to control and manage all effluent from vessels; ·
A policy of no dumping
of rubbish, food, oil, or chemicals should be strictly enforced. This should also be covered in the
contractor briefings; ·
Every attempt should
be made to minimize the effects of construction of the Project on the water
quality of the area; |
Within the marine works area
/Throughout the construction period /Operation of the additional berthing
facility |
Contractor / CLP Power (as
CAPCO operator) |
|
ü |
ü |
|
- |
S8.9 |
To limit
potential impacts to cetaceans from underwater percussive piling, the following
steps should be taken: · Quieter hydraulic hammers should be used instead of the noisier diesel
hammers; · An exclusion zone of 500 m radius should be scanned around the work
area for at least 30 minutes prior to the start of piling. If cetaceans are observed in the
exclusion zone, piling should be delayed until they have left the area; and, · Acoustic decoupling of noisy equipment on work barges should be
undertaken. These techniques
include the use of a soft sling to retain the pile driving hammer, rubber tyred air compressor for bubble jacket/curtain, rubber
pads on barge leaders and guides, and an air curtain around the pile barge. |
Within the dredging area
/Throughout the construction period |
Contractor |
|
ü |
|
|
- |
VISUAL – CONSTRUCTION PHASE |
||||||||
S9.3.5 |
The new
structures associated with the Project, including those of the additional
conveyor systems, should be painted in a colour
scheme that complements the surrounding industrial setting of the existing
CPPS. |
New structures associated
with the Project |
Contractor |
|
ü |
|
|
- |
VISUAL – OPERATIONAL PHASE No mitigation measures are
required. |
Des=Design;
C=Construction; O=Operation; Dec=Decommissioning