3                                  Project Description

3.1                            The Project Site

Hei Ling Chau is an outlying island to the east of Lantau Island with an approximate total area of 1.9km2 (190 ha).  The entire island is currently under the management of the Correctional Services Department (CSD).  The facilities on the island include the Hei Ling Chau Correctional Institution, Hei Ling Chau Addiction Treatment Centre, Hei Ling Chau Addiction Treatment Centre (Annex) and Lai Sun Correctional Institution (see Figure 3.1a).  There are also other supporting facilities, including administration buildings, staff quarters, two helipads and a guard dog kennel.  The island is only accessible by marine transport and access is restricted.  Visitors normally land at the passenger ferry jetty at the north-western tip of the island.  There is also a berthing facility associated with the Hei Ling Chau Refuse Transfer Station.  A number of breakwaters have been constructed to the south-west of the island to form a typhoon shelter.  The island is served by a single-lane paved vehicular road connecting the various CSD facilities.

The proposed Project Site is located on relatively level ground at an approximate elevation of +70mPD in the southern part of Hei Ling Chau.  Considering the potential height of the wind turbine (see Table 3.2a), the elevation of the wind turbine is expected to be about +160mPD.  The dimensions of the Project Site, including the construction lay down areas for the various components of the wind turbine system, are approximately 54m x 100m (see Figure 3.1b).  According to information provided by CSD and site observations, the Project Site is currently used for the temporary storage of construction materials and equipment.

The two helipads on the island are regularly used by the Government Flying Service (GFS) to support the operation of the CSD facilities.  The nearest helipad is located over 170m from the planned location for the wind turbine (see Figure 3.1b).  The helipad is used once a day on average.  The centre of the wind turbine tower will be located at least 150m away from the approach path and exit zone of the helipad.  The building height limit associated with the safe operation of the Hong Kong Airport at the Project Site is approximately +169 mPD, as per consultation with CAD.

3.2                            The Wind Turbine

The proposed wind turbine will be a three-bladed horizontal axis machine (Figure 3.2a illustrates a typical three-bladed horizontal axis wind turbine).  The main electrical and mechanical parts, including the gearbox, the generator with a rated capacity of between 800 kW to 1.3 MW and the yaw mechanism, will be housed in the nacelle, which is located on top of a tower.  The tower will likely be a tubular steel structure, but may be fabricated from other materials such as concrete ([1]).  The tower will stand upon a concrete base with approximate dimensions of 9 m x 9 m.

Figure 3.2a    A Typical 3-bladed Wind Turbine

The rotor blades capture the wind and transfer its power to the rotor hub, which is connected to the electrical generator via the gearbox.  The electrical power generated is transmitted via a step-up transformer to a substation, from where the power is fed into the nearest existing 11 kV power grid through overhead or underground transmission cables (see Figure 3.1b).  A summary of the general wind turbine specification is presented in Table 3.2a.

Table 3.2a      A Summary of the General Wind Turbine Specification

Parameter

General Specification

Type

3-bladed horizontal axis machine

Rated Capacity

800kW – 1.3 MW, 50 Hz, 690 V

Grid Connection

11 kV

Power Regulation

Stall or pitch control

Design Lifetime

20 years

Size of Rotor Blade

Up to 30m length, 5 tonnes weight (assembled 3-bladed rotor weighs up to 21.5 tonnes)

Blade Rotating Speed

14 – 31 rpm

Size of Nacelle

Up to 12m (l) x 4.5m (h) x 3.6m (w), 43 tonnes in weight

Size of Tower

Up to 60m height (in 3 sections, vary from about 17m to 23m each) and up to 42 tonnes each in weight)

Overall Size of Wind Turbine

Up to about 90m tip height

Ground Level of the Base of the Tower

About + 70 mPD

Hub Height

About +130 mPD

Tip Blade Height

About +160 mPD

3.3                            Construction of the Project

The major construction activities for the Project will include upgrading some sections of existing roads and creation of temporary access for the delivery of construction materials and equipment, formation of the platform for the erection of the tower, construction of the tower foundation, erection of the tower, installation of the nacelle and rotor and installation of the control and transmission systems.

Two access routes have been identified for the delivery of construction materials and equipment to the Project Site (see Figure 3.3a).  The first route, the long access route, makes use of the existing heavy load berthing facilities and road system.  The route will take the northern part of the existing loop route and follow the existing alignment to the Project Site.  Minor enabling works including utility diversions, removal of structures blocking the transport route, signs and street furniture, and minor road widening, and minor slope works will be required at a few locations to facilitate vehicle passage (see Figures 3.3b to 3.3e).  The long access route will be used for the delivery of the following major plant items and construction materials to the Project Site.

·        Self-propelled transporter (1 unit, for transportation of the crawler crane from the existing pier to the Project Site and temporary bridge of the short access route);

·        Crawler crane (1 to 2 unit(s), to be disassembled into smaller components and transported by the self-propelled transporter and assembled on site using a 55-tonne mobile crane);

·        55-tonne mobile crane (2 units, for assemble of the crawler crane);

·        Flat-bed truck (1 to 2 unit(s));

·        Concrete pump truck (1 unit);

·        Piling plant (1 unit) and pile casing (to be transported by flat bed truck);

·        Concrete wagons;

·        Dump truck (1 unit);

·        Site cabins (to be transported by flat bed truck);

·        Compactor (1 unit, to be transported by flat bed truck);

·        Excavator (1 unit, to be transported by flat bed truck); and

·        Soil-nailing plant (1 unit, to be transported by flat bed truck).

The large construction plant will be delivered to the existing heavy load berthing facility at the northern part of the island by flat top barge with a large capacity derrick crane.  The small construction materials and plant items will be delivered to the pier using a derrick lighter.  A clear water depth at high tide of around 2.5 to 3m will be required.  A hydrographical survey has been carried out at the existing berthing facility and has confirmed that there is sufficient water depth and hence no dredging of the approach channel and the berthing area will be required (see Figures 2.4a and 2.4c).  

Due to the size and weight of the wind turbine components (including the blades, nacelle and steel tower sections), the transportation of these components using the long access route will require significant road upgrading works (including major slope works) at many locations.  An alternative route, the short access route, will therefore be used to transport these components to the Project Site.  The turbine components will be delivered by a flat bed barge with an attendant crane and moored off-shore, adjacent to the existing pier at the southern part of the island within the typhoon shelter.  The barge will require a clear water depth of 2m.  A hydrographical survey has been carried out in the area and confirmed that there is sufficient water depth and hence no dredging will be required (see Figures 2.4b and 2.4c).   

The short access route (see Figure 3.3a) will involve the construction of a temporary steel platform at the existing jetty in the south-western part of the island and temporary steel bridge structure (see Figure 3.3f).   The temporary platform will be constructed above the high tide level and no marine works will be required.  The wind turbine components (including the blades, nacelle, and steel tower sections) will be lifted from the barge to the temporary steel platform using a floating crane.  The components will be lifted to the deck of the temporary bridge by the crawler crane and then transported by the self-propelled transporter to the Project Site along the existing road.  Minor widening or slope trimming may be required at certain locations of the short access route for the passage of long vehicles delivering the wind turbine components (see Figures 3.3a and 3.3g). 

The Project Site (see Figure 3.1b) will occupy an approximate area of 54m x 100m, including the lay down areas for construction materials and wind turbine components.  It is currently anticipated that only minor site clearance and formation will be required.  The engineering design indicates that the materials underneath the Project Site comprise poor quality fill overlying rock.  A reinforced concrete foundation with pre-bored H-piles will be required for supporting the wind turbine.

The main construction activities at the Project Site are:

·        site clearance and formation;

·        pre-bored H-piling and construction of reinforced concrete foundation (about 9m x 9m x 2m) for the wind turbine;

·        erection of wind turbine tower by assembling pre-fabricated steel tower sections;

·        installation of nacelle and rotor blades using the cranes;

·        installation of step up transformer and substation;

·        installation of transmission cables between the substation and the 11 kV supply grid; and

·        testing and commissioning of the wind turbine system.

3.3.1                      Operation of the Project

The operation of the wind turbine, including start-up and shut-down, will be automatic.  It will produce electricity when the wind speeds are in the range of 3 to 25 m s-1.  The wind turbine brakes by full feathering of the blades.  The blades of the wind turbine will be locked automatically when the wind speed is above 25 m s-1 to avoid damage. 

The wind turbine will be unmanned and attendance by operational personnel will only be required during emergencies or routine maintenance.  All functions of the wind turbine will be monitored and controlled remotely at the control room of one of CAPCO’s power stations or CLP’s sub-stations.  Users with appropriate access rights can send a Stop, Pause, Start or Reset command to the turbine using the remote control system.

3.4                            Planning and Implementation Programme

The Project will be planned and implemented by CAPCO together with consultants and contractors.  Subject to the review of the wind turbine feasibility assessment results and ongoing regulatory discussions with the HKSAR government (**), the current envisaged key stages of the Project are presented in Table 3.4a.

Table 3.4a      Proposed Project Programme

Key Stage of the Project

Indicative Date

EIA and Permitting

Q2-Q4, 2006

Project construction **

2007

Operation of the wind turbine **

2008

3.5                            Concurrent Projects

At present there are no planned projects to be constructed in sufficient proximity to the Project Sites to cause cumulative environmental impacts.



 

([1])     If a concrete tower (constructed using pre-fabricated reinforced concrete rings) is used, it will be wider than a steel tower by around 1m over the full height.