2.                            PROJECT DESCRIPTION

 

2.1                        Background

 

2.1.1                  The project is entitled “Drainage Improvement in Northern New Territories – Package C” and is referred to as “the Project”. It is one of the work packages recommended by the Drainage Master Plan in the Northern New Territories (DMP Study).

 

2.1.2                  The Preliminary Project Feasibility Study (PPFS) completed in August 2001 under the DMP Study concluded that rapid developments in the study area have resulted in higher runoff and some existing drainage systems are inadequate in respect to flood protection capacities. Consequently, severe flooding occurs in these low-lying areas during heavy rainfall.

 

2.1.3                  The proposed drainage improvements to designated project (DP) channels under the Project involve the construction of the secondary local drainage channels at Lin Ma Hang in the Ganges Basin and the secondary and local channels at Man Uk Pin in the Indus Basin. The purpose of the Project is to alleviate recurring flooding problems in Man Uk Pin and Lin Ma Hang areas by improving the secondary and local stormwater drainage systems in accordance with the recommendation of the DMP Study. Figure 1.1 shows the locations of all the proposed drainage channels. Figure 2.1 shows the locations of the proposed DP
channels. The DP channels are assessed in this EIA Study.

 

2.1.4                  An Environmental Review (ER) was completed in May 2000 under the DMP Study to assess potential environmental impacts of the proposed drainage improvement works. The ER concluded that several components of the proposed drainage improvement works are regarded as a DP under the Environmental Impact Assessment Ordinance (EIAO).

 

2.2                        Location and Description of the Project

 

2.2.1                  The drainage improvement work for Package C involves construction of river channels in the identified flood-prone regions. The proposed works consist of improving the river channels to convey a 10 year return period event including freeboard within the channel banks meeting the flood protection standard for villages. Details of the proposed works are provided below and shown in Figures 2.2 – 2.5.

 

                


Lung Yeuk Tau and Kwan Tei South Region

 

2.2.2                  The proposed works within this region consist of widening and formalizing the existing channel, LYT04.

 

2.2.3                  The proposed channel, LYT04, was previously identified as a DP. Subsequent to design changes, LYT04 is confirmed as not a DP. Further elaboration is provided below.

 

2.2.4                  LYT04 was originally proposed as a 2 m wide open concrete channel in the DMP Study (Figure 2.6). It was considered as a DP by virtue of Item I.1(b)(ii) of the EIAO as it discharges into an area within 300 m of an existing site of cultural heritage (the Entrance Tower of Ma Wat Wai) and an EIA Study Brief covering LYT04 together with other DPs in Package C works was obtained.

 

2.2.5                  However, during the public consultation, the villagers of Shung Him Tong objected the previous proposal of open channel along private lands and requested alternative options. Upgrading of the existing underground single-cell box culvert is proposed to convey flows from upland catchment to the tributary of Ma Wat Channel near Ma Wat Wai. The existing underground single-cell box culvert will be replaced by a new 107 m long twin-cell box culvert of internal cell size, 2.3 m wide by 2.3 m high underneath the access road connecting Ma Wat Wai and Shung Him Tong area (Figure 2.7). The downstream interfaced section of Ma Wat Channel and its tributary have already been trained. There were no further objections by the villagers on the revised design.

 

2.2.6                  Based on revised scope and design of LYT04 which does not involve drainage channel works, it was confirmed that the works is not regarded as DP under the EIAO and hence would not be subject to the provision of the Ordinance. Relevant correspondence pertaining to LYT04 is enclosed in Appendix A2.

 

Man Uk Ping Region

 

2.2.7                  Works within this region consist of upgrading and improving the River Indus, its tributaries and two roadside drains within Man Uk Pin region. The works are subdivided into five reaches, three of which are DPs as it discharges into an area within 300 m from the nearest boundary of an existing Conservation Area land use zoning.

 

2.2.8                  The original preliminary channel design consists of channels with concrete base and geotextile reinforced grass as banks (Figure 2.8). Further design changes has been undertaken to align with the recommendations in the Government’s technical circulars on protection of natural streams and rivers and to take into account comments received during public consultation.

 

2.2.9                  The proposed channel MUP03 (Figures 2.2 & 2.3) is located to the north of Loi Tung Village running in an east-west direction. Improvement works are proposed to the existing crossroad pipe and roadside drains on the southern verge of Sha Tau Kok Road (Wo Hang Section) westbound carriageway. The works include about 90 m of trapezoidal channel with a base width of 1.2 m and about 150 m of U-channel with 600 mm nominal width. MUP03 will connect with River Indus (Channel MUP05) through the proposed crossroad box culvert of internal size of 1 m high and 3 m wide and the 600 mm diameter crossroad drainage pipe under Sha Tau Kok Road. For ease of differentiation, the proposed trapezoidal channel is referred as MUP03B while the U-channel is referred as MUP03A.

 

2.2.10              The proposed channel MUP04B (Figure 2.3) is located to the west of Loi Tung Village along the southern verge of Sha Tau Kok Road (Wo Hang Section). The proposed channel MUP04A (Figure 2.3) is located at the southwestern side of Man Uk Pin and Loi Tung village running in north-south direction.

 

2.2.11              Surface roadside drains (MUP04B) and a trapezoidal gabion channel (MUP04A) are proposed to collect flow from upland and Loi Tung areas. The existing local stream at Loi Tung is to be upgraded as the trapezoidal channel (MUP04A) of size 4.5 m (base width) by 1.75 m (depth) which will tie into River Indus at the downstream via three proposed 1950 mm diameter crossroad drainage pipes underneath Sha Tau Kok Road. Surface drains (MUP04B) consist of U-channels and carrier pipes to be constructed alongside the southern verge of Sha Tau Kok Road westbound carriageway.

 

2.2.12              The proposed channel MUP05 (Figures 2.2, 2.3 and 2.5) is located at the existing River Indus at the southwest of Loi Tung Village running along the northern verge of Sha Tau Kok Road (Wo Hang Section). The improvement to the existing River Indus is proposed from its confluence with MUP01 and MUP02 extending to the existing culvert underneath Wo Keng Shan Road over a length of approximately 690 m. A further 320 m of roadside drain along the north of Sha Tau Kok Road from the confluence with MUP01 and MUP02 to the access to Man Uk Pin Village will also be improved.  The proposed channel of the River Indus is a ‘Two-Stage Channel’ of maximum 2.5 m deep, while the roadside drain is proposed to be a 3 m (base width) by 2.8 m (depth) trapezoidal gabion channel with a short section of single cell box culvert.

 

2.2.13              The other proposed channels in the region (MUP01 and MUP02) are non-DP. These are included in the EIA for potential cumulative impacts.

 

 

Lin Ma Hang Region

 

2.2.14              The DMP Study recommends a flood by-pass channel of approximate 250 m in length and average 4 m wide concrete base to alleviate flooding at Lin Ma Hang (Figure 2.9). During the Adoptive Review Stage, an alternative scheme of raising local access bridges and bank levels was proposed, thereby achieving the objective of flood prevention without taking up the potentially valuable wetland area or Lin Ma Hang stream for the construction of the flood by-pass channel. This is discussed further in the subsequent sections.

 

2.2.15              The adopted proposed drainage improvement works along the existing Lin Ma Hang stream, LMH01 (Figure 2.4), consist of replacing the existing sub-standard screen with a combination of flap valve and security grille underneath the Border Road at the confluence with the Shenzhen River. The primary function is to avoid accumulation of obstacles and to provide a secure boundary. The improvement works also include modifying short section of concrete lined channel to gabion channel just upstream of the Border Road, localized bank improvement and reconstruction of vehicular crossings just upstream of Lin Ma Hang Village. Level recorders / sensors will be installed at the watercourse which will be linked to flood sirens within the village.

 

2.2.16              The general location plan of the proposed DP channels is shown in Figure 2.1. The major items of DP channel works as assessed in the EIA are summarized in Table 2.1 below and shown in Figures 2.2 – 2.5.

 


Table 2.1

Summary of Works for the Proposed Designated Projects of Channel Improvement Works

 

Channel

Proposed Works

Extent of Works

Approximate Length

Approximate Width

Approximate Depth

MUP03
(Figures 2.2 & 2.3)

U-channel (Diameter = 0.6m)

150m

-

-

Drainage pipe (Diameter = 0.6m)

12m

-

-

Box culvert connecting MUP05

28m

3m

1m

Trapezoidal channel with gabion walls and mattress lining

93m

Top = 2.4m – 2.7m
Base = 1.2m

1.2m – 1.5m

Re-provision of crossings

One footbridge

MUP04A
(Figure 2.3)

Trapezoidal channel with gabion walls and mattress lining

163m

Top = 6.3m
Base = 4.5m

1.75m

Drainage pipes (Diameter = 1.95m)

21m

-

-

Re-provision of crossings

Two vehicular bridges

MUP04B
(Figure 2.3)

U-channel (Diameter = 0.9m)

58m

-

-

Drainage pipes (Diameter = 1.35m)

138m

-

-

MUP05
(Figures 2.2 & 2.3)

Trapezoidal channel with gabion walls and mattress lining

287m

2m – 3m

2m – 2.8m

Trapezoidal channel with gabion walls and mattress lining

54m

Top = 15.4m
Base = 13m

2.5m

Two-stage channel with existing natural river bed retained

554m

Top = 15.4m
Base = 13m

2.5m

Trapezoidal channel with gabion walls and mattress lining

69m

Top = 20.3m
Base = 13.7m

2.2m

Box culvert

50m

3m

2m

Re-provision of crossings

Five footbridges, four vehicular bridges

LMH01
(Figure 2.4)

Gabion channel and localised bank improvement

190m

5m

1.5m

Re-provision of crossings

Three vehicular bridges

 

Notes:

Other ancillary works include provision of inlet/outlet pipes, maintenance ramps & accesses and final landscaping works.

 


2.3                        Consideration of the Merit of the Proposed Project for Flood Alleviation

 

Standard of Flood Protection

 

2.3.1                  The current standard of flood protection of the watercourses is very low, with the majority having a standard of protection of 1 year or less. These watercourses were highlighted in the DMP Study as having insufficient flow capacity leading to localized flooding and causing danger to villagers and risk of economic loss.

 

2.3.2                  In view of the fact that most of the proposed secondary channels under Package C project are currently located in relatively rural areas, the sizes of these secondary channels are designed to achieve the standards set out in the Stormwater Drainage Manual for village drainage with the current sizes of the downstream channels under the existing scenario for the planned development conditions (equivalent to the DMP’s Planned Scenario). This design requirement could avoid unnecessarily large sizes of the proposed channels due to the limitation on capacities of the downstream channels / rivers. As such, upgrading works to the Package C channels shall be designed to achieve a 10 year design return period flood protection standard under the existing scenario for the planned development conditions for villages.

 

MUP Channels

 

2.3.3                  Extensive hydraulic and hydrological predictions were carried out at Man Uk Pin area. Figure 2.10 shows the flood extent map under a 10 year return period event with and without the proposed project at Man Uk Pin. As shown in the figure, without the proposed channels, there would be flooding ranging from 0.1 m deep to more than 2 m deep during heavy rainstorm.

 

MUP04A

 

2.3.4                  Site survey reveals flooding occurs at both the village area and the agricultural fields further upstream. Site visit also indicates that while the upstream portion consist of active and inactive agricultural fields, the downstream portion has been heavily disturbed from village development (portion of the stream has been culverted for an access road) with construction debris found dumped at the stream banks. It is therefore proposed to channelised the heavily modified downstream portion with gabion channel while leaving the upstream portion untouched to minimize impact on the stream habitats, the aquatic life therein and the wildlife that depends on the stream.

 


MUP05

 

2.3.5                  To minimize ecological impact to the stream at MUP05, ‘two-stage’ channel design has been adopted whereby natural stream banks and bed will be retained.

 

2.3.6                  Hydraulic modelling results revealed that the extent of improvements for the channels MUP01 and MUP02 (Non-DP elements but identified as Ecologically Important Streams (EIS)) could be modified due to the direct beneficial effect on flow conveyance after upgrading the channel MUP05 at their immediate downstream. The flooding situation of MUP01 and MUP02 can be further improved by removing the existing bottleneck at their confluence with the proposed MUP05 near Sha Tau Kok Road. Channelisation works for MUP01 and MUP02 have been substantially replaced by localised bank raising works as a result of the proposed MUP05 works.

 

LMH01

 

2.3.7                  Lin Ma Hang is located to the east of Wang Lek in the Ganges Basin. The Lin Ma Hang stream (LMH01) is to the north of Lin Ma Hang village running in south-north direction. The existing watercourse discharges to Shenzhen River to the north. The existing channel as shown in Figure 2.4 mainly runs through fields and open areas located in the closed boundary area. As advised by local residents and maintenance staff of DSD, flooding has been largely due to entrapment of debris at the security grille at the confluence with the Shenzhen River and at stream crossings just upstream of reaching the flood plain.

 

2.3.8                  Some past flooding records at Lin Ma Hang areas are listed below.

 

-                        There was a storm event on 24 May 1998, which caused the collapse and closure of Lin Ma Hang Road, the only vehicular access linking Lin Ma Hang village and the outside. The bridge across Shenzhen River and the boundary fences were also damaged.

 

-                        Heavy rain occurred in June 2001 with the Hong Kong Observatory issuing a consecutive nine days of Rainstorm Warning Signal from 5 June – 13 June 2001. There was widespread flooding in various parts of northern New Territories.

 

-                        Rain bands associated a trough of low pressure caused exceptionally heavy rainfall to the north and northwestern part of the New Territories in the early morning of 5 May 2003. A number of flooding incidents were reported in the North District. Lin Ma Hang Road and adjacent areas in Ta Kwu Ling were flooded to a depth of about 1.5m. FSD and Police were involved in search and rescue.

 

2.3.9                  Previous surveys indicated that Lin Ma Hang consists of high ecological value of lowland streams for freshwater fish, and lowland habitats for bats. Currently, there is a proposal on designation of the Lin Ma Hang stream as a Site of Special Scientific Interest (SSSI) due to the high diversity of freshwater fish of high conversation concern. The nearby abandoned Lin Ma Hang lead mine is a designated SSSI for bats.

 

2.3.10              Alternative means to achieve flood alleviation were therefore considered necessary for Lin Ma Hang stream to avoid direct ecological impacts on the aquatic life, wildlife and habitats that depend on the stream and its associated wetlands. Lin Ma Hang is the nearest village to Lin Ma Hang stream. According to the 2001 Population Census, the population at Lin Ma Hang is about 144. The majority of the village houses are located on the upland side. Preliminary assessment indicates that without constructing the bypass channel (proposed under the DMP Study), the possible flooding extent would only be limited to the abandoned agricultural lands in the vicinity of Lin Ma Hang stream. Some village houses, however, could still be affected by flood water.

 

2.3.11              Following extensive consultation and hydraulic analysis, it is proposed that the stream be retained to avoid posing unacceptable environmental impacts (especially ecological impact).

 

2.3.12              The hydraulic performance of the existing watercourse has been studied. The existing fields on either side of the watercourse could act as flood plain, providing additional storage during flood peaks (Figure 2.11). There are local constraints at existing footbridges just upstream of the village which have low soffits, these inhibit the hydraulic performance of the existing channel. Whilst the main village itself is unaffected by flooding, access is limited when these footbridges are submerged (Figure 2.11). Rising of local footbridges and bank levels will enable stream flow to pass through to downstream reaches without adverse effect to the village.

 

2.3.13              Based on site observation and discussions in joint site visits with DSD, DO/N and the Village Representatives, the local residents of Lin Ma Hang are more concerned about overflow at various stream crossings and blockage of the Lin Ma Hang stream outlet, rather than the flooding in the abandoned fallow field, which is the floodplain of the stream. Generally, most village houses are located on sufficiently high ground free from damage in previous flooding events. However, the houses near stream crossings may still be affected by localised flooding when these crossings are flooded (Figure 2.11). A pragmatic approach is therefore adopted in formulating the flood protection measures at Lin Ma Hang.

 


2.3.14              The proposed drainage measures comprise raising the existing stream crossings to allow flood flow under the design standard to pass through, improvement to unstable stream banks, improvement to the security grille at the outlet of Lin Ma Hang stream and installation of flood detection & alarm systems which are elaborated further in the subsequent sections.

 

Justification and Benefits of the Project

 

2.3.15              The DMP Study investigated the need to improve secondary and local drainage systems to alleviate recurring flooding problems in the study area. The proposed Project is expected to contribute to the relief of the present drainage problems that have repeatedly led to severe flooding in the study area.

 

2.3.16              The current standard of flood protection of the watercourses is very low, with the majority having a standard of protection of 1 year or less. These watercourses were highlighted in the DMP Study as having insufficient flow capacity leading to recurring flooding problems. Upon completion of the Project, the standard of protection will be increase to 1 in 10 years.

 

2.3.17              The population (based on the Population Census in 2001) expected to be directly benefited by the proposed drainage improvement will be about 780.

 

§                        MUP channels – 634

§                        LMH01 – 144

 

                 Consequences of Not Proceeding, ‘No-go’ Scenario

 

2.3.18              Consequences of not proceeding with the Project include recurringe flooding in the low lying areas during severe rainstorms resulting in danger to life, property damage, economic loss and inconvenience to the public.

 

                 Previous Studies and Policy Acceptance

 

2.3.19              The DMP Study was one of the seven DMP studies under the Governor’s Policy Address of 1995 to cover all flood prone areas of the territories. Drainage Services Department completed a PPFS for the Project in August 2001. The Project was included in Category B as Item No. 4119CD in November 2001. The Preliminary Environmental Review (PER) conducted for the PPFS was reviewed by EPD and was considered satisfactory from their point of view. It was considered necessary to carry out additional environmental studies for the project at a later stage.

 


The Need for the Project

 

2.3.20              The drainage basins in Northern New Territories comprise both urban and rural sub-catchments and are characterized by steep upland portions with abrupt transitions to flat lowland areas at downstream that are susceptible to flooding.

 

2.3.21              The current standard of flood protection of the watercourses is very low, with the majority having a standard of protection of 1 year or less. Flooding has occurred repeatedly in the study area leading to property damage, economic loss and disruption to everyday life.

 

2.3.22              Hydraulic analysis indicates that backwater from the main rivers / channels causes local flooding in their tributary drainage systems at upstream. Also, developments within floodplains have reduced the flows and storage capacities of the existing natural drainage systems.

 

2.4                        Consideration of Alternative Means and Avoidance of Environmental Impacts

 

Alternative Solution to Flooding Problem at Lin Ma Hang

 

2.4.1                  Under the DMP Study, a bypass channel of approximately 250 m in length and 13 m in width (with concrete base) was to be provided for the prevention of flooding at Lin Ma Hang (Figure 2.9).

 

2.4.2                  As described in the previous sections, Lin Ma Hang area is of high ecological value due to the high diversity of freshwater fish (of high conservation concern) found in Lin Ma Hang stream and due to the lowland habitats for bats.

 

2.4.3                  Based on extensive consultation and hydraulic analysis, it is proposed that the stream be retained to avoid posing unacceptable environmental impacts (especially ecological impact).

 

2.4.4                  However, there are concerns about overflow at various stream crossings and blockage of the Lin Ma Hang stream outlet. A pragmatic approach is therefore adopted in formulating the flood protection measures at Lin Ma Hang. The proposed measures would comprise the following:

 

Improvement to Stream Crossings

 

2.4.5                  The soffits of the existing stream crossings are too low to allow flood flow to pass during severe rainstorms. The crossings would be demolished and re-constructed to a higher level to allow flood flow at the design standard to pass through. Proper safety railings would also be installed. A total of three vehicular crossings will be demolished and raised.

 

Improvement to River Banks

 

2.4.6                  Repair and strengthening of damaged or eroded stream banks with gabions would be implemented. It is worthy to note that some of the banks are close to village houses and any further deterioration would pose a safety hazard to the residents.

 

2.4.7                  After site meetings, the Green Groups supported the use of gabion for the bank improvement works including the downstream end of the stream as it would enhance the ecology of the current concrete lined stream banks and bed.

 

Improvement to the Security Grille at the Outlet of Lin Ma Hang Stream

 

2.4.8                  The existing security grille was engineered and installed in accordance with the recommendations in the DMP Study. As advised by DSD/MN, this design failed to resolve the problem of blockage to the flow in the past rainstorms. The existing grille has trapped tree branches, debris, and silt washed down from the water course, contributing to historical flood events. Improvement to the current security grille at the outlet to Shenzhen River will be undertaken. It has been proposed that the grille be replaced by a combination of flap valve and security grille.

 

Installation of Flood Alarm System

 

2.4.9                  Flood alarm system would be provided for the Lin Ma Hang villagers. The flood level detector would be located at the outlet of Lin Ma Hang stream. Flood alarm sirens would be located at the community hall of the village and would be activated once the flood level is reached. The alarm signal would also be sent to DSD/MN, Ta Kwu Ling Police Station, DO/N and Ambulance Command/NTE of FSD. The system will be further reviewed in the detailed design stage.

 

2.4.10              Based on the above minimized improvement works at LMH01, there will be no direct adverse ecological impacts on the Lin Ma Hang stream, its tributaries and associated wetland as well as the aquatic life, wildlife therein and habitats that depends on the stream.

 

Alternatives to Avoid Loi Tung Stream

 

2.4.11             Section 3.3.1 of the EIA Study Brief has specifically indicated the consideration of alternative channelisation of Loi Tung stream (MUP04A). The DMP Study originally proposed a 340 m length channel with concrete base (Figure 2.8). Site survey reveals that flooding occurs at both the village area and the agricultural fields further upstream. Site visit also indicates that the downstream portion has been heavily disturbed from village development (portion of the stream has been culverted for an access road) with construction debris found dumped at the stream banks. The ecological value of this downstream section is considered as very low. The upstream portion of moderate ecological value mostly flows adjacent to abandoned agricultural fields. With due consideration of the potential ecological value of the upstream portion of MUP04A, the latest adopted design avoided the channelisation of this upstream portion altogether (approximately 180 m). Only the downstream portion near the village area would be channelised using gabions. Localized flooding of the inactive agricultural land would remain at the upstream portion (Figure 2.10).

 

2.4.12             With the avoidance of channelising the upstream portion, there will be no direct adverse ecological impacts on the Loi Tung stream, its tributaries and associated wetland as well as the aquatic life, wildlife therein and habitats that depends on the stream.

 

Alternative Design to Channels in Man Uk Pin

 

2.4.13              The DMP Study originally proposed a 14 m wide channel with concrete base and geotextile reinforced grass as bank (Figure 2.8). The middle section of MUP05 consists of semi-natural stream bank with riparian vegetation and is of moderate ecological value. The upper section and downstream end are heavily modified and lined with concrete and is of very low ecological value. To minimise ecological impact as a result of the proposed channelisation works, a ‘two-stage channel’ design has been adopted. Some section of the banks would be retained. Likewise, portion of the stream bed would be retained or be provided with natural bedding to minimise potential ecological and visual impacts.

 

2.4.14              Hydraulic modelling results revealed that the extent of improvements for the channels MUP01 and MUP02 (Non-DP elements but identified as Ecologically Important Streams (EIS)) could be modified due to the direct beneficial effect on flow conveyance after upgrading the channel MUP05 at their immediate downstream. The flooding situation of MUP01 and MUP02 can be further improved by removing the existing bottleneck at their confluence with the proposed MUP05 near Sha Tau Kok Road. As a result, channelisation works for MUP01 and MUP02 have been substantially replaced by bank raising.

 

2.4.15             With the minimisation of channelisation works and adopting environmental friendly ‘two-stage’ channel design, there will be no direct adverse ecological impacts on MUP05 stream, its tributaries and associated wetland as well as the aquatic life, wildlife therein and habitats that depends on the stream.

 


2.5                        Design Considerations

 

Relevant Technical Circulars / Guidelines

 

2.5.1                  Reference has been made to the following Government Technical Circulars / Guidelines in designing the proposed channels.

 

Ÿ                     ETWB Technical Circular (Works) No. 5/2005 – Protection of Natural Streams / Rivers from Adverse Impacts Arising from Construction Works

Ÿ                     DSD Technical Circular No. 2/2004 – Protection of Natural Rivers and Streams from Adverse Impacts Arising from Construction Works

Ÿ                     DSD Practice Note No. 1/2005 – Guidelines on Environmental Considerations for River Channel Design

Ÿ                     DSD Report – Aesthetic, Environmental and Ecological Considerations in the Design of Drainage Channels

 

2.5.2                  The first two Technical Circulars provide an administrative framework to better protect all natural streams / rivers from the impacts of construction works, to provide guidelines for the planning and execution of construction works and for the vetting of development proposals that affect natural rivers and streams.

 

2.5.3                  The DSD Practice Note presents the essential environmental considerations that should be taken into account and incorporated wherever practicable, in the design of river channels. The Practice Note addresses the need for more environmentally friendly river channel design and be in-line with the new measures being put in place by Government to strengthen the protection of natural rivers and streams (as depicted in the above two Technical Circulars).

 

2.5.4                  The DSD Report prepared by Research & Development Section of Land Drainage Division summarizes the review of the recent major drainage improvement projects in Hong Kong and recommends good practice for drainage channel design with due consideration on the aesthetic, environmental and ecological aspects.

 

Essential Design Considerations / Principles Adopted

 

2.5.5                  In addition to the Government guidelines, the following essential design considerations / principles were considered in formulating the preferred channel alignment / lining.

 

Ÿ                    Adequate flow capacity – the size of the river channels should have adequate capacities to convey design flood flows within bank to achieve the design flood protection standard.

Ÿ                    Public safety – bank stabilisation work is required for unstable banks and where houses and structures are located very close to the existing river banks.

Ÿ                    Existing conditions of the river banks – some sections of the existing river banks have loose surfaces and are prone to erosion and scouring.

Ÿ                    Land constraints – physical features such as road carriageway at one side of the existing river control the widening of the channel at that side.

Ÿ                    Accessibility for maintenance – provision of adequate access for future long-term maintenance of the completed channels is necessary.

Ÿ                    Disturbance to the public – resumption of private domestic houses / any commercial use lands / factories need to be minimize as much as possible.

 

2.6                        Consideration of Alternative Drainage Design

 

Alternative Alignment

 

2.6.1                  The proposed alignment as recommended under the DMP generally follow the alignment of existing watercourses in order to minimise land resumption requirements wherever possible (thus reducing disturbance and inconvenience to the public) and to facilitate interception of incoming watercourses. The alignment is also dictated by physical features constraint such as Sha Tau Kok Road, village areas, and existing trees.

 

2.6.2                  Other alternative alignments were evaluated but are considered not practicable, cost effective or would result in adverse environmental impacts.

 

2.6.3                  The upstream invert of the proposed channel has been designed to match with the level of the existing watercourse, whilst the downstream is governed by the primary channel and the invert levels of side connections.

 

2.6.4                  In general, the bank level of the proposed channel will match with the adjacent ground levels thus allowing free surface runoff by gravity into the proposed channel. Invert levels of the proposed channels also take due consideration of side connections.

 

Alternative Location of Stormwater Drains and Discharge Points

 

2.6.5                  The proposed stormwater drains including cross road drains consist of existing drains to be replaced or upgraded. Other alternative locations were considered but are not practicable, cost effective or not preferable in terms of land constraints, and hydraulic capacity.

 

2.6.6                  The proposed MUP channels eventually need to discharge into the recently upgraded River Indus. No alternative discharge points for the proposed channels are therefore suitable or practical.

 

Design of Channelisation

 

2.6.7                  The design of channelisaton generally follows the avoidance and minimization approach as promulgated in Government technical circulars and guidelines. These are elaborated further below.

 

Alternative Drainage Options

 

2.6.8                  The drainage options (with reference to the DSD Practice Note No. 1/2005) that have been considered before arriving at the current proposed design are shown in Table 2.2. Its corresponding equivalent as promulgated in ETWB TCW No. 5/2005 and as required under the EIA study brief is also tabulated. The evaluation of the environmental benefits, dis-benefits and potential impacts on the stream, aquatic life, and surrounding wildlife therein as well as other considerations for the proposed DPs of channel improvement works are summarized in Table 2.3.

 


Table 2.2

Alternative Drainage Options Considered for the Proposed DP Channels

 

Approach*

Option*

DSD Practice Note No. 1/2005*

ETWB TCW No. 5/2005**

Avoidance

Option 1

Distant flood banks+

N/A

Option 2

Two-stage (or multi-stage) channels

N/A

Option 3

Relief or by-pass channels++

N/A

Option 4

Flood storage+++

N/A

Minimization

Option 5

Bank stabilization

(i)         protection / stabilization of river bank at locations prone to erosion by use of natural materials such as rock

Option 6

Clearing and removal of obstructions

(ii)        removal of fallen objects / obstructions and clearing of vegetation in a selected manner

Option 7

Enlargement of channel by widening

(iii)      enlargement of channel by modifying one bank only

(iv)      enlargement of channel by modifying / widening both banks

Option 8

Enlargement of channel by deepening

(v)       enlargement of channel by deepening

Option 9

Realignment / straightening

(vi)      realigning by creating a new channel

Option 10

Use of artificial non-vegetative smooth lining

(vii)    construction of a new channel using artificial non-vegetative smooth lining such as concrete

 

Notes:

*      Options as promulgated in DSD Practice Note No. 1/2005 – Guidelines on Environmental Considerations for River Channel Design

**    Options as promulgated in ETWB TCW No. 5/2005 – Protection of natural streams / rivers from adverse impacts arising from construction works - Appendix C (A)

+      Equivalent to bunds as flood barriers design option as highlighted in EIA Study Brief

++     Equivalent to bypass design option as highlighted in EIA Study Brief

+++   Equivalent to flood pond design option as highlighted in EIA Study Brief

 


2.6.9                  The various options are described briefly below.

 

Option 1     Distant flood banks – Flood banks (using earth bunds as barriers) are set back from the rivers and allow the river to meander freely within their bounds.

 

Option 2     Two-stage channels – Excavating the surface section of the flood plain adjacent to the river, with the original river channel preserved while higher flows are contained within the newly created berms.

 

Option 3     Relief or bypass channels – Constructed channels with the aim of diverting excessive water from the main natural channel during periods of high flows.

 

Option 4     Flood storage – Intercept the runoff at the upstream area and temporarily store in a flood storage pond/area for release later when water level in the downstream river recedes.

 

Option 5     Bank stabilisation – Use of natural materials for bank stabilization in areas prone to erosion while the entire stream is left intact.

 

Option 6     Clearing and removal of obstructions – Removal of fallen trees, debris or other obstructions and desilting in a selective manner to restore the river capacity.

 

Option 7    Enlargement by widening – River channel is enlarged by widening while the stream bed is left intact.

 

Option 8     Enlargement by deepening – Channel bed is excavated to a greater depth to increase the flow capacity.

 

Option 9     Realignment / straightening – Meandering river channel is realigned or straightened to increase flood conveyance capacity.

 

Option 10   Use of artificial non-vegetative smooth lining – Use of concrete on the river bank and bed to reduce roughness and protect them from scouring thereby increasing the flood conveyance capacity.

 

 


Table 2.3

Summary of the Evaluation of Alternative Drainage Options for the Proposed DP Channels

 

Drainage Option

Environmental Benefits

Environmental
Dis-benefits

Recommendation

Reasons & Considerations

Option 1 - Distant flood banks

§   No excavation of the existing streams at Man Uk Pin and Lin Ma Hang will be required. The existing streams would be left untouched hence the stream habitats will be preserved.

§   There will be no ecological impacts on Man Uk Pin and Lin Ma Hang streams, aquatic life and surrounding wildlife therein.

 

§   This option requires substantial earth bund to provide adequate flood protection which may lead to potential visual impact to the villagers of Lin Ma Hang and Loi Tung.

§   The earth bund may hinder passage of wildlife across flood banks especially in Lin Ma Hang.

§   This option is considered not practicable for the proposed DP channels and is therefore not recommended.

§   More land resumption is required and mostly on private land.

§   The option is constrained by physical features such as Sha Tau Kok Road and nearby village houses of Loi Tung and Lin Ma Hang.

§   Potential visual impact problem on residents at Lin Ma Hang and Loi Tung.

§   The flood protection level provided is still very low. Local flooding will occur outside the distant bank when the flood water retained by the bank is at high level.

Option 2 - Two-stage (or multi-stage) channels

§   No excavation of the existing streams at Man Uk Pin and Lin Ma Hang will be required. The existing streams would be left untouched hence the stream habitats will be preserved.

§   There will be no ecological impacts on Man Uk Pin and Lin Ma Hang streams, aquatic life and surrounding wildlife therein.

§   Different flood regimes and water tables result in the development of different types of habitat.

§   Depending on the design, excavated rocks and soils could be reuse as channel bed thereby reducing offsite disposal.

§   Potential environmental impacts may arise from construction of the widened sections in particular potential adverse construction phase impact to the sensitive Lin Ma Hang stream.

§   There may be potential lost of stream banks (depending on design adopted).

 

 

§   This option is only recommended for the middle portion of MUP05.

§   Not recommended for LMH01 due to potential adverse ecological impact during construction.

§   More land resumption is required and mostly on private land.

§   Construction works will adversely affect the sensitive Lin Ma Hang stream.

§   The option could only be adopted at existing natural stream sections (i.e. not applicable for the existing roadside concrete drains at MUP03 and MUP04B).

§   The middle section of MUP05 is of moderate ecological value on natural stream habitat. The adoption of two-stage channel approach is effective to minimize the potential ecological impact.

§   Not suitable for small stream or where there is land and physical features constraints such as MUP04A which is constrained by Loi Tung village.

Option 3 - Relief or by-pass channels

§   No excavation of the existing Man Uk Pin and Lin Ma Hang streams will be required. The existing streams would be left untouched hence the stream habitats will be preserved.

§   There will be no ecological impacts on Man Uk Pin and Lin Ma Hang streams, aquatic life and surrounding wildlife therein.

 

§   The bypass section may impose environmental impacts to other areas.

§   It may pose ecological impact on surrounding inactive wet & dry agricultural land of low to moderate ecological value at Man Uk Pin and Lin Ma Hang.

§   This option is considered not practicable for the proposed DP channels and is therefore not recommended.

§   More land resumption is required.

§   The option is constrained by availability of land and physical features such as Sha Tau Kok Road and nearby village houses, therefore not suitable for the MUP channels and LMH01.

§   A very effective option at meander. However, it is less practicable to be adopted at relatively straight streams like MUP05. The construction of bypass channel will require extensive land resumption and will impose adverse impact to other areas further away from the stream.

Option 4 - Flood storage

§   No excavation of the existing Man Uk Pin and Lin Ma Hang streams will be required. The existing streams would be left untouched hence the stream habitats will be preserved.

§   There will be no ecological impacts on Man Uk Pin and Lin Ma Hang streams, aquatic life and surrounding wildlife therein.

 

§   There will be potential environmental impacts associated with the construction and operation of storage ponds and pumping station.

§   Potential visual impact of the pumping station on Lin Ma Hang and Man Uk Pin areas may arise.

§   This option is considered not practicable for the proposed DP channels and is therefore not recommended.

§   More land resumption is required.

§   The option is constrained by availability of land and physical features such as Sha Tau Kok Road and nearby village houses.

§   This option will incur higher construction and maintenance costs.

§   This option is not practical given the large volume of runoff needed to be stored. Substantial land resumption and construction & operation of pumping station will be required.

Option 5 - Bank stabilization

§   No excavation of the existing Man Uk Pin and Lin Ma Hang streams will be required. The existing stream bed will be left intact hence preserving the stream habitat.

§   The use of gabion / mattress lining to replace existing sections of concrete lining at LMH01 will enhance the stream habitat by allowing recolonization of riparian vegetation. It will also improve the aesthetic appearance of the current shotcrete lined sections.

§   As the works will be at the banks, the likely impacts on the Lin Ma Hang stream, aquatic life and surrounding wildlife therein will be reduced.

§   Some minor localised environmental impacts will still be inevitable during construction.

 

§   This option is only recommended for the ecologically sensitive stream LMH01, not practicable for the MUP channels.

§   Suitable for locations with localised flooding or requiring minor bank improvement works such as LMH01.

§   This option is not suitable for channel predicted to have insufficient hydraulic capacity and requires widening such as MUP channels.

§   This option was also recommended by the Green Groups to enhance the ecology of the existing shotcrete banks at LMH01.

Option 6 - Clearing and removal of obstructions

§   As no major construction works are necessary, there will only be very minimal impact on the environment and ecology of the Man Uk Pin and Lin Ma Hang streams.

§   The area of the stream to be affected will be the least.

§   No major environmental dis-benefits are anticipated.

§   This option is recommended for ecologically sensitive stream LMH01 by providing security flap valve to replace existing security grille which is prone to obstruction, not practicable for the MUP channels.

§   This option can only marginally improve the capacity of the existing streams and may need to tie-in with other drainage options.

§   There will be no adverse impact on ecology of the streams.

§   The flood protection level provided is still very low and is not suitable for larger channels. Flooding may still continue.

Option 7 - Enlargement of channel by widening

§   The environmental condition can be improved with suitable design on lining and bedding such as gabion mattress or rip-rap lining to replace some sections of engineered banks and beds.

§   As the improvement works will be carried out along existing streams, it can minimize major resumption of land and reduce environmental impacts imposed to other areas of Man Uk Pin.

§   Impacts on the existing streams such as the sensitive Lin Ma Hang unavoidable.

§   This option is recommended in combination with other suitable options for MUP channels only.

§   Not recommended for LMH01 due to potential adverse ecological impact during construction.

§   Widening and deepening is the most effective way to increase the flood conveyance of the watercourses.

§   Land resumption and generation of C&D materials will be minimized as the improvement works will be carried out along the existing watercourse.

§   Ecological impacts can be mitigated or even enhanced with environmental friendly channel design (e.g. gabions, natural banks / beds, and riparian planting).

§   This option is more reliable and cost effective when compare with other options.

Option 8 – Enlargement of channel by deepening

§   Same as Option 7

§   Same as Option 7

§   Same as Option 7

§   Same as Option 7

Option 9 - Realignment / straightening

§   Some meanders may be preserved but must be properly designed to ensure continuous water flow.

§   Significant impact on existing Man Uk Pin and Lin Ma Hang streams, especially on those abandoned sections.

§   The hydrology and ecology of the whole stream will be changed.

§   This option will result in unacceptable adverse environmental and ecological impacts to Man Uk Pin and Lin Ma Hang streams, it is therefore not recommended.

§   This option can provide fast flood flow conveyance thereby achieving the objective of flood alleviation.

§   This option will have an impact on the ecology of the whole watercourse.

§   Environmental impacts outweigh engineering benefits for this option.

Option 10 - Use of artificial non-vegetative smooth lining

§   None

§   This option will result in total loss of stream habitats at Man Uk Pin and Lin Ma Hang.

§   There is no ecological value and will result in high visual impact.

§   This option will result in unacceptable adverse environmental and ecological impacts to Man Uk Pin and Lin Ma Hang streams, it is therefore not recommended.

§   This option can provide fast flood flow conveyance thereby achieving the objective of flood alleviation.

§   Very little maintenance is needed for this option.

§   Environmental impacts outweigh engineering benefits for the proposed channels.


 

Alternative Channel Bed Lining / Embankment Lining Options

 

2.6.10              Common channel bed and embankment lining consists of:

 

§                     Natural / unlined;

§                     Rip-rap lining;

§                     Gabion / mattress lining;

§                     Rubbles / stones embedded in concrete / mortar;

§                     Geotextile reinforced grass lining;

§                     Grassed cellular concrete paving; and

§                     Concrete lining.

 

2.6.11              The various options are described briefly below.

 

Natural / unlined – Channel bed is left untouched or paved with original bed substrates to retain its natural conditions.

 

Rip-rap lining – This is formed by a layer of different-sized, angular rocks or boulders, sometimes underlaid with a layer of filter fabric or granular materials.

 

Gabion / mattress lining – consists of wired gabion baskets filled with small to medium size rock or granular material, placed over the channel bank or bed.

 

Rubbles / stones embedded in concrete / mortar – This is not much different from the concrete lining.

 

Geotextile reinforced grass lining – The channel bank or bed is covered with top soil and grassed with a layer of geotextile woven fabric provided underneath the top soil to reinforce the soil layer and to provide erosion protection to the bedding.

 

Grassed cellular concrete paving – The channel bank or bed is covered with interlocking hollow concrete panels / blocks that are filled with topsoil and grassed.

 

Concrete lining – The channel bank or bed is lined with concrete.

 

2.6.12              The evaluation of the environmental benefits, dis-benefits, potential impacts on the stream, aquatic life, and surrounding wildlife therein as well as other considerations for the proposed DP channels are summarized in Table 2.4.

 


Table 2.4

Summary of the Evaluation of Alternative Channel Bed / Embankment Lining Options

 

Lining Option

Environmental Benefits

Environmental
Dis-benefits

Other Considerations / Recommendations

Natural / unlined

§   No works will be carried out on the Man Uk Pin and Lin Ma Hang streams hence stream habitats can be preserved.

§   Very minimum impact during construction is expected when compared with other lining options.

§   As the channel bed will be left in its natural conditions, it is visually more acceptable.

§   Prone to scouring and erosion of banks during flood flows which may affect the structural integrity of the channel in particular to some sections of Man Uk Pin channels.

§   A wider channel may be needed to cater for poorer hydraulic performance which in turn may impose environmental impacts to other areas such as Lin Man Hang stream.

§   Natural beddings have poor hydraulic performance and high roughness.

§   Suitable where the flow velocity is low.

§   Recommended for middle portion of MUP05 (two-stage channel).

Rip-rap lining

§   Provides moderate habitat for aquatic community.

§   Accumulation of silt in the  interstices allow recolonzation of benthic community in the long term.

§   As natural material will be used, it is visually more acceptable.

§   Provides opportunity to reuse excavated rocks and soils thereby reducing burden on offsite disposal sites.

§   Prone to scouring and erosion of banks during flood flows which may affect the structural integrity of the channel in particular to some sections of Man Uk Pin channels.

§   A wider channel may be needed to cater for poorer hydraulic performance which in turn may impose environmental impacts to other areas such as Lin Ma Hang stream.

§   Rip-rap linings have poor hydraulic performance and high roughness.

§   Suitable where the flow velocity is low.

§   Recommended for middle portion of MUP05 (two-stage channel).

Gabion / mattress lining

§   Provides moderate habitats for aquatic communities.

§   Accumulation of silt in the  interstices allow recolonzation of benthic community in the long term.

§   As natural material will be used, it is visually more acceptable.

§   Provides ecological enhancement to the current concrete lined section of Lin Ma Hang stream.

§   Provides opportunity to reuse excavated rocks and soils thereby reducing burden on offsite disposal sites.

§   Moderate impact to the stream and aquatic life during construction.

§   Prone to damage if poorly designed.

§   Moderate hydraulic performance.

§   High maintenance efforts and costs in replacement.

§   Susceptible to corrosion.

§   Recommended for MUP03, MUP04A, MUP05 and downstream section of LMH01.

Rubbles / stones embedded in concrete / mortar

§   Slightly better appearance than concrete.

§   No ecological value.

§   Offer little opportunity for riparian vegetation and benthic community to thrive.

§   Adverse impact during construction.

§   Better hydraulic performance.

§   Little maintenance.

§   Not recommended.

Geotextile reinforced grass lining

§   Good aesthetic appearance.

§   Low ecological value.

§   Offer little opportunity for riparian vegetation and benthic community to thrive.

§   High maintenance cost

§   Not recommended.

Grassed cellular concrete paving lining

§   Slightly better appearance than concrete.

§   Low ecological value.

§   Offer little opportunity for riparian vegetation and benthic community to thrive.

§   Adverse impact during construction.

§   Fast conveyance of flood flows.

§   Better structural integrity.

§   Little maintenance .

§   Applied to MUP05 as maintenance access only.

Concrete lining

§   None

§   No ecological value.

§   Offer no opportunity for riparian vegetation and benthic community to thrive.

§   Adverse impact during construction.

§   Fast conveyance of flood flows.

§   Little maintenance.

§   Environmental impacts outweigh engineering benefits.

§   Not recommended.

 


Final Recommended Drainage Improvement Design Options

 

2.6.13              The design of each channel is evaluated with reference to the environmental benefits and dis-benefits as well as engineering considerations presented above. The evaluation presented in Table 2.5 and paragraphs 2.6.14 to 2.6.35 details the suitability and practicability of each option to the proposed channel. The final recommended alignment, location and design options are selected from the options that are considered engineering feasible and have the least impacts to the environment and the ecology of the streams, aquatic life therein as well as other habitats that depend on the streams. The final recommended channel designs are presented in Figures 2.2 – 2.5 and Table 2.6 and elaborated in the subsequent sections.

 

Table 2.5

Evaluation of the Drainage Design Options adopted for the Proposed Channels

 

Drainage Design Options

Proposed Channels

MUP03

MUP04A & 04B

MUP05

LMH01

Option 1 – distant flood bank

û

û

û

û

Option 2 – two-stage channel

û

û

û

Option 3 – relief or by-pass channel

û

û

û

û

Option 4 – flood storage

û

û

û

û

Option 5 – bank stabilization

û

û

û

Option 6 – clearing and removal of obstructions

û

û

û

Option 7 – enlargement by widening

û

Option 8 – enlargement by deepening

û

Option 9 – realignment / straightening

û

û

û

û

Option 10 – artificial non-vegetative smooth lining

û

û

û

û

Proposed Design Option(s)

Gabion channel

Gabion channel

Two-stage channel (with natural bank and bed retained) & gabion channel

Bank stabilization, replacement of security grille

Notes:

- Applicable

û - Not applicable

Table 2.6

Major Design Characteristics and Environmental Friendly Design Measures

Adopted in the Proposed Channels

 

 

Proposed Channel

Drainage Design Option Adopted

Channel Lining Option Adopted

Major Design Characteristics and Environmental Friendly Design Measures Adopted

MUP03

Option 7

Option 8

Gabion bank and bed

§         Existing road side concrete drains to be replaced by trapezoidal channel with gabion bank and mattress lining.

§         Gabion banks with a tilted angle of 10o for stability purpose.

§         Silt will be allowed to accumulate for recolonization of benthic community.

§         Opportunity to reuse excavated rocks in the gabion.

MUP04A

Option 7

Option 8

Gabion bank and bed

§         About 180 m of the original channelisation work (proposed under the DMP) at the upstream portion is avoided.

§         Highly disturbed downstream portion to be replaced by trapezoidal channel with gabion bank and mattress lining.

§         Gabion banks with a tilted angle of 10o for stability purpose.

§         Silt will be allowed to accumulate for recolonization of benthic community.

§         Opportunity to reuse excavated rocks in the gabion.

MUP04B

N/A

N/A

§         Channel size is reduced with new underground drainage pipes.

§         Land resumption kept to a minimum.

MUP05

Option 2

Option 7

Option 8

Gabion bank and bed

Natural river bed

Rip-rap lining

Grassed cellular concrete paving

 

§         Existing road side concrete drains to be replaced by trapezoidal channel with gabion bank and mattress lining.

§         Original trapezoidal (Grasscrete®) channel design (proposed under the DMP) is replaced by an environmentally acceptable “Two-Stage Channel”.

§         Existing natural stream bed to be retained and/or widened with natural substrate.

§         Some semi-natural stream banks (and riparian vegetation) to be retained while the others will be stabilized with gabions.

§         Silt will be allowed to accumulate for recolonization of benthic community.

§         Opportunity to reuse excavated rocks and soils in the gabion and rip-rap lining.

§         Some sections of the maintenance access to be provided inside the channel above bed level with Grasscrete® or similar design.

§         Removal of bottleneck at confluence of two tributaries (MUP01&02) to minimize the channelisation of the two upstream Ecologically Sensitive Streams (MUP01&02).

LMH01

Option 5

Option 6

Gabion bank

§         Original channelization works (proposed under the DMP) avoided altogether.

§         Only localized stream bank stabilization (with gabions) and re-construction of crossings & security grille are to be carried out. The stream bed will remain untouched.

§         Existing downstream concrete lined section to be replaced by gabion bank and mattress lining allowing recolonization of riparian vegetation and accumulation of silt for benthic community, thereby enhancing the existing habitat.

 

 

MUP03 & MUP04B

 

2.6.14              MUP03 and MUP04B involve construction and/or reconstruction of roadside drains which are intended to collect surface runoff from village areas on the south side of Sha Tau Kok Road. MUP03 is proposed to flow directly into MUP05 whilst MUP04B would first join MUP04A.

 

2.6.15              As they are local drains collecting water from small catchment areas, options like distant flood bank, two-stage channel, by-pass channel and flood storage are not suitable. These options are severely constrained by Sha Tau Kok Road and any additional land takes would pose adverse environmental impacts on the surrounding environment (including nearby villages). As the current flooding problem of the existing watercourse is neither attributed to bank erosion nor obstruction of debris, the options of clearing and removal of obstructions and bank stabilization could not achieve the required flood protection system and are therefore not recommended. Option of small scale widening and deepening is therefore considered most feasible and thus selected. The existing 300 mm wide concrete U-channels will be replaced by larger sized channels or pipes.

 

2.6.16              Part of MUP03 will be upgraded as a 1.2 m wide gabion lined channel (MUP03B). In order to enhance the ecology at these gabion channels, their profile has been adjusted such that the channel sides are stepped rather than vertical, whilst the base have a mattress lining rather than being formed with concrete.

 

2.6.17              For the remaining part of MUP03, due to the constraints of Sha Tau Kok Road and a massive structure on its southern side, there is no sufficient room to accommodate a gabion channel. As such, it will be replaced by a 600 mm nominal size U-channel (MUP03A).

 

2.6.18              For the downstream section of MUP04B, 1350 mm diameter drain pipes are proposed to connect its upstream (U-channel) to MUP04A. The pipes will run underneath a local road of Loi Tung village.

 

2.6.19              These channels are currently road side concrete drains or are along the verge of Sha Tau Kok Road. The areas are highly disturbed from village development and Sha Tau Kok Road and have low ecological value.

 

2.6.20              The construction and operation of these channels are not expected to adversely affect the existing stream, aquatic life and surrounding wildlife therein. 

 

MUP04A

 

2.6.21              The downstream section of MUP04A has been heavily modified and has very low ecological value. The upstream section is a stretch of semi-natural stream which is bordered by agricultural habitats on both sides. It has higher ecological value than its downstream section.

 

2.6.22              Several options to increase the flood protection standard of MUP04A have been considered. Distant flood bank, flood storage, by-pass channel and two-stage channel are considered not feasible due to the need of resuming extensive private land (and impose potential environmental impacts) to the nearby sensitive receivers including the newly built small houses on both sides of the stream. As the current flooding problem of the existing watercourse is neither attributed to bank erosion nor obstruction of debris, the options of clearing and removal of obstructions and bank stabilization could not achieve the required flood protection system and are therefore not recommended. The most appropriate option is to widen the watercourse and transforming it to a gabion-lined channel.

 

2.6.23              Based on the ecological assessment, the channelization of the upstream portion of MUP04A will cause moderate impacts on the semi-natural stream and the adjacent inactive agricultural land, which is unpopulated. Based on such findings, the proposal is revised not to channelise the upper portion in order to avoid the associated impacts. Localized flooding of the inactive agricultural land would remain at the upstream portion (see Figure 2.10). Only the downstream portion which has been heavily modified will be constructed to a gabion channel.

 

2.6.24              The construction and operation of this channel is not expected to adversely affect the existing stream, aquatic life and surrounding wildlife therein. 

 

 


MUP05

 

2.6.25              The upper watercourse of MUP05 has been heavily modified, with most of the bank and bottom concreted, and therefore provides very few ecological resources for wildlife or aquatic life. In contrast, the middle and lower watercourse, except a small portion at its most downstream, is a semi-natural stream which has moderate ecological value.

 

2.6.26              Options such as distant flood bank and flood storage had been considered. However they require extensive private land resumption and clearance of adjacent house and are considered not favourable. By-pass channel is also not suitable as the alignment of MUP05 is generally straight. The presence of Sha Tau Kok Road also poses a constraint on the option selection. As the current flooding problem of the existing watercourse is neither attributed to bank erosion nor obstruction of debris, the options of clearing and removal of obstructions and bank stabilization could not achieve the required flood protection system and are therefore not recommended.

 

2.6.27              In view of such, two-stage channel is proposed for the downstream portion of MUP05 to minimize the impact to this semi-natural stream. The upstream portion however will not be upgraded to a two-stage channel as it has already been concrete lined and has low ecological value. It is considered appropriate to replace this section by a gabion lined channel.

 

2.6.28              The construction and operation of this channel is not expected to adversely affect the existing stream, aquatic life and surrounding wildlife therein. 

 

LMH01

 

2.6.29              LMH01 is a stream which remains in a largely natural state and is unpolluted. Ecological surveys have confirmed the importance of the stream for fish and dragonflies, both pollution sensitive groups.

 

2.6.30              The proposed improvement works to be carried out at LMH01 are therefore limited to avoidance approach. The option of providing a by-pass channel to reduce the flood risk was firstly considered (Figure 2.9). Under such option, the existing watercourse will not be touched except at its confluences with the by-pass channel. However it will require large land resumption on the adjacent abandoned fallow fields.

 

2.6.31              During the consultation, the Villager’s Representative indicated that local residents of Lin Ma Hang are more concerned with overflow at various stream crossings and blockage of the Lin Ma Hang stream outlet, rather than the flooding in the abandoned fallow field, which is the floodplain of the stream.  The abandoned fallow field has been assessed to be of moderate environmental values.  Generally, most village houses are located on sufficiently high ground to be free from damage in previous flooding events. Some village houses near crossings however still experience localised flooding when the stream crossings are flooded.

 

2.6.32              Site meeting had been arranged with Green Groups to discuss the proposed drainage improvement works. During the meeting, the Green Groups requested to replace some concrete lined stream sections by gabion in order to enhance the ecological value of the area.

 

2.6.33              In view of the above, instead of adopting by-pass channel or other options, it was opted to undertake bank stabilization and reinstatement using gabions at the sections where erosion is occurring or being lined by concrete, replacement of three bridges to higher levels, and the security grille at the stream outlet. These drainage improvement design options would result in the least environmental and ecological impacts while achieving the project objective of flood protection.

 

2.6.34              The revised proposal was presented to North District Council and Green Groups who indicated no adverse comment. The revised proposal is thus adopted for the improvement to Lin Ma Hang stream.

 

2.6.35              The construction and operation of this channel is not expected to adversely affect the existing stream, aquatic life and surrounding wildlife therein.

 

                 Channel Lining Evaluation

 

2.6.36              Channel lining is required to maintain the structural integrity of the channel in order that it can continue to perform its hydraulic function to contain and convey the design flood flows.

 

2.6.37              The choice of channel lining is a compromised solution between various factors including hydraulic characteristics, cost, operation and maintenance needs, environmental and ecological considerations, visual and aesthetic impacts, availability of materials, etc.

 

2.6.38              Following comprehensive research several solutions and the pertinent issues were discussed with interested Government departments at the Workshop held on 10 May 2004.  Further refinement were conducted with due regards to hydraulic capacity and ecological impact. The preferred solution for each of the proposed channels is discussed below.

 

 

2.6.39              Options for channel lining for stream banks and bed include natural bed (gravel or mud), gabions, concrete or grasscrete. While the hydraulic performance of concrete and grasscrete lined channels are the best for smooth flow and easy maintenance, they will remove the ecological values of the land on which they occupy. Also, the rate of transport of sediments downstream, whether clean or contaminated, will also increase, resulting in increase in suspended solids and biological oxygen demand in water at the downstream.

 

2.6.40              Gabions and natural stream beds offer surfaces that will sustain a bottom community and are better for retaining sediments and establishment of vegetation on banks. This would also reduce the rate of sediment loss from the catchment which will ultimately reach Deep Bay. Nevertheless, they are more expensive to maintain as they are often displaced or damaged after heavy storms. Annual trimming of bank side vegetation and removal of excess sediments will be required to ensure that sufficient hydraulic capacity is retained. Natural banks are especially prone to erosion and subject to scour.

 

2.6.41              Natural river bed lining would be applied to parts of MUP05. However, to retain sufficient hydraulic capacity of flood prevention and cost effectiveness in maintenance, it is considered not viable to adopt natural stream bed for the smaller channels, i.e. MUP03 and MUP04A.

 

Proposed Gabion Channels for MUP Channels

 

2.6.42              The DMP proposed deep U-shaped reinforced concrete channels and/or trapezoidal grasscrete lined channels for MUP03, MUP04A, MUP04B and MUP05. Whilst this offers the most efficient hydraulic solution to convey flood flows downstream in the minimum possible time, it exacerbates peak flood flows and has negligible ecological value and is aesthetically problematic.

 

2.6.43              It is proposed that the channel beds be constructed of a 300mm thick gabion mattress; this is essentially graded stone contained in a wire cage. The stone is graded in a manner which will allow some sedimentation and eventually re-colonization of the channel bed by benthic organisms. Although, in the case of the smaller channels, it is felt that the relative narrowness of the channel in relation to depth may limit the development of natural flora and fauna. The mattress also has the effect of holding the stone in place and limiting migration of bed material during flood flows.

 

2.6.44              Whilst limited migration of bed material is preferred and would simulate the natural ecosystem more accurately, the wholesale migration of large quantities of bed material during a major flood, in channels in this nature could have catastrophic consequences. The structural integrity of the channel itself could be compromised if the banks are buffeted by large quantities of material.

 

2.6.45              The channel banks are to be constructed from gabions, wire cages filled with stone. The gabion retaining structure will be wider at the base stepping back to a thinner structure closer to the natural ground level. It will be tilted to an angle of about 10o for stability purpose. This produces the ‘V’ effect in the channel. The extent to which the width of the gabion retaining structure will vary, will need to be determined during the detailed design stage. Typical preliminary cross-sections are shown as insets in the figure for each channel.

 

2.6.46              A minimum of 75 mm thick sediment will be allow to accumulate at the future gabion channels bed to permit recolonization of benthic communities.

 

2.6.47              It is possible to introduce pre-seeded topsoil into the gabion wall, however this may led to the introduction of invasive non-native species to the area and thus is more preferable to let the channel ‘green-up’ naturally.

 

2.6.48              During detailed design the draw-down effect on the local water table will be reviewed. If necessary an appropriate geotextile will be recommend to line the rear of the gabion walls and control water ingress and egress from the channel. It is more likely that in these areas a geotextile separation layer will be employed.

 

                 Dry Weather Flow Channel

 

2.6.49              DSD Stormwater Drainage Manual specifies that dry weather flow channels are desirable for non-tidal sections of channel to minimise siltation during low flow conditions. However, in nature, a certain amount of siltation will occur in natural channels. One of the overriding principles of this Project is that the design is working with nature without precluding engineering solutions. A controlled amount of sediment built-up is necessary if the beds of these channels are to mimic natural conditions. Accordingly, as the proposed channels are not wide, no dry weather flow channel will be adopted in the channel design. The water will naturally develop its own low-flow channel, through the bed of the channel. The channel should be permitted to find (and adjust) its own natural low flow channel and natural changes in the deposition of silt, sand and rock should be tolerated. A minimum of 75 mm thick sediment will be allowed to accumulate to permit recolonization of benthic communities in the future channels.

 

2.6.50              Locating the channel immediately adjacent to the river bank allows bankside vegetation to overhang the river whilst in low flow which provides shading conditions conducive to sustaining riparian species.

 


2.7                        Ancillary Infrastructure

 

                 Maintenance Access Road

 

2.7.1                  DMP proposes that a 3.5 m wide maintenance access channel be provided on the verge of the channel, used and maintained by DSD. In order to minimize land resumption and potential visual impact, the base of the channel has been used as maintenance access wherever possible (downstream portion of MUP05) for maintenance vehicles carrying out desilting and repair works. Grasscrete verges of 1.6 m and 1.0 m wide respectively are being provided on opposite sides of the smaller channels (MUP03, MUP04A and upstream portion of MUP05) as delineation of the channels and providing accesses for inspection. The detailed arrangement for maintenance access roads and ramps will be explored further during detailed design.

 

                 Crossings

 

2.7.2                  Existing pedestrian crossings, vehicular roads and bridges affected by the proposed channel will be reinstated as appropriate. These crossings and bridges will be reinstated to Highways Department’s Structures Design Manual.  The responsible maintenance authority will be identified during the detailed design stage. Full liaison will be undertaken to ensure that the design of the works is to the authority's satisfaction. Also the re-provided crossings will have soffit above the estimated water level with adequate freeboard to allow design flow to pass without obstruction.

 

2.8                        Construction Related Aspects

 

                 Construction Method

 

2.8.1                  Construction of the proposed channels generally involves standard construction methods such as site clearance, excavation and filling, assembly of gabion wall and mattress lining, construction of maintenance / access roads and finally landscaping works.

 

2.8.2                  The box culvert, cross road drains and drainage pipes will be constructed by conventional methods which involve site clearance, excavation, installation of temporary support, erection of formwork, construction of box culvert, laying of pipes and drains, backfilling, and surface reinstatement.

 

2.8.3                  Since some of the existing pedestrian and vehicular accesses / crossings will be affected by the proposed works, it will be demolished and re-provided. Temporary provision will be provided during the construction stage to facilitate passage and reduce inconvenience to the public. Such accesses and crossings will be constructed by typical cast in-situ construction method.

 

2.8.4                  Bank improvement works at LMH01 involves breaking and removal of existing shotcrete banks, and replacing them with gabions. Breaking of the shotcrete will be done using hand-held equipment. No concrete is necessary for the construction of the gabion banks.

 

2.8.5                  For the gabion channels, woven wire-mesh gabions will be used for their comparatively higher flexibility than welded wire-mesh gabions as channel lining materials. Geotextile will be provided before the gabions are placed. Empty gabion baskets (cages) or mattress will be assembled and laced together with connecting and binding (lacing) wires.

 

2.8.6                  Filling of the gabions with graded stones will be carried out either by hand or by machine depending on the accessibility of the site and the finishing requirements. Suitable rocks / stones and fines from the excavation of the channels will be reused as far as practicable in filling the gabions to reduce the amount of excavated materials requiring off-site disposal.

 

2.8.7                  Natural stream bed will be left undisturbed as far as practicable. Where widening and deepening of the stream is necessary, the stream bed materials will be excavated and temporarily stored for reuse as the new channel bed. Natural substrates (e.g. sand, gravel and cobbles) will be carefully arranged so as to re-create natural stream bed.

 

2.8.8                  If the stream is wide enough, excavation works will be carried out at half-width of the stream. Adequate width of the stream will be left intact with the flow maintained so that disturbance to the aquatic ecosystem is kept to a minimum. Adequate temporary diversion (if necessary) will be provided to ensure continuous water flow to the downstream and to prevent exacerbated flooding to the surrounding areas as a result of the construction works especially during wet seasons. Temporary containment will be provided to maintain a dry working condition.

 

Site Access

 

2.8.9                  All the proposed channels can be readily accessed through existing roads. Temporary run-in will be provided for the construction vehicles to enable them to merge and diverge from the normal traffic as smoothly as possible.

 

2.8.10              For Lin Ma Hang, as the channel is located in Closed Area, permits issued by the Hong Kong Police Force are required for all works-related persons and vehicles.

                

Implementation Programme

 

2.8.11              The implementation programme for the proposed works is tentatively expected to start in end 2007 for completion by mid 2011.  Detailed construction programme is not available at this current stage.  The tentative key milestone dates are tabulated in Table 2.7 below and shown in Figure 2.12.

 

Table 2.7

Tentative Key Milestone Dates

 

Key Milestones

Date (month/year)

Tender Gazetting of Works Contract

08/2007

Construction Contract Award of Works Contract

12/2007

Completion of All Works Contracts

mid 2011

 

 

2.9                        Consideration of Alternative Construction Methods

 

Comparison of the Environmental Benefits and Dis-benefits of Alternative Construction Methods

 

U-channels / Gabion Channels

 

2.9.1                  Potential alternative construction method includes offsite precast structures for U-channels and pre-filled gabion blocks. The benefit involves less environmental nuisance to nearby sensitive receivers during construction. However, for the excavation and construction of the open channel, there are no other suitable or practicable alternative construction methods.

 

2.9.2                  In order to match with existing topography, off-site precast structures are not preferable, impractical or cost effective. Although on-site construction could pose environmental nuisance in terms of noise, dust and water quality, the duration and magnitude of the impacts are temporary and localized given the short section and small size U-channels to be constructed. It can be mitigated by appropriate measures. Pre-filled gabion blocks are not practicable as heavy lifting appliances will be required to lift even a half loaded gabion. It will be dangerous and will hinder the assembly process as well as restrict the potential reuse of excavated rocks within the site. Therefore, conventional construction method of in-situ construction of channels as well as assembly and filling of gabions is considered more suitable and practical.

 

Crossings / Bridges

 

2.9.3                  Similar to the above elaboration and due to narrow access, off-site precast structures are not preferable, impractical or cost effective. Although on-site construction could pose environmental nuisance in terms of noise, dust and water quality, the duration and magnitude of the impacts are temporary and localized given the short section and small size crossings to be constructed. It can be mitigated by appropriate measures. Therefore, conventional construction method of in-situ construction of bridge/crossing structure is considered more suitable and practical.

 

Box Culvert / Drainage Pipes

 

2.9.4                  The construction of the box culvert and drainage pipes will employ common cut and cover construction method. Possible alternative construction methods include the use of ‘no-dig’ trenchless techniques such as pipe jacking, micro-tunneling.  Such techniques have the advantage of less traffic disruption (for road crossings), and less construction noise & dust arising from trenching works. However, the trenchless techniques were considered not practicable for the Project due to the following reasons:

 

§                     only short section of pipes are proposed hence not cost effective;

§                     presence of sewers and other utilities which will need to be diverted;

§                     drains are close to existing road/track level and there are inadequate cover for safe operation of jacking or tunneling;

§                     drains need to connect to the invert levels of upstream and downstream sections;

§                     ground treatment such as grouting may be necessary for stability purpose, which will generate additional wastewater;

§                     need several working pits to accommodate bends and curves; and

§                     requires specialized skills during construction.

 

2.9.5                  Although on-site construction could pose environmental nuisance in terms of noise, dust and water quality, the duration and magnitude of the impacts are temporary and localized given the short section and small size box culvert and drainage pipes to be constructed. It can be mitigated by appropriate measures. Therefore, conventional construction method of in-situ construction of box culvert / drainage pipes is considered more suitable and practical.

 


Justification of the Construction Methods

 

2.9.6                  The construction methods to be employed are all conventional construction method. Impacts on the environment from any construction activities are inevitable. However, the impacts are expected to be localized and temporary, which can be readily mitigated by well proven environmental protection measures. As assessed in the respective assessment chapters, no adverse environmental impact is expected during construction phase of the Project.

 

Environmental Implications of Potential Flooding at Downstream Areas during Wet Season

 

2.9.7                  The proposed construction works will widen the existing channels and thereby increase their capacities. In order to maintain the existing standard of flood protection during construction, it is necessary to phase the works so that the receiving channel (downstream) has sufficient capacity to receive the design flow. It is therefore necessary that construction works along a given reach be carried out from the downstream towards upstream. However, the contractor may start at isolated sections to suit their allocation of resources and the availability of site access provided that adequate measures are in place to ensure the existing flood protection level is maintained throughout the construction of the works.

 

2.9.8                  It will be necessary to carry out careful phasing of the works to re-connect existing incoming watercourses to ensure satisfactory diversion of flows without the risk of flooding to adjacent areas especially during wet seasons.  It is recommended that the connection of existing watercourses should be carried out during dry season to minimize flooding risks.

 

2.9.9                  Adverse effect on hydraulic performance of the channels during construction can be managed and controlled to a minimum by well construction planning and adopting proper construction methodology, monitoring and contingency measures. According to the Drainage Impact Assessment (DIA) conducted under this Project, no adverse impacts to the drainage system and catchment characteristics are anticipated.

 

2.9.10              Cumulative environmental implications of potential flooding at downstream areas during wet season are not expected.

 


Cumulative Effects for the Construction of the Proposed Channels

 

2.9.11              Cumulative impacts associated with the construction of the proposed channels (MUP03, MUP04A, MUP04B, MUP05 & LMH01) have been assessed and presented in the subsequent assessment chapters. It is concluded that there will be no adverse cumulative impacts.

 

2.9.12              In summary, having regard to the cumulative effects for the construction of the proposed channels and the severity of the construction impacts to the affected sensitive receivers along the proposed channels, the EIA study has concluded that there will be no adverse environmental impacts.

 

2.10                    Justification of the Final Channel Design Recommendations

 

2.10.1              The recommended channel design has essentially followed the avoidance and minimization approach promulgated in the Government’s technical circulars and guidelines on protection of natural rivers and streams. Consideration and evaluation of the merits of the Project for flood alleviation, the various alternative drainage design, the various alternative means to achieve flood alleviation, and the various alternative construction methods presented above have demonstrated the Project will not adversely affect the existing stream, the aquatic life and surrounding wildlife therein. The detailed environmental impact assessment presented in the subsequent chapters has also demonstrated the adopted channel design can avoid and minimize adverse environmental impacts.

 

2.11                    Project Interfaces / Concurrent Projects

 

2.11.1              There are a number of projects that are planned or on-going in the Study area (Table 2.8). Many do not have a significant influence on the proposed channels in this Project. However, if interfacing does occur, close liaison will be conducted to ensure adequate phasing with each concurrent projects is taken into consideration.

 

2.11.2              The interfacing with the non-DP channels has been assessed in the cumulative impact section of the relevant assessment chapters of this EIA. According to the EIA findings, no adverse cumulative environmental impact is expected.

 


Table 2.8

On-going and Planned Projects in the Study Area

 

Concurrent Projects

Tentative Programme

Project Interfaces with Proposed Channels

Drainage Improvement in Northern New Territories – Package C (non-DP channels MUP01 and MUP02)

end 2007 – mid 2011
(same time frame)

Interfacing with MUP05

North District Sewerage, Stage 3 Phase 1 – Package ND1 (Sewerage to Man Uk Pin)

02/2008 – 02/2010

Very minor interfacing with upstream portion of MUP05

North District Sewerage, Stage 3 Phase 1 – Package ND1 (Sewerage to Loi Tung)

02/2008 – 02/2010

Minor interfacing with proposed 1350mm drainage pipes at MUP04B

North District Sewerage, Stage 2 (Sewerage to Lin Ma Hang)

2/2008 – 10/2009 (Cat B item – under planning)

Minor interfacing with proposed vehicular crossings V1 & V2 at LMH01

North-east New Territories (NENT) Landfill Extension

2008 - 2009

MUP channels and LMH01, no interfacing expected

 

 

2.12                    Scope of Works during Operational Phase

 

2.12.1              Maintenance would be necessary for the proposed gabion channels to remove excessive silts, vegetation, debris and obstructions in order to maintain its hydraulic performance and structural integrity. Siltation will generally be allowed to accumulate and removal of excess silt would be carried out at locations only if it would impede water flow. Such small scale maintenance would require only light mechanical equipment such as a small loader and/or a small crane truck. Hand-held equipment will be used for vegetation removal. Little or no maintenance will be necessary for the ‘two-stage’ channel at MUP05 and the natural stream sections of LMH01.

 


2.13                    Maintenance Responsibilities

 

2.13.1              The works included in this Project will be handed over to relevant Government Departments for maintenance upon completion of the construction contracts.

 

2.13.2              The scope and maintenance responsibilities of individual government Departments are generally well established. Table 2.9 outlines the proposed maintenance responsibilities based on current Government practices and relevant Technical Circulars.

 

Table 2.9

Proposed Maintenance Responsibilities

 

Items

Management Department

Maintenance Department

Proposed channels

DSD

DSD

Proposed box culvert, drainage pipes, U-channel

DSD

DSD

Maintenance access roads (not open to public)

DSD

DSD

Local access roads / footpaths (open to public)

DO/N

DO/N

Pedestrian and vehicular crossings

DO/N

DO/N

Vegetation within the proposed channels

DSD

DSD

Roadside landscape hardworks and softworks

LCSD

LCSD

Channel verge landscape hardworks and softworks

LandsD

LandsD

 

                 Notes:

1.           The departmental responsibilities for the maintenance of the completed channel as well as unchannelised stream course including meanders will follow the schedule of responsibilities as stipulated in Appendix A of ETWB TCW No. 14/2004 – Maintenance of Stormwater Drainage Systems and Natural Watercourse.

2.           The departmental responsibilities for the maintenance of the vegetation and hard landscape features will follow the schedule of responsibilities as stipulated in Appendix A of ETWB TCW No. 2/2004 – Maintenance of Vegetation and Hard Landscape Features.

 


2.14                    Continuous Public Involvement

 

2.14.1              The process of Continuous Public Involvement (CPI) through public consultation and site visits were undertaken since early 2005 (Table 2.10).

 

Table 2.10

Summary of Continuous Public Involvement

 

Relevant Parties

Process

Date

Sha Tau Kok Rural Committee

Village Representatives (VRs) of Man Uk Pin and Lin Ma Hang

meeting

4 February 2005

site visits

24 February 2005 & 18 March 2005

VRs of Lin Ma Hang

site visit

24 February 2005

Fanling Rural Committee

VRs of Fanling Rural Committee

meeting

13 April 2005

site visits

21 & 22 May 2005

Shung Him Tong and Lung Yeuk Tau Village Representatives

site visits

21 & 22 April 2005

North District Council – District Development and Environmental Improvement (NDC DD&EI) Committee

meeting

23 May 2005

Green Groups

§         Conservancy Association (CA)

§         Friends of the Earth (FoE)

§         Green Power (GP)

§         Hong Kong Bird Watching Society (HKBWS)

§         Kadoorie Farm and Botanic Garden (KFBG)

§         World Wide Fund for Nature Hong Kong (WWF)

consultation paper

6 October 2005

site visits

25 October 2005 (attended by GP, HKBWS and KFBG)

16 January 2006 (attended by KFBG and WWF)

letter on latest progress of design

31 July 2006

 

2.14.2              The channel details were reviewed and revised according to the comments and recommendations from the relevant parties. The main comments and recommendations are summarized in Table 2.11 below.

 


Table 2.11

Summary of Public Consultation

 

Relevant Parties

Main Comments / Recommendations

Responses / Outcomes

Sha Tau Kok Rural Committee

Lin Ma Hang VRs

Request for river training / additional bank improvements to the existing Lin Ma Hang stream (LMH01).

Site visit was arranged with the Lin Ma Hang VRs to investigate local flooding situations and identify critical locations for improving for improving the existing river banks. The proposed additional bank improvement works were provided to the VRs. No further comments were received.

Fanling Rural Committee

Shung Him Tong VRs

Lung Yeuk Tau VRs

Shung Him Tong and Lung Yeuk Tau VRs objected the locations of the proposed open-channel (LYT04) alongside the existing road within private farmlands. They proposed to re-construct and enlarge the existing under-road box culvert.

Site visits with the VRs were arranged. To take into account the objection raised by the VRs, the proposed channel LYT04 was revised to a twin cell culvert under the existing access road. The alternative proposal could reduce the resumption of private lands but would require temporary traffic diversions during construction. No further comments were received.

(As a result of the design changes, LYT04 is confirmed not to be a DP under the EIAO and will be excluded from this EIA.)

North District Council – District Development and Environmental Improvement (NDC DD&EI) Committee

Enquired whether the Project is governed by the EIA Ordinance, to consider the latest Government circulars and guidelines on protection of natural rivers and the likely environmental protection measures to be taken.

The Project will undergo the EIA process under the EIA Ordinance. The Project will also take into account the latest relevant Government circulars and guidelines. Gabions and other environmental friendly channel design will be incorporated to the proposed channels.

Green Groups

LMH

The Green Groups opined that the downstream section currently stabilized by shotcrete is not ecological friendly and several sections of the stream banks were not in good condition. They suggest replacing it with natural materials.  Also expressed concerns of potential pollution during construction and request adequate supervision of the contractor as well as to carry out works during dry season and in phases.

The design has been reviewed and sections of the banks will be replaced/stabilized with gabions. Stringent mitigation measures will be proposed in the EIA to ensure no adverse impacts on Lin Ma Hang stream during construction. Construction phase monitoring and audit will also be recommended.

MUP

Provision of proper support and protection to a big tree at MUP05.

Several large trees within MUP05 will be preserved in-situ with proper support and protection.

 

2.14.3              Overall, the relevant Rural Committee and North District Council members, together with Village Representatives supported the proposed Project as it would bring relieve to the flooding in the Northern New Territories. The Green Groups appreciate the adoption of environmental friendly designs such as two-stage channel, etc in this drainage improvement project to minimize the potential impacts to the ecology and the environment. No adverse comments were received from the Green Groups.