3.                       Air Quality IMPACT Assessment

 

3.1                    Introduction

 

3.1.1              This Chapter presents a qualitative assessment of air quality impact associated with the construction and operation of the secondary channels: MUP03, MUP04A, MUP04B, MUP05 & LMH01 (the Project). Potential construction phase air quality impact consists of increased fugitive dust at the nearby air quality sensitive receivers.

 

3.1.2              Annual maintenance cutting of vegetation and sediment removal may be necessary during operation of the drainage channels. Such activities are not expected to have any significant air quality impacts.

 

3.2                    Air Quality Assessment Criteria

 

3.2.1              The criteria for evaluating air quality impacts and the guidelines for air quality assessment are laid out in Annex 4 and Annex 12 of the Technical Memorandum on Environmental Impact Assessment Process (TM-EIA).

 

3.2.2              The principal legislation regulating air emissions in Hong Kong is the Air Pollution Control Ordinance (APCO) (Cap.311) of 1983 and its subsidiary regulations. The whole of the HKSAR has been covered by Air Control Zones. The Hong Kong Air Quality Objectives (AQOs) stipulate maximum acceptable concentration of air pollutants. The AQOs for 1 hour, 24 hour and annual concentrations of four major pollutants are shown in Table 3.1.

 

Table 3.1

Hong Kong Air Quality Objectives (AQOs)

 

Pollutants

Concentration in

Micrograms per Cubic Meters (µg/m3)

Averaging Time

1 hourA

24 hourB

1 yearC

Nitrogen Dioxide (NO2)

300

150

80

Sulphur Dioxide (SO2)

800

350

80

Total Suspended Particulates (TSP)

500E

260

80

Respirable Suspended Particulates (RSP)D

--

180

55

 

Notes:

Concentrations measured at 298K (25°C) and 101.325 kPa (one atmosphere).

A              1 hour criteria not to be exceeded more than 3 times per year.

B              24 hour criteria not to be exceeded more than once per year.

C              Arithmetic means.

D              Respirable suspended particulates means suspended particulates in air with a nominal aerodynamic diameter of 10 micrometer (µm) or smaller

E              This control limit has no statutory basis but is used as a target level for limiting fugitive dust emissions generated by construction activities.

 

3.2.3              The TM-EIA also stipulates that the odour level at a sensitive receiver should not exceed 5 odour units based on an averaging time of 5 seconds for odour prediction assessment..

 

3.3                    Air Sensitive Receivers

 

3.3.1              The representative air sensitive receivers (ASRs) that may potentially be impacted by the Project are listed in Table 3.2 and shown in Figures 3.1 – 3.3.

 

Table 3.2

Representative Air Sensitive Receiver (ASR)

 

Channels

Representative ASR

General Description

No. of Floors

Approximate Distance to Works Site Boundary, m

MUP03

MUP03-1

Village house near Sha Tau Kok Road – Wo Hang Section

2

34

MUP03

MUP03-2

Village house near Sha Tau Kok Road – Wo Hang Section

1

14

MUP04A

MUP04A-1

23 King Ngai Garden near Loi Tung Village

3

34 (to MUP04B)
46 (to MUP04A)

MUP04A-2

Village house near Loi Tung Village

3

5

MUP04B

MUP04B-1

Tung Shing Garden near Loi Tung Village

3

23

MUP04B-2

Village house near Loi Tung Village

3

3 (to 1350mm pipe)
38 (to 600 U-channel)

MUP05

MUP05-1

Village house near Sha Tau Kok Road – Wo Hang Section

2

20

MUP05-2

Village house at Loi Tung North

2

24

MUP05-3

Village house at Loi Tung North

2

7

MUP05-4

Village house at Loi Tung North

2

12

MUP05-5

Village house near Sha Tau Kok Road – Wo Hang Section

2

43

MUP05-6

Village house at Loi Tung North

2

4

LMH01

LMH01-1

Village house at No. 166 Lin Ma Hang

2

8

LMH01-2

Village house at No. 213A Lin Ma Hang

3

6

LMH01-3

Village house at No. 139B Lin Ma Hang

3

32

LMH01-4

Village house at No. 71 Lin Ma Hang

2

10

LMH01-5

Village house at No. 1A Lin Ma Hang

3

116

 

Note:

The location of the ASRs is shown in Figures 3.1 - 3.3.

 

3.4                    Baseline Air Quality

 

3.4.1              The Study Area is located in the northern part of Hong Kong and to the north is Shenzhen. This area falls within the Deep Bay Airshed and is topographically confined. The area generally exhibits a limited dispersive capacity because of the occurrence of inversion layers in the morning and evening[1]. In other words, the stable layer associated with the inversion layer acts as a lid, trapping any pollutants[2].

 

3.4.2              The wind rose from the Ta Kwu Ling Station indicates that the dominant wind direction is east-south-easterly and easterly.

 

Existing Air Conditions

 

3.4.3              As there is no monitoring station at the Study Area, EPD's Air Quality Monitoring Station at Tai Po was used to establish ambient air quality over the Study Area. According to data collated from the Tai Po Station, the concentrations of the TSP and RSP in 2003 [3] are shown in Table 3.3 below.

 

Table 3.3

Air Pollutants Concentrations at Tai Po EPD Station (2003)

 

Pollutants

Annual Concentration in Micrograms per Cubic Meter (μg/m3)

 

Average

AQOs

TSP

71

80

RSP

54

55

 

3.4.4              The table indicates that the annual concentration of TSP and RSP at Tai Po are below the AQOs.

 

3.4.5              For the study area, vehicular exhaust emissions from Sha Tau Kok Road, Wo Keng Shan Road and Ping Che Road are the major pollutant sources of the area. The NENT Landfill including its extension, over 1.7km from MUP channels and 0.9km from LMH01, is unlikely to have any impact on the Project. No other major air pollutant emission sources have been identified.

 

3.5                    Air Quality Impact Assessment

 

Construction Phase

 

               Dust

 

3.5.1              The principal potential source of air quality impact arising from the construction of the Project will be fugitive dust. The temporary dust nuisance, measurable as TSP (Total Suspended Particulates) and RSP (Respirable Suspended Particulates) will be generated as a result of construction activities, especially from site clearance / excavation works where dusty and silty material movement may be involved. However, the nuisance from emission of construction vehicles and plant will be relatively small for the area involved, as the number of construction vehicles and plant is expected to be limited and small. Moreover, the dust impact is expected to be relatively insignificant as the excavated material of the area will be mainly from river channel which have high moisture content. The major items of the works are:

 

Ÿ                MUP03           construction of approximately 93 m long (1.2 m width) channel using gabion lining and associated U-channel

Ÿ                MUP04A        construction of approximately 163 m long (4.5 m width) channel using gabion lining and associated drainage pipes

Ÿ                MUP04B        construction of U-channels and drainage pipes

Ÿ                MUP05           construction of approximately 1014 m long (of varying widths) channel using gabion lining

 

              The works also include the various ancillary infrastructure works such as footbridge, vehicular bridge, maintenance ramp, etc.

 

3.5.2              The construction duration for this Project as a whole is expected to last for about 3.5 years within the tentative construction programme timeframe of end 2007 to mid 2011. Each channel would have individual construction programme depending on the size of the proposed channel.

3.5.3              The most affected air sensitive receivers will be those village houses near and around the works areas. Only minor impacts will be expected due to off-site transportation of spoil materials because the volume of spoil materials is expected to be relatively small.

 

3.5.4              Due to the limited scale of construction works required and the fact that the use of gabions have been proposed for lining the channels, no concrete batching plants will be required for this Project. Construction tenders / contracts will stipulate that on-site concrete batching shall not be practised.

 

3.5.5              Parts of the proposed secondary channel sites are natural streams. The proposed construction works will involve site clearance in the works areas, excavation to formation levels of secondary channels, lining of channel banks and bases, and restoration landscaping works following the construction activities.

 

3.5.6              Portion of the natural stream banks and beds at MUP05 will be retained, while MUP03 and MUP04B will be small channels or drainage pipes. The amount of spoil and construction activities is expected to be relatively minor.

 

3.5.7              Ready mixed concrete would mostly likely be supplied by existing batching plant nearby.

 

3.5.8             Alternative solutions to flooding problem at Lin Ma Hang stream (LMH01) instead of a bypass channel have been recommended under this Project to avoid impacts on the valuable ecological resources in the area. The revised works for Lin Ma Hang comprise the local improvement of crossings, footbridges, stream banks as well as improvement to the existing security grille at the outlet of Lin Ma Hang stream. It also includes the installation of several flood alarm system in the village. As a consequence, construction activities are substantially scaled down. Given the small scale works, construction dust is considered to be negligible.

 

3.5.9              As the construction works will likely be constructed section by section, construction dust nuisance is not expected to cause any significant dust impacts to the nearby sensitive receivers. The quantity of the spoil materials from site clearance and excavation is unlikely to be large enough to cause a significant dust nuisance. It is anticipated that excavated material will only be stockpiled on each local works area and the duration of the stockpiling will be as short as possible. The feasibility of reusing some of the excavated materials as backfilling materials will be rigorously examined during the detailed design stage. As some materials may be used back in the construction processes, the quantity of material need to be disposed of or imported can be reduced. Hence construction dust nuisance at nearby representative sensitive receivers will expect to be insignificant. In addition, the distance between the channel construction works and most of the air sensitive receiver is over 5 m or more. This buffer distance is adequate to alleviate the ASR from the construction dust nuisance provided that proper construction dust mitigation measures are in place as required by the Air Pollution Control (Construction Dust) Regulation.

 

3.5.10          As the proposed channels are close to existing roads, purpose-built haul road is not expected for the transportation of excavated material and filling material. Nonetheless, the Contractor should identify any alternative access route away from any ASR to further minimise any possible dust nuisance, if required. For the channels at Man Uk Pin, access to the sites is easily accessible via Sha Tau Kok Road.

 

Odour

 

3.5.11          Odour is not expected from the excavated stream material. In the unlikely event that potential odourous materials are encountered during construction, excavation works should be conducted in the shortest time span possible. Programming of the works should be carried out to ensure that the time for such works can be minimised. If necessary, the contractors should also liaise with local resident to inform them of the duration of potential odour nuisance, and that efforts are made to minimise and mitigate such nuisance. Odorous excavated material should be placed as far away from air sensitive receivers as possible. Temporary stockpiles of odorous excavated material should be removed off-site as soon as practically possible within 24 hours to avoid odour nuisance arising.

 

Operational Phase

 

3.5.12          Maintenance would be necessary for the proposed gabion channels to remove excessive silts, vegetation, debris and obstructions in order to maintain its hydraulic performance and structural integrity. Siltation will generally be allowed to accumulate and removal of excess silt would be carried out at locations where it would impede water flow. Little or no maintenance will be necessary for the ‘two-stage’ channel at MUP05 and the natural stream sections of LMH01. Therefore the operation phase of this Project would unlikely cause any adverse air quality impacts in terms of dust and odour.

 


3.6                    Mitigation Measures

 

Construction Dust

 

3.6.1              In order to comply with Air Pollution Control Ordinance (APCO), the Contractor should undertake at all times measures to prevent dust nuisance as a results of his activities. The Contractors are required to follow all the requirements for dust control stipulated in the Air Pollution Control (Construction Dust) Regulation. Dust suppression measures should be installed as part of good construction practice, and they should be incorporated in the Contract Specification and implemented to minimize dust nuisance to within acceptable levels arising from the works. The followings are examples of the dust suppression measures.

 

(i)                  The area in which excavation takes place shall be sprayed with water immediately prior to, during and immediately after the excavation to minimise dust generation.

 

(ii)                The Contractor shall frequently clean and water the site to minimize fugitive dust emissions.

 

(iii)               Effective water sprays shall be used during the delivery and handling of aggregate, and other similar materials, when dust is likely to be created and to dampen all stored materials during dry and windy weather.

 

(iv)              Watering of exposed surfaces shall be conducted at least 2 times per day especially during dry and windy weather.

 

(v)                Areas within the site where there is a regular movement of vehicles must be regularly watered as often as necessary for effective suppression of dust or as often as directed by the Engineer.

 

(vi)              Where dusty material are being discharged to vehicle from a conveying system at a fixed transfer point, a three-sided roofed enclosure with a flexible curtain across the entry shall be provided. Exhaust fans shall be provided for this enclosure and vented to a suitable fabric filter system.

 

(vii)             The Contractor shall restrict all motorised vehicles within the site, excluding those on public roads, to a maximum speed of 15 km per hour and confine haulage and delivery vehicles to designated roadways inside the site.

 

(viii)           Wheel washing facilities shall be installed and used by all vehicles leaving the site. No earth, mud, debris, dust and the like shall be deposited on public roads. Water in the wheel cleaning facility shall be changed at frequent intervals and sediments shall be removed regularly. The Contractor shall submit details of proposals for the wheel cleaning facility. Such wheel washing facilities shall be usable prior to any earthworks excavating activity on the site. The Contractor shall also provide a hard-surfaced road between any washing facility and the public road.

 

(ix)              All vehicle exhausts should be directly vertically upwards or directed away from the ground.

 

(x)                Any materials dropped on paved roads will need to be cleaned up immediately to prevent dust nuisance.

 

              Odour

 

3.6.2              In the event that excavated materials are found to be odourous, the following measures should be implemented by the Contractor.

 

(i)                  Place odorous excavated material as far away (say, at least 20m) from air sensitive receivers as possible.

 

(ii)                Temporary stockpiles of odorous excavated material should be properly covered with tarpaulin and should be removed off-site as soon as practically possible within 24 hours to avoid any odour nuisance arising.

 

3.7                    Cumulative Impacts

 

3.7.1             There are projects in the vicinity of the proposed drainage channels. These are described in Chapter 2. Many do not have significant influence on the Project, some are on-going projects that will be completed by the time works commences for this Project.

 

3.7.2             The major public works project in the area is the Fanling Bypass for the Ping Che / Ta Kwu Ling Development proposed under the NENT Study. However, there is still no programme for the preliminary design or implementation of this project and thus will not be consider in the cumulative impact assessment.

 

3.7.3             The only likely potential cumulative impact would be from construction works of the drainage channels under this Assignment, specifically the Non-DP channels at MUP01 and MUP02 (which drains into MUP05). Works associated with the Non-DP channels at MUP01 and MUP02 will be limited as only short sections of gabion banks / landscaped embankment slopes will be required. As such, adverse cumulative air quality impact is not expected.

 

3.8                    Monitoring and Audit Requirements

 

3.8.1              Dust impacts during the construction phase can be readily mitigated through implementation of standard mitigation measures and good housekeeping practices.

 

3.8.2              However, if the proposed construction dust mitigation measures are not fully implemented, it is likely that some nearest air sensitive receivers would suffer unacceptable impact. It is therefore recommended that an Environmental Monitoring & Audit (EM&A) programme in respect of dust issue be carried out at representative sensitive receivers to monitor the effectiveness and efficiency of the dust suppression measures.

 

3.8.3              It is recommended that at least the following representative ASRs (Table 3.4) should be selected for monitoring purposes during the construction stage. These representative sensitive receivers have been selected for monitoring because of their locations are close to the construction works areas, and/or are downwind from the sites under the most predominant meteorological conditions, and/or are close to concurrent construction activities and hence, are the mostly likely being impacted if dust suppression measures are not properly implemented. Given the relatively small scale improvement works, monitoring at Lin Ma Hang is not required.

 

3.8.4              No monitoring is required during operational phase.

 

3.8.5              The monitoring requirement is broadly presented in Chapter 10 of this Report. Details of the monitoring and audit of construction dust will be presented in the separate EM&A Manual.

 


Table 3.4

Representative ASRs chosen for Air Quality Monitoring during Construction Stage

 

Air Quality Monitoring Station

ASR ID

Representative for

Secondary Channels

MUP-A1

MUP05-2

Village north of Loi Tung

MUP05 and potential concurrent activities at MUP01, MUP02, MUP03, MUP04A and MUP04B

MUP-A2

MUP05-4

Village north of Loi Tung

MUP05 and potential concurrent activities at MUP04A and MUP04B

MUP-A3

MUP04A-2

Village house near Loi Tung

MUP04A

 

Note: Channels MUP01, MUP02 are non-DPs.

 

3.9                    Summary

 

3.9.1              The construction dust impact assessment has identified Air Sensitive Receiver (ASR) within the Study Area. Potential works that may cause potential construction dust nuisance is also identified. Mitigation measures, as required by Air Pollution Control (Construction Dust) Regulation, are also highlighted. Provided that the Contractor implements all the necessary mitigation, construction dust nuisance at nearby representative sensitive receivers is expected to be complied with Air Quality Objectives.

 

3.9.2              No operational phase air quality impact is expected.



    [1]            Royal Observatory Hong Kong (1984) Meteorological Assessment of Atmospheric Transport Condition in the Deep Bay Airshed.

    [2]            Roland, B.S. (1988) An Introduction to Boundary Layer Meteorology, Kluwer Academic Publishers, p.666.

    [3]            Environmental Protection Department (2004) Air Quality in Hong Kong 2003. Hong Kong Government [Report Number: EPD/TR 02/03].