1 INTRODUCTION
1.1.1
A Permanent Aviation Fuel Facility (PAFF) is required to ensure a
secure means to supply aviation fuel during the operational lifetime of the
Hong Kong International Airport (HKIA).
The PAFF will replace the existing temporary Aviation Fuel Receiving
Facility adjacent to Sha Chau, as the existing facility does not have
sufficient capacity. The PAFF must meet the capacity demand for the 2040
planning horizon of the airport and must be able to provide for strategic
storage. The Airport Authority Hong Kong
(AAHK) is committed to provide a replacement facility, after which the Sha Chau
facility will be used for emergency backup purposes only. The proposed PAFF
with its associated pipeline and jetty is shown in Figure 1.1.
1.1.2
The proposed project is designated under Sections H.2 and L.4 of
Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) and as such
the statutory procedures under the EIAO need to be followed and an
environmental permit is required prior to the commencement of construction.
1.1.3 The AAHK first commissioned Meinhardt Infrastructure and Environment Ltd (known as Mouchel Asia Limited at that time) in June 2001 to provide professional environmental services in respect of assessing Tuen Mun Area 38 as the location for a PAFF and to proceed with obtaining an Environmental Permit for the PAFF based on the EIA Study Brief No. ESB-072/2001 received from the Environmental Protection Department (EPD). An EIA of the PAFF facility (EIAO Register Number AEIAR-062-2002), based upon the layout detailed in Figure 2.1a, was prepared in accordance with EIA Study Brief issued by the EPD in May 2001 and submitted under the EIAO in May 2002 and subsequently Environmental Permit EP-139/2002 was granted on the 28th August 2002.
1.1.4 However, the decision by EPD to grant the Environmental Permit was subject to a Judicial Review, with further details provided on Section 1.1.5 of the EIA Report. The Judicial Review sided in the favour of the DEP, as did the subsequent Judgement from the Court of Appeal from the High Court for Judicial Review in March 2005. However, the DEP’s decision to grant the EP was quashed by the Judgement of the Court of Final Appeal of July 2006.
1.1.5 Construction work for the PAFF had commenced as early as November 2005 under Environmental Permit EP-139/2002 but works were stopped following the Judgement of the Court of Final Appeal of July 2006. As such, in order to continue with the construction of the project, the project needs to again go through the statutory procedures under the EIAO in order to obtain an environmental permit.
1.1.6 As noted above, while the previous EIA study (April 2002) was undertaken based upon the project layout detailed in Figure 2.1a, the need for minor changes to the detailed layout of the site and the site boundary were identified and consequently an Application for Variation to the Environmental Permit (VEP) (VEP-133/2004) was submitted to the Director of Environmental Protection (DEP) for approval of the following changes:
¨ A change in the detailed layout
of the site, in particular the designed height and dimension of the tanks. The height of the tanks has been reduced in
compliance with FSD’s specific requirements, where as the diameters of some
tanks have been increased as a consequence of compliance with FSD’s tanks
height reduction requirements in order to maintain the designed fuel storage
capacity of the tank farm.
¨ A shift of the whole site by 10 metres
to the southeast to accommodate Land’s Department’s commitment of land
extension to Shiu Wing Steel Ltd.
1.2.1 The variation to the EP (EP-139/2002/A) was granted by EPD in February 2004. Details of the revised layout are provided in Section 2, Project Description and Figure 2.1b. In addition, the phasing of the tanks has changed with 8 (eight) to be constructed initially as shown in Figure 2.1c. The key objectives of this Assignment is, therefore, to update the previous EIA study (April 2002) taking into account changes in the site layout as necessary. Also, given the time lapse between the previous and this EIA study, relevant changes to the surrounding area including additional sensitive receivers have also been taken into account. The details and recommendations of the Judgement of the Court of Final Appeal of July 2006 must also be followed in updating the previous EIA Report.
1.1.7 The current EIA for the project has recommended comprehensive Environmental Monitoring and Audit requirements to be undertaken during the construction and operational stages of the project. This Report constitutes the Environmental Monitoring and Audit (EM&A) Manual for the proposed Permanent Aviation Fuel Facility, providing details of the EM&A recommendations and constitutes and update from the previous EM&A (April 2002), including the following additional details:
¨ Section 5: Ecology - details on dolphin monitoring requirements
specified;
¨ Section 6: Water Quality -
additional water quality monitoring stations added to the EM&A programme
and details on water quality monitoring requirements specified.
¨ Section 9: Cultural Heritage -
new section detailing marine archaeology requirements.
1.1.8
The Hong Kong SAR Government’s applicable
environmental regulations for noise, air quality, ecology, water quality,
landscape and visual resources, waste management and heritage protection, the
Hong Kong Planning Standards and Guidelines and recommendations in the
Permanent Aviation Fuel Facility EIA Report have served as guidance documents
in the preparation of this Manual. This
EM&A Manual fulfills the requirements of the EIA Study Brief, Clause
3.3.15, and follows the approach recommended in EPD’s Generic EM&A Manual,
Annex 21 of the Technical Memorandum on the EIA Process and EM&A Guidelines
for Development Projects in
1.2.1 The
Franchisee’s Site Representative (FSR) and the Contractor shall adopt
Environmental Policy Statements in accordance with the requirements of this
Manual in order to foster a sound EM&A programme to protect the
environment. The following policy
statements shall be adopted:
¨
establish a
commitment to environmental excellence in all activities arising from the
development project;
¨
encourage
the adoption of environmental management principles to prevent potential
impacts and minimise adverse impacts; and
¨
commit to
the recommendations in the EIA study report and related EIA process
requirements.
1.3.1
The broad objective of this EM&A Manual is to define the procedures
of the EM&A programme for monitoring the environmental performance of the
Permanent Aviation Fuel Facility project during design, construction and
implementation.
1.3.2
The manual provides details of the environmental monitoring and audit
requirements arising from the EIA for water quality, noise, air, water quality,
ecology, landscape and visual, waste, land contamination, hazard to life and
fuel spill risks and cultural heritage. The purposes of the defined EM&A
programme are as follows:
¨
to ensure
the specified mitigation recommendations of the EIA are included in the design
of the project;
¨
to clarify and
identify sources of pollution, impact and nuisance arising from the works;
¨
to confirm
compliance with legal, contract specifications and EIA study recommendations;
¨
to provide
an early warning system for impact prevention;
¨
to provide
a database of environmental parameters against which to determine any short
term or long term environmental impacts;
¨
to propose
timely, cost-effective and viable solutions to actual or potential
environmental issues;
¨
to monitor performance
of the mitigation measures and to assess their effectiveness and, whenever
necessary, identify any further need for additional measures;
¨
to verify
the EIA predicted impacts;
¨
to collate
information and evidence for use in public, District Council and Government
consultation; and
¨
to audit
environmental performance.
1.3.2
EM&A procedures
are required during the design, construction and operational phases of the
project implementation and a summary of the requirements for each of the
environmental parameters is detailed in Table 1.1 below.
Table 1.1 Summary of EM&A Requirements
Parameter |
EM&A Phase |
||
Design Phase(1)
|
Construction Phase |
Operational Phase |
|
Air Quality |
- |
Y |
- |
Noise |
- |
Y |
- |
Water Quality |
- |
Y |
Y |
Ecology |
- |
Y |
- |
Landscape and Visual |
Y |
Y |
Y |
Cultural Heritage |
- |
Y |
- |
Hazard to Life |
Y |
- |
Y |
Fuel Spillage Risk |
Y |
- |
Y |
Fisheries |
- |
- |
- |
Land Contamination |
Y |
- |
Y |
Waste |
- |
Y |
- |
Note: (1) Detailed design of the facility will extend into the construction period and as such EM&A for the Design Phase refers to audit of the design as and when it is completed and not necessary pre-construction.
1.4 Scope of the
EM&A Programme
1.4.1 The scope of the
EM&A programme is to undertake the following:
(i)
Implement
monitoring and audit activities for each environmental parameter as follows:
Dust: a) Implement construction phase audit requirements for dust aspects.
Noise: a) Implement construction phase audit requirements for noise aspects.
Ecology: a) Implement
post-construction phase dolphin abundance monitoring prior to the operation of
the PAFF.
Water Quality: a) Establish
baseline water quality levels at specified locations and review these levels on
a regular basis.
b) Implement construction water quality impact
monitoring programme.
Landscape a) Design
detailed landscape specifications.
and Visual b) Implement
baseline survey to establish/confirm
existing
landscape and visual conditions.
b)
Implement construction phase audit requirements for
landscape and visual resources.
c)
Implement operational phase audit requirements for
landscape and visual resources.
Waste a) Implement
construction phase audit requirements for waste aspects.
Heritage a) Implement construction phase audit requirements for marine archaeological resources in accordance
with MAI requirements and recommendations.
Hazard to Life
Fuel
Spill Risk
Land
Contam. a) Prepare an
Environmental Management Plan within 3 months of the commencement of the
operation of the PAFF to ensure the on-going adequacy of the fuel spill
contingency plan and that it is being implemented as required and that the
above mitigation measures have been incorporated and are effective. Undertake regular audits at least every 24
months as part of the implementation of the EMP.
b) The Franchisee to undertake regular inspections
and audits two inspections every year of the tank farm, jetty and pipelines
including one undertaken pursuant to the Joint Inspection Group (JIG) explained
above; inspection of the whole sub sea pipelines every 5 to 10 years; Health, Safety and Environmental audit of
the facility once every 3 years; and inspection of the structural integrity of
the tanks once per year.
c) During the operational phase, undertake a
review of the EIA report at the time of the planning for the Phase II expansion
of the tank farm (around 2025 as required) to ensure that the required measures
in terms of latest technology, standards and statutory requirements are taken
account in the planning and design of the future tanks. This is only required if the latest technology,
standards and statutory requirements are deemed to have changed at that time.
d) The Franchisee to undertake some routine
monitoring of water quality in the vicinity of the PAFF site to check the
effectiveness of the proposed precautionary
measures implemented for on-site spill control. Details will be agreed with the relevant authorities within 3 months of
the commencement of operation of the PAFF.
(ii) Liaison
and provision of advice to construction site staff on the purposes and implementation
of the EM&A programme.
(iii) Identify
and resolve environmental issues that may arise from the project.
(iv) Check
and quantify the Contractor’s overall performance, implement Event/Action Plans
and recommend and implement remedial actions to mitigate adverse environmental
effects as identified by the EM&A programme and EIA.
(v)
Conduct
monthly reviews of monitored impact data during the construction phase and
bi-monthly reviews during the operational phase as the basis for assessing
compliance with defined criteria and ensuring that necessary mitigation
measures are identified, designed and implemented and to undertake additional
ad hoc monitoring and audit as required by particular circumstances.
(vi) Evaluate
and interpret all environmental monitoring data to provide an early indication
should any of the environmental control measures or practices fail to achieve
the acceptable standards and to verify the environmental impacts predicted in
the EIA.
(vii) Manage
and liaise with other individuals or parties concerning any relevant
environmental issues.
(viii) Audit
the effectiveness of the Environmental Management System (EMS) practices and
procedures and implement any changes as appropriate.
(ix) Conduct
regular site audits of formal or informal nature to assess:
- the
level of the Contractor’s general environmental awareness;
- the
Contractor’s implementation of the recommendations in the EIA;
- the
Contractor’s performance as measured by the EM&A;
- the
need for specific mitigation measures to be implemented or the continued usage
of those previously agreed; and
-
to advise the site staff of any identified potential
environmental issues.
(x) Submit
EM&A reports which summarise project monitoring and auditing data, with
full interpretation, illustrating the acceptability or otherwise of any
environmental impacts and identification or assessment of the implementation
status of agreed mitigation measures.
1.4.2 Thus, this EM&A Manual provides the
following information:
(i) Description of the project.
(ii) Identification and recommendations for
monitoring requirements for all phases of development, including:
¨
identification
of sensitive receivers;
¨
monitoring
locations;
¨
monitoring
parameters and frequencies;
¨
monitoring
equipment to be used;
¨
programmes
for baseline monitoring and impact monitoring; and
¨
data
management of monitoring results.
(iii) The organisation management structure, and
procedures for auditing of the Project and implementation of mitigation
measures that are recommended for the Project.
(iv) The environmental quality performance
limits for compliance auditing for each of the recommended monitoring parameters
to ensure compliance with relevant environmental quality objectives, statutory
or planning standards.
(v) Organisation and management structure,
and procedures for reviewing the design submissions, monitoring results and
auditing the compliance of the monitoring data with the environmental quality
performance limits, contractual and regulatory requirements, and environmental
policies and standards.
(vi) Event and Action plans for impact and
compliance procedures.
(vii) Complaints handling, liaison and
consultation procedures.
(viii) Interim notification of exceedances,
reporting procedures, report formats and reporting frequency including
periodical quarterly summary reports and annual reviews to cover all
construction, post-Project and operational phases of the development.
(ix)
Implementation schedules, summarising all recommended
mitigation measures.
1.4.3 This Manual is considered to be a working
document and should be reviewed periodically and revised once substantial
changes have been made.
1.5.1
For the purpose of this EM&A Manual, the Airport
Authority Hong Kong appointed Franchisee is referred to as the “Employer” and
the Project “Engineer” defined as the Franchisee’s Site Representative (FSR),
who will be responsible for the supervision of the construction of the Project.
1.5.2
The specifications for certain risk and spill control mitigation
measures will be required to be designed during the detailed design phase of
the project. These items will include:
¨ land and marine spill response plan;
¨ pipeline leak detection and automatic shut-off system;
¨ pipeline rock armour protection;
¨ tank high level shut-off;
¨ tank bunding;
¨ tank leak drainage isolation and containment system;
¨ on-site fire fighting equipment;
¨ jetty protection; and
¨ emergency shut down valves for fuel delivery.
1.5.3
In addition, the landscape design drawings and dolphin
exclusion zone during dredging will require specifications during the detailed
design and could require the input of specialists.
1.5.4
In respect of the design phase EM&A, the Engineer
commissioned to undertake the Design and Construction Assignment will be
required to designate an auditor(s) to undertake an environmental audit of the design
of these measures in order to ensure that the recommendations of the EIA have
been fully and properly specified.
Detailed design of the facility will extend into the construction period
and as such EM&A for the Design Phase refers to audit of the design as and
when it is completed and not necessary pre-construction. As such, the design
audit shall be undertaken as and when the relevant design aspects are produced
and the Engineer will be required to prepare a Design Audit Report at the end
of the detailed design which will confirm that the requirements of the EIA have
been fully taken into account in the project design. The Engineer shall use suitably qualified
staff to undertake the audit requirements.
A flow chart of the design phase EM&A procedures is shown in Figure
1.2.
1.5.5
During the construction phase of the project, an
Environmental Team Leader (ETL) is to be employed by the Contractor. He shall ensure the Contractor’s compliance with
the project’s environmental performance requirements during construction and
undertake the post construction EM&A works and his responsibilities will
include field measurements, sampling, analysis of monitoring results, reporting
and auditing. The ETL shall be approved
by the ER and shall be competent and shall have at least 7 years relevant
environmental monitoring and audit experience on projects of a similar scale
and nature.
1.5.6
The ETL will require suitably qualified support staff (the Environmental
Team, (ET)) to carrying out the EM&A programme. Both the ETL and members of the ET shall be
independent and shall not be in any way connected to the Contractor’s company. Due to the specialist nature of some of the
EM&A works required for this project, the ET should comprise professionals
proficient to undertake the tasks involved.
Thus, the ET should include personnel experienced in noise, dust and
water quality monitoring and supervision of waste management.
1.5.7
Accordingly, qualified specialists in dolphin survey
monitoring, with a minimum of 2 years post qualification experience and two
years practical experience in this field, will be required as part of the ET to
undertake the post construction abundance monitoring of the dolphins prior to
the operation of the facility. In addition, a Registered Landscape Architect,
as defined by the Landscape Architect’s Registration Board, will be required on
the ET to monitor and audit the landscaping installation works.
1.5.8
In addition, a qualified marine archaeologist to the
satisfaction of the AMO will be required to undertake the audit of the
potential marine archaeological resources as defined by the Marine
Archaeological Investigation. The qualified archaeologist should possess
professional qualifications such as an academic degree in archaeology, relevant
experience in marine archaeology at a supervision level and be familiar with
the archaeology of Hong Kong and/or
1.5.9
The future, operational stage, EIA review at the planning
stage for the future tanks should be undertaken by an environmental specialist appointed by
the Franchisee at that time.
1.5.10
The overall duties of ETL and the team are as follows:
¨
Sampling, analysis
and statistical evaluation of monitoring parameters with reference to the EIA
study recommendations and requirements in respect of water quality.
¨
Environmental
site surveillance.
¨
Audit of compliance
with environmental protection and pollution prevention and control regulations.
¨
Monitor the
implementation of environmental mitigation measures.
¨
Monitor
compliance with the environmental protection clauses/specifications in the
Contract.
¨
Review
construction programme and comment as necessary.
¨
Review
construction methodology and comment as necessary.
¨
Complaint
investigation, evaluation and identification of corrective measures.
¨
Audit of
the
¨
Liaison
with the Independent Checker (Environment) (IEC) on all environmental
performance matters.
¨
Advice to
the Contractor on environmental improvement, awareness, enhancement matter,
etc., on site.
¨
Timely submission
of the designated EM&A reports to the FSR, the IEC, the DEP, the AFCD, the
AMO and PlanD/LPU as appropriate.
1.5.11
In addition to the ETL and ET, an Independent Checker
(Environment) (IEC) shall be employed to advise the ER on environmental issues related
to the project. The role of the IEC
shall be independent from the management of construction works, but the IEC
shall be empowered to audit the environmental performance of the construction
activities and operational mitigation.
The IEC shall have project management experience in addition to the
requirements of the ETL specified in Section 1.5.5 and the appointment of the
ICE will be subject to the approval of the FSR.
The IEC may require specialist support staff in order to properly carry
out his duties which shall include the following:
¨
Review and
audit all aspects of the EM&A programme.
¨
Validate
and confirm the accuracy of monitoring results, monitoring equipment,
monitoring locations, monitoring procedures and locations of sensitive receivers.
¨
Carry out
random sample check and audit on monitoring data and sampling procedures, etc.
¨
Conduct
random site inspection.
¨
Audit the
EIA recommendations and requirements against the status of implementation of environmental
protection measures on site.
¨
Review the
effectiveness of environmental mitigation measures and project environmental
performance.
¨
Audit the
Contractor’s construction methodology and agree the least impact alternative in
consultation with the ETL and the Contractor.
¨
Check
complaint cases and the effectiveness of corrective measures.
¨
Review
EM&A report submitted by the ETL.
¨
Feedback
audit results to ETL by signing off relevant EM&A proformas.
1.5.12
An organisation chart showing the lines of communication
between the key parties with respect to the EM&A works is provided on
Figure 1.3. Both the ETL and IEC shall be retained for the duration of the
EM&A works which will span the construction phase. The operational EM&A works will be the
responsibility of the Contractor and will be undertaken in parallel to the
maintenance period after the completion of construction.
1.6.1 To clarify the terminology for impact
monitoring and audit, key definitions are specified below and are used
throughout this Manual.
1.6.2
Monitoring refers to the systematic collection of data
through a series of repetitive measurements. The stages of monitoring are
defined in this document as follows:
(i) Baseline Monitoring refers to the
measurement of parameters, such as noise and air quality impact parameters,
during a representative pre-project period for the purpose of determining the
nature and ranges of natural variation and to establish, where appropriate, the
nature of change.
(ii)
Impact Monitoring involves the measurement of environmental
impact parameters, such as noise and air quality, during Project construction
and implementation so as to detect changes in these parameters which can be
attributed to the Project.
1.6.3 Audit is a term that infers the
verification of a practice and certification of data. The types of audit are
defined below:
(i)
Compliance audit is defined as follows:
¨
the process
of verification that all or selected parameters measured by a noise or air
quality impact monitoring programme or levels of an operation are in compliance
with regulatory requirements and internal policies and standards; and
¨
the determination
of the degree and scope of any necessary remediation in the event of exceedance
of compliance.
(ii) Post Project Audit is carried out after
the implementation and commissioning of a Project.
1.6.4 For the purpose of noise, air and water quality
impact monitoring and audit, the Action and Limit Levels are defined as
follows:
(i) The Action Level is the level defined in which there is an indication of a deteriorating ambient level for which a typical response could be an increase in the monitoring frequency.
(ii) The Limit Level is the level beyond the appropriate remedial pollution control ordinances, noise and air quality impact objectives or Hong Kong Planning Standards and Guidelines established by the EPD for a particular project, such that the works should not proceed without appropriate remedial action, including a critical review of plant and work methods.