4                                  Noise

4.1                            Introduction

This Section assesses the potential noise impacts associated with the construction and operation of the Project.

4.2                            Relevant Legislation and Guidelines

4.2.1                      Construction Noise

The principal legislation relating to the control of construction noise is the Noise Control Ordinance (Cap. 400) (NCO).  Various Technical Memoranda (TMs), which stipulate control approaches and criteria, have been issued under the NCO.  The following TMs are applicable to the control of noise impacts from construction activities:

·           Technical Memorandum on Noise from Percussive Piling (PP-TM);

·           Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM); and

·           Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM).

The Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) also provides means to assess construction noise impacts.  The Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), issued under the EIAO, provides guidelines and noise criteria for evaluating construction noise impacts.

General Construction Works

Under the EIAO, potential noise impact arising from general construction works during normal working hours (ie 07:00 to 19:00 hrs on any day not being a Sunday or public holiday) at the openable windows of buildings is to be assessed in accordance with the noise criteria specified in the EIAO-TM.  The EIAO-TM noise standards are presented in Table 4.2a.

Table 4.2a      EIAO-TM Day-time Construction Noise Standard (Leq, 30 min dB(A))

When assessing a Construction Noise Permit (CNP) application for the use of Powered Mechanical Equipment (PME) during the restricted hours, the Noise Control Authority will compare the Acceptable Noise Levels (ANLs), as promulgated in GW-TM, and the Corrected Noise Levels (CNLs) (ie after accounting for factors such as barrier effects and reflections) associated with the proposed PME operations.  The ANLs are related to the noise sensitivity of the area in question and different Area Sensitivity Ratings (ASR) have been established to reflect the background characteristics of different areas.  The appropriate ASR for the Noise Sensitive Receiver (NSR) is determined with reference to Table 4.2b.

Table 4.2b      Area Sensitivity Ratings

The relevant ANLs are shown in Table 4.2c.

Table 4.2c  Acceptable Noise Levels (ANL, Leq, 5 min dB(A))

As the Project Site is located in a rural area and no influencing factors affect the NSRs, an ASR of “A” has been assigned. 

The Noise Control Authority will consider a well-justified CNP application,  for construction works within restricted hours as guided by the relevant Technical Memorandum issued under the NCO.  The Noise Control Authority will take into account adjoining land uses and any previous complaints against construction activities at the site before making a decision.  Nothing in this EIA Report shall bind the Noise Control Authority in making its decision.  The Noise Control Authority may include any conditions in a CNP that it considers appropriate.  Failure to comply with any such conditions may lead to cancellation of the CNP and prosecution action under the NCO.

4.2.2                      Operational Noise

The EIAO-TM and Technical Memorandum on Noise From Places Other than Domestic Premises, Public Places or Construction Sites (IND-TM) specifies the applicable ANLs for the operation of the Project.  The ANLs are dependent on the ASR and the time of the day and are presented in Table 4.2d.

Table 4.2d ANLs to be used as Operation Noise Criteria

Fixed Plant Noise

Fixed plant noise is controlled under Section 13 of the NCO and the predictions will be undertaken in accordance with the IND-TM.  The noise criteria for planning and design of Designated Projects are set out in the EIAO-TM as follows:

·           the noise level at the facade of the nearest NSR is at least 5 dB(A) lower than the appropriate ANL (as shown in Table 4.2d) as specified in the IND-TM; or,

·           the prevailing background noise level (for quiet areas with a noise level 5 dB(A) below the appropriate ANL). 

The noise criteria stipulated in the IND-TM are also dependent on the ASR of the NSR, as shown in Table 4.2d.

As the Project Site is located in a rural area and no influencing factors affect the NSRs, an ASR of “A” has been assigned.  Background noise measurement has been conducted to investigate the prevailing noise level in the Study Area.  A 24-hour continuous measurement of prevailing free field noise levels in the vicinity of Hei Ling Chau Correctional Institution (N1) gave levels in the range 42 to 56 dB(A) LAeq, 30min.  With the inclusion of façade correction, the measured prevailing noise level will be equal to the (ANL – 5) criterion, and therefore the (ANL – 5) criterion, ie 45 dB(A) LAeq, 30min for night-time period will be considered as the stipulated noise limit for the assessment of operational noise impact.  Details of the background noise measurements are provided in Section 4.3.3.

4.3                            Baseline Environmental Conditions and Noise Sensitive Receivers

4.3.1                           Baseline Environmental Conditions

The proposed wind turbine will be located at the southern side of Hei Ling Chau.  An associated temporary steel platform and bridge will be located at the south-western part of the island.  The Study Area is rural in nature and is characterised by the low-rise buildings of the Correctional Institution and Addiction Treatment Centre.  Background noise levels are typical of a general rural environment and there are limited numbers of vehicles or noisy plant items within the Study Area.  The major noise sources are identified as the noise from the Correctional Institution and Addiction Treatment Centre, the traffic noise within the island and noise from passing marine vessels.

4.3.2                      Noise Sensitive Receivers

The nearest NSRs are the Hei Ling Chau Correctional Institution (N1) and Hei Ling Chau Addiction Treatment Centre (Annex) (N2), which are located at about 740m and 380m away from the Project Site, respectively (see Figure 4.3a).  The nearest NSR that may be affected by the enabling works along the long access route has been identified as the Staff Quarters (N3) ([1]) (see Figure 4.3a).  For other locations along the long access route, there is either no NSR within a 300m radius or those that are presented are screened by non-sensitive air-conditioned administration buildings.  The natural terrain between the NSRs (N1 and N2) and the Project Site will act as a barrier and reduce the potential construction and operational noise impacts.  Terrain profiles between the NSRs (N1 and N2) and the Project Site are presented in Annex A1.  The separation distances between the NSRs and the Project Site are summarised in Table 4.3a.  No planned NSR is identified within 2 km of the Project Site. 

Table 4.3a      Identified Noise Sensitive Receivers

4.3.3                      Baseline Noise Measurement

To investigate the prevailing noise levels at Hei Ling Chau, noise measurements were made from 6 to 7 June 2006 at the boundary of Hei Ling Chau Correctional Institution (N1).  The noise measurements were conducted using a SVAN 949 Sound Level Meter (Type 1), calibrated using a SVAN Sound Level Calibrator Type 4231 with a calibration signal of 94.0 dB(A) at 1kHz.  The measurements were conducted with reference to the calibration and measurement procedures stated in the IND-TM. 

As the background noise at Hei Ling Chau is generally low, the baseline noise measurement represents the typical acoustic environment in the vicinity of the NSRs.  The measurement results are summarised in Table 4.3b.  Since the microphone was set in the free field measurement mode, an appropriate façade correction of 3dB(A) has been applied to the noise measurement results.  The timeline chart showing the prevailing noise levels at N1 is presented in Figure 4.3b. 

Table 4.3b      Measured Prevailing Noise Levels (with 3dB(A) Façade Correction)

The measured noise levels at NSR N2 are in the range of 51 – 54dB(A) Leq, 30min during daytime, which are similar to the noise levels measured at NSR N1.  It is anticipated that the background noise levels at NSR N2 during night-time will be similar to that measured at NSR N1 due to the similar environment on the island.

4.4                            Potential Sources of Impact

4.4.1                      Construction Phase

The main construction activities associated with the Project with the potential to cause noise impacts to the identified NSRs are as follows:

·           Construction of the temporary steel platform and bridge at the short access route – transportation of plant and equipment, rock breaking, micro-piling, excavation, soil nailing, concreting, erection of the temporary bridge and transportation of wind turbine components;

·           Enabling works along the long access route – minor road widening and slope works at some sections of the existing road; and

·           Construction works at wind turbine site – site formation and erection of wind turbine.

The construction works for the temporary steel platform and bridge at the short access route and at the Project Site will be carried out in phases without overlapping in accordance with the proposed construction work programme.  As per the proposed construction programme, there will be about 1 to 2 vehicles passing through the long and short access routes per hour. 

 

The construction noise assessment was undertaken based on the proposed construction work programme and plant inventory presented in Annex A2 and Figures 3.1b, 3.3a to 3.3g.  The plant inventory has been reviewed by the Design Engineer and is confirmed to be suitable for completing the Project within the scheduled timeframe.

The normal working hours of the contractor will be between 07:00 and 19:00 hours from Monday to Saturday (except public holidays).  Construction activities during restricted hours are not expected.  Should evening and night works between 19:00 and 07:00 hours or on public holidays (including Sundays) be required, the contractor will submit a CNP application which will be assessed by the Noise Control Authority.  Conditions stipulated in CNP will be strictly followed.

4.4.2                      Operational Phase

Sources of Wind Turbine Noise

The sources of noise emitted from the operating the wind turbine include the rotation of mechanical and electrical equipment and aerodynamic noise originating from the flow of air around the blades.  The mechanical and electrical equipment that may have potential noise producing effects are the gearbox, transformer and generator.  The aerodynamic noise generally increases with increases in rotor speed. 

With reference to a published study ([2]), it is anticipated that vibration introduced by the wind turbine will not be a concern as the components of the wind turbine are attached in such a way that vibrations are either not transmitted or are damped.  Wind turbine manufactures use computer aided models for wind turbine design and fabrication to ensure that the vibration of different components does not interact to amplify noise.

It is now a standard practice for the wind turbine manufacturers to incorporate low-noise features into their standard products.  Sound insulation materials will be used in the nacelle to enclose the generator, shaft and gearbox so as to reduce the medium and high frequency noises.  The airfoil blades are purposely designed to reduce aerodynamic noise generated during wind turbine operation. 

For the proposed wind turbine, the use of a synchronous generator makes it possible to transfer the revolution of the wind turbine directly to the power generator without using a multiplying gear, which contributes to the elimination of noise caused by the gear and saving the labour needed for its maintenance. 

Wind Turbine Noise Source Term

The proposed wind turbine has a capacity of 800kW to 1.3MW, with a design maximum blade rotating speed of about 31 rpm (refer to Table 3.2a).  This design limits the noise generation, and hence it will also limit the noise impacts to the identified NSRs.  In addition, modern wind turbines have already incorporated many design features to reduce noise emissions.     

Information sourced from wind turbine suppliers indicates that the typical sound power level of a wind turbine with a capacity of 800kW to 1.3MW can be designed to 104 dB(A), inclusive of the rotation of mechanical parts, sound of electrical components and aerodynamic noise.

The sound power level of the proposed wind turbines covers the full range of operation, including start-up, shut-down, cut-in, cut-out, braking and yawing and the full range of wind speeds.  It is technically feasible and practicable to limit the operational noise level for a wind turbine to 104 dB(A) and with no tone, impulse and intermittency characteristics by applying standard plant design features (see Annex 3).  The tender specification of the Project will specify that the wind turbine will have a typical operational noise level of 104 dB(A) with no tonality, impulsiveness and intermittency characteristics.

In view of the above, an overall sound power level of 104 dB(A) with no tonal, impulse and intermittency characteristics has been assumed in the noise impact assessment. 

Description of Wind Turbine Operation

Normally the rotor speed of proposed wind turbine will vary from 14 to 31 rpm in the range of effective wind speed, ie 3 to 25 m s-1.  The rotors will reach the maximum speed when wind speed reaches about 10 to 15 m s-1 and thereafter remain at the same speed up to 25 m s-1.  With reference to a wind turbine model that is a suitable size for the Hei Ling Chau site, the noise level reaches maximum noise level of 104dB(A) at about 15 m s-1 (see Annex A3.3).  When the wind speed exceeds 25 m s-1, the wind turbine will cut-off, ie the rotating parts of the wind turbine including rotor, blades and shaft will all stop, and hence the wind turbine will not cause any mechanical noise.  With reference to the hourly wind speed data obtained from the Hong Kong Observatory at Cheung Chau Station for Year 2004, about 96% of the data were below 15 m s-1, in which 93% were below 10 m s-1.  It should also be noted that in high wind speeds exceeding 10 m s-1, the background noise generated by trees, shrubs, terrain and wind itself would gradually exceed and mask the wind turbine noise.  Therefore, an overall sound power level of 104 dB(A) has been adopted as the reasonable worst-case.

The anticipated sound power levels of the wind turbine in 1/3 octave bands are presented in Annex A3.1.

4.5                            Assessment Methodology

4.5.1                      Construction Phase

The construction noise impact assessment was undertaken in accordance with the procedures outlined in the GW-TM, which is issued under the NCO and the EIAO-TM.  The assessment methodology is summarised below.

·           Locate representative NSRs that may be affected by the Project;

·           Determine the plant teams for corresponding activities, based on the agreed plant inventory;

·           Assign sound power levels (SWLs) to the PME proposed based on the GW-TM or other sources;

·           Calculate the correction factors based on the distance between the NSRs and the notional noise source position of the work sites;

·           Apply corrections in the calculations, such as potential screening effects and acoustic reflection, if any; and

·           Predict the construction noise levels at NSRs in the absence of any mitigation measures.

The total SWL associated with each construction activity was based on an assumed plant inventory.  All PME are assumed to be stationary while performing the noisiest activity, such as loading/off-loading, lifting and rock breaking at different Notional Noise Sources attributed to various construction activities.  The notional source positions of the work sites were established in accordance with the procedures stated in the GW-TM.  As per the proposed construction programme, about 1 to 2 vehicles will pass through the long and short access routes per hour.  No adverse impact is anticipated due to vehicle movements along the access routes.  The potential noise impacts at NSRs were subsequently evaluated by comparing the predicted noise levels with the EIAO-TM day-time construction noise limits (Leq, 30min dB(A)), as outlined in Section 4.2.1.

4.5.2                      Operational Phase

The operational noise impact assessment was undertaken in accordance with the procedures outlined in the ISO 9613 ([3]) and IND-TM, which is issued under the NCO and the EIAO-TM.  The assessment took into account the distance attenuation, atmospheric absorption and corrections of tonality, impulsiveness and intermittency, if any, in accordance with the IND-TM. 

4.6                            Evaluation of Impacts

4.6.1                      Construction Phase

The source-to-NSR distances are presented in Table 4.6a.

Table 4.6a      Noise Sensitive Receivers and Horizontal Distance to Major Noise Sources

Based on existing topography, NSR N1 will not have direct line of sight to the Project Site.  Therefore, with reference to the GM-TM, a negative correction of 10 dB(A) has been included in the construction noise assessment. 

There will be some enabling works along some sections of the long access route, including slope cutting, erection of temporary platform and backfilling.  The nearest NSR (N3) that may be affected is located next to one of the enabling work areas along the route (see Figure 3.3c).  Due to the close proximity to the work area, practicable mitigation measures, including limiting the concurrent use of construction equipment, using quiet construction plant and noise barriers, are recommended to be implemented when works are undertaken near NSR N3.  Since the works area is very close to this NSR, it would be possible for the contractor to provide noise barrier in the form of site hoardings to achieve the screening effect, provided that the barriers have no openings or gaps ([4]).  The proposed barriers should be at least 3m high with a superficial surface density of at least 10 .  This would provide a minimum 10 dB(A) attenuation.  The contractor will ensure that the conditions of the hoardings are properly maintained throughout the construction period. 

As NSR N3 is located at more than 1.5km and 2km from the temporary steel platform and bridge at the short access route and the Project Site, respectively, it is anticipated that the construction works at these locations will have negligible noise impacts to NSR N3.  Similarly, the enabling works along the long access route will have negligible noise impacts to NSRs N1 and N2.

The predicted noise levels at NSRs N1 and N2 due to the construction works at the temporary steel platform and bridge and the Project Site comply with the stipulated criterion.  The predicted noise levels at NSR N3 (after the implementation of the recommended mitigation measures) due to the enabling works along the long access route range from 79 to 83 dB(A), which exceed the noise criterion by 4 to 8 dB(A).

Details of the noise calculations are presented in Annex A2.  A summary of the construction noise levels is presented in Table 4.6b.  As per the proposed construction programme, there will not be overlapping periods between construction activities. 

Table 4.6b      Predicted Construction Noise Levels at NSRs

The assessment indicates that the predicted noise levels will exceed the day-time construction noise criterion after the implementation of the recommended mitigation measures due to the close proximity of the NSR N3 to the works area.  Details of the residual construction noise impact associated with the enabling works along the long access route are summarised in Table 4.6c.  Erection of a full enclosure is considered not practicable due to the space constraints. 

Table 4.6c      Predicted Residual Noise Impacts at N3 (After Mitigation)

Due to the construction sequence, it is not possible that all the construction plant and equipment to be delivered or transported to the Project Site using the short access route (see Section 2).  Although residual impacts from the enabling works along the route are predicted, the period of exceedance is very short.  The works near the staff quarters will last for about a week only and the affected time is very short when compared with the overall construction programme of about 12 months. 

As confirmed on site, air-conditioners are provided for the NSR N3 and the quarter is not currently occupied.  CSD agreed not to arrange staff to stay at this quarter as far as possible when construction works are undertaken in the area.  CAPCO will inform CSD prior to the commencement of the construction works.  The noise impacts to the NSR N3 would be considered as low and acceptable in terms of the magnitude and the effects on health.  No long-term adverse impact is anticipated. 

It should be noted that the construction noise assessment presented above is based on a worst case scenario in which the construction plant are assumed to be operated continuously and simultaneously during each construction stage.  In reality, this scenario is unlikely to occur.  

As per the proposed construction programme, there will not be overlapping periods between each construction activities.  Therefore, cumulative noise impacts during the construction period will not be a concern.  Given that there will be residual impacts from the enabling works in the area of the long access route, mitigation measures as recommended in Section 4.7 should be implemented.

4.6.2                      Operational Phase

Based on the typical sound power level of 104 dB(A), the facade noise levels at the identified NSRs are predicted and summarised in Table 4.6d.  The predicted noise levels comply with both of the stipulated (ANL-5) daytime and night-time noise criteria of 55 dB(A) and 45 dB(A).  A 10 dB(A) screening effect has been taken into account for NSR N1 due to topography shielding and no direct line of sight to the whole swept area of the rotors (see Annex A1.1).  Some buildings in NSR N2 may have line of sight to a small part of the swept area of the blades but most part of the wind turbine will be screened off (see Annex A1.2).  Therefore, a 5 dB(A) attenuation was included in the calculation.  The terrain profiles presented in Annex A1 are derived from a Digital Elevation Model (DEM) based on the Land Information Centre (LIC) data obtained from the Lands Department.  Details of the noise calculations are presented in Annex A4.

Table 4.6d      Predicted Facade Noise Levels at NSRs

It should be noted that the assessment is conservative as a hemispherical propagation model has been assumed.  If spherical propagation is adopted, which is considered a feasible approach for a project with one wind turbine surrounded by soft ground, the noise level at the NSRs will be further reduced by 3 dB(A).  Also, based on the methodology outlined in the ISO 9613, the predicted noise levels are the maximum worst-case as the assessment has assumed 100% downwind propagation ([5]).  Graphical representations of the wind direction and wind speed prepared based on the hourly wind data obtained from the Hong Kong Observatory at Cheung Chau Station in Year 2004, and the wind monitoring data obtained from the on-site wind monitoring station are presented in Annex A5.  It is indicated that the prevailing wind propagation are from north and east.  In reality, NSRs N1 and N2 are not located along the downwind propagation paths as they are located to the north and north-west of the wind turbine, respectively.  Therefore, the actual noise levels perceived at the NSRs are expected to be lower than those shown in Table 4.6d. 

4.7                            Mitigation Measures

4.7.1                      Construction Phase

The contractor is required to adopt site specific direct technical measures as specified below for the enabling works along the long access route near NSR N3.

·           Avoid or reduce concurrent operation of construction equipment;

·           Use of quiet construction plant;

·           Use of site hoarding barriers with a minimum height of 3m.  In general, this would provide a minimum 10 dB(A) attenuation for the low-rise receivers.  The barriers should not have openings or gaps and have a superficial surface density of at least 10 kgm-2.  The location and extent of the proposed barrier are shown in Figure 4.7a;

·           As a last resort, indirect mitigation measures in the form of window insulation and air-conditioning (air-conditioners have been provided for the staff quarters) are recommended to mitigate the residual noise impact.  In general, this would provide a minimum 10 dB(A) attenuation for the receivers. 

·           After consultation with CSD, agreed mitigation measures would be implemented (eg the use of air-conditioners and avoidance of use of the affected staff quarter during the period when works are undertaking in the area).  The Contractor will closely liaise with the CSD to programme the noisy construction works such that the noise impact to the CSD staff will be avoided or reduced.  Prior to commencement of the construction, CSD will be notified with the programme of the works, the planned construction activities, the potential impacts to the Staff Quarters, the measures to mitigate the impacts, the monitoring programme to check the efficiency of the measures, and the communication channels between CSD and the Site Engineer.

4.7.2                      Operation Phase

Noise reduction methods for wind turbines include special finishing of gear teeth, using low speed cooling fans and adding baffles and acoustic insulation to the nacelle.  The detailed methods to be employed vary from supplier to supplier.  It is practicable and achievable to reduce the wind turbine with typical sound power level to 104 dB(A) during the detailed design stage of the wind turbine.

The noise assessment indicates that under the worst-case scenario (covering a full range of operation including start-up, shut-down, cut-in, cut-out, braking and yawing; and the full range of wind speeds), with a wind turbine with typical sound power level of 104 dB(A) and with no tone, impulse and intermittence characteristics, the predicted facade noise levels at the identified NSRs will comply with the day-time and night-time noise limits at all NSRs.

4.8                            Environmental Monitoring and Audit

4.8.1                      Construction Phase

Noise monitoring is recommended during the construction phase to ensure the compliance to acceptable noise levels at the identified NSRs.  Noise monitoring will be undertaken at two locations, Hei Ling Chau Addiction Treatment Centre (Annex) (N2) and Staff Quarters (N3) ([6]), and at a frequency of once a week.  Regular site audits (ie once a month) will be conducted to ensure that the proposed mitigation measures are implemented properly and that the plant inventory used on site is consistent with the assumptions used in the EIA Report. 

4.8.2                      Operation Phase

During the operation phase, noise monitoring will be undertaken at the nearest NSR (ie Hei Ling Chau Addiction Treatment Centre (Annex) (N2)) during the night-time period at the agreed monitoring location to ensure the compliance with the stipulated noise criterion.  As wind speed will vary throughout the year and hence the potential noise impacts, it is recommended to monitor noise levels at monthly intervals for the first 12 months of the operation of the wind turbine.   The monitoring frequency will increase to biweekly intervals during the higher wind speed months (ie winter months - from December to January), and storm season – (July) within the first 12-month monitoring period.

4.9                            Conclusion

No adverse construction phase noise impacts are predicted at NSRs N1 and N2.  The mitigated construction noise activities for the enabling works along the long access route near the CSD’s Staff Quarters (N3) would cause a temporary exceedance of the day-time construction noise criterion.  Mitigation measures have been recommended.

The tender specification of the Project will specify that the wind turbine will have a typical sound power level of 104 dB(A) with no tonality, impulsiveness and intermittency characteristics.  For a wind turbine with a typical sound power level of 104 dB(A), the consequent predicted facade noise levels will comply with the day-time and night-time noise limits at all NSRs.  Noise monitoring for the first 12 months of operation of the wind turbine is recommended to ensure compliance with the stipulated noise limits.

 



 

([1])     It is a bungalow type accommodation not designed for family units.  Site visit indicated that the quarter has not been occupied for sometime.

([2])     Wind Turbine Issues, March 2004.  A White Paper prepared by the Renewable Energy Research Laboratory, Centre for Energy Efficiency and Renewable Energy Department of Mechanical and Industrial Engineering, University of Massachusetts at Amherst.

([3])     ISO 9613 Acoustics - Attenuation of Sound during Propagation Outdoors.

([4])    If CSD could arrange not to use this staff quarter during the construction period, there will be no noise impact to this NSR. It will not be necessary to provide a noise barrier at this location.

([5])    Various combinations of temperature and relevant humidity applicable to Hong Kong climate has been assessed for atmospheric adsorption of noise and the worst case scenario (ie at 30oC and relative humidity of 100%) has been adopted in the assessment.  Please see Annex A4.3 for details.

([6])    If CSD could arrange not to use this staff quarter (NSR N3), there will be no potential noise impact to this NSR.  Noise monitoring will not be required at this location.