A1.1
Introduction
This Annex summarises all the
mitigation measures recommended in the EIA
Study and presents them in the form of an Implementation Schedule in
accordance with the requirements of Section 3.4.9.3 of the EIA Study Brief No. ESB-145/2006.
The Implementation Schedule has the following column headings:
EIA
Ref
This denotes the section number or reference from the EIA Report Main
text.
EM&A Ref
This denotes the sequential number of each of the recommended mitigation
measures specified in the Implementation Schedule.
Recommended
Mitigation Measures
This denotes the recommended mitigation measures, courses of action or
subsequent deliverables that are to be adopted, undertaken or delivered to
avoid, reduce or ameliorate predicted environmental impacts.
Objectives
of the Recommended Measure and Main Concerns to be Addressed
This denotes the objectives of the recommended mitigation measures and
main concerns to address.
Location/Duration
of Measures/Timing of Completion of Measures
This indicates the spatial area in which the recommended mitigation
measures are to be implemented together with details of the programming or
timing of their implementation.
Implementation Agent
This denotes where the responsibility lies
for the implementation of the recommended mitigation measures.
Implementation Stage
This denotes the stage at which the
recommended mitigation measures are to be implemented either during the Design,
Construction, Operation or Decommissioning phases.
Relevant
Legislation
This defines the controlling legislation that is required to be complied
with.
Table A1.1a Implementation Schedule
EIA Ref. |
EM&A
Ref |
Environmental
Protection Measures |
Objectives
of the Recommended Measure & Main Concerns to address |
Location/Duration
of Measures/Timing of Completion of Measures |
Implementation
Agent |
Implementation Stage |
Relevant
Legislation Guidelines |
|||
Des |
C |
O |
Dec |
|||||||
Noise – Construction Phase |
|
|
|
|
|
|
|
|
||
4.7.1 |
1 |
·
Avoid or reduce concurrent operation of
construction equipment; ·
Use of quiet construction plant; ·
Use of site hoarding barriers ([1]) with a minimum
height of 3m. In general, this would
provide a minimum 10 dB(A) attenuation for the
low-rise receivers. The barriers
should not have openings or gaps and have a superficial surface density of at least 10 kgm-2. The location and extent of the proposed
barrier are shown in Figure 4.7a; ·
As a last resort, indirect mitigation
measures in the form of window insulation and air-conditioning
(air-conditioners have been provided for the staff quarters) are recommended
to mitigate the residual noise impact.
In general, this would provide a minimum 10 dB(A)
attenuation for the receivers. |
To minimise potential
noise nuisance arising from the enabling works to CSD’s Staff Quarters
(NSR N3). |
During
construction of enabling works near CSD’s Staff
Quarters (NSR N3) |
Construction
contractor |
|
ü |
|
|
Noise Control Ordinance (NCO) and Annex 5 of the EIAO-TM |
|
|
·
Close liaison with the CSD to programme
the noisy construction works. Prior to
commencement of the construction, CSD will be notified with the programme of the
works, the planned construction activities, the potential impacts to the
Staff Quarters, the measures to mitigate the impacts, the monitoring
programme to check the efficiency of the measures, and the communication
channels between CSD and the Site Engineer. |
|
|
|
|
|
|
|
|
Noise –
Operational Phase |
|
|
|
|
|
|
|
|
||
4.7.2 |
2 |
A wind turbine with typical sound power
level of 104 dB(A) with no tone, impulse and intermittence characteristics
shall be adopted. |
To minimise potential noise nuisance arising from
operation of wind turbine. |
During detailed design stage |
CAPCO |
ü |
|
ü |
|
Noise Control
Ordinance (NCO) and Annex 5 of the EIAO-TM |
4.8.2 |
3 |
During the operation phase, noise monitoring will
be undertaken at the nearest NSR (ie Hei Ling Chau Addiction Treatment Centre
(Annex) (N2)) during the
night-time period at the agreed monitoring location to ensure the compliance
with the stipulated noise criterion.
As wind speed will vary throughout the year and hence the potential
noise impact. It is recommended to
monitor the noise levels at monthly intervals for first 12 months of the
operation of the wind turbine. The monitoring
frequency will be increased to biweekly intervals for the higher wind speed
months (ie winter months (from December to January)
and storm season (July)). |
To ensure that adverse environmental
impacts are prevented |
At NSR N2 for the first 12 months of
operation of the wind turbine |
CAPCO |
|
|
ü |
|
|
Ecology – Construction Phase |
|
|
|
|
|
|
|
|
||
5.10.2 |
4 |
To mimimise the loss of Common Rat Snake
and Bodagek’s Burrowing Lizard due to the
development of wind turbine, a search of the Common Rat Snake and Bodagek’s Burrowing Lizard within the Project Site and
along the impacted sections of the Long and Short Access Routes will be
conducted prior to the commencement of the construction works. Due to the small size of the Project Site
and given that there are no optimal habitats for Common Rat Snake and Bodagek’s Burrowing Lizard, one day-time survey is
considered sufficient. The impacted
areas will be actively searched with special attention to the leave litters
and rocks. All recorded Common Rat
Snake and Bodagek’s Burrowing Lizard will be caught
by hand and translocated to the shrubland
at the north of the Hei Ling Chau
Correctional Centre (Annex), which is the less disturbed shrubland
habitat within the Study Area, immediately after the search. The search and the translocation (if
required) will be undertaken by a qualified ecologist with relevant
experience in faunal translocation works. |
To mimimise the
loss of Common Rat Snake and Bodagek’s Burrowing
Lizard (if any) due to the development of wind turbine |
Prior to
commencement of construction work |
Construction
contractor |
ü |
|
|
|
Annex 16 of the EIAO-TM
|
5.10.2 |
5 |
Construction Runoff: Storm water run-off from the construction
sites will be directed into existing drainage channel via adequately designed
sand/silt removal facilities such as sand traps, silt traps and sediment
basins. Channels, earth bunds or sand
bag barriers will be provided on site to properly direct storm water to such
silt removal facilities. |
To
minimise potential ecological impacts arising from the works. |
During
construction phase for all construction work sites |
Construction
contractor |
|
ü |
|
|
Annex 16 of the EIAO-TM |
5.10.2 |
6 |
Good Construction
Practice: ·
Erect fences along the boundary of the
Project Site before the commencement of works to prevent vehicle movements,
and encroachment of personnel, onto adjacent areas; ·
Regularly check the work site boundaries
to ensure that they are not breached and that damage does not occur to
surrounding areas; and, ·
Reinstate temporary impacted area,
immediately after completion of construction works. |
To minimise potential ecological
impacts arising from the works. |
During construction phase |
Construction contractor |
|
ü |
|
|
Annex 16 of the EIAO-TM |
5.10.3 |
7 |
Some trees within the work areas of the proposed road
upgrading works may need to be removed during construction. The actual number of trees affected will be
determined in the Tree Survey during the detailed design. The impacted trees will either be
transplanted or compensated by tree planting along the access routes or
within the Project Site. |
To compensate for the trees removed due
to the construction works. |
During construction phase |
Construction contractor |
|
ü |
|
|
Annex 16 of the EIAO-TM |
Ecology – Operational Phase |
|
|
|
|
|
|
|
|
||
5.12.2 |
8 |
During the operation
of the wind turbine, bird collision monitoring will be undertaken at monthly
intervals for a period of 12 months.
An area of 50m radius will be searched around the base of the wind
turbine. If, after the 12-months monitoring period,
insignificant number of bird collisions have been reported then the
monitoring will be ceased. |
To minimise
the ecological impacts arising from the works |
Project Site/12 months from the
commencement of operation phase and until no bird
collisions have been reported |
CAPCO |
|
|
ü |
|
Annex 16 of the EIAO-TM |
Landscape and Visual – Construction
Phase |
|
|
|
|
|
|
|
|
||
6.4.8 |
9 |
Landscape
Mitigation Measures: ·
LMM 1 – Cultivation of areas impacted
during construction. Areas
impacted during the construction phase that are not required during the
operation phase, are to be cultivated to a depth of 300mm. |
To
minimise the impact on the Landscape Resources (LRs). |
Impacted
area during construction phase |
Construction
contractor |
|
ü |
|
|
Annexes 10 and 18
of EIAO-TM and EIAO Guidance Note 8/2002 |
|
|
·
LMM 2 – Soil stabilisation and embankment
planting. During the design process a soil stabilisation and embankment
planting strategy will ensure that all land affected by slope excavation can
be replanted, wherever practicable.
All soil preparation and the selection and provision of suitable
growing medium is to be completed in accordance with the relevant best
practice guidelines. |
To
minimise the impact on the LRs. |
Enabling
works area and Project Site/ during detailed design phase |
CAPCO/
Construction contractor |
ü |
ü |
|
|
Annexes 10 and 18
of EIAO-TM and EIAO Guidance Note 8/2002 |
|
|
·
LMM 3 – Tree and shrub planting. All planting of trees and shrubs is to be
carried out in accordance with the relevant best practice guidelines. Plant densities are to be provided in
future detailed design documents and are to be selected so as to achieve a
finished landscape that matches the surrounding, undisturbed, equivalent
landscape types. |
To minimise the impact on the LRs. |
Enabling works area and Project Site
/during construction |
Construction contractor |
|
ü |
|
|
Annexes 10 and 18 of EIAO-TM and EIAO Guidance
Note 8/2002 |
6.4.10 |
10 |
There will be moderate to significant visual impact
from the VSR of Hei Ling Chau
among the eleven VSRs. Although the visual impact is unable to
mitigate practically, the adverse effects are not considered too excessive in
view of the size of landtake and form of the
structure. Hence, the visual impact is
not unacceptable. There are no
significant visual impacts for other VSRs and there
will be no interference with key views.
Therefore, the landscape and visual impacts will be acceptable. |
|
|
|
|
|
|
|
|
Landscape and Visual – Operational
Phase |
|
|
|
|
|
|
|
|
||
6.4.8
& 6.4.10 |
11 |
The impacts on landscape resource will mainly be
associated with the construction phase.
With the implementation of the recommended landscape mitigation
measures, the long term impacts of the Project on landscape resource of Hei Ling Chau will be negligible. The Project Proponent will maintain the
landscape mitigation measures (see EM&A Ref. Item no. 9) during the
operation phase. |
To
minimise the impact on the LRs. |
Enabling
works area and Project Site /during operation |
CAPCO |
|
|
|
ü |
Annexes 10 and 18
of EIAO-TM and EIAO Guidance Note 8/2002 |
6.5.15 |
12 |
There will be moderate to significant visual impact
from the VSR of Hei Ling Chau
among the eleven VSRs. Although the visual impact is unable to
mitigate practically, the adverse effects are not considered too excessive in
view of the size of landtake and form of the
structure. Hence, the visual impact is
not unacceptable. There are no
significant visual impacts for other VSRs and there
will be no interference with key views.
Therefore, the landscape and visual impacts will be acceptable. |
|
|
|
|
|
|
|
|
Water
Quality – Construction Phase |
|
|
|
|
|
|
|
|
||
7.5.1 |
13 |
Establishment of a drainage
management plan |
To ensure discharges from the Project Site
drainage system in compliance with the Water
Pollution Control Ordinance. |
Project
Site and associated enabling works/during construction phase |
Construction
contractor |
ü |
|
|
|
Water
Pollution Control Ordinance |
7.6.1 |
14 |
Construction Runoff and Drainage ·
Provision of perimeter channels to
intercept stormwater run-off from outside the
site. These will be constructed prior
to the site formation works and other earthworks at the Project Site. |
To minimise potential water quality
impacts arising from the construction works |
All
construction works areas/ during construction phase |
Construction
contractor |
ü |
|
|
|
EPD Practice Note for Professional Persons, Construction
Site Drainage (ProPECC PN 1/94) |
|
|
·
Exposed soil surfaces will be covered by
a tarpaulin as soon as possible to reduce the potential for soil erosion. |
|
|
|
|
ü |
|
|
|
|
|
·
Open stockpiles of construction materials
on site will be covered with tarpaulin or similar fabric during rainstorms. |
|
|
|
|
ü |
|
|
|
|
|
·
Storm water run-off from the construction
site will be directed into an existing stream channel via adequately designed
sand/silt removal facilities such as sand traps, silt traps and sediment
basins. Channels, earth bunds or sand
bag barriers will be provided on site to properly direct storm water to such
silt removal facilities. |
|
|
|
ü |
ü |
|
|
|
|
|
·
Silt removal facilities, channels and
manholes will be maintained and the deposited silt and grit will be removed
regularly, at the onset of and after each rainstorm to ensure that these
facilities are functioning properly at all times. |
|
|
|
|
ü |
|
|
|
|
|
·
During excavation in the wet season,
temporarily exposed soil surfaces will be covered, eg
by tarpaulin, and temporary access roads will be protected by crushed stone
or gravel, as excavation proceeds.
Intercepting channels will be provided (eg
along the crest/edge of the excavation) to prevent storm runoff from washing
across exposed soil surfaces.
Arrangements will always be in place to ensure that adequate surface
protection measures can be safely carried out well before the arrival of a
rainstorm. |
|
|
|
|
ü |
|
|
|
|
|
·
Earthworks final surfaces will be well
compacted and the subsequent permanent work or surface protection will be
carried out as soon as practical after the final surface are formed to
prevent erosion caused by rainstorms.
Appropriate intercepting channels will be provided, where
necessary. Rainwater pumped out from
trenches or foundation excavations will be discharged into storm drains via
silt removal facilities. |
|
|
|
|
ü |
|
|
|
|
|
·
The contractor(s) concerned will apply
for and obtain all the necessary discharge licences. |
|
|
|
|
|
|
|
|
7.6.2 |
15 |
General Construction Activities ·
Debris and rubbish generated on-site will
be collected, handled and disposed of properly to avoid entering the nearby
storm water drains and open drainage channels. |
To minimise potential water quality
impacts arising from the construction works |
All construction
works areas/ during construction phase |
Construction
contractor |
|
ü |
|
|
EPD Practice Note for Professional Persons, Construction
Site Drainage (ProPECC PN 1/94) |
|
|
·
All fuel tanks and storage areas will be
provided with locks and be sited on sealed areas, within bunds of a capacity
equal to 110% of the storage capacity of the largest tank. |
|
|
|
|
ü |
|
|
|
|
|
·
Open storm water drains and culverts near
the works area will be covered to block the entrance of large items of debris
and refuse. |
|
|
|
|
ü |
|
|
|
7.6.3 |
16 |
Sewage from Workforce Portable chemical
toilet will be provided at the work areas.
A licensed contractor will be employed to collect and dispose the
sewage. |
To minimise potential water quality
impacts arising from the works |
Work
areas/ during construction |
Construction
contractor |
|
ü |
|
|
EPD Practice Note for Professional Persons, Construction
Site Drainage (ProPECC PN 1/94) |
7.8 |
17 |
·
To carry out monthly site audits to the
works areas to monitor the environmental performance of the Project and to enable
prompt actions to rectify any malpractice which may give rise to water
pollution problem. ·
To carry out ad-hoc visits to the
impacted sites in responses to any complaints or reported non-compliance on
water quality aspect. |
To minimise potential water quality
impacts arising from the works |
All work
areas /throughout construction phase |
Construction
contractor/ CAPCO |
|
ü |
|
|
|
Waste Management – Construction Phase |
|
|
|
|
|
|
|
|
||
8.5 |
18 |
All the necessary waste disposal permits are
obtained prior to the commencement of construction work. |
To ensure that adverse environmental impacts are
prevented |
Before
construction works commence |
Construction
contractor |
|
ü |
|
|
|
8.5.1 |
19 |
Construction Waste Wherever
practicable, the excavated soil will be segregated from other wastes to avoid
contamination and reused on-site for the site formation works to reduce the
amount of construction waste to be disposed off-site. The Contractor must ensure that no waste, spoil or
excavated materials arising from the Project will be improperly dumped in the
Hei Ling Chau Island, in
particular the environmental sensitive area/ecological habitat identified in
the Section 5 of the EIA report. |
To ensure that adverse environmental impacts are
prevented |
All work
areas /throughout construction phase |
Construction
contractor |
|
ü |
|
|
|
8.5.2 |
20 |
Chemical
Waste The construction contractor will be
registered as a chemical waste producer with the EPD. Chemical waste will be handled in
accordance with the Code of Practice on
the Packaging, Handling and Storage of Chemical Wastes. |
To ensure proper handling of chemical waste |
All work areas
/throughout construction phase |
Construction
contractor |
|
ü |
|
|
Code of Practice on the Packaging, Handling and Storage of
Chemical Wastes |
8.5.3 |
21 |
Management
of Waste Disposal The construction
contractor will open a billing account with the EPD in accordance with the Waste Disposal (Charges for Disposal of
Construction Waste) Regulation.
Every construction waste or public fill load to be transferred to the Hei Ling Chau Refuse Transfer
Station will produce a valid “chit”. A trip-ticket system will also be established in
accordance with Works Bureau Technical
Circular No.31/2004 to monitor the disposal of construction waste at the Hei Ling Chau Refuse Transfer
Station, and to control fly-tipping.
The trip-ticket system will be included as one of the contractual
requirements and implemented by the contractor. |
To ensure that adverse environmental impacts are
prevented |
All work
areas /throughout construction phase |
Construction
contractor |
|
ü |
|
|
Waste Disposal (Charges for Disposal of Construction
Waste) Regulation Works Bureau Technical Circular No.31/2004 |
8.5.4 |
22 |
Staff
Training At the
commencement of the construction works, training will be provided to workers
on the concepts of site cleanliness and on appropriate waste management
procedures, including waste reduction, reuse and recycling. |
To ensure that adverse environmental impacts are
prevented |
All work
areas /throughout construction phase |
Construction
contractor |
|
ü |
|
|
|
8.7 |
23 |
Environmental
Monitoring & Audit Requirements Monthly audits of the waste management practices
will be carried out during the construction phase to determine if wastes are
being managed in accordance with the good site practices described in this EIA Report. The audits examine all aspects of waste
management including waste generation, storage, recycling, transport and
disposal. |
To ensure that
adverse environmental impacts are prevented |
All work areas /throughout construction
phase |
Construction contractor |
|
ü |
|
|
|
Cultural Heritage – Construction Phase |
|
|
|
|
|
|
|
|
||
9.6 |
24 |
Since the Project will not impose any
direct or indirect impact on identified cultural heritage resources, no
mitigation measures are required. |
|
|
|
|
|
|
|
|
Cultural Heritage – Operational Phase |
|
|
|
|
|
|
|
|
||
9.6 |
25 |
Since the Project will not impose any
direct or indirect impact on identified cultural heritage resources, no
mitigation measures are required. |
|
|
|
|
|
|
|
|
(1)