8.                       LANDSCAPE AND VISUAL ASSESSMENT

 

8.1                   Introduction

 

8.1.1             This section summarises the findings of the landscape and visual impact assessment (LVIA) for the proposed Permanent Aviation Fuel Facility (PAFF) at Tuen Mun Area 38.

 

8.1.2             The purpose of the LVIA is as follows:

 

a.           to undertake detailed baseline review and impact assessment on the preferred location at Tuen Mun Area 38;

b.          identify key issues and potentially significant changes to the existing landscape and visual conditions that could result from the PAFF and associated facilities during construction and operation; and

c.           recommend mitigation measures in terms of reducing landscape and visual impacts.

 

8.2                   Principal Environmental Legislation and Guidelines

 

8.2.1             The methodology of the LVIA is based on Annexes 10 and 18 in the Hong Kong SAR Government's Technical Memorandum on the Environmental Impact Assessment Process (EIAO-TM) under the EIA Ordinance (Cap.499, S16), entitled "Criteria for Evaluating Visual and Landscape Impact" and "Guidelines for Landscape and Visual Impact Assessment", respectively and the EIAO Guidance Note No. 8/2002 “Preparation of Landscape and Visual Impact Assessment Under the Environmental Impact Assessment Ordinance.”

 

8.3                   Assessment Methodology

 

8.3.1             Background

 

8.3.1.1       The main components of the LVIA are as follows:

 

a.           Description of the proposed project

b.          baseline study of landscape and visual resources including a review of planning and development control framework;

c.           landscape impact assessment during construction and operation;

d.          visual impact assessment during construction and operation;

e.           recommendations for landscape and visual mitigation measures for both construction and operation stage; and

f.            assessment of residual impact and conclusion on the acceptability of the PAFF.

 

8.3.2             Baseline Landscape and Visual Resource Study

 

8.3.2.1       The baseline study identified and examined existing landscape and visual resources within the study area of the selected site at Tuen Mun Area 38. Under the study brief, the study area defined for the landscape impact assessment is approximately 500 metres out from the proposed works site boundary. The area for the visual impact assessment is defined by a visual envelope. This is generally the viewshed formed by natural/man-made features such as ridgeline and building blocks.

8.3.2.2       Landscape resources considered include topography, woodland, other vegetation, built forms, settlement patterns, land use, scenic spots and details of local streetscapes.  The baseline study describes the landscape resources by identifying broadly homogenous landscape character units (LCUs) of a similar character.  The landscape character was rated low, medium or high depending not only on the quality of elements present but also to its sensitivity to change and its importance at a local, district, regional or international level.  The mapping of the LCUs referred to Planning Department’s Landscape Character Map of Hong Kong and related descriptions on the Landscape Character Types (LCTs) to further assist an understanding of the baseline conditions. 

 

8.3.2.3       Visual resources considered were typical viewpoints located and directed towards the project.  A visual envelope has been established which defined the extent of visual influence of the project and, therefore, of the potential visual impacts. Definition of the extent of the viewshed was based on desktop study and site investigation. Sensitive visual receivers (SVRs) identified in this report are “representative” in that individuals or groups that have a similar sensitivity to changes in the visual and landscape environment are grouped together within a single SVR that can represent the whole group. (SVRs) are individuals or groups of who are sensitive to changes in the visual environment.  The Hong Kong Planning Standards & Guidelines, Chapter 9 Environment, defines sensitive uses as “land uses which, by virtue of the nature of the activities thereon are susceptible to the influence of residual or physical changes generated by polluting uses”.

 

8.3.3             Review of the Planning and Development Control Framework

 

8.3.3.1       A review of the planning and development control framework has been undertaken and this information has been mapped and analysed to provide an insight to the future outlook of the area affected and the way the Project would fit into its wider context.  The purpose of this planning and development control review is to give further insight into possible future sensitive uses and/or sensitive receivers that might be affected by the proposed project.

 

8.3.4             Landscape Impact Assessment

 

8.3.4.1       Impacts on the landscape and visual resources were assessed for both construction and operation stages. The impact assessments allow predictions to be made about the likely levels and significance of landscape and visual impacts.  The assessment of LANDSCAPE impacts will result from:

 

a.         the landscape character and its quality;

b.         the sensitivity of the landscape in accommodating change;

c.         source, nature and magnitude of impacts;

d.         the degree of change caused by the impacts to the existing landscape;

e.         significance of the change in consideration of the local and regional areas and other developments;

f.           cumulative effects with other proposals; and

g.         identification of vegetation of significant value which should be conserved.

 

8.3.4.2       The sensitivity / quality for landscape characters/resources are based on:

 

a.         quality of landscape characters/resources,

b.         importance and rarity of special landscape elements,

c.         ability of the landscape to accommodate change,

d.         significance of the change in local and regional context, and

e.         maturity of the landscape.

 

8.3.4.3       The sensitivity / quality of the landscape characters/resources will be assessed as follows:

 

a.         High: e.g. important components or landscape of particularly distinctive character susceptible to small changes;

b.         Medium: e.g. a landscape of moderately valued characteristics reasonably tolerant to change;

c.         Low: e.g. a relatively unimportant landscape, which is able to accommodate extensive change.

 

8.3.4.4       The magnitude of change of landscape characters/resources is based on:

 

a.         compatibility of the project with the surrounding landscape,

b.         duration of impacts under construction and operation phases,

c.         scale of development, and

d.         reversibility of change.

 

8.3.4.5       The magnitude of change in the landscape is as follows:

 

a.         Large – notable change in the landscape characteristics over an extensive area ranging to very intensive change over a more limited area;

b.         Intermediate – moderate changes to a local area;

c.         Small –changes to components; and

d.         Negligible – no perceptible changes.

 

8.3.4.6       The system for the assessment of landscape impact is summarised in Tables 8.1 and 8.2 below.  The significance threshold of landscape impact is derived from the combined analysis of the magnitude of change and the landscape’s quality and sensitivity to change.  The matrix in Table 8.1 indicates how the significance threshold is derived.  Table 8.2 explains the terms used in Table 8.1.  This analysis of the significance of threshold of landscape impact will apply in the majority of situations, however in certain cases a deviation may occur e.g. the impact may be so major that a significant impact may occur to a low quality element.

Table 8.1        Significance Threshold of Landscape Impact

Magnitude of Change

 

Sensitivity / Quality

 

Low

Medium

High

Large

Moderate Impact

Moderate / Significant Impact

Significant Impact

Intermediate

Slight /Moderate Impact

Moderate Impact

Moderate / Significant Impact

Small

Slight Impact

Slight / Moderate Impact

Moderate Impact

Negligible

Negligible

Negligible

Negligible

Table 8.2      Adverse / Beneficial Impacts of Landscape Impact

Significant:

Moderate:

Slight:

Negligible:

adverse / beneficial impact where the proposed project would cause significant degradation or improvement in existing landscape baseline conditions.

adverse / beneficial impact where the proposed project would cause noticeable degradation or improvement in existing landscape baseline conditions

adverse/beneficial impact where the proposed project would cause a barely noticeable degradation or improvement in existing landscape conditions or where the changes brought about by the project would not be apparent in visual terms

The proposed project does not perceptibly affect the existing landscape baseline conditions

 

8.3.5             Visual Impact Assessment

 

8.3.5.1       The assessment of potential VISUAL impacts will result from:

 

a.         the sensitivity of the viewer groups at SVR locations to change and visual intrusion; and

b.         the magnitude of change to the visual baseline condition.

 

8.3.5.2       The sensitivity of receivers is based on:

 

a.         value and quality of existing views,

b.         availability and amenity alternative views,

c.         type and estimated number of receiver population,

d.         duration or frequency of view, and

e.         degree of visibility.

      

8.3.5.3       The sensitivity of viewer groups at SVR locations will be classified as follows:

 

¨             High:

-            the nature of the viewer groups expects a high degree of control over their immediate environment, (e.g. people residing in their homes);

-            the viewer groups are in proximity to the project; and

-           the foreground and middle ground cannot visually absorb the Project.

-            

¨             Medium:

-           the nature of the viewer groups expects a high degree of control over their immediate environment, (e.g. people residing in their homes); but

-           the viewer groups are not in proximity to the Project; and

-           the foreground and middle ground can partially absorb views of the Project.

¨             Low:

-           the nature of the viewer groups do not expect a high degree of control over their immediate environment, (e.g. people at their place of employment or temporarily in attendance at the SVR location); and

-            people in transit (e.g. drivers and passengers in vehicles).

8.3.5.4       The magnitude of change of the visual resources is based on:

 

a.         compatibility of the project with the surrounding landscape;

b.         duration of impacts under construction and operation phases;

c.         scale of development;

d.         reversibility of change;

e.         viewing distance; and

f.           potential blockage of view.

 

8.3.5.5       The magnitude of change is classified as follows:

 

¨             Large:

-           prominent and permanent visual changes in the foreground, middle-ground or background where the project dominates the view;

-           permanent visual changes where the project contrasts conspicuously against the middle  ground and/or background;  and

-           temporary visual changes where the project dominates the foreground view.

¨             Intermediate:

-           permanent visual changes in the foreground or middle ground where the project is prominent but does not dominate the view;

-           permanent visual changes where the project is discernible against background, but is not conspicuous; and

-           temporary visual changes where the project dominates the middle ground view.

¨             Small:

-           permanent visual changes in the foreground, middle ground or background where the project is present but not noticeable; and

-           temporary visual changes where the project dominates the background view.

¨             Negligible:

-            No visual changes are apparent.

 

8.3.5.6       The significance threshold of visual impact is rated in a similar fashion to the landscape impact and is illustrated in Tables 8.3 and 8.4 below.

Table 8.3        Significance Threshold of Visual Impact

Magnitude of Change

 

Sensitivity to Change and Visual Intrusion

 

Low

Medium

High

Large

Moderate Impact

Moderate / Significant Impact

Significant Impact

Intermediate

Slight / Moderate Impact

Moderate Impact

Moderate / Significant Impact

Small

Slight Impact

Slight / Moderate Impact

Moderate Impact

Negligible

Negligible

Negligible

Negligible

 

 

 

 

Table 8.4      Adverse/Beneficial Impacts of Visual Impact

Significant:

Moderate:

Slight:

No impact:

adverse/beneficial impact where the proposed project would cause significant degradation or improvement in existing visual baseline conditions.

adverse/beneficial impact where the proposed project would cause noticeable degradation or improvement in existing visual baseline conditions.

adverse/beneficial impact where the proposed project would cause a barely noticeable degradation or improvement in existing landscape conditions or where the changes brought about by the project would not be apparent in visual terms

The proposed project does not perceptibly affect the existing visual baseline conditions.

 

8.3.6             Night-time Glare Assessment

 

8.3.6.1       In accordance with the brief, nighttime glare is considered in the visual impact assessment.  The proposed form and finishes of PAFF will be similar to the existing facility at Chek Lap Kok.  The designs of this kind of facility are standardised.  The existing fuel farm at Chek Lap Kok is taken as an example to investigate the possible nighttime glare brought by this facility to the environment.

 

8.3.7             Recommendation for Mitigation Measures

 

8.3.7.1       The identification of the landscape and visual impacts will highlight those sources of conflict requiring design solutions or modifications to reduce impacts and, if possible, absorb the development and associated activities into the surrounding landscape. These mitigation efforts should consider factors including:

 

a.         woodland, tree and shrub planting to new or disturbed slopes, amenity strips, highway reservations and adjacent to any proposed structures;

b.         contouring of new slopes to blend with existing topography in a natural manner;

c.         landscaped perimeter bund and screen planting;

d.         highlighting unacceptable impacts and considering alternative proposals;

e.         hard landscape elements including design and appearance of  proposed facility;

f.           significant landscape elements; and

g.         night-time glare solution.

 

8.3.7.2       The above will result in the formation of landscape mitigation proposals which will as far as possible help to alleviate the previously identified landscape and visual impacts.

 

8.3.8             Residual Landscape and Visual Impacts

 

8.3.8.1       The final stage of the LVIA study is to assess the significance of the residual impacts of the study assuming landscape mitigation measures are incorporated into the design.  In conclusion the landscape and visual impacts were then classified into one of five levels of significance based on criteria in Annex 10 of the EIAO-TM, as summarised below:

 

a.         the impact  is beneficial if the project will complement the landscape and visual character of its setting, will follow the relevant planning objectives and will improve the overall and visual quality of the study area;

b.         the impact is acceptable if the assessment indicates that there will be no significant effects on the landscape, no significant visual effects caused by the appearance of the project, or no interference with key views;

c.         the impact is acceptable with mitigation measures if there will be some adverse effects, but these can be eliminated, reduced or offset to a large extent by specific measures;

d.         the impact is unacceptable if  the adverse effects  are considered too excessive and are unable to mitigate practically;

e.         The impact is undetermined if significant adverse effects are likely, but the extent to which they may occur or may be mitigated cannot be determined from the study. Further detailed study will be required for the specific effects in question

 

8.4                   Project Description

 

8.4.1             General

 

8.4.1.1       The site identified in this section for the PAFF is the preferred location determined by a previous comprehensive site and environmental search. This search included the assessment of eight alternative locations and the selection criteria included a landscape and visual factors. A full description of the site of this assessment is given in Appendix A and Section 2 of this EIA Report.

 

8.4.1.2       The details of the project are described in full in below and in Section 3. An illustration of the PAFF is also shown in Figure 8.1.  The major elements can be summarised as:

 

a.         About 6.75 ha. of land to locate the aviation fuel tank farm and associated facilities;

b.         a jetty with two berths, able to accommodate 10,000 to 80,000 dwt vessels. It will be located a minimum 200m away from the water frontage with the length approximately 575m;

c.         a gross aviation fuel tankage capacity of approx. 264,000,m3 in the initial phase,  increasing in stages to match the anticipated growth in aviation fuel demand to an ultimate gross tankage capacity in the region of 388,000 m3.  Tank sizes will be between 23m to 24.7m in height and 33.5m to 43.5m in diameter with a capacity of between 19,000m3 to 35,000m3. For the initial phase, while all 8 tanks are 24.7m high, 6 of them are 43.7m in diameter, the other two are 41.5m and 35m in diameter respectively;

d.         tanks will be built in phases, starting with 8 tanks when the facility initially starts operation in 2009.  Four additional tank will be required to meet the future demand after 2025.  The proposed site will accommodate up to 12 fuel tanks at 2040;

e.         pumps and associated facilities;

f.           on site operational facilities including an administration office which will be approximately 30 metres by 40 metres and two stories in height;  and

g.         pipelines to transfer the fuel to the aviation fuel system at the airport.   A twin pipeline will connect the facility to the airport pipeline system.  The pipelines will be buried at 3m depth and protected by rock armour.

 

 

8.4.2       Tank Farm and Onshore Facilities

 

8.4.2.1        About 6.75 ha of land is required to accommodate the aviation fuel tank farm and associated facilities.  The proposed site for the tank farm at Tuen Mun Area 38 has been reclaimed by Government and is zoned for industrial use.  The site is situated at Siu Lang Shui just southeast of the Castle Peak Power station and is adjoined on the west by the Shiu Wing Steel Mill and on the south-east by the proposed EcoPark and adjacent to that is land earmarked for industrial use in keeping with the other land uses in the area.  Further east is the River Trade Terminal. The allocated plot has a short length of sea frontage of 60m in width which extends inland for about 140m before widening out to a square area of about 217m in length by 278m in width, see Figure 3.2c.

 

8.4.2.2        The closest residential development is Melody Garden in Tuen Mun, which is at least 3 kilometres from the proposed site.  The villages at Lung Kwu Tan are closer at about 2km away but are screened from the site by the Castle Peak topography. However, there is a planned Holiday Camp to the North-East of the site along Lung Man Road at over 500m away.

 

8.4.2.3        The tank farm will initially house 8 storage tanks, 6 tanks of 43.5m diameter by 24.7m in height, one of 41.5m diameter by 24.7m in height and one of 35m diameter by 24.7m in height.  These tank heights refer to the total tank height but it should be noted that part of the tank will be positioned in the ground and as such only 23m will protrude above ground level.  The tanks provide a storage capacity of between 35,000m3 to 22,000m3.   It is intended that the tankage capacity would be increased once the initial capacity of 264,000m3 has been reached around 2025 to 2040. It is intended that the remaining 4 tanks would be built all together after 2025 to increase the tankage capacity to the ultimate design tankage capacity of PAFF i.e. 388,000m3.  The heights of 3 of the remaining tanks would be 24.7m, with one tank of 23m and their capacities would vary accordingly between 35,000m3 and 19,000m3.  The 4 remaining tanks will be built according to the latest technology, industrial standards and statutory requirements at that time.  The tank farm would be provided with bundwalls and contained drainage.  Each tank will be designed with a fixed cone roof. The Tanks are of a standard design and will be finished in a neutral grey non-reflective paint.

 

8.4.2.4        Other shore based facilities would include office buildings for administrative and security control, leak detection instrumentation, fire fighting and emergency spill equipment, workshops and basic infrastructure including roads, drains, telecommunications, power supply and lighting.

 

Project Construction and Design

 

8.4.2.5        The land required for the PAFF tank farm has been minimized by stipulating that large diameter tanks (40metres) should be used.  A total of 12 tanks will ultimately be required at the PAFF tank farm.  These, together with an administration building, workshop, car park, pumps, filters, bunding and other facilities will occupy a minimum land area of 6 Ha.

 

8.4.2.6        Initially a site was selected adjacent to Shiu Wing Steelworks of dimensions 150 metres by 400 metres, the waterfront being 150 metres.

8.4.2.7        Subsequently, there was pressure to reduce the water frontage to a minimum, to accommodate other users, on the basis that it was unnecessary to locate aviation fuel tanks directly on the waterfront.  It was determined that a minimum water frontage of 60 metres was required for the PAFF for the following reasons:

 

a.         To accommodate the fireboat;

b.         To accommodate the work-boats to service the jetty with men, materials and equipment;

c.         To allow for access to pipelines and other services from the jetty to the tank farm, and pipelines from the tank farm to the airport;

d.         To locate a stormwater drainage outfall and fire water inlet;

e.         To house spill response equipment;

f.           To provide landscaping; and

g.         To allow for delivery of heavy equipment and material by sea, for future phases of tank farm construction.

 

8.4.2.8        Other constraints in determining the shape of the PAFF tank farm layout are as follows:

 

a.         Access to Shiu Wing Steelworks must be maintained on the north west boundary of the PAFF tank farm from Lung Yiu Street.  In addition, a turning circle at the end of the spur road would be required;

b.         Adjacent facilities to the south east of the PAFF tank farm would require a set back of the PAFF from the quay wall of 140 metres;

c.         Direct access from Lung Mun Road to the PAFF tank farm would not be acceptable;

d.         No reprovisioning of the temporary car park or other facilities currently provided in the PAFF tank farm area, are required; and

e.         Adequate landscaping for the PAFF tank farm area should be provided.

 

8.4.2.9        Based on all the above constraints, the tank farm layout was determined, as shown in Figure 3.2c, to require a land take of about 6.75Ha.  This comprises an approximately rectangular shape of about 280 metres by 215 metres with an additional irregular shape area towards the sea culminating in a 60 metre water frontage.  In this configuration, it should be noted that, because this irregular shape towards the waterfront is of insufficient width to accommodate a tank, with consideration of potential enhancement of existing landscape, it is best used for other facilities such as the administration building, pumps and landscaping. In addition, allowance for further access for emergency vehicles (EVA) is provided along the north west boundary of the PAFF tank farm. Regarding to the standard requirement, a provision of landscaped boundary is also considered along the set back of the PAFF tank farm area.

 

8.4.2.10    It should be noted that the previous EIA study (April 2002) was undertaken based upon the project layout detailed in Figure 3.2a.  However, changes were made to the detailed layout and an application for a variation (Application No. VEP-133/2004) to the then valid Environmental Permit EP-139/2002 was made.  A variation to the EP (EP-139/2002/A) was granted by EPD in February 2004.  Details of the revised layout approved by the VEP are provided in Figure 3.2b and details of the improvements made to the tank farm layout are detailed in EP Variation Application No. VEP-133/2004 and summarized in Table 3.2.  As part of the changes made, and as shown in Figure 3.2b, the whole site has been shifted 10m to the southeast from that proposed in the original EIA of April 2002, to accommodate Lands Department’s commitment of a land extension to Shiu Wing Steel Mill. 

 

8.4.2.11    Aviation fuel storage normally comprises above ground vertical cylindrical tanks of large diameter.  Alternative means of storage exists worldwide (e.g. underground storage) and were considered for the PAFF but rejected for the following reasons:

 

a.           For construction, underground tanks would need to allow for greater external forces and possibly floatation and would need complex ventilation system;

b.          From the operation perspective, maintenance of the quality of aviation fuel is the prime requirement as fuel required for aircraft must meet stringent standards.  Unlike aboveground tanks, for underground tanks there are two prime issues: (i) because PAFF at TMA 38 is on reclaimed land, the tanks will have to be built in the seawater and there is a risk of seawater seeping into the tanks; and (ii) there is a greater potential for bacteriological growth contaminating the fuel;

c.           From the environmental perspective, there is also a risk of aviation fuel seeping out of tanks into sea water thus creating environmental pollution;

d.          From safety perspective, because of confined space, the means of escape would not be easy as the tanks need to be accessed on a routine basis and the atmosphere would need to be monitored for presence of oxygen, and absence of flammable vapours.  This safe atmosphere would need to be maintained by a sophisticated ventilation system.  Personnel in the cavern or galleries would be at risk should such systems fail.  The means of escape in case of a fire would not be straight forward; and

e.           From the regulatory perspective, underground tanks would not comply with the Hong Kong Code of Practice for Oil Storage. The Institute of Petroleum Model Code of Practice Part 2 Section 3.2.15 recommends that buried tanks be avoided.

 

8.4.3       Berthing Jetty

 

8.4.3.1        The PAFF requires the construction of a twin berth jetty.  This will be sited approximately 200m offshore with no direct access to shore.  The two end to end berths would run approximately parallel to the quay wall and fuel tanker berthing would be provided on the sea facing side. The main activity at the jetty will be unloading of the tankers to the storage tanks in the tank farm.  Two unloading arms on one berth and three unloading arms at the other berth will be provided to unload the fuel at each berth.  Fuel lines and services will run to shore through submarine pipes and cabling protected by rock armour not protruding above the existing seabed, so as to provide marine access to other facilities adjoining the tank farm. Details of the jetty are provided in Figure 3.2c.

 

8.4.3.2        The sea bed level at the site lies between –17 and –18m PD indicating that water depths can reach 19.5-20.5m during the highest high tides.  As the berthing jetty would be built on piles, 100 tubular steel piles of diameter 800mm to 1000mm have already been driven into the seabed from 29 November 2005 to 29 March 2006 (with about 59 days for actual pile driving time) using hydraulic hammers.  A key consideration in the design and construction was how to mitigate noise.

 

8.4.3.3        A particular consideration for this project is the need to protect marine mammals from disturbance during the piling.  Similar issues were raised when the temporary AFRF was constructed near Sha Chau in 1995.  At that time the Airport Authority were advised by a panel of international cetacean experts that percussively driven piles would be preferred over in-situ bored piles, as was the original intention at that time, based upon the decreased time required for this technique, although it would be important to strive to mitigate noise. (ERM 1996).  A similar approach was adopted in the piling of the PAFF but a range of mitigation measures were applied before and during these piling works in accordance with the previous Environmental Permit EP-139/2002/A. 

 

8.4.3.4        Two defensive fender piles have already been installed on the on shore side of the jetty to prevent any possible collision from small craft straying into the prohibited area.  Coupling points on the ship would be provided with slop trays to catch occasional minor spills of unloaded fuels during coupling and de-coupling and the vessels will deal with the spills.

 

8.4.4       Pipeline

 

8.4.4.1        A short buried submarine twin pipeline will connect the reception jetty to the onshore tank farm, together with the utilities required for the jetty.  The fuel from the jetty to the tank farm will be transferred at a rate of 3,500m3 per hour.  It is proposed that the fuel would then be delivered to the airport site by means of further buried twin subsea pipelines which would connect to the existing facility at Sha Chau.  The total length of the pipelines would be about 4.8km including a 400m stretch within the Lung Kwu Chau and Sha Chau Marine Park in the approach to the existing AFRF pipeline.

 

8.4.4.2        The twin pipelines would each have an outside diameter of 500mm. The pipelines will be operated at a pressure of 30 barg (gauge pressure) and have a pumping rate of 30,000m3 per day or 1,500m3 per hour based upon 20 hours per day of pumping.  It is assumed that these would be continuously welded, encased in concrete and lowered into a trench of 3m depth to protect against 6 to 22 tonne anchors.   Future dredging activities are planned along the pipeline route for a coal berth for CLP in Urmston Road and, therefore, in this section of the alignment, the pipeline depth will be increased to about 6.5m below seabed.  In both cases, the trench would then be backfilled with graded stones and rock armour to protect the pipelines.  Schematic illustrations of the proposed pipelines and utilities from the jetty to shore and from the tank farm to the connection with the AFRF at Sha Chau are provided in cross sections (A) and (B) respectively in Figure 3.3.

 

8.4.4.3        The pipeline from the PAFF to the existing AFRF would be connected by being brought up one of the existing dolphin piles and flanged together with the existing pipeline using a new valve arrangement incorporated in-between.

 

8.4.4.4        The trench is assumed to be formed by a combination of trailer suction hopper dredger for the deeper areas in Urmston Road and by grab dredging for the remaining length.  Sand for the pipeline backfill would be placed by bottom dumping from barges.  

 

8.4.4.5        A possible alternative to dredging a trench for the pipelines would be horizontal directional drilling, tunnel and ploughing.  These techniques have been discussed in Section 2 of this report and dismissed on engineering, programming, environmental and cost constraints. 

 


8.4.5       Tanker Visit Frequency

 

8.4.5.1       The fuel reception jetty will provide two berths to allow flexibility to accommodate a full range of vessels within the size range 10,000 to 80,000dwt.  Fuel would typically be received at a frequency of three times per week rising to a forecasted average of 3.6 occasions per week at the 2040 planning horizon.

 

8.5                   Baseline Study of Landscape and Visual Resources

 

8.5.1             Background

 

8.5.1.1       Tuen Mun Area 38 is new reclaimed land zoned for industry, facing south towards Urmston Road (Harbour) with the Castle Peak as its backdrop.  To the west, it is adjacent to Shiu Wing Steelworks and the Castle Peak Power Station. To the east, there is the CED reclamation site which is zoned as a resource recovery facility referred hereafter as an “Eco-Park”, The landscape character in the vicinity varies between from woodland, industrial/utility, transport corridor, pier and waterfrontage, as shown in Figures 8.3.1 and 8.3.2 and the landscape resources shown in Figure 8.4.  The site is open to view from the sea with a water frontage of approximately 60m in length.  It is enclosed by future industrial development on the Special Industrial Area (S.I.A.), refer to Section 8.5 on S.I.A. definition.  Visual resources are mainly in the local context and the sea traffic along Urmston Road (Harbour). 

 

8.5.2             Baseline Landscape Resources

 

8.5.2.1       In accordance with the study brief, landscape character units (LCUs) and landscape elements have been identified within 500m from the site boundary.  The LCUs have been selected depending on the presence and combination of landscape pattern, mass and scale of buildings and structures, topography, and existing vegetation. Reference was made to the Landscape Character Map of Hong Kong.  For each LCU assessment has been made of its quality and sensitivity to change. The landscape elements (including trees, coastline, sea, existing roads etc) have been quantified. The methodology refers to Section 1.3.  The results of the landscape baseline study are described in Table 8.5a, Table 8.5b and shown on Figures 8.3.1and 8.3.2.

 

8.5.2.2       The combination of the Landscape Character Units are discussed below and shown in Table 8.5a.

 

a.         Woodland, grassland and shrubland (LCU1) –Existing green areas comprising woodland (of predominantly native tree species), grassland and shrubland, including major ridgelines in southwest New TerritoriesCastle Peak. This LCU encompasses south facing wooded slopes that provide a green backdrop to the proposed project.  The topography is fairly steep, rising to Castle Peak to the north. Parts of the woodland resource Castle Peak Bay have been disturbed by formation works required for road and/or industrial uses. Despite this disturbance, LCU1 remains an important landscape resource in the local context of Castle Peak as well as Hong Kong as a whole. Because of this distinct character, LCU1 has a high landscape quality and a high sensitivity to change.

 

b.         Transport Corridor (LCU2) – Existing linear structures for vehicles, Lung Mun Road. Lung Mun Road is the key local access from Tuen Mun Town Centre to Lung Kwu Tan via Tuen Mun Area 38.  It is a linear engineering structure, which can always adapt to change and has a low sensitivity. Common species of roadside trees are found along the corridor.  LCU2 has a medium landscape quality.

 

c.           Industrial/ Utility (LCU3) – LCU3 comprises the industrial development at Castle Peak Bay including existing factories, laundry workshop, cargo terminal, steel mill and power station. This LCU has an industrial character comprising large scale infrastructure elements such as chimneys, industrial buildings and sheds and loading and unloading machinery. Much of this area comprises reclaimed land. This LCU also includes small areas of roadside amenity planting along the local road and at the entrances to industrial sites. Most of this planting is immature comprising largely whips and shrubs but with some trees (common species).  It should be noted that as some construction works have already been undertaken as described in Section 1 of this report, all the road side trees to be affected by the PAFF have already been felled or transplanted. The future outlook is described under the Draft Tuen Mun OZP No. S/TM/22. Under this draft planning document the area is zoned for ‘OU’ (Special Industries Area) and is reserved for land-extensive and capital investment industry as well as for other special industries. Under the draft OZP further reclamation is proposed. This includes the formation of new land (currently in progress by CEDD) to the south east of the proposed site. LCU3 is assessed as having a low landscape quality and that is can accommodate change.  The proposed PAFF is located within LCU3

 

According to the Landscape Character Map of Hong Kong, the proposed PAFF is mapped as a LCU of “Industrial Urban Landscape” within a LCT of “Urban Landscape”.  The explanatory statement accompanying the Landscape Character Map states that industrial urban landscapes are “generally found on low-lying areas of reclaimed land and often along the coasts of urban areas, these are landscapes defined by their almost exclusively industrial land uses. They typically include areas of industrial buildings, often in very dense arrangements. Any occasional open areas are used for vehicle parking or open storage. Streets are mainly residual spaces, with little or no vegetation. On the peripheries, there may be areas of vacant land. These landscapes also include industrial estates: extensive areas of comprehensively developed low-rise buildings with wider roads, which are often tree lined, usually found at the edges of new towns, such as Yuen Long or Tai Po. Their unifying characteristics are their large utilitarian buildings, their limited coherence of spaces, features and materials, and absence of significant vegetation cover”.  The characteristics of LCU Industrial Urban Landscape/LCT Urban Landscape as identified in the Landscape Character Map were found to be in accordance with LCU3 as mapped by the LVIA and therefore LCU3 is assumed to incorporate the findings of the Landscape Character Map.   

 

d.         Pier (LCU4) – This LCU is characterised by berthing points for the power plant, cement works and steel mill as well as other engineered infrastructure. These aretypical landscape elements found along the Tuen Mun Area 38 waterfront.  LCU4 has a low landscape quality and a low sensitivity to change.

 

e.         Waterfront (LCU5) – LCU5 comprises a manmade straight edge along Area 38 with berthing points for sea vessels and harbour interface with the site. The harbour edge is formed by a typical seawall. This runs along the reclaimed area of Castle Peak Bay. Although marine habitat adjacent to the site has been disturbed by the on-going reclamation activities at Castle Peak Bay, Urmston Road (Harbour) is still recognized as a regionally significant marine habitat.  The overall landscape quality and sensitivity to change of LCU5 remains high.

 

Table 8.5a    Landscape Character Units (LCUs)

 

LCU

Name

Description

Quality/Sensitivity to Change

LCU 1 

Woodland, grassland and shrubland

Existing green areas comprise the predominantly wooded (of native tree species) backdrop of Castle Peak and related hills.

 

u High/High

LCU 2

Transport Corridor

 

Existing linear structures for vehicles, Lung Mun Road.

u Medium/Low

LCU 3

Industrial/ Utility  (incorporating LCU Industrial Urban Landscape of the Landscape Character Map of Hong Kong)

Industrial/ Utility facilities next to the sites, including power station, steel mill, river trade terminal (container terminal), pumping station and container storage and repair, warehouses, future EcoPark, C&D Recycling Facility on CEDD reclamation site etc.

u Low/Low

 

LCU 4

Pier

Built element for power plant, cement works, steel mill.

u Low/Low

 

LCU 5

Water frontage

Reclamation edge, manmade seawall.

u High/High

 

8.5.2.3       Within the 500m study, the proposed PAFF falls within Industrial/Utility (LCU3) where the local industrial landscape character comprises a unique pattern of existing uses and planned uses (refer to Section 8.5) at Tuen Mun Area 38. The landscape elements (refer to Table 8.5b) are changing due to reclamation and other construction activities and the overall quality of LCU3 will remain industrial in the future. The proposed PAFF is located on reclaimed Government land without anything on it except a temporary car park with a local access and an EVA.  A total of 292 trees and whips were found at the site and in the adjacent roadside areas (23 were subsequently found missing).  As part of the construction works undertaken in 2005 prior to the quashing of the original Environmental Permit, a total of 209 trees have been transplanted, 29 felled and 31 retained. As such there are no further trees or whips to be disturbed by the future works. 

 


Table 8.5b    Landscape Resources

 

Type

Description

Total area within the LVIA Study Area

Secondary Woodland

Existing secondary woodland associated with rocky area on the Castle Peak, north to the Proposed PAFF.  Typical species are Acacia confuse, Celtis sinensis, Cratoxylum cochinchinensis, Elaeocarpus hainanensis, Ficus virens, Ficus mircocarpa, Ficus superba, Ficus variegate, Litsea glutinosa, Machilius chekiangensis, Macaranga tanarius, Mallotus paniculata.  No Old and Valuable or Champion Trees found.

Approx. 14ha.

Trees on the site and by the road side

Planting along roads.

 (Of the original 292 existing trees identified adjacent and within the site area, 23 were found missing, 31 were retained, 209 were already transplanted and 29 felled by works undertaken in 2005 (see Section 1).  No further disturbance to the remaining trees will occur during future works.)

Approx. 6ha (1000 nos. of trees/whips)

Cut Slope

Existing cut slope along Lung Mun Road and also near the container storage areas.

Approx. 4.7ha.

Sea

 

Approx. 230ha.

Transport Corridor (i.e. existing roads and footpaths)

 

Existing linear structures for vehicles, Lung Mun Road.

Approx. 19ha

Industrial Built-up area

Reclaimed land at Tuen Mun Area 38 along Castle Peak Bay.  Built elements are power plant, cement works, steel mill, future

EcoPark.

Approx. 42ha.

Manmade Coastline

Existing manmade seawall along Tuen Mun Area 38.

Approx. 2700m length

 

8.5.3             Baseline Visual Resources

 

8.5.3.1       In accordance with the study methodology in Section 8.3, the Sensitive Visual Receivers (SVRs) within the visual envelope were identified and grouped into types, as shown in Figures 8.5.1 to 8.5.4.  In summary, the SVRs can be classified into five representative groupings (i.e. some groups will have more than one SVR) according to the location of the proposed PAFF as defined in Table 8.6.  The visual resources closely relate to the landscape character units (LCUs). These units vary from the water frontage to the industrial/utility facilities.

 

8.5.3.2       To assist in determining Sensitive Visual Receivers (SVRs), a visual envelope has been determined as illustrated on Figure 8.5.1 and key views from and toward the proposed PAFF are described as below. 

8.5.3.3       Key views from the proposed PAFF are:

 

a.         partially obstructed view to the east towards the River Trade Terminal across CEDD reclamation site planned for use as an EcoPark and C&D recycling facility adjacent;

b.         oblique and obstructed view to Shiu Wing Steel Mill and Castle Peak Power Station;

c.         north with open view to the green backdrop of  the Castle Peak;

d.         south with open view to the sea (Urmston Road); and

e.         south distant view to Chek Lap Kok Airport.

 

8.5.3.4       Key views toward the proposed PAFF are summarised in Figure 8.6 and listed below:

 

a.         oblique and open views north across the site from the sea (Urmston Road);

b.         open and partial views from Lung Mun Road immediately adjacent to the site;

c.         partial obstructed view from structures in the adjacent industrial development and by future screen planting to be implemented as part of the future EcoPark (as described  in the EIA for this development)  which is immediately adjacent to the site;

d.         distant views from north Chek Lap Kok Airport and North Lantau Express; and

e.         elevated views from a future Holiday Camp at Siu Lang Shui.

 

8.5.3.5       Details of the SVRs are provided below and summarised in Table 8.6:

 

a.         SVR1 are the passengers and staff on vessels travelling along the Urmston Road Channel. They have oblique and open views north to the proposed PAFF and other industrial development at Castle Peak Bay from the sea.  Their views are transient in nature and distant from the proposed PAFF. Their sensitivity to change is low.

 

b.         SVR2 are predominantly the drivers and passengers of vehicles using the Lung Mun Road. They largely have partially obstructed views across Area 38 which are blocked by the huge machinery at the River Trade Terminal and the Castle Peak Power Station.  Although they are proximate to the proposed PAFF, these receivers are in transit and relatively small in number.  Pedestrians along Lung Mun Road are relatively infrequent. Their sensitivity to change is low.

 

c.         SVR3 are the workers working at Tuen Mun Area 38 during working hours only. Views from the industrial buildings are limited and always blocked by the huge machinery at the River Trade Terminal and the Castle Peak Power Station.   Their sensitivity to change is low.

 

d.         SVR4 are the passengers using the North Lantau Express and visitors and staff using the north side of Chek Lap Kok Airport.  They have very distant views, at a minimum 6000m across the Urmston Road Channel to the proposed PAFF. Residents at Tung Chung in the higher towers are over 8000m distant. Their views are dominated by the foreground of Chek Lap Kok Airport and the PAFF will be a very small distant element within the general context of the Tuen Mun industrial area. Due to the local climatic conditions resulting in a high incidence of sea mist, the proposed PAFF will only be visible intermittently through out the year. Local climatic conditions mean that, in general, during spring and summer, Castle Peak Bay cannot be seen clearly from the SVR4 location.  Their sensitivity to change is medium.

 

e.         SVR5 are the future users of the proposed Holiday Camp at Siu Lang Shu.  The future users would overlook the proposed PAFF from the north-east from a distance of approximately 730 metres.  The PAFF would be a conspicuous view when seen from this location.  The most noticeable objects would be the fuel tanks which would dominate the middle-ground of the view, framed by existing vegetation in the foreground and the sea in the background.  The sensitivity to change would be medium as the camp would not be permanently occupied and the main users would use the facility for a brief period only.

 

8.5.3.6       Principal viewpoints (Vpt.) are selected from each SVRs to illustrate their sensitivity and the extent of change with the proposed PAFF (see Figure 8.5.1).


Table 8.6         Sensitive Visual Receivers

 

SVR

Name

Nature of  Viewer Group

Distance to Proposed PAFF

Frequency and duration of view towards proposed PAFF and source of impact type of  view

Value and Quality of Existing View towards PAFF

Availability and amenity of alternative views

Sensitivity to change and visual intrusion

SVR 1 

Sea traffic along Urmston Road

 

Vpt. 1Urmston Road near River Trade Terminal

 

Quantity of SVRs:  small

Passengers and Workers on  vessels using Urmston Road Channel

 

200m-5000m

 

 

2141m

Oblique and open views north across the site from the sea

Low frequency transition view during daytime

Immediate foreground of sea and distant background views of attractive vegetated hillsides. Middleground view dominated by steel mill, industrial in appearance, not considered attractive or interesting 

Wide range of alternative views available which are high in amenity value.

u Low

SVR 2

Traffic from Lung Mun Road

 

Vpt. 2 Elevated view from Lung Mun Road

 

Quantity of SVRs:  small

Passengers + pedestrians

 

 

50m-2000m

 

 

50m

Partial view towards south Area38 blocked by River Trade Terminal.

Low frequency transition view during day & night

Immediate foreground of sea and distant background views of attractive vegetated hillsides. Middleground view dominated by steel mill, industrial in appearance, not considered attractive or interesting

Wide range of alternative views available which are high in amenity value.

u Low

SVR 3

Industrial/ Utility facilities 

 

Vpt. 3.1 From River Trade Terminal

Vpt. 3.2          From Proposed Eco-Park (Resource Recovery Park)

 

Quantity of SVRs:  small

Workers

at River Trade Terminal

Tuen Mun Area 38,

EcoPark, C&D Recycling facility

 250m-4000m

 

 

1800m

 

250m

Partial and obstructed views toward the site blocked by ancillary machinery and structures at the River Trade Terminal and Castle Peak Power Station

 

Low frequency view during working hours

Immediate foreground of sea and distant background views of attractive vegetated hillsides. Middleground view dominated by steel mill, industrial in appearance, not considered attractive or interesting

 

Wide range of alternative views available which are high in amenity value.

u Low

SVR 4

North Lantau development including Tung Chung

 

Vpt. 4.1 Chek Lap Kok Airport

Vpt. 4.2 North Lantau Highway/Airport Railway/MTR Tung Chung Line

Vpt 4.3 Tung Chung Residents

 

Quantity of SVRs:   large

Staff + Visitors + Passengers and Local Residents of Tung Chung

 

Over 6000m

 

 

Residents of Tung Chung are over 8000m distant from PAFF

Very Distant and transient view towards the site  Medium frequency view during daytime

Foreground to distant background dominated by water views, amenity considered to be very high,

Wide range of alternative views available also high in amenity

u  Medium

SVR5

Siu Lang Shui Holiday Camp

 

Vpt 5 Future users

 

Quantity of SVRs - Small

Staff and users of proposed Holiday camp

730m

Open and unobstructed views

High amenity value

Wide range of alternative views available high in amenity value

u Medium

 


8.5.3.7       In addition, views from residents at Tuen Mun Town and Lung Kwu Tan have also been considered.  Although they are about 2km away or more from the site and screened by natural topography, photographs have been taken from the view point options (Vpt. A1 – A3) in Table 8.7 to demonstrate that they are out of the visual envelope of the proposed PAFF, as shown in Figure 8.5.3.

 

Table 8.7           Viewpoint Options from the Nearest Residents

 

Vpt. Options

Name

Nature of  Viewer Group

Distance to Proposed PAFF

Type of  view

Vpt. A1 

Lung Kwu Tan

 

Residents + Visitors

 

over 1700m

Obstructed Views toward the site, blocked by Tap Shek Kok and Castle Peak Power Station.

Vpt. A2

Melody Garden near Butterfly  Beach

 

Residents + Visitors

 

over 3600m

Obstructed/ Elevated Views toward the site, blocked by natural topography.

Vpt. A3

Tuen Mun Ferry Pier Residential Blocks

Miami Beach Tower

Residents

 

over 4000m

Obstructed/ Elevated Views toward the site, blocked by natural topography and River Trade Terminal.

 

8.5.3.8       The lookout point in the Marine Park at Sha Chau is a dolphin survey point used only by AFCD.  It is not accessible by the public and, hence, not considered as a SVR.

 

8.6                   Review of Planning and Development Control Framework

 

8.6.1             The planning and development control framework is shown in Figure 8.4.  The broad statutory planning framework and intention for the proposed site is currently covered by the Draft Tuen Mun Outline Zoning Plan (OZP) No. S/TM/22 exhibited on 27.10.2006. According to the Draft Tuen Mun OZP No. S/TM/22, the Site is zoned for ‘OU’ (Special Industries Area). This area is reserved for land-extensive and capital investment industry as well as for other special industries. This may include uses such as the proposed PAFF. Under Column 2 of the Statutory Notes, a ‘Utility Installation not Ancillary to the Specified Use’ may be permitted with or without conditions on application to the TOWN PLANNING BOARD (OZP and Statutory Notes at the front of this Statement refer).

 

8.6.2             The area in which the Site is located (i.e. Planning Area 38) will be dominated by industrial and OU uses (OZP at the front of this Statement refers). These include existing and proposed uses such as the Castle Peak Power Station, Green Island Cement Plant, Shiu Wing Steel Mill, ‘Special Industries Area’, a River Trade Terminal, piers, Container Storage and Repair Depot, Breakwater, and Sewerage Treatment Plant. These are all non-sensitive uses. The proposed PAFF would, therefore be compatible with adjacent developments.

 

8.6.3             The non-statutory Planning Context is indicated in the Tuen Mun New Town Areas 38 & 47 Layout Plan which was adopted on 2 June 1992 (Figure 3.1), the sites along Lung Mun Road (including the Site) are zoned for Industrial (Types B and C) uses. The proposed PAFF site falls within a site reserved for a Centralised Incineration Facility (Site B), a Chemical Waste Bulking/ Treatment Plant (Site C) and two other sites reserved for industrial uses (Sites D and E). With the proposed PAFF, the incinerator and waste treatment plant sites are likely to be relocated elsewhere within the Tuen Mun Area 38 (e.g. Sites F to Q).

 

8.6.4             Other non-statutory guidance from Government on the need for PAFF has been recognised by the HKSAR Government. In March 2001, the facility received support from the Chief Secretary, Sir Donald Tsang and Government bureaux. There has been ongoing liaison with the Advisory Council on the Environment (ACE), Green Groups, the Country and Marine Parks Board (CMPB), and the Tuen Mun District Council. Most departments and organisations have given in-principle support to Tuen Mun Area 38 as the preferred site for the PAFF. There has been, in conjunction with Government, ongoing consultation with the Tuen Mun District Council (who are the only objectors to the proposed project). The local community has voiced concerns over risk and visual matters. The Airport Authority has given a commitment that adverse landscape and visual impacts would be fully mitigated and with a resultant negligible residual impact.

 

8.6.5             The future planning outlook and interface with sensitive uses and sensitive visual receivers indicates that Tuen Mun Area 38 will remain designated as a ‘Special Industries Area’. There are a number of potential uses for the area. These include Environmental Protection Department’s 20 ha Eco-Park (Resource Recycling Park) located southeast of the proposed PAFF. Processing plants for batteries, electrical and electronic appliances, glass, metal, organic waste, waste oil, paper, plastics and foam, textile waste, toner cartridge, tyre, wood, etc. may also be included within the Park.  The PAFF would be likely to interface with these future uses. However since all the proposed uses are non-sensitive uses, the interface can be ameliorated by buffer planting, sensitive site layout and orientation.  These possible future uses have a low sensitivity and given the overall industrial context it is predicted that PAFF would result in a negligible change and impact on such uses.

 

8.6.6             In accordance with the broad statutory planning framework mentioned above, the planning of Tuen Mun Area 38 is particularly for industries, which require large pieces of land and high capital investment.  Since the proposed PAFF development complies with this planning intention, no potential conflicts are found with respect to landscape and visual impacts with the existing planning and development control framework. 

 

8.7                   Landscape and Visual Impact Assessment during Construction

 

8.7.1             Background

 

8.7.1.1       The proposed site is on reclaimed land.  Potential construction impacts will be building materials delivery, dredging for the pipeline, piling and construction activities of the jetty, formation of the access road and associated facilities.  Construction of the 12 proposed fuel tanks would be in phases over about a 30 year period. Phase 1 will comprise construction of the first 8 cylindrical fuel tanks, the administration block, proposed jetty and landscaped perimeter bunds.  In order to meet the future demand of the aviation fuel storage, future expansion is required and fuel tanks will be required until 2040.

 


8.7.2             Prediction and Evaluation of Landscape Impacts during Construction (without Mitigation Measures)

 

8.7.2.1       A landscape impact is a physical change to an existing landscape resource.  By mapping the extent and location of these changes, any loss or alteration can be assessed and, where possible, re-provisioned or compensated by landscape mitigation measures incorporated into a Project.

 

Disturbance to Existing Vegetation

 

8.7.2.2       Construction activities will comprise site formation and building of fuel tanks and administration blocks.  Site formation includes clearance of the whole site. Earthworks will be undertaken to form a low bund around the tanks comprising a concrete containment bundwall, access road and security fencing.  The fuel tanks will be located inside these bunded areas. Other sources of construction impacts will result from storage of construction materials and the movement of machinery.  As detailed in Section 1, some construction works have been undertaken under the previous Environmental Permit EP-139/2002/A.  These activities have included some site clearance.  As such,  209 trees have already been transplanted and these transplanted trees, the remaining 31 trees retained and other vegetation within LCU3 will not be further disturbed by future works.  The high landscape quality of the natural setting of Castle Peak (LCU1) behind the proposed PAFF will remain unaffected.

 

Disturbance of the Existing Waterfront

 

8.7.2.3       The construction activity of the proposed jetty, (which is 200m away from the waterfront) and dredging for the seabed pipelines will result in some disturbance to LCU5. Approximately 60m of existing manmade waterfront and approximately 1.5 hectares of sea area will be affected. The proposed jetty massing is low, long and narrow. Connecting pipes are laid under the sea. The jetty proposal will therefore result in a slight/moderate change to the existing condition.  Compared to disturbance resulting form the CEDD reclamation that has been undertaken next to the proposed PAFF, the jetty construction impact will be comparatively small.  Corresponding landscape mitigation measures are discussed in Section 8.10.

 

Disturbance of the Industrial/Utility Areas

 

8.7.2.4       The site for the proposed PAFF comprises about 6.75 hectares of reclaimed land in LCU 3.   It is currently fenced and used as a material storage and car parking area.  Compared to the neighbouring industrial facilities, such as River Trade Terminal, Castle Peak Power Station, EcoPark and C&D recycling facility, as well as the construction activities at the Castle Peak Bay, the construction impacts of the proposed PAFF will be relatively small.  None of the ferry piers of LCU 4 will be affected.

 

8.7.2.5       During construction, LCU3 and LCU5 will have “slight adverse” impacts. These result from the site formation and the construction of the initial phase of the tank farm (8 tanks).  The magnitude of change to LCU3 and LCU5 is assessed as small when considered in relation to the industrial context of the neighbouring heavy industry.  The landscape character of LCU1, LCU2 and LCU4 will remain unchanged, as summarised in Tables 8.9a, Tables 8.9b and 8.10.


Table 8.9a      Summary of Disturbance to Landscape Character Units (without Mitigation Measures)

 

Description

Disturbances

LCU 1 Woodland, grassland and shrubland

Nil

LCU 2 Transport Corridor

Nil

LCU 3 Industrial/Utility (incorporating LCU Industrial Urban Landscape of the Landscape Character Map of Hong Kong)

About 6.75 ha. of land zoned for Industrial Uses

LCU 4 Pier

Nil

LCU5  Waterfront

Approx. 60m length of disturbed waterfront. 

 

 

Table 8.9b      Summary of Disturbance to Landscape Elements (without Mitigation Measures)

 

Type of Landscape Element

Total area within the Study Area of the PAFF

Area in Interaction with the PAFF

Secondary Woodland

Approx. 14ha.

Nil

Cut Slope

Approx. 5ha.

Nil

Sea

Approx. 230ha.

Approx. 1.5ha. sea area

Transport Corridor (i.e. existing roads and footpaths)

Approx. 19ha

375m long existing access road.

Industrial Built-up area

Approx. 42ha.

Approx. 6.75ha. reclaimed land

Manmade Coastline

Approx. 2700m length

60m length

Roadside vegetation

Approx 6ha

0.25ha

 

8.7.3             Prediction and Evaluation of Visual Impacts during Construction (without Mitigation Measures)

 

8.7.3.1       In general, the main source of the unmitigated visual impact on all SVRs is the tanks.  The massing and scale of these structures would make them noticeable and distinctive objects in the foreground when viewed from within two to three kilometres (see Figures 8.8.1 and 8.8.4).  The ancillary structures such as offices, workshops and jetty are not considered to be significant sources of visual impact.  Beyond three kilometres, the attenuating effects of distance, the surrounding industrial setting and the availability of alternative views would make the tanks less distinctive although they would remain noticeable if the viewer was looking directly at them (see Figure 8.8.8). Table 8.11a describes how the magnitude of visual change was assessed for each of these conditions, while Table 8.11b summarises the resulting visual impacts.

 

8.7.3.2       The visual impacts arising assuming no mitigation measures will be:

 

a.         the interruption and obstruction of views northwards by built elements and the dredging activities from the vessels using the Urmston Road (Harbour) will result in “slight adverse” visual impacts for SVR1;

b.         the conspicuous interruption and obstruction of views southwards towards the Harbour from the vehicles using Lung Mun Road, will result in “slight/moderate” visual impacts  for SVR2 (see Figure 8.8.4); 

c.         the conspicuous interruption and obstruction of views along the waterfront from the adjacent properties will result in “slight/moderate” visual impacts for SVR3 (see Figure 8.8.1);

d.         the change of visual quality northwards from the distant North Lantau Island would be small owing to the distance and will result in “slight/moderate adverse” visual impacts for SVR4; and

e.         the proposed Holiday Camp at SVR5.  As the PAFF is more advanced in terms of project planning, it is assumed that the initial phase of the PAFF would be constructed before the Holiday Camp is operational.  Therefore, no visual impacts are predicted for SVR5 during construction phase of the PAFF.  Figure 8.8.8 illustrates the appearance of the tanks from this location in any case

 

8.7.3.3       The visual envelope shown on Figure 8.5.1 illustrates the possible inter-visibility of views toward the proposed project. Although the visual envelope extends south to Lantau (including Tung Chung and Chep Lap Kok Airport), north toward Castle Peak, east along the sea channel to Tai Lam Chung and Yam O and west to Sha Chau Island many of these views are over very long distances (over 8km). At these distances the proposed project it is predicted that the proposed project will result in an imperceptible magnitude of change and negligible adverse impact. Importantly, for potentially local sensitive residents at Lung Kwu Tan to the north west and adjacent Butterfly Beach to the east it is assessed that local topography will obstruct views to the proposed project. These local residents will therefore not be adversely impacted by the proposed project.

 

8.8                   Landscape and Visual Impact Assessment during Operation (without Mitigation Measures)

 

8.8.1             Background

 

8.8.1.1       The PAFF is a static storage facility.  Few operational activities will be involved in the day to day running of the facility.  The initial operational phase of the PAFF will not result in any further perceptible changes to the existing landscape and visual character.  Although permanent built elements intrude into the local landscape context, the overall quality of the industrial context will remain unchanged. It is anticipated that new tanks will be built in one additional phase between 2025 and 2040 until the development comprises a total of 12.  The development will be completed by 2040.  This construction programme is related to the future expansion and demand at the Airport. Cumulative landscape and visual impacts will result from the construction of the additional fuel tanks.

 

8.8.2             Prediction and Evaluation of Landscape Impacts during Operation (without Mitigation Measures)

 

8.8.2.1       During operation from 2009 to 2025 it is predicted that the magnitude of change from the baseline condition will be negligible. With the gradual and periodic construction of new fuel tanks after 2025, a “slight adverse” landscape impact to LCU3 is predicted as shown in Table 8.10.  No change is predicted to the other LCUs. 

 

8.8.3             Prediction and Evaluation of Visual Impacts during Operation (without Mitigation Measures)

 

8.8.3.1       The visual impacts in comparison to the baseline condition arising from the initial operation phase of PAFF and its gradual and periodic expansion to 2040 are discussed below. Table 8.11a describes how the magnitude of visual change was assessed for each of these conditions, while Table 8.11b summarises the resulting visual impacts. 

 

a.         visual impacts to SVR1 resulting from  an increase in vessel traffic using the Urmston Road will be small. The PAFF vessel traffic will constitute less than 1% (0.2%) of the existing traffic volume at initial phase (see Table 3.3).  Visual impacts to SVR1 resulting from the presence of the fuel tanks are predicted to be also “slight”, owing to the small level magnitude of change to the VSR and the low sensitivity of the VSR, but adverse as they will block views of the hills behind;

b.         In the initial phases, the new tanks will constitute “intermediate” changes within the views looking from SVR2 to SVR3.  Although in general the project is compatible with the existing surrounding industrial landscape (e.g. the River Trade Terminal and the Shiu Wing steel mill) and will be compatible with the future EcoPark resource recycling centre when it is constructed, the new tanks will constitute an “intermediate” magnitude of change when viewed from these locations.  This will result in “slight/moderate” visual impact;

c.         When viewed from SVR4, the magnitude of change will be small, however this SVR is sensitive to change (owing to the presence of residents) and therefore the visual impact will be “slight/moderate adverse”;

d.         In the expansion phases from 2025 to 2040 the new tanks will generally be placed and obscured by those constructed in the initial phase. As a result the cumulative magnitude of change for SVR1 and SVR4 that could result from the maximum utilisation of PAFF, is predicted to  be no worse than the initial phase;

e.         for SVR2 the cumulative impact from expansion of PAFF to 2040 (through interruption/obstruction in views from the south) is predicted to result in a “moderate” visual impact as Lun Mun Road is very close to the development;

f.           for SVR3 the cumulative impact from expansion of PAFF to 2040 (through interruption/obstruction in views from the adjacent properties) will result in “moderate” visual impacts as the four new tanks will be relatively obvious new elements in the scenery;

g.         cumulative adverse visual impacts will result from the permanent intrusion up 12 fuel tanks at  2040; and

h.         It is assumed that the initial phase of the PAFF would be constructed before the Holiday Camp at SVR5 is operational, as the PAFF implementation programme is running well in advance.  After the Holiday Camp is implemented, the PAFF initial phase development would be an existing element within the view and appear as a conspicuous element.  Owing to its industrial appearance, it is unlikely to contribute to an attractive outlook when viewed from the future camp.  If the Holiday Camp were operational before the PAFF initial phase development and the fuel tanks were introduced into the existing view, the visual impact could be considered as “significant adverse”.  However, where the development is pre-existing to the SVR, it is concluded that that visual impact must be less and therefore no visual impact is predicted during the operation of the PAFF initial phase.  During the PAFF expansion phase, the change in the middle-ground view would be conspicuous as additional fuel tanks are constructed.  Under these circumstances the visual change is likely to be intermediate.  The choice of “intermediate” rather than “high” visual change is based on the judgement that large fuel tanks would already be a conspicuous part of the middle ground.  Under these circumstances, visual impact is predicted to be “moderate adverse” during the expansion phase of operation (2025 to2040).

 

8.9                   Night-time Glare Assessment

 

8.9.1             In order to meet safety and security requirements permanent 24 hours lighting of the proposed PAFF is necessary.  As the lighting requirements for these types of facilities are standard, they will be very similar to those used on the existing Chek Lap Kok Facility.  Night-time glare is potentially a significant visual impact.  Studies of the night-time glare from the existing Chek Lap Kok fuel tank farm give an estimate of the potential glare from the proposed PAFF.  Figure 8.6.2 indicates the night-time lighting of existing Chek Lap Kok fuel tank farm. As shown, lighting is required along staircases and railings only.  The intensity, luminance and lighting levels of the fuel tank farm are low. Lighting is generally focussed and shielded to reduce glare and illuminate required areas only.  Compared to road lighting the levels are low.

 

8.9.2             The impact of night-time lighting of the proposed PAFF will be reduced due to its remote location away from residents and sensitive receivers. The impact will be further mitigated by its absorption into the overall and existing night-time glare of the neighbouring industry, including the River Trade Terminal (24 hours container delivery operation) and the Castle Peak Power Station.  Night-time glare from these facilities will be more conspicuous than that for the proposed PAFF.  A slight cumulative impact from night glare is anticipated as the tank farm expands over the period from 2025 to 2040.  However, it is predicted that the magnitude of change will be small resulting in “slight/negligible adverse” impact.

 


Table 8.10a    Summary of Landscape Impacts on LCUs (without Landscape Mitigation Measures)

 

LCU Name

Disturbed Area

Quality/ Sensitivity to Change

Construction Phase

Operation Phase  Initial Phase

Operation Phase  2025 - 2040

Magnitude of Change and Source of Landscape Impact

Significance Threshold of Landscape Impact

Magnitude of Change during Operation Phase

Significance Threshold of Landscape Impact

Magnitude of Change during Operation Phase

Significance Threshold of Landscape Impact

LCU 1

Woodland, grassland and shrubland

Nil

High

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

LCU 2

Transport Corridor

Nil

Low

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

LCU 3

Industrial/ Utility (incorporating LCU Industrial Urban Landscape of the Landscape Character Map of Hong Kong)

Approx. 6.75 ha.

Low

Small

(site formation + construction of fuel tanks & administration blocks + delivery construction materials + temporary hoarding)

Slight Adverse

Negligible

Negligible

Small

(fuel tank farm extension of 4 tanks)

Slight Adverse

LCU 4 

Pier

Nil

Low

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

LCU 5

Water frontage

Approx. 60m long for administration blocks

approx. 1.5ha. sea area  for the proposed jetty

High

Small

construction of jetty + delivery construction materials + dredging seabed + temporary hoarding

Moderate

Adverse

Negligible

Negligible

Negligible

Negligible

 

 


Table 8.10b    Summary of Landscape Impacts on Landscape Elements (without Landscape Mitigation Measures)

 

Type of Landscape Element

Disturbed Area

Quality/ Sensitivity to Change

Construction Phase

Operation Phase  Initial Phase

Operation Phase  2025 - 2040

 

 

 

Magnitude of Change and Source of Landscape Impact

Significance Threshold of Landscape Impact

Magnitude of Change during Operation Phase

Significance Threshold of Landscape Impact

Magnitude of Change during Operation Phase

Significance Threshold of Landscape Impact

Secondary Woodland

Nil

High

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

Cut Slope

Nil

Low

Negligible

Negligible

Negligible

Negligible

Negligible

Negligible

Sea

Approx. 1.5ha. sea area reclaimed

High

Small

Moderate

Negligible

Negligible

Negligible

Negligible

Transport Corridor (i.e. existing roads and footpaths)

 

375m long existing access road.

Low

Small

Slight

Negligible

Negligible

Negligible

Negligible

Industrial Built-up area

Approx. 6.75ha. previously reclaimed land

Low

Small

Slight

Negligible

Negligible

Negligible

Negligible

Manmade Coastline

60m length

Low

Small

Slight

Negligible

Negligible

Negligible

Negligible

Roadside vegetation

0.25ha

Low

Small

Slight

Negligible

Negligible

Negligible

Negligible


Table 8.11a     Assessment of Visual Magnitude of Change (without Landscape Mitigation Measures)

 

SVR1

 

Items

Construction Phase

Operation Phase (Initial Phase)

Operation Phase (2025-2040)

a.   compatibility of the project with the surrounding landscape

Compatible

Compatible

Compatible

b.   duration of impacts under construction and operation phases

Temporary

Approximately 40 years

Approximately 40 years

c.   scale of development (when viewed from this SVR)

Distinctive but not out of scale

Distinctive but not out of scale

Distinctive but not out of scale

d.   reversibility of change

Reversible

Reversible

Reversible

e.   viewing distance

2km

2km

2km

f.    potential blockage of view

Low

Low

Low

Magnitude of Visual Change SVR1

Small

Small

Small

 

 

SVR2

 

Items

Construction Phase

Operation Phase (Initial Phase)

Operation Phase (2025-2040)

a.   compatibility of the project with the surrounding landscape

Compatible

Compatible

Compatible

b.   duration of impacts under construction and operation phases

Temporary

Approximately 40 years

Approximately 40 years

c.   scale of development (when viewed from this SVR)

Large and Distinctive

Large and Distinctive

Large and Distinctive

d.   reversibility of change

Reversible

Reversible

Reversible

e.   viewing distance

50m

50m

Next to SVR

f.    potential blockage of view

High

High

High

Magnitude of Visual Change SVR2

Intermediate

Intermediate

Large

 

 

 

 

Table 8.11a (continued) Assessment of Visual Magnitude of Change (without Landscape Mitigation Measures)

 

SVR3

 

Items

Construction Phase

Operation Phase (Initial Phase)

Operation Phase (2025-2040)

a.   compatibility of the project with the surrounding landscape

Compatible

Compatible

Compatible

b.   duration of impacts under construction and operation phases

Temporary

Approximately 40 years

Approximately 40 years

c.   scale of development (when viewed from this SVR)

Distinctive

Distinctive

Distinctive

d.   reversibility of change

Reversible

Reversible

Reversible

e.   viewing distance

250m

250m

250m

f.    potential blockage of view

High

High

High

Magnitude of Visual Change SVR3

Intermediate

Intermediate

Large

 

 

SVR4

 

Items

Construction Phase

Operation Phase (Initial Phase)

Operation Phase (2025-2040)

a.   compatibility of the project with the surrounding landscape

Compatible

Compatible

Compatible

b.   duration of impacts under construction and operation phases

Temporary

Approximately 40 years

Approximately 40 years

c.   scale of development (when viewed from this SVR)

Noticeable but not out of scale

Noticeable but not out of scale

Noticeable but not out of scale

d.   reversibility of change

Reversible

Reversible

Reversible

e.   viewing distance

6km

6km

6km

f.    potential blockage of view

Low

Low

Low

Magnitude of Visual Change SVR4

Small

Small

Small

 

 

 

 

Table 8.11a (continued) Assessment of Visual Magnitude of Change (without Landscape Mitigation Measures)

 

SVR5

 

Items

Construction Phase

Operation Phase (Initial Phase)

Operation Phase (2025-2040)

a.   compatibility of the project with the surrounding landscape

SVR not existing

SVR not existing

Compatible

b.   duration of impacts under construction and operation phases

 

 

Approximately 40 years

c.   scale of development (when viewed from this SVR)

 

 

Conspicuous in middleground

d.   reversibility of change

 

 

Reversible

e.   viewing distance

 

 

730m

f.    potential blockage of view

 

 

Low

Magnitude of Visual Change SVR5

Not Applicable

Not Applicable

Intermediate

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Table 8.11b     Assessment of Visual Impacts (without Landscape Mitigation Measures)

 

SVR

Name

Sensitivity to Change and Visual Intrusion

Construction Phase

Operation Phase Initial Phase

Operation Phase  2025 – 2040*

Magnitude of Visual Change

Significance Threshold of Visual Impact

Magnitude of Visual Change

Significance Threshold of Visual Impact

Magnitude of Visual Change

Significance Threshold of Visual Impact

SVR 1 

Sea traffic along Urmston Road

 

Vpt. 1       Urmston Road near River Trade Terminal

 

Quantity of SVRs:  small

Low

Small

Slight Adverse

 Small 

 Slight Adverse 

 Small

Slight Adverse

SVR 2

Traffic from Lung Mun Road

 

Vpt. 2 Elevated view from Lung Mun Road

 

Quantity of SVRs:  small

Low

 Intermediate

Slight/Moderate

 Intermediate

 Slight/Moderate

 Large

Moderate

SVR 3

Industrial/ Utility facilities 

 

Vpt. 3.1    From River Trade Terminal

Vpt. 3.2EcoPark (Resource Recovery Park)

 

Quantity of SVRs:  small

Low

 Intermediate

Slight/Moderate

 Intermediate

 Slight/Moderate

 Large

Moderate

 

SVR 4

North Lantau Development including Tung Chung

 

Quantity of SVRs:  large

 Medium

Small

Slight/Moderate Adverse

 Small 

 Slight/Moderate Adverse

 Small

Slight/ModerateAdverse

SVR 5

Siu Lang Shui Holiday Camp

 

Vpt 5 Future users

 

Quantity of SVRs - small

Medium

Not Applicable

None

Not Applicable

None

Intermediate

Moderate Adverse

* Operation Phase 2025-2040 has been compared to the baseline case


8.10               Recommended Landscape and Visual Mitigation Measures

 

8.10.1         Background

 

8.10.1.1   The assessment in the previous section predicts that the majority of visual impacts both during construction and initial operation at 2009 and expansion from 2025 to 2040 will be “slight adverse”.  The impact on the landscape character is predicted as negligible primarily because of the existing industrial landscape character into which the proposed PAFF will be located, as well as its remote and enclosed location. Minor adverse impacts include: a “slight adverse” landscape impact to the “Industrial/Utility” LCU 3 during construction and operation phase 2025 to2040, and a “moderate adverse” landscape impact to the “Water Frontage” LCU5 during construction.  Impacts on the visual resources and SVRs are also predicted to be slight, primarily due to the remote and enclosed location of the proposed PAFF. A “slight adverse” visual impact is, however, predicted to viewer groups at SVR2 and SVR3 at Year 2040, when the tank farm is at capacity. 

 

8.10.1.2   The key source landscape impacts arise from construction activities, such as building material delivery, construction of jetty, fuel tanks and associated facilities.  The key source of the visual impact is the permanent intrusion of the jetty and fuel tanks in views from all SVRs.

 

8.10.1.3   In order to mitigate these impacts a comprehensive range of landscape mitigation measures (LMMs) and landscape framework have been developed in-conjunction with the site planning and phasing of the site. The landscape framework includes the following enhancement and mitigation measures to be implemented in the construction phase:

 

a.         managed construction programming (LMM1);

 

b.         landscaped perimeter bund and buffer planting (LMM2);

 

c.         advanced transplantation of existing trees (LMM2);

 

d.         selection of fast growing and native tree and shrub mixes (LMM2); and

 

e.         recessive colours and recessive night-time lighting to tanks and associated buildings (LMM3 and LMM4).

 

8.10.1.4   All of the above landscape mitigation measures have been confirmed with the project proponent for incorporation into the proposed PAFF.  The mitigation measures are summarised in the following paragraphs and outlined in Tables 8.12 and 8.13, Figures 8.7.1 and 8.7.2 and in the Environmental Mitigation Implementation Schedules in Appendix B.  No off-site mitigation measures have been proposed. Table 8.14 gives a full description of the Landscape Mitigation Measures and their proposed programming, funding, implementation, management and maintenance.


8.10.2         Landscape Mitigation Measure 1 (LMM1) –Managed Construction Programming and Soil Conservation

 

8.10.2.1   Soil conservation is consideration in the management of the construction process. Existing soil resources on site such as at the existing amenity areas will be conserved in stockpiles with a maximum height of 2m, and re-used in the formation of the proposed landscaped perimeter bund (see LMM2) as far as possible. In addition soil required in formation of the temporary bund will also be conserved and stored for use on and/or off site.  Work on the bunds using material from the site has already commenced under the previous Environmental Permit EP-1/39/2002/A prior to the suspension of works following the Judgement of the Court of Final Appeal of July 2006.

 

8.10.2.2   The construction programme for the PAFF should be reduced to the shortest possible period.  Additionally, the extent and periphery of the works areas should be managed so that they are as small as possible and do not appear cluttered, untidy and unattractive, particularly to road traffic along Lung Mun Road. Temporary hoarding barriers should be of a recessive visual appearance in both colour and form. Measures should be implemented during construction to store materials in areas with the least obstruction to residents, pedestrians and traffic and cover all material stockpiles (2m high maximum) with impermeable material and sandbagging diversions around exposed soil. Construction of fuel tank expansion should be in a group of 4 to minimise the construction impacts over the period from 2025 to 2040.

 

8.10.3         Landscape Mitigation Measure 2 (LMM2) – Advanced Transplantation and Boundary Planting Buffer/Perimeter Landscape Bund

 

8.10.3.1   In accordance with the recommendation of the previous EIA Report (April 2002) which stated that the transplantation of the existing road side and site trees and vegetation should be undertaken as early as possible in the construction period, as noted above, the transplantation of 209 trees and whips was undertaken at the very start of the original construction period in 2005 prior to the quashing of the Environmental Permit and the subsequent suspension of works. A raised landscaped perimeter bund comprising containment bund-wall, access road and planting buffer is proposed around the tank farm. The planting buffer will be planted on the higher parts of the bund. This measure will help soften and screen the built elements and mitigate the landscape and visual impacts (refer to Figures 8.7.1 & 8.7.2). Planting will be undertaken to form a perimeter landscaped bund around the site at phase 2009. This will allow the maximum time for establishment period and higher success rate for the survival and the early establishment of new screen and compensatory planting. The planting buffer will comprise a mix of native species and species that have a tall habit and are fast growing. This will include rows of Causuarina (Causuarina equisetifolia) trees that will form a tall and evergreen buffer.  The Causuarina trees are anticipated to form an effective and mature screen by 2040. The following boundary planting mix is proposed:

 

a.           Dominant Species: Causuarina equisetifolia (Planted as whips and heavy standards/mature specimens where required) will be used to provide the screen effect and will therefore form the dominant species.

 

b.          Edge Species: Native and dense mix of planting is proposed along the edge (and within) of the dominant species. This will provide a more mixed edge effect and break-up the overall visual dominance of the Causuarina. The following species are proposed:

 

Trees

Low maintenance, salt and wind tolerant tree planting of heavy-standard and seedling sized trees

Shrubsand Small Tree Mix

Low maintenance, salt and wind tolerant densely planted large shrubs

Hydro_seeding Shrub and Groundcover mix Low maintenance, salt and wind tolerant grass and shrub planting

Tristania conferta

 

Nerium indicum

 

Thevetia  peruviana

Cassia suranttensis

 

Thevetia peruviana

 

Nerium indicum

Cassia siamea

 

Bauhinia tormentosa

 

 

Bombax malabaricum

 

Bauhinia galpinii

 

Ligustrum sinense

Casuarina equetisetifolia

 

Bauhinia acumentata

 

Sapium discolour

 

Hibiscus rosa-sinensis

Mekastoma candidum

Schefflera octophylla

 

Murraya paniculata

Clerodendron fragrans

Ficus microcarpa

Rhododendron pulchrum

Cynodon dactylon (Bermuda grrass)

Malaleuca leucadendron

 

Paspalum notadum

Schima superba

 

Lolium perenne

Schefflera aboricola

 

 

 

8.10.3.2   A planting scheme will be implemented as shown on Figures 8.7.4 and 8.7.5.  It will comprise planting on the proposed planting buffer at Day 1 of the construction period, site boundary and along Lung Mun Road. Compensatory planting should be at a minimum 1 to 2 basis, comprising a matrix of semi-standard and transplants at a proposed rate of 4-6m centres. A 24-month maintenance (including defects liability) period will also be needed to ensure the transplantation of the trees already undertaken and plant establishment for compensatory tree planting is successful, (refer to Figures 8.7.1-8.7.5).

 

8.10.4         Landscape Mitigation Measure 3 (LMM3) – Compact Site Planning and Sensitive Design

 

8.10.4.1   Apart from functional issues a primary role of the architectural and landscape design is to reduce adverse visual and landscape impacts to an acceptable level if possible. The key design considerations:

 

a.           Site planning: a layout which is compact as possible: This will primarily be driven from the refinement of the engineering requirements. Limiting and concentrating the zones of activity will help reduce visual impact;

 

b.          Visual Screens: landform, landscaped perimeter bunds, screen planting, walls, and fences will be used to hide activities from view. The design of the structures themselves will have a visual impact and must be designed to reduce this as far as possible; and

 

c.           Coherent Design of Structures and Materials: producing a family of structures and treatments will help co-ordinate appearance and lessen visual impact from different activities.

 

8.10.4.2   The tanks and jetty will be standardised components. Due to the high safety and risk standards that these built elements have to meet there is little opportunity to amend their design. For these built elements it is recommended that there are finished in a non-reflective neutral grey colour with a low chromatic intensity to reduce the potential contrast between the structures and their background.

 

8.10.4.3   The design of the administration office and the associated elements should incorporate materials, details and textures so as to be as visually recessive and in a style that fits with the surrounding industrial setting. The following is recommended:

 

a.           Massing and Form: The building massing will appear less if the roofs have a thin edge and if walls are set back, and are dark either in colour or by being in shadow;

 

b.          Colour: to assist the proposed built forms to recess and blend into their surroundings the use of light colours and tones of grey, green and blue are recommended. The colours surrounding the PAFF site are influenced by the reflectance of light and colour of the sea. Colours within the immediate vicinity are muted, generally light hues and tones of grey, green and blue;

 

c.           Roofs: For the roof a fired rated, durable (up to 25 years), insulated, self cleansing, rigid curved metal cladding system is proposed (either steel or aluminium). There are several standard products locally available which would be suitable. A non-reflectant (matt and/or textured) finish would be required; and

 

d.          External Walls: For the external walls it is proposed that the Office accommodation be finished in an aluminum panel to match and signify the important role of this component. General walls to be finished in ceramic tile (self cleaning/dust-proof) and/or durable textured external spray paint (Cost effective).

 

8.10.4.4   The phasing of PAFF will have a significant impact on its cumulative landscape and visual impact. The following phasing is recommended:

 

a.           Advanced Planting, and Permanent Landscaped Perimeter Bunds: to be commenced on Day 1 of construction.

 

 

 

 

 

 

8.10.5         Landscape Mitigation Measure 4 (LMM4) – Minimise the Night-time Glare

 

8.10.5.1   Compared to the existing fuel tank farm at Chek Lap Kok, the possible night-time glare from the proposed PAFF is not significant to the Tuen Mun Area 38, see Figure 8.5b, as night time glare is also found in the neighbourhood, such as from the River Trade Terminal and the Castle Peak Power Station.  However, the following lighting measures should be considered:

 

a.           minimum amount of lighting, only applied for safety at the key access points and staircases;

b.          limited lighting intensity; and

c.           directional down lighting is suggested to minimise light spill to the surrounding areas.

 

8.11               Residual Impacts and Acceptability of the Proposed PAFF

 

8.11.1         Analysis of Impacts

 

8.11.1.1   The significance of the landscape and visual impacts assuming mitigation measures included in the proposed PAFF was examined in accordance with Section 8.3. The proposed PAFF is compatible with the existing zoned special industries area. Proposed mitigation measures will help to reduce slight to negligible adverse impacts during construction and operation.

 

8.11.2         Residual Landscape Impacts

 

8.11.2.1   A summary of residual landscape impacts is shown in Table 8.12.  In general, the incorporation of mitigation measures into the proposed PAFF will be effective in reducing “slight adverse” construction impacts in Industrial/Utility LCU3 to negligible, “moderate adverse” construction impacts at Waterfront LCU5 to “slight adverse” impact.  Early implementation of the planting buffer (LMM2) will help to reduce the operational impact at LCU3 to “slight” impact. These reductions can be achieved by the mitigation measures recommended in Section 8.9 above.

 

8.11.3         Residual Visual Impacts

 

8.11.3.1   A summary of residual visual impacts is shown in Table 8.13. In general, the landscape mitigation measures are predicted to reduce the levels of visual impact of the proposed development when viewed from all SVR locations.

 

8.11.3.2   Unmitigated visual impact from SVR5 is predicted to be “moderate adverse” during the construction stage of the expansion phase of operation (2025 to 2040) mainly owing to the appearance of an additional four tanks and associated construction activity.  After completion of the tanks, the visually recessive design (LMM3) would result in the new structures being rapidly absorbed visually into the mass and scale of the existing tanks, particularly as the bulk of the new tanks would be concealed by the initial phase tanks.  Under these circumstances, the residual visual impact is forecast to be “slight/moderate adverse”. 

 

8.11.4         Acceptability of Development

 

8.11.4.1   Using the criteria as set out in Section 8.3, the significance of these residual visual impacts are evaluated as being acceptable with mitigation measures in accordance with Annex 10 of the TM EIAO, owing to the following factors:

 

a.           the proposed PAFF incorporates landscape and visual mitigation measures, which will reduce overall adverse levels of visual impact to an acceptable level. Views from the nearest residents at Miami Beach Towers and Melody Garden are obstructed by the River Trade Terminal, as shown in Figure 8.5.3, and thus, the adverse visual impacts brought by the proposed PAFF will be limited to its industrial neighbourhood denoted by SVR3 and SVR5 where the number of sensitive receivers are small and relatively insensitive.  The planting buffer and temporary landscape works for the reserved area will enhance the local visual quality.

 

b.          night-time glare is considered to be acceptable within the visual envelope.  The change to the baseline condition will be negligible; and 

 

c.           potential landscape impacts are restricted to a local level only, which is of low landscape quality and of a low sensitivity to change.  Careful phasing programme and site planning could avoid loss of roadside trees and maximise the planting buffer along the Lung Mun Road.  Within the immediate landscape context of adjacent industrial uses the proposed PAFF is predicted to be acceptable with landscape and visual mitigation measures implemented.

 

8.12               Conclusion and Summary of Findings

 

8.12.1         The major findings and residual and cumulative landscape and visual impacts predicted by the LVIA are as follows:

 

a.           The majority of the baseline condition of the study area comprises existing industrial uses and is considered to be of low quality and sensitivity to change.  A part of the study area also comprises the sea lanes of Urmiston Road and the wooded slopes (as part of Castle Peak) that is of regional importance.  These areas will not be affected by the proposed project.

b.          No areas designated with a landscape zoning such as country park, open space or green belt would be affected by the Project and therefore the Project is compatible with the Government’s statutory planning framework in terms of landscape conservation. 

c.           The Project overall would result in the loss of approximately, 0.25ha of roadside vegetation and affects 1.5ha of open sea under the jetty.  Compensatory planting will comprise 0.6ha of screen planting on the perimeter bund and roadside planting resulting in a net a gain of 0.35ha of vegetation. (This excludes the trees that have been transplanted and the bunding formed during the construction period and that will be maintained at Day 1 of operation).

d.          The introduction of the proposed project into the study area will result in mainly “slight adverse” to negligible landscape impacts assuming mitigation measures are incorporated into the scheme.

e.           The introduction of the proposed project into the study area will result in mainly “slight/moderate” and “slight” visual impacts assuming mitigation measures are incorporated into the scheme.

f.            Views toward the proposed project are generally over medium to long distances (up to 8km). At these distances the proposed project is predicted to result in an imperceptible magnitude of change and negligible adverse impact.

g.           For potentially local sensitive residents at Lung Kwu Tan to the north west and adjacent Butterfly Beach to the east it is assessed that local topography will obstruct views to the proposed project. These local residents will therefore not be adversely impacted by the proposed project.

h.           Future users at a proposed Holiday Camp at Siu Lang Shui will receive on “slight/moderate” levels of visual impact on views overlooking the proposed site during the expansion stage of the development (2025 to 2040), as the new tanks will be substantially blocked by existing tanks in front.

i.             The PAFF will be viewed in conjunction with the future EcoPark resource recycling centre, the existing steel mill, the River Trade Terminal and other industrial uses in the local district.  The visual characteristics of the PAFF are industrial in appearance and therefore compatible with these future and existing uses.  The cumulative visual impact on views from SVRs of all these elements viewed within the same panorama is not predicted to reach a level whereby it would exceed the visual impact level of the PAFF when assessed separately as summarised in Table 8.13.

 

8.12.2         The Landscape and Visual Impact Assessment highlights that no significant impacts will occur during both construction and operation phases. The disturbance to existing trees will be compensated during construction of the initial phase. The disturbed waterfront is man-made with a low sensitivity to change, landscape mitigation measures will minimise adverse impacts.  It is predicted that the proposed PAFF will have limited adverse landscape and visual impacts on the baseline conditions (through introduction of additional landscape areas).  In conclusion, the landscape and visual impacts are considered acceptable with mitigation measures.

 

8.13               Environmental Monitoring and Audit

 

8.13.1         It is recommended that implementation and operational maintenance of all proposed Landscape and Visual Mitigation Measures is included within the EM&A.  The design stage EM&A will consist of auditing the detailed landscape designs. Construction and operational stage EM&A will comprise audit of the compensatory planting/transplantation and planting establishment in the form of site inspection.  Further details of the specific EM&A requirements are detailed in Section 15 of this report and in the EM&A Manual.


Table 8.12a     Summary of Residual Landscape Impacts on LCUs (with Landscape Mitigation Measures)

 

LCU Name

Without Recommended Mitigation Measures

Recommended  Mitigation Measures

 

With Recommended Mitigation Measures

Significance Threshold of Landscape Impact during Construction

Significance Threshold of Landscape Impact during Operation

Significance Threshold of Landscape Impact during Construction

Significance Threshold of Landscape Impact during Operation Phase  Initial Phase

(Day 1)

Significance Threshold of Landscape Impact During Operation  Phase

(Year  2040)

Phase 2009

Phase to 2040

LCU 1

Woodland, grassland and scrubland

Negligible

Negligible

Negligible

Nil

Negligible

Negligible

Negligible

LCU 2

Transport Corridor

Negligible

Negligible

Negligible

Nil

Negligible

Negligible

Negligible

LCU 3

Industrial/ Utility (incorporating LCU Industrial Urban Landscape of the Landscape Character Map of Hong Kong)

Slight

Adverse

Negligible

Slight Adverse

LMM1, LMM2, LMM3, LMM4

Negligible

Slight Adverse

Negligible

LCU 4 

Pier

Negligible

Negligible

Negligible

Nil

Negligible

Negligible

Negligible

LCU 5

Water frontage

Moderate

Adverse

Negligible

Negligible

LMM2, LMM3, LMM4

Slight Adverse

Negligible

Negligible

 


Table 8.12b     Summary of Residual Landscape Impacts on Landscape Elements (with Landscape Mitigation Measures)

 

Landscape Element

Without Recommended Mitigation Measures

Recommended  Mitigation Measures

 

With Recommended Mitigation Measures

Significance Threshold of Landscape Impact during Construction

Significance Threshold of Landscape Impact during Operation

Significance Threshold of Landscape Impact during Construction

Significance Threshold of Landscape Impact during Operation Phase  Initial Phase

(Day 1)

Significance Threshold of Landscape Impact During Operation  Phase

(Year  2040)

Phase 2009

Phase to 2040

Secondary Woodland

Negligible

Negligible

Negligible

Nil

Negligible

Negligible

Negligible

Cut Slope

Negligible

Negligible

Negligible

Nil

Negligible

Negligible

Negligible

Sea

Moderate

Moderate

Moderate

LMM2, LMM3, LMM4

Slight

Slight

Slight

Transport Corridor (i.e. existing roads and footpaths)

 

Slight

Slight

Slight

LMM1, LMM2, LMM3, LMM4

Slight/Negligible

Slight/Negligible

Slight/Negligible

Industrial Built-up area

Slight

Slight

Slight

LMM1, LMM2, LMM3, LMM4

Slight/Negligible

Slight/Negligible

Slight/Negligible

Manmade Coastline

Slight

Slight

Slight

LMM1, LMM2, LMM3, LMM4

Slight/Negligible

Slight/Negligible

Slight/Negligible

Roadside vegetation

Slight

Slight

Slight

LMM1, LMM2, LMM3, LMM4

Slight/Negligible

Slight/Negligible

Slight/Negligible


Table 8.13       Summary of Residual Visual Impacts (with Landscape Mitigation Measures)

 

SVR Number

Without Recommendation Mitigation Measures

Recommended Mitigation Measures

With Recommendation Mitigation Measures

Significance Threshold of Visual Impact during Construction

Significance Threshold of Visual Impact during Operation

Significance Threshold of Visual Impact during Construction

Significance Threshold of Visual Impact during Operation

Initial Phase

Future Phase 2025-2040

Initial Phase

DAY 1

Future Phase 2025 – 2040

YEAR 2040

SVR 1  Sea traffic along Urmston Road

Slight

Adverse

Slight Adverse

Slight Adverse

LMM1, LMM2, LMM3, LMM4

Slight

Slight

Slight

SVR 2  Traffic from LungMun Road

Slight/Moderate

 

Slight/Moderate

Moderate

LMM1, LMM2, LMM3, LMM4

Slight

Slight

Slight/Moderate

SVR 3  Industrial/ Utility facilities

Slight/ Moderate

 

Slight/Moderate

Moderate

LMM1, LMM2, LMM3, LMM4

Slight

Slight

Slight/Moderate

SVR 4 North Lantau Development including Ting Chung

Slight/Moderate Adverse

Slight/Moderate Adverse

Slight/ModerateAdverse

LMM1, LMM2, LMM3, LMM4

Slight

Slight

Slight

SVR 5 Proposed Holiday Camp

None

None

Moderate

LMM3, LMM4

Moderate Adverse (Expansion phase construction stage only)

 N/A

 Slight/Moderate


Table 8.14       Summary Landscape Mitigation Measures Programming, Funding, Implementation, Management and Maintenance Agents

 

LMM Reference

Description of Landscape Mitigation Measures

Programming

Programme Stages

Funding and Implementation Agent

Management and Maintenance

Agency

D

C

O

LMM1

The construction programme for the PAFF should be reduced to the shortest possible period and should be executed in phases with future phases of tanks built in a set of 4.

PAFF site / throughout construction period

Y

Y

 

Project Proponent

Project Proponent

LMM1

The extent and periphery of the works areas should be managed so that they are as small as possible and do not appear cluttered, untidy and unattractive, particularly to road traffic along Lung Mun Road.

PAFF site /  throughout construction period

 

 

Y

Y

Project Proponent

Project Proponent

LMM1

Temporary hoarding barriers should be of a recessive visual appearance in both colour and form.

PAFF site /  throughout construction period

Y

Y

 

 

Project Proponent

Project Proponent

LMM1

Materials should be stored in areas with the least obstruction to residents, pedestrians and traffic

PAFF site /  throughout construction period

 

 

Y

Y

Project Proponent

Project Proponent

LMM1

All material stockpiles (2m high maximum) should be covered with an impermeable material and sandbagging diversions should be placed around exposed soil

PAFF site /  throughout construction period

 

 

Y

Y

Project Proponent

Project Proponent

LMM1

Conservation of existing and imported soil resources. Existing soil resources on site will be conserved in stockpiles with a maximum height of 2m(see LMM2).  

PAFF site / throughout construction period of fuel tank expansion.

 

 

 

Y

Project Proponent

Project Proponent

LMM2

A landscaped perimeter bund comprising containment bund-wall, access road and planting buffer shall be built and maintained around the tank farm.

PAFF site/ On Commencement of Construction

Y

Y

Y

Project Proponent

Project Proponent

LMM3

The design of the PAFF should incorporate materials, details and textures that are visually recessive.

PAFF site /design

Y

Y

Y

Project Proponent

Project Proponent

LMM3

Colours should be of low chromatic intensity to reduce the potential contrast between the structures and their background

PAFF site /design

Y

Y

Y

Project Proponent

Project Proponent

LMM4

Minimum amount of lighting for the tanks shall be used, only applied for safety at the key access points and staircases

Tanks/Operational phase

Y

Y

Y

Project Proponent

Project Proponent

LMM4

Limited lighting intensity on the site

PAFF site /Operational phase

Y

Y

Y

Project Proponent

Project Proponent

LMM4

Directional down lighting is suggested to minimise light spill to the surrounding area.

 

PAFF site /Operational phase

Y

Y

Y

Project Proponent

Project Proponent